Professional Documents
Culture Documents
Chap 3
Chap 3
Chap 3
compounding
A sum invested today will earn interest. compounding calculates the future or terminal value of a
given sum invested today for a number of years.
To compound a sum the figure is increased by the amount of interest it would earn over the period .
Discounting
As cash flows may arise at different points in time in a potential project to make a useful comparison
of different flows they must all be converted to a common point in time usually the present day
year 0 1 2 3 4…...
CFs 2000 2000 2000 2000 2000
PV 2000 2000 x 9% PF
perpetuities
year 0 1 2 3 4 5…..
CFs 200 200 200
PV 4000
3628.12
NPV vs IRR
both NPV and IRR are investment appraisal techniques that discount cash flows and are superior to the
nasic techniques. However only NPV can be used to distinguish between two mutually exclusive projects
Discounting annuities
Example 01 r 8%
year 0 1 2 3 4 5
CFs 20000 20000 20000 20000 20000
PV 92457.59328
deferred annuity
example 02 r 0.08
year 0 1 2 3 4 5
CFs 20000 20000 20000
PVs 79267.48395 92457.5933
PV = FV / (1+r)^n
example 03 r 11%
year 0 1 2 3 4 5
CFs 25000
PV 60865.04607 92397.42544
example 04 r 10%
year 0 1 2 3 4 5
CFs 22000 22000 25000
PV 38181.8182 83397.31
98861.42211 31555.2216 15523.03308 51783.17
example 05 r 10%
year 0 1 2 3 4 5
CFs 10000 8000 8000 8000
PV 9090.909091 19894.81593 25358.92
18086.1963
15745.89637
42923.00176
PV 42923.00176 9090.909091 6611.57025 6010.51841 5464.107643 0
example 06 r 13%
year 0 1 2 3 4 5
CFs 1700 3000 1700 1700 1700 3000
PV 1700 2654.867257 7083.457794
2654.867257 4013.959416
3552.176475
4344.417322
-1128.479585
1331.539334
3992.171086
PV of total 16446.69189
annuity due
Example 07 r 8%
year 0 1 2 3 4 5
CF 20000 20000 20000 20000 20000 20000
PV 92457.59328
112457.5933
method 1
PV = ordinary annuity formula x ( 1 + r )
112457.5933 where n is te no. of CF years in this case is 7
method 2
PV = annuity CF x Annuity factor +1
20000 5.62287966
112457.5933
r 10%
year 0 1 2 3 4
CFs 10000 10000 10000 10000 10000
PV using method 1 41698.65446
PV using method 2 41698.65446
perpetuity
annuity without an end date
PV = cashflow x 1/r
ordinary pepetuity r 8%
year 0 1 2 3 4 5
5000 5000 5000 5000 5000
PV 62500
pertuity due r 8%
year 0 1 2 3 4 5
CF 5000 5000 5000
PV 53583.67627 62500
deferred perpetuity r 8%
year 0 1 2 3 4 5
CFs 5000 5000 5000 5000 5000 5000
PV method 1 67500
PV method 2 67500
payback
Example 01
example 02
discounted payback cost of capital 8%
Years 0 1 2 3 4 5
Investment (15,000,000)
Net cashflows 2,000,000 3,000,000 4,000,000 5,000,000 #######
8% 0.926 0.857 0.794 0.735 0.681
PV of cashflow (15,000,000) 1,851,852 2,572,016 3,175,329 3,675,149 #######
Cumulative NPV (15,000,000) (13,148,148) (10,576,132) (7,400,803) (3,725,653) #######
disocunted payback
5 years 6 months
discounted payback
8 years 11.6 months
Years 0 1 2 3 4 5
Investment (50,000) 18,000 25,000 20,000 10,000 5,000
15% 1 0.870 0.756 0.658 0.572 0.497
PV (50,000) 15,652 18,904 13,150 5,718 2,486
25% 1.000 0.800 0.640 0.512 0.410 0.328
PV -50000 14400 16000 10240 4096 1638
IRR
IRR 21.20%
L 15%
H 25%
L 15%
NL (NPVL) 5,909.51 IRR 21.2%
H 25%
NH (NPVH) (3,625.60)
Net Present Value (NPV)
Represents the surplus funds (after funding the investment) earned on the project by discounting
all the relevant cash flows associated with the project back to their PV.
if NPV > 0 then financially viable NPV gives the impact of the project on
If NPV = 0 project breaks even shareholder wealth.
If NPV < 0 then project is not financially viable
You should never include interest payments as cash flows within an NPV calculation as these are taken
account of by the cost of capital
Advantages
NPV is superior to all others
considers time value of money - impact of interest, inflation anf risk over time
absolute meaure of return - allows for more effective planning
based on cash flows and not profits - subjectivity of cash flows make them less reliable for decision
considers whole life of the project - considers all relevant cash flows
should lead to maximisation of shareholder wealth
disadvantages
1. difficult to explain to managers - to understand NPV calc and discounting not intuitive as payback
2. requires knowledge of the cost of capital - gathering data and making calc based on data and
estimates
3. relatively complex
to calculate the exact DCF rate of return that the project us expected to achieve.
if NPV > 0 it is earning more than the COC and vice versa
the % return on investment must be the rate of discount or COC at which NPV is 0 - IRR or the DCF yield
if its hgher than the target rate of return then project is financially viable.
IRR = L+ NL x (H - L ) L is the lower rate of interest NL - NPV at lower rate
NL - NH H is higher rate of interest NH - NPV at higher rate
IRR may be calculated by a linear interpolation by assuming a linear relationship between NPV
and discount
IRR with perpetuities
annual inflow x 100
initial investment
Advantages
1. considers time value of money, the current value earned from an investment project = more accurate
2. IRR is a percentage and hence easily understood. This can be simply compared with the required
rate of return of the organisation
3. IRR uses cash flows and not profits, less subjective
4. considers the whole life of the project
5. means selecting projects where IRR exceeds the COC should increase shareholders wealth. This holds
true given that the project CF follow the standard pattern of an outfow by a series of inflows.
Disadvantages
1. it is not a measure of absolute profitability
2. interpolation only provides an estimate and an accurate estimate requires the use of a spreadsheet
programme, the COC itself is only an estimate and if the margin between required return and IRR is
small then this lack of accuracy could actually mean the wrong decision is taken
3. It is fairly complicated to calculate. Note that where small margins exists, the projects success
would be considered to be sensitive to the discount rate
4. non conventional cash flows may give rise to multiple IRRs which means the interpolation method
cant be used. Even where the project has one IRR it can be seen from the graph that the decision
rule would lead to the wrong result as the project does not earn a positive NPV at any COC
5. Contains an inherent assumption that cash returned from the project will be re-invested at the
porjects IRR, which may be unrealistic. The assumption is that the cash inflows generated by the
project will be reinvested at an equally beneficial level of return as this project; whereas cash is more
likely to be invested un projects at that return or above.
ying the IRR rule it is possible for a project to have upto as many
terms, A has the IRRs as there are sign changes in the cashflows
NPV profile could take various forms depending
on the relative magnitude of the CFs
ues as it tells us the IRR and Cost of initial investment are
alth as a result of independent of the risk of the project
COC. IRR simply
ase before the
TYU 1
6700.478203
TYU 2
68068.32331
TYU 3
year 0 1 2 3 4
CFs -25000.0 6000.0 10000.0 8000.0 7000.0
6% 1.0 0.9 0.9 0.8 0.8
PV -25000.0 5660.4 8900.0 6717.0 5544.7
NPV 1822.0
TYU 4
year 0 1 2 3 4 5
CFs -240000 80000 120000 70000 40000 20000
9% 1.000 0.917 0.842 0.772 0.708 0.650
PV -240000 73360 101040 54040 28320 13000
NPV 29760
TYU 9
14.17%
6
20000
6 7 8
20000 20000 20000
6 7 8 9
25000 25000 25000 25000
6 7 8 9 10
22000 22000 22000 22000 22000
6 7 8 9
8000 8000 8000 8000
6 7 8 9 10 11 12
3000 3000 -3000 4000 3000 3000 3000
11992.6494
6
20000
…infinity
5000
…infinity
5000
…infinity
5000
6 7 8
6 7 8 9 10 11
5,910
-3626
13 14 15
3000 3000 3000