Framework For RBI
Framework For RBI
Framework For RBI
Project Cost > $7.5 – $15 M > $15 –$30 M > $30 – $75 M > $75 – $150 M > $150 M
Site Supervisors Resident Technical
Requirements Officer (RTO) Site
1 RTO 1 RE 1 RE + 1 RTO 1 RE + 2 RTO 2 RE + 3RTO
Supervisors
`
Immediate supervision x full time supervision for x QP’s inspection before or during execution of x full time supervision for structural elements of all
for structural elements of all complex structures building works
building works (including x full time supervision for structural elements of x checklist for Supervision of Tunnelling works
x concreting demolition works) all building works (including demolition works) x Exc_GBW_Annex C-1 and ERSS_GBW_Annex E
x piling x Exc_non-GBW_Annex C-1 x Certificate of Supervision on Pile Load Test forms for GBW works
x pre-stressing and ERSS_Annex E forms for (Annex B)
x tightening of high- non-GBW works x Certificate of Supervision on Piling Works in Supervision duties under Eighth Schedule, Part 2 of BC
friction grip bolts two stages [50% and 100% (Annex C)] Regulations
x the construction of x Building settlement monitoring plan &
ERSS settlement limit (Annex D)
Supervision x other critical x Exc_non-GBW_Annex C-1 and ERSS_Annex
requirements structural works such E forms for non-GBW works
as demolition works
82
x Foundation works (Bored x PPVC (Conrete)
Minimum level of Piles) x Post-Installed Anchors/Rebars
immediate supervision x Foundation works x ERSS
(refer to Annex 5) (Displacement Piles) x Tunnelling works (for GBW)
x Structural Steelworks
x Mass Engineered Timber
x Reinforcement
x Demolition works
Note:
* For major building works, the QP(ST) shall not be the officer, employee or partner of the developer or builder.
** For building fall under complex structures, refer to Annex A (criteria for complex building) of circular dated 2nd June 2014
# For project values more than $7.5 M, refer to Building Control Regulations 24
## For buildings more than 10 storey
83