JOB LIST T/A TH. 2023 REV.

4
JOB LIST TA-22 KILANG PT.TPPI TUBAN
PT. Trans Pasific Petrochemical Indotama
Turnaround - Relita Department
CRETERIA REFERENCE
NO. EQUIPMENT NO. SERVICE JOB LIST RECOMMENDATION-INSP/REL/PE REASON MAIN JOB TA-22
PI MI INSP OPT
NO. DESCRIPTION

Normalize double
feeder incomer feeder
A dan B dari source
CTG serta Normalize ke source CTG untuk incomer
Menaikkan kehandalan jaringan listrik Normalize ke source CTG untuk incomer feeder A &B
637 menambahkan Sumber listrik di SS 800 feeder A &B serta Provide incomer r feeder A x IOM-REL-003 Pengajuan Job List TA 2022
Tidak handal karena source CTG hanya single feeder di bus B saja serta Provide incomer incomer feeder A dari PLN
incomer feeder A dari dari PLN
source PLN
Status : MOC
20000070
1. Isolated of power supply and put in rack out position
2. Inspect jointing and re tighten bus bar
3. Inspect enclosure, power and control cable
915 800-SWGR-011 6.3kV MV SWITCHGEAR BUS TIE SS-200
Periodic maintenance, inspection MW SWGR IOM-REL-003 Pengajuan Job List TA 2022 Periodic maintenance and inspection
4. Inspect and test vacuum circuit breaker
5. Secondary relay test injection
6. Check and verification CT / PT
Equipment obsoleted 1. Isolated of power supply and put in rack out position
Incase terjadi trouble relay protection tidak bisa di perbaiki, Potensi terjadi interuption dan 2. Inspect jointing and re tighten bus bar
Improvement dan upgrade relay protection
Medium voltage 6.3KV switchgear PIR TA 2017 Post Implementation Review peralatan loss of protection 3. Inspect enclosure, power and control cable
916 200-SWGR-011A system di switchgear 6.3KV 0 1 0 0
di SS 200 IOM-REL-003 Pengajuan Job List TA 2022 Inspection dan periodic maintenance tidak bisa di lakukan dalam kondisi energize dan harus 4. Inspect and test vacuum circuit breaker
Internal Inspection & Periodic Maintenance
dalam kondisi shutdown/ 5. Secondary relay test injection
Terjadi unplan breakdown dan catastropic failure 6. Check and verification CT / PT
1. Isolated of power supply and put in rack out position
2. Inspect jointing and re tighten bus bar
Improvement dan upgrade relay protection
Medium voltage 6.3KV switchgear PIR TA 2017 Post Implementation Review Equipment obsoleted 3. Inspect enclosure, power and control cable
917 200-SWGR-011B system di switchgear 6.3KV 0 1 0 0
di SS 200 IOM-REL-003 Pengajuan Job List TA 2022 4. Inspect and test vacuum circuit breaker
Internal Inspection & Periodic Maintenance
5. Secondary relay test injection
6. Check and verification CT / PT
1. Isolated of power supply and put in rack out position
2. Inspect jointing and re tighten bus bar
35kV HV SWITCHGEAR BUS A TO Retrofit relay protection system REF 542 di PIR TA 2017 Post Implementation Review 3. Inspect enclosure, power and control cable
918 800-SWGR-001 0 1 0 0 Part obsoleted
200-XFMR-002A switchgear 6.3KV IOM-REL-003 Pengajuan Job List TA 2022 4. Inspect and test vacuum circuit breaker
5. Secondary relay test injection
6. Check and verification CT / PT
1. Isolated of power supply and put in rack out position
2. Inspect jointing and re tighten bus bar
35kV HV SWITCHGEAR BUS A TO Periodic maintenance, inspection MW SWGR 3. Inspect enclosure, power and control cable
919 800-SWGR-001A IOM-REL-003 Pengajuan Job List TA 2022 Periodic maintenance and inspection
200-XFMR-002A & retrofit relay protection 4. Inspect and test vacuum circuit breaker
5. Secondary relay test injection
6. Check and verification CT / PT
1. Isolated of power supply and put in rack out position
2. Inspect jointing and re tighten bus bar
35kV HV SWITCHGEAR BUS A TO Periodic maintenance, inspection MW SWGR 3. Inspect enclosure, power and control cable
920 800-SWGR-001B IOM-REL-003 Pengajuan Job List TA 2022 Periodic maintenance and inspection
200-XFMR-002B & retrofit relay protection 4. Inspect and test vacuum circuit breaker
5. Secondary relay test injection
6. Check and verification CT / PT
1. Isolated of power supply and put in rack out position
2. Inspect jointing and re tighten bus bar
Medium voltage 6.3KV switchgear Retrofit relay protection system REF 542 di PIR TA 2017 Post Implementation Review 3. Inspect enclosure, power and control cable
922 800-SWGR-011A 0 1 0 0 Part obsoleted
di SS 800 switchgear 6.3KV IOM-REL-003 Pengajuan Job List TA 2022 4. Inspect and test vacuum circuit breaker
5. Secondary relay test injection
6. Check and verification CT / PT
1. Isolated of power supply and put in rack out position
2. Inspect jointing and re tighten bus bar
Medium voltage 6.3KV switchgear Retrofit relay protection system REF 542 di PIR TA 2017 Post Implementation Review 3. Inspect enclosure, power and control cable
923 800-SWGR-011B 0 1 0 0 Part obsoleted
di SS 800 switchgear 6.3KV IOM-REL-003 Pengajuan Job List TA 2022 4. Inspect and test vacuum circuit breaker
5. Secondary relay test injection
6. Check and verification CT / PT
1. Isolated of power supply and put in rack out position
2. Inspect jointing and re tighten bus bar
Periodic maintenance, inspection MW SWGR 3. Inspect enclosure, power and control cable
924 860-SWGR-011 6.3kV MV SWITCHGEAR BUS VT SS-860 IOM-REL-003 Pengajuan Job List TA 2022 Periodic maintenance and inspection
& retrofit relay protection 4. Inspect and test vacuum circuit breaker
5. Secondary relay test injection
6. Check and verification CT / PT
1. Isolated of power supply and put in rack out position
2. Inspect jointing and re tighten bus bar
Medium voltage 6.3KV switchgear PIR TA 2017 Post Implementation Review Inspection dan periodic maintenance tidak bisa di lakukan dalam kondisi energize dan harus 3. Inspect enclosure, power and control cable
925 860-SWGR-011A Internal inspection and periodic maintenance 0 1 0 0
di SS 860 IOM-REL-003 Pengajuan Job List TA 2022 dalam kondisi shutdown/Terjadi unplan breakdown dan catastropic failure 4. Inspect and test vacuum circuit breaker
5. Secondary relay test injection
6. Check and verification CT / PT
1. Isolated of power supply and put in rack out position
2. Inspect jointing and re tighten bus bar
Medium voltage 6.3KV switchgear PIR TA 2017 Post Implementation Review Inspection dan periodic maintenance tidak bisa di lakukan dalam kondisi energize dan harus 3. Inspect enclosure, power and control cable
926 860-SWGR-011B Internal inspection and periodic maintenance 0 1 0 0
di SS 860 IOM-REL-003 Pengajuan Job List TA 2022 dalam kondisi shutdown/Terjadi unplan breakdown dan catastropic failure 4. Inspect and test vacuum circuit breaker
5. Secondary relay test injection
6. Check and verification CT / PT
1. Isolated of power supply and put in rack out position
2. Inspect jointing and re tighten bus bar
Medium voltage 6.3KV switchgear PIR TA 2017 Post Implementation Review Inspection dan periodic maintenance tidak bisa di lakukan dalam kondisi energize dan harus 3. Inspect enclosure, power and control cable
927 900-SWGR-011 Internal inspection and periodic maintenance 0 1 0 0
di SS 900 IOM-REL-003 Pengajuan Job List TA 2022 dalam kondisi shutdown/Terjadi unplan breakdown dan catastropic failure 4. Inspect and test vacuum circuit breaker
5. Secondary relay test injection
6. Check and verification CT / PT
1. Isolated of power supply and put in rack out position
2. Inspect jointing and re tighten bus bar
Inspection dan periodic maintenance tidak bisa di lakukan dalam kondisi energize dan harus
3. Inspect enclosure, power and control cable
928 900A-SWGR-011 Medium voltage 6.3KV switchgear di SS 900A inspection and periodic maintenance
Internal x IOM-REL-003 Pengajuan Job List TA 2022 dalam kondisi shutdown
4. Inspect and test vacuum circuit breaker
Terjadi unplan breakdown dan catastropic failure
5. Secondary relay test injection
6. Check and verification CT / PT
1. Isolated of power supply and put in rack out position
2. Inspect jointing and re tighten bus bar
Medium voltage 6.3KV switchgear PIR TA 2017 Post Implementation Review Inspection dan periodic maintenance tidak bisa di lakukan dalam kondisi energize dan harus 3. Inspect enclosure, power and control cable
929 980-SWGR-011 Internal inspection and periodic maintenance 0 1 0 0
di SS 980 IOM-REL-003 Pengajuan Job List TA 2022 dalam kondisi shutdown/Terjadi unplan breakdown dan catastropic failure 4. Inspect and test vacuum circuit breaker
5. Secondary relay test injection
6. Check and verification CT / PT
1. Isolated of power supply and put in rack out position
2. Inspect jointing and re tighten bus bar
3. Inspect enclosure, power and control cable
930 980-SWGR-011A 6.3kV MV SWITCHGEAR BUS VT SS-809
Periodic maintenance, inspection MW SWGR IOM-REL-003 Pengajuan Job List TA 2022 Periodic maintenance and inspection
4. Inspect and test vacuum circuit breaker
5. Secondary relay test injection
6. Check and verification CT / PT
1. Isolated of power supply and put in rack out position
2. Inspect jointing and re tighten bus bar
3. Inspect enclosure, power and control cable
931 980-SWGR-011B 6.3kV MV SWITCHGEAR BUS VT SS-809
Periodic maintenance, inspection MW SWGR IOM-REL-003 Pengajuan Job List TA 2022 Periodic maintenance and inspection
4. Inspect and test vacuum circuit breaker
5. Secondary relay test injection
6. Check and verification CT / PT
1. Isolated of power supply and put in rack out position
2. Inspect jointing and re tighten bus bar
3. Inspect enclosure, power and control cable
PIR TA 2017 Post Implementation Review Inspection dan periodic maintenance tidak bisa di lakukan dalam kondisi energize dan harus
932 200-MCC-101 Low voltage 0.4KV MCC di SS 200 Internal inspection and periodic maintenance 0 1 0 0 4. Inspect and test air circuit breaker
IOM-REL-003 Pengajuan Job List TA 2022 dalam kondisi shutdown/ Terjadi unplan breakdown dan catastropic failure
5. Inspect and test MCCB and main contactor
6. Verification thermal over load relay
7. Check and verification CT / PT
1. Isolated of power supply and put in rack out position
2. Inspect jointing and re tighten bus bar
3. Inspect enclosure, power and control cable
PIR TA 2017 Post Implementation Review Inspection dan periodic maintenance tidak bisa di lakukan dalam kondisi energize dan harus
933 200-MCC-101A Low voltage 0.4KV MCC di SS 200 Internal inspection and periodic maintenance 0 1 0 0 4. Inspect and test air circuit breaker
IOM-REL-003 Pengajuan Job List TA 2022 dalam kondisi shutdown/ Terjadi unplan breakdown dan catastropic failure
5. Inspect and test MCCB and main contactor
6. Verification thermal over load relay
7. Check and verification CT / PT
1. Isolated of power supply and put in rack out position
2. Inspect jointing and re tighten bus bar
3. Inspect enclosure, power and control cable
PIR TA 2017 Post Implementation Review Inspection dan periodic maintenance tidak bisa di lakukan dalam kondisi energize dan harus
934 200-MCC-101B Low voltage 0.4KV MCC di SS 200 Internal inspection and periodic maintenance 0 1 0 0 4. Inspect and test air circuit breaker
IOM-REL-003 Pengajuan Job List TA 2022 dalam kondisi shutdown/ Terjadi unplan breakdown dan catastropic failure
5. Inspect and test MCCB and main contactor
6. Verification thermal over load relay
7. Check and verification CT / PT
1. Isolated of power supply and put in rack out position
2. Inspect jointing and re tighten bus bar
3. Inspect enclosure, power and control cable
PIR TA 2017 Post Implementation Review Inspection dan periodic maintenance tidak bisa di lakukan dalam kondisi energize dan harus
935 200-MCC-102 Low voltage 0.4KV MCC di SS 200 Internal inspection and periodic maintenance 0 1 0 0 4. Inspect and test air circuit breaker
IOM-REL-003 Pengajuan Job List TA 2022 dalam kondisi shutdown/ Terjadi unplan breakdown dan catastropic failure
5. Inspect and test MCCB and main contactor
6. Verification thermal over load relay
7. Check and verification CT / PT
1. Isolated of power supply and put in rack out position
2. Inspect jointing and re tighten bus bar
3. Inspect enclosure, power and control cable
PIR TA 2017 Post Implementation Review Inspection dan periodic maintenance tidak bisa di lakukan dalam kondisi energize dan harus
936 200-MCC-102A Low voltage 0.4KV MCC di SS 200 Internal inspection and periodic maintenance 0 1 0 0 4. Inspect and test air circuit breaker
IOM-REL-003 Pengajuan Job List TA 2022 dalam kondisi shutdown/ Terjadi unplan breakdown dan catastropic failure
5. Inspect and test MCCB and main contactor
6. Verification thermal over load relay
7. Check and verification CT / PT
1. Isolated of power supply and put in rack out position
2. Inspect jointing and re tighten bus bar
3. Inspect enclosure, power and control cable
PIR TA 2017 Post Implementation Review Inspection dan periodic maintenance tidak bisa di lakukan dalam kondisi energize dan harus
937 200-MCC-102B Low voltage 0.4KV MCC di SS 200 Internal inspection and periodic maintenance 0 1 0 0 4. Inspect and test air circuit breaker
IOM-REL-003 Pengajuan Job List TA 2022 dalam kondisi shutdown/ Terjadi unplan breakdown dan catastropic failure
5. Inspect and test MCCB and main contactor
6. Verification thermal over load relay
7. Check and verification CT / PT
1. Isolated of power supply and put in rack out position
2. Inspect jointing and re tighten bus bar
3. Inspect enclosure, power and control cable
PIR TA 2017 Post Implementation Review Inspection dan periodic maintenance tidak bisa di lakukan dalam kondisi energize dan harus
938 200-MCC-103 Low voltage 0.4KV MCC di SS 200 Internal inspection and periodic maintenance 0 1 0 0 4. Inspect and test air circuit breaker
IOM-REL-003 Pengajuan Job List TA 2022 dalam kondisi shutdown/ Terjadi unplan breakdown dan catastropic failure
5. Inspect and test MCCB and main contactor
6. Verification thermal over load relay
7. Check and verification CT / PT
1. Isolated of power supply and put in rack out position
2. Inspect jointing and re tighten bus bar
3. Inspect enclosure, power and control cable
PIR TA 2017 Post Implementation Review Inspection dan periodic maintenance tidak bisa di lakukan dalam kondisi energize dan harus
939 200-MCC-103A Low voltage 0.4KV MCC di SS 200 Internal inspection and periodic maintenance 0 1 0 0 4. Inspect and test air circuit breaker
IOM-REL-003 Pengajuan Job List TA 2022 dalam kondisi shutdown/ Terjadi unplan breakdown dan catastropic failure
5. Inspect and test MCCB and main contactor
6. Verification thermal over load relay
7. Check and verification CT / PT

Finalisasi Job List TA-23 rev4 230518 1 OF 19


JOB LIST T/A TH. 2023 REV.4
JOB LIST TA-22 KILANG PT.TPPI TUBAN
PT. Trans Pasific Petrochemical Indotama
Turnaround - Relita Department
CRETERIA REFERENCE
NO. EQUIPMENT NO. SERVICE JOB LIST RECOMMENDATION-INSP/REL/PE REASON MAIN JOB TA-22
PI MI INSP OPT
NO. DESCRIPTION
1. Isolated of power supply and put in rack out position
2. Inspect jointing and re tighten bus bar
3. Inspect enclosure, power and control cable
PIR TA 2017 Post Implementation Review Inspection dan periodic maintenance tidak bisa di lakukan dalam kondisi energize dan harus
940 200-MCC-103B Low voltage 0.4KV MCC di SS 200 Internal inspection and periodic maintenance 0 1 0 0 4. Inspect and test air circuit breaker
IOM-REL-003 Pengajuan Job List TA 2022 dalam kondisi shutdown/ Terjadi unplan breakdown dan catastropic failure
5. Inspect and test MCCB and main contactor
6. Verification thermal over load relay
7. Check and verification CT / PT
1. Isolated of power supply and put in rack out position
2. Inspect jointing and re tighten bus bar
3. Inspect enclosure, power and control cable
PIR TA 2017 Post Implementation Review Inspection dan periodic maintenance tidak bisa di lakukan dalam kondisi energize dan harus
941 200-MCC-104 Low voltage 0.4KV MCC di SS 200 Internal inspection and periodic maintenance 0 1 0 0 4. Inspect and test air circuit breaker
IOM-REL-003 Pengajuan Job List TA 2022 dalam kondisi shutdown/ Terjadi unplan breakdown dan catastropic failure
5. Inspect and test MCCB and main contactor
6. Verification thermal over load relay
7. Check and verification CT / PT
1. Isolated of power supply and put in rack out position
2. Inspect jointing and re tighten bus bar
3. Inspect enclosure, power and control cable
PIR TA 2017 Post Implementation Review Inspection dan periodic maintenance tidak bisa di lakukan dalam kondisi energize dan harus
942 200-MCC-104A Low voltage 0.4KV MCC di SS 200 Internal inspection and periodic maintenance 0 1 0 0 4. Inspect and test air circuit breaker
IOM-REL-003 Pengajuan Job List TA 2022 dalam kondisi shutdown/ Terjadi unplan breakdown dan catastropic failure
5. Inspect and test MCCB and main contactor
6. Verification thermal over load relay
7. Check and verification CT / PT
1. Isolated of power supply and put in rack out position
2. Inspect jointing and re tighten bus bar
3. Inspect enclosure, power and control cable
PIR TA 2017 Post Implementation Review Inspection dan periodic maintenance tidak bisa di lakukan dalam kondisi energize dan harus
943 200-MCC-104B Low voltage 0.4KV MCC di SS 200 Internal inspection and periodic maintenance 0 1 0 0 4. Inspect and test air circuit breaker
IOM-REL-003 Pengajuan Job List TA 2022 dalam kondisi shutdown/ Terjadi unplan breakdown dan catastropic failure
5. Inspect and test MCCB and main contactor
6. Verification thermal over load relay
7. Check and verification CT / PT
1. Isolated of power supply and put in rack out position
2. Inspect jointing and re tighten bus bar
3. Inspect enclosure, power and control cable
PIR TA 2017 Post Implementation Review Inspection dan periodic maintenance tidak bisa di lakukan dalam kondisi energize dan harus
944 200-MCC-105 Low voltage 0.4KV MCC di SS 200 Internal inspection and periodic maintenance 0 1 0 0 4. Inspect and test air circuit breaker
IOM-REL-003 Pengajuan Job List TA 2022 dalam kondisi shutdown/ Terjadi unplan breakdown dan catastropic failure
5. Inspect and test MCCB and main contactor
6. Verification thermal over load relay
7. Check and verification CT / PT
1. Isolated of power supply and put in rack out position
2. Inspect jointing and re tighten bus bar
3. Inspect enclosure, power and control cable
PIR TA 2017 Post Implementation Review Inspection dan periodic maintenance tidak bisa di lakukan dalam kondisi energize dan harus
945 200-MCC-105A Low voltage 0.4KV MCC di SS 200 Internal inspection and periodic maintenance 0 1 0 0 4. Inspect and test air circuit breaker
IOM-REL-003 Pengajuan Job List TA 2022 dalam kondisi shutdown/ Terjadi unplan breakdown dan catastropic failure
5. Inspect and test MCCB and main contactor
6. Verification thermal over load relay
7. Check and verification CT / PT
1. Isolated of power supply and put in rack out position
2. Inspect jointing and re tighten bus bar
3. Inspect enclosure, power and control cable
PIR TA 2017 Post Implementation Review Inspection dan periodic maintenance tidak bisa di lakukan dalam kondisi energize dan harus
946 200-MCC-105B Low voltage 0.4KV MCC di SS 200 Internal inspection and periodic maintenance 0 1 0 0 4. Inspect and test air circuit breaker
IOM-REL-003 Pengajuan Job List TA 2022 dalam kondisi shutdown/ Terjadi unplan breakdown dan catastropic failure
5. Inspect and test MCCB and main contactor
6. Verification thermal over load relay
7. Check and verification CT / PT
1. Isolated of power supply and put in rack out position
2. Inspect jointing and re tighten bus bar
3. Inspect enclosure, power and control cable
PIR TA 2017 Post Implementation Review Inspection dan periodic maintenance tidak bisa di lakukan dalam kondisi energize dan harus
947 200-MCC-106 Low voltage 0.4KV MCC di SS 200 Internal inspection and periodic maintenance 0 1 0 0 4. Inspect and test air circuit breaker
IOM-REL-003 Pengajuan Job List TA 2022 dalam kondisi shutdown/ Terjadi unplan breakdown dan catastropic failure
5. Inspect and test MCCB and main contactor
6. Verification thermal over load relay
7. Check and verification CT / PT
1. Isolated of power supply and put in rack out position
2. Inspect jointing and re tighten bus bar
3. Inspect enclosure, power and control cable
PIR TA 2017 Post Implementation Review Inspection dan periodic maintenance tidak bisa di lakukan dalam kondisi energize dan harus
948 200-MCC-106A Low voltage 0.4KV MCC di SS 200 Internal inspection and periodic maintenance 0 1 0 0 4. Inspect and test air circuit breaker
IOM-REL-003 Pengajuan Job List TA 2022 dalam kondisi shutdown/ Terjadi unplan breakdown dan catastropic failure
5. Inspect and test MCCB and main contactor
6. Verification thermal over load relay
7. Check and verification CT / PT
1. Isolated of power supply and put in rack out position
2. Inspect jointing and re tighten bus bar
3. Inspect enclosure, power and control cable
PIR TA 2017 Post Implementation Review Inspection dan periodic maintenance tidak bisa di lakukan dalam kondisi energize dan harus
949 200-MCC-106B Low voltage 0.4KV MCC di SS 200 Internal inspection and periodic maintenance 0 1 0 0 4. Inspect and test air circuit breaker
IOM-REL-003 Pengajuan Job List TA 2022 dalam kondisi shutdown/ Terjadi unplan breakdown dan catastropic failure
5. Inspect and test MCCB and main contactor
6. Verification thermal over load relay
7. Check and verification CT / PT
1. Isolated of power supply and put in rack out position
2. Inspect jointing and re tighten bus bar
3. Inspect enclosure, power and control cable
PIR TA 2017 Post Implementation Review Inspection dan periodic maintenance tidak bisa di lakukan dalam kondisi energize dan harus
950 200-MCC-107 Low voltage 0.4KV MCC di SS 200 Internal inspection and periodic maintenance 0 1 0 0 4. Inspect and test air circuit breaker
IOM-REL-003 Pengajuan Job List TA 2022 dalam kondisi shutdown/ Terjadi unplan breakdown dan catastropic failure
5. Inspect and test MCCB and main contactor
6. Verification thermal over load relay
7. Check and verification CT / PT
1. Isolated of power supply and put in rack out position
2. Inspect jointing and re tighten bus bar
3. Inspect enclosure, power and control cable
PIR TA 2017 Post Implementation Review Inspection dan periodic maintenance tidak bisa di lakukan dalam kondisi energize dan harus
951 200-MCC-107A Low voltage 0.4KV MCC di SS 200 Internal inspection and periodic maintenance 0 1 0 0 4. Inspect and test air circuit breaker
IOM-REL-003 Pengajuan Job List TA 2022 dalam kondisi shutdown/ Terjadi unplan breakdown dan catastropic failure
5. Inspect and test MCCB and main contactor
6. Verification thermal over load relay
7. Check and verification CT / PT
1. Isolated of power supply and put in rack out position
2. Inspect jointing and re tighten bus bar
3. Inspect enclosure, power and control cable
PIR TA 2017 Post Implementation Review Inspection dan periodic maintenance tidak bisa di lakukan dalam kondisi energize dan harus
952 200-MCC-107B Low voltage 0.4KV MCC di SS 200 Internal inspection and periodic maintenance 0 1 0 0 4. Inspect and test air circuit breaker
IOM-REL-003 Pengajuan Job List TA 2022 dalam kondisi shutdown/ Terjadi unplan breakdown dan catastropic failure
5. Inspect and test MCCB and main contactor
6. Verification thermal over load relay
7. Check and verification CT / PT
1. Isolated of power supply and put in rack out position
2. Inspect jointing and re tighten bus bar
3. Inspect enclosure, power and control cable
953 800-MCC-101 NORMAL LV MCC 420V BUS TIE SS-800Periodic maintenance and inspection LV MCC x IOM-REL-003 Pengajuan Job List TA 2022 Periodic maintenance and inspection LV MCC 4. Inspect and test air circuit breaker
5. Inspect and test MCCB and main contactor
6. Verification thermal over load relay
7. Check and verification CT / PT
1. Isolated of power supply and put in rack out position
2. Inspect jointing and re tighten bus bar
3. Inspect enclosure, power and control cable
PIR TA 2017 Post Implementation Review Inspection dan periodic maintenance tidak bisa di lakukan dalam kondisi energize dan harus
954 800-MCC-101A Low voltage 0.4KV MCC di SS 800 Internal inspection and periodic maintenance 0 1 0 0 4. Inspect and test air circuit breaker
IOM-REL-003 Pengajuan Job List TA 2022 dalam kondisi shutdown/ Terjadi unplan breakdown dan catastropic failure
5. Inspect and test MCCB and main contactor
6. Verification thermal over load relay
7. Check and verification CT / PT
1. Isolated of power supply and put in rack out position
2. Inspect jointing and re tighten bus bar
3. Inspect enclosure, power and control cable
PIR TA 2017 Post Implementation Review Inspection dan periodic maintenance tidak bisa di lakukan dalam kondisi energize dan harus
955 800-MCC-101B Low voltage 0.4KV MCC di SS 800 Internal inspection and periodic maintenance 0 1 0 0 4. Inspect and test air circuit breaker
IOM-REL-003 Pengajuan Job List TA 2022 dalam kondisi shutdown/ Terjadi unplan breakdown dan catastropic failure
5. Inspect and test MCCB and main contactor
6. Verification thermal over load relay
7. Check and verification CT / PT
1. Isolated of power supply and put in rack out position
2. Inspect jointing and re tighten bus bar
3. Inspect enclosure, power and control cable
956 840-MCC-101 NORMAL LV MCC 420V BUS TIE SS-840Periodic maintenance and inspection LV MCC x IOM-REL-003 Pengajuan Job List TA 2022 Periodic maintenance and inspection LV MCC 4. Inspect and test air circuit breaker
5. Inspect and test MCCB and main contactor
6. Verification thermal over load relay
7. Check and verification CT / PT
1. Isolated of power supply and put in rack out position
2. Inspect jointing and re tighten bus bar
3. Inspect enclosure, power and control cable
PIR TA 2017 Post Implementation Review Inspection dan periodic maintenance tidak bisa di lakukan dalam kondisi energize dan harus
957 840-MCC-101A Low voltage 0.4KV MCC di SS 840 Internal inspection and periodic maintenance 0 1 0 0 4. Inspect and test air circuit breaker
IOM-REL-003 Pengajuan Job List TA 2022 dalam kondisi shutdown/ Terjadi unplan breakdown dan catastropic failure
5. Inspect and test MCCB and main contactor
6. Verification thermal over load relay
7. Check and verification CT / PT
1. Isolated of power supply and put in rack out position
2. Inspect jointing and re tighten bus bar
3. Inspect enclosure, power and control cable
PIR TA 2017 Post Implementation Review Inspection dan periodic maintenance tidak bisa di lakukan dalam kondisi energize dan harus
958 840-MCC-101B Low voltage 0.4KV MCC di SS 840 Internal inspection and periodic maintenance 0 1 0 0 4. Inspect and test air circuit breaker
IOM-REL-003 Pengajuan Job List TA 2022 dalam kondisi shutdown/ Terjadi unplan breakdown dan catastropic failure
5. Inspect and test MCCB and main contactor
6. Verification thermal over load relay
7. Check and verification CT / PT
1. Isolated of power supply and put in rack out position
2. Inspect jointing and re tighten bus bar
3. Inspect enclosure, power and control cable
959 860-MCC-101 NORMAL LV MCC 420V BUS TIE SS-860Periodic maintenance and inspection LV MCC x IOM-REL-003 Pengajuan Job List TA 2022 Periodic maintenance and inspection LV MCC 4. Inspect and test air circuit breaker
5. Inspect and test MCCB and main contactor
6. Verification thermal over load relay
7. Check and verification CT / PT
1. Isolated of power supply and put in rack out position
2. Inspect jointing and re tighten bus bar
3. Inspect enclosure, power and control cable
PIR TA 2017 Post Implementation Review Inspection dan periodic maintenance tidak bisa di lakukan dalam kondisi energize dan harus
960 860-MCC-101A Low voltage 0.4KV MCC di SS 860 Internal inspection and periodic maintenance 0 1 0 0 4. Inspect and test air circuit breaker
IOM-REL-003 Pengajuan Job List TA 2022 dalam kondisi shutdown/ Terjadi unplan breakdown dan catastropic failure
5. Inspect and test MCCB and main contactor
6. Verification thermal over load relay
7. Check and verification CT / PT
1. Isolated of power supply and put in rack out position
2. Inspect jointing and re tighten bus bar
3. Inspect enclosure, power and control cable
PIR TA 2017 Post Implementation Review Inspection dan periodic maintenance tidak bisa di lakukan dalam kondisi energize dan harus
961 860-MCC-101B Low voltage 0.4KV MCC di SS 860 Internal inspection and periodic maintenance 0 1 0 0 4. Inspect and test air circuit breaker
IOM-REL-003 Pengajuan Job List TA 2022 dalam kondisi shutdown/ Terjadi unplan breakdown dan catastropic failure
5. Inspect and test MCCB and main contactor
6. Verification thermal over load relay
7. Check and verification CT / PT
1. Isolated of power supply and put in rack out position
2. Inspect jointing and re tighten bus bar
3. Inspect enclosure, power and control cable
962 900A-MCC-101 NORMAL LV MCC 420V BUS TIE SS-900A
Periodic maintenance and inspection LV MCC x IOM-REL-003 Pengajuan Job List TA 2022 Periodic maintenance and inspection LV MCC 4. Inspect and test air circuit breaker
5. Inspect and test MCCB and main contactor
6. Verification thermal over load relay
7. Check and verification CT / PT

Finalisasi Job List TA-23 rev4 230518 2 OF 19


JOB LIST T/A TH. 2023 REV.4
JOB LIST TA-22 KILANG PT.TPPI TUBAN
PT. Trans Pasific Petrochemical Indotama
Turnaround - Relita Department
CRETERIA REFERENCE
NO. EQUIPMENT NO. SERVICE JOB LIST RECOMMENDATION-INSP/REL/PE REASON MAIN JOB TA-22
PI MI INSP OPT
NO. DESCRIPTION
1. Isolated of power supply and put in rack out position
2. Inspect jointing and re tighten bus bar
3. Inspect enclosure, power and control cable
PIR TA 2017 Post Implementation Review Inspection dan periodic maintenance tidak bisa di lakukan dalam kondisi energize dan harus
963 900A-MCC-101A Low voltage 0.4KV MCC di SS 900A Internal inspection and periodic maintenance 0 1 0 0 4. Inspect and test air circuit breaker
IOM-REL-003 Pengajuan Job List TA 2022 dalam kondisi shutdown/ Terjadi unplan breakdown dan catastropic failure
5. Inspect and test MCCB and main contactor
6. Verification thermal over load relay
7. Check and verification CT / PT
1. Isolated of power supply and put in rack out position
2. Inspect jointing and re tighten bus bar
3. Inspect enclosure, power and control cable
PIR TA 2017 Post Implementation Review Inspection dan periodic maintenance tidak bisa di lakukan dalam kondisi energize dan harus
964 900A-MCC-101B Low voltage 0.4KV MCC di SS 900A Internal inspection and periodic maintenance 0 1 0 0 4. Inspect and test air circuit breaker
IOM-REL-003 Pengajuan Job List TA 2022 dalam kondisi shutdown/ Terjadi unplan breakdown dan catastropic failure
5. Inspect and test MCCB and main contactor
6. Verification thermal over load relay
7. Check and verification CT / PT
1. Isolated of power supply and put in rack out position
2. Inspect jointing and re tighten bus bar
3. Inspect enclosure, power and control cable
965 900-MCC-101 NORMAL LV MCC 420V BUS TIE SS-900Periodic maintenance and inspection LV MCC x IOM-REL-003 Pengajuan Job List TA 2022 Periodic maintenance and inspection LV MCC 4. Inspect and test air circuit breaker
5. Inspect and test MCCB and main contactor
6. Verification thermal over load relay
7. Check and verification CT / PT
1. Isolated of power supply and put in rack out position
2. Inspect jointing and re tighten bus bar
3. Inspect enclosure, power and control cable
PIR TA 2017 Post Implementation Review Inspection dan periodic maintenance tidak bisa di lakukan dalam kondisi energize dan harus
966 900-MCC-101A Low voltage 0.4KV MCC di SS 900 Internal inspection and periodic maintenance 0 1 0 0 4. Inspect and test air circuit breaker
IOM-REL-003 Pengajuan Job List TA 2022 dalam kondisi shutdown/ Terjadi unplan breakdown dan catastropic failure
5. Inspect and test MCCB and main contactor
6. Verification thermal over load relay
7. Check and verification CT / PT
1. Isolated of power supply and put in rack out position
2. Inspect jointing and re tighten bus bar
3. Inspect enclosure, power and control cable
PIR TA 2017 Post Implementation Review Inspection dan periodic maintenance tidak bisa di lakukan dalam kondisi energize dan harus
967 900-MCC-101B Low voltage 0.4KV MCC di SS 900 Internal inspection and periodic maintenance 0 1 0 0 4. Inspect and test air circuit breaker
IOM-REL-003 Pengajuan Job List TA 2022 dalam kondisi shutdown/ Terjadi unplan breakdown dan catastropic failure
5. Inspect and test MCCB and main contactor
6. Verification thermal over load relay
7. Check and verification CT / PT
1. Isolated of power supply and put in rack out position
2. Inspect jointing and re tighten bus bar
3. Inspect enclosure, power and control cable
PIR TA 2017 Post Implementation Review Inspection dan periodic maintenance tidak bisa di lakukan dalam kondisi energize dan harus
968 980-MCC-101 Low voltage 0.4KV MCC di SS 980 Internal inspection and periodic maintenance 0 1 0 0 4. Inspect and test air circuit breaker
IOM-REL-003 Pengajuan Job List TA 2022 dalam kondisi shutdown/ Terjadi unplan breakdown dan catastropic failure
5. Inspect and test MCCB and main contactor
6. Verification thermal over load relay
7. Check and verification CT / PT
1. Isolated of power supply and put in rack out position
2. Inspect jointing and re tighten bus bar
3. Inspect enclosure, power and control cable
969 700-MCC-101 NORMAL LV MCC 420V SS-700 Periodic maintenance and inspection LV MCC x IOM-REL-003 Pengajuan Job List TA 2022 Periodic maintenance and inspection LV MCC 4. Inspect and test air circuit breaker
5. Inspect and test MCCB and main contactor
6. Verification thermal over load relay
7. Check and verification CT / PT
1. Isolated of power supply and put in rack out position
2. Inspect jointing and re tighten bus bar
3. Inspect enclosure, power and control cable
970 200-MCC-12A 6.3kV MV MCC (5300KW) BUS A SS-200
Periodic maintenance and inspection MV MCC x IOM-REL-003 Pengajuan Job List TA 2022 Periodic maintenance and inspection MV MCC 4. Inspect and test air circuit breaker
5. Inspect and test MCCB and main contactor
6. Verification thermal over load relay
7. Check and verification CT / PT
1. Isolated of power supply and put in rack out position
2. Inspect jointing and re tighten bus bar
3. Inspect enclosure, power and control cable
971 200-MCC-12B 6.3kV MV MCC (5300KW) BUS A SS-200
Periodic maintenance and inspection MV MCC x IOM-REL-003 Pengajuan Job List TA 2022 Periodic maintenance and inspection MV MCC 4. Inspect and test air circuit breaker
5. Inspect and test MCCB and main contactor
6. Verification thermal over load relay
7. Check and verification CT / PT
1. Isolated of power supply and put in rack out position
2. Inspect jointing and re tighten bus bar
3. Inspect enclosure, power and control cable
972 200-MCC-11A 6.3kV MV MCC BUS A SS-200 Periodic maintenance and inspection MV MCC x IOM-REL-003 Pengajuan Job List TA 2022 Periodic maintenance and inspection MV MCC 4. Inspect and test air circuit breaker
5. Inspect and test MCCB and main contactor
6. Verification thermal over load relay
7. Check and verification CT / PT
1. Isolated of power supply and put in rack out position
2. Inspect jointing and re tighten bus bar
3. Inspect enclosure, power and control cable
973 200-MCC-11B 6.3kV MV MCC BUS A SS-200 Periodic maintenance and inspection MV MCC x IOM-REL-003 Pengajuan Job List TA 2022 Periodic maintenance and inspection MV MCC 4. Inspect and test air circuit breaker
5. Inspect and test MCCB and main contactor
6. Verification thermal over load relay
7. Check and verification CT / PT
1. Isolated of power supply and put in rack out position
2. Oil purifying and oil testing (DGA, BDV, water
Finding oil leak akibat gasket sudah jenuh dan bushing trafo, di perlukan drain oil main tank
content and etc.)
Overhaul Trafo include Replace gasket and dan Pergantian gasket serta bushing trafo
974 200-XFMR-001A HV Transformer 36/6.3 KV x IOM-REL-003 Pengajuan Job List TA 2022 3. Inspect and testing (Tan delta, index polarity, ratio
bushing (oil leak) Dielectric strength turun dan protection bucholz relay active, Terjadi breakdown dan
test, winding resistant test and etc.)
catastropic failure, Loss of power di area proses ISBL
4. Inspect and tighten all connection
5. Check and function protection device
1. Isolated of power supply and put in rack out position
2. Oil purifying and oil testing (DGA, BDV, water
Finding oil leak akibat gasket sudah jenuh dan bushing trafo, di perlukan drain oil main tank
content and etc.)
Overhaul Trafo include Replace gasket and dan Pergantian gasket serta bushing trafo
975 200-XFMR-001B HV Transformer 36/6.3 KV x IOM-REL-003 Pengajuan Job List TA 2022 3. Inspect and testing (Tan delta, index polarity, ratio
bushing (oil leak) Dielectric strength turun dan protection bucholz relay active, Terjadi breakdown dan
test, winding resistant test and etc.)
catastropic failure, Loss of power di area proses ISBL
4. Inspect and tighten all connection
5. Check and function protection device
1. Isolated of power supply and put in rack out position
2. Oil purifying and oil testing (DGA, BDV, water
Finding oil leak akibat gasket sudah jenuh dan bushing trafo, di perlukan drain oil main tank
content and etc.)
Overhaul Trafo Replace gasket and bushing (oil dan Pergantian gasket serta bushing trafo
976 200-XFMR-002A HV Transformer 36/6.3 KV x IOM-REL-003 Pengajuan Job List TA 2022 3. Inspect and testing (Tan delta, index polarity, ratio
leak) Dielectric strength turun dan protection bucholz relay active, Terjadi breakdown dan
test, winding resistant test and etc.)
catastropic failure, Loss of power di area proses ISBL
4. Inspect and tighten all connection
5. Check and function protection device
1. Isolated of power supply and put in rack out position
2. Oil purifying and oil testing (DGA, BDV, water
Finding oil leak akibat gasket sudah jenuh dan bushing trafo, di perlukan drain oil main tank
content and etc.)
Overhaul Trafo Replace gasket and bushing (oil dan Pergantian gasket serta bushing trafo
977 200-XFMR-002B HV Transformer 36/6.3 KV x IOM-REL-003 Pengajuan Job List TA 2022 3. Inspect and testing (Tan delta, index polarity, ratio
leak) Dielectric strength turun dan protection bucholz relay active, Terjadi breakdown dan
test, winding resistant test and etc.)
catastropic failure, Loss of power di area proses ISBL
4. Inspect and tighten all connection
5. Check and function protection device
1. Isolated of power supply and put in rack out position
2. Oil purifying and oil testing (DGA, BDV, water
content and etc.)
HV TRANSFORMER 11 - 35kV AT Overhaul, periodic maintenance and N1+0
978 800-XFMR-001A IOM-REL-003 Pengajuan Job List TA 2022 3. Inspect and testing (Tan delta, index polarity, ratio
CTG-101 inspection HV Transformer Periodic Maintenance
test, winding resistant test and etc.)
4. Inspect and tighten all connection
5. Check and function protection device
1. Isolated of power supply and put in rack out position
2. Oil purifying and oil testing (DGA, BDV, water
content and etc.)
HV TRANSFORMER 11 - 35kV AT Overhaul, periodic maintenance and N1+0
979 800-XFMR-001B IOM-REL-003 Pengajuan Job List TA 2022 3. Inspect and testing (Tan delta, index polarity, ratio
CTG-102 inspection HV Transformer Periodic Maintenance
test, winding resistant test and etc.)
4. Inspect and tighten all connection
5. Check and function protection device
1. Isolated of power supply and put in rack out position
2. Oil purifying and oil testing (DGA, BDV, water
content and etc.)
HV TRANSFORMER 11 - 35kV AT Overhaul, periodic maintenance and N1+0
980 800-XFMR-001C IOM-REL-003 Pengajuan Job List TA 2022 3. Inspect and testing (Tan delta, index polarity, ratio
CTG-103 inspection HV Transformer Periodic Maintenance
test, winding resistant test and etc.)
4. Inspect and tighten all connection
5. Check and function protection device
1. Isolated of power supply and put in rack out position
2. Oil purifying and oil testing (DGA, BDV, water
content and etc.)
HV TRANSFORMER B 35 - 6.3kV AT Overhaul, periodic maintenance and N2+0
981 800-XFMR-002A IOM-REL-003 Pengajuan Job List TA 2022 3. Inspect and testing (Tan delta, index polarity, ratio
SS-800 inspection HV Transformer Periodic Maintenance
test, winding resistant test and etc.)
4. Inspect and tighten all connection
5. Check and function protection device
1. Isolated of power supply and put in rack out position
2. Oil purifying and oil testing (DGA, BDV, water
content and etc.)
HV TRANSFORMER B 35 - 6.3kV AT Overhaul, periodic maintenance and N2+0
982 800-XFMR-002B IOM-REL-003 Pengajuan Job List TA 2022 3. Inspect and testing (Tan delta, index polarity, ratio
SS-800 inspection HV Transformer Periodic Maintenance
test, winding resistant test and etc.)
4. Inspect and tighten all connection
5. Check and function protection device
1. Isolated of power supply and put in rack out position
2. Oil purifying and oil testing (DGA, BDV, water
content and etc.)
HV TRANSFORMER B 35 - 6.3kV AT Overhaul, periodic maintenance and N1+0
983 860-XFMR-001A IOM-REL-003 Pengajuan Job List TA 2022 3. Inspect and testing (Tan delta, index polarity, ratio
SS-800 inspection HV Transformer Periodic Maintenance
test, winding resistant test and etc.)
4. Inspect and tighten all connection
5. Check and function protection device
1. Isolated of power supply and put in rack out position
2. Oil purifying and oil testing (DGA, BDV, water
content and etc.)
HV TRANSFORMER B 35 - 6.3kV AT Overhaul, periodic maintenance and N2+0
984 900-XFMR-002A IOM-REL-003 Pengajuan Job List TA 2022 3. Inspect and testing (Tan delta, index polarity, ratio
SS-800 inspection HV Transformer Periodic Maintenance
test, winding resistant test and etc.)
4. Inspect and tighten all connection
5. Check and function protection device
1. Isolated of power supply and put in rack out position
2. Oil purifying and oil testing (DGA, BDV, water
content and etc.)
HV TRANSFORMER B 35 - 6.3kV AT Overhaul, periodic maintenance and N2+0
985 900-XFMR-002B IOM-REL-003 Pengajuan Job List TA 2022 3. Inspect and testing (Tan delta, index polarity, ratio
SS-800 inspection HV Transformer Periodic Maintenance
test, winding resistant test and etc.)
4. Inspect and tighten all connection
5. Check and function protection device

Finalisasi Job List TA-23 rev4 230518 3 OF 19


JOB LIST T/A TH. 2023 REV.4
JOB LIST TA-22 KILANG PT.TPPI TUBAN
PT. Trans Pasific Petrochemical Indotama
Turnaround - Relita Department
CRETERIA REFERENCE
NO. EQUIPMENT NO. SERVICE JOB LIST RECOMMENDATION-INSP/REL/PE REASON MAIN JOB TA-22
PI MI INSP OPT
NO. DESCRIPTION
1. Isolated of power supply and put in rack out position
2. Oil purifying and oil testing (DGA, BDV, water
content and etc.)
LV TRANSFORMER 6 - 0.42kV FOR Overhaul, periodic maintenance and N2+0
986 200-XFMR-011A IOM-REL-003 Pengajuan Job List TA 2022 3. Inspect and testing (Tan delta, index polarity, ratio
200-MCC-101A inspection LV Transformer Periodic Maintenance
test, winding resistant test and etc.)
4. Inspect and tighten all connection
5. Check and function protection device
1. Isolated of power supply and put in rack out position
2. Oil purifying and oil testing (DGA, BDV, water
content and etc.)
LV TRANSFORMER 6 - 0.42kV FOR Overhaul, periodic maintenance and N2+0
987 200-XFMR-011B IOM-REL-003 Pengajuan Job List TA 2022 3. Inspect and testing (Tan delta, index polarity, ratio
200-MCC-101B inspection LV Transformer Periodic Maintenance
test, winding resistant test and etc.)
4. Inspect and tighten all connection
5. Check and function protection device
1. Isolated of power supply and put in rack out position
2. Oil purifying and oil testing (DGA, BDV, water
content and etc.)
LV TRANSFORMER 6 - 0.42kV FOR Overhaul, periodic maintenance and N2+0
988 200-XFMR-012A IOM-REL-003 Pengajuan Job List TA 2022 3. Inspect and testing (Tan delta, index polarity, ratio
200-MCC-102A inspection LV Transformer Periodic Maintenance
test, winding resistant test and etc.)
4. Inspect and tighten all connection
5. Check and function protection device
1. Isolated of power supply and put in rack out position
2. Oil purifying and oil testing (DGA, BDV, water
content and etc.)
LV TRANSFORMER 6 - 0.42kV FOR Overhaul, periodic maintenance and N2+0
989 200-XFMR-012B IOM-REL-003 Pengajuan Job List TA 2022 3. Inspect and testing (Tan delta, index polarity, ratio
200-MCC-102B inspection LV Transformer Periodic Maintenance
test, winding resistant test and etc.)
4. Inspect and tighten all connection
5. Check and function protection device
1. Isolated of power supply and put in rack out position
2. Oil purifying and oil testing (DGA, BDV, water
content and etc.)
LV TRANSFORMER 6 - 0.42kV FOR Overhaul, periodic maintenance and N2+0
990 200-XFMR-013A IOM-REL-003 Pengajuan Job List TA 2022 3. Inspect and testing (Tan delta, index polarity, ratio
200-MCC-103A inspection LV Transformer Periodic Maintenance
test, winding resistant test and etc.)
4. Inspect and tighten all connection
5. Check and function protection device
1. Isolated of power supply and put in rack out position
2. Oil purifying and oil testing (DGA, BDV, water
content and etc.)
LV TRANSFORMER 6 - 0.42kV FOR Overhaul, periodic maintenance and N2+0
991 200-XFMR-013B IOM-REL-003 Pengajuan Job List TA 2022 3. Inspect and testing (Tan delta, index polarity, ratio
200-MCC-103B inspection LV Transformer Periodic Maintenance
test, winding resistant test and etc.)
4. Inspect and tighten all connection
5. Check and function protection device
1. Isolated of power supply and put in rack out position
2. Oil purifying and oil testing (DGA, BDV, water
content and etc.)
LV TRANSFORMER 6 - 0.42kV FOR Overhaul, periodic maintenance and N2+0
992 200-XFMR-014A IOM-REL-003 Pengajuan Job List TA 2022 3. Inspect and testing (Tan delta, index polarity, ratio
200-MCC-104A inspection LV Transformer Periodic Maintenance
test, winding resistant test and etc.)
4. Inspect and tighten all connection
5. Check and function protection device
1. Isolated of power supply and put in rack out position
2. Oil purifying and oil testing (DGA, BDV, water
content and etc.)
LV TRANSFORMER 6 - 0.42kV FOR Overhaul, periodic maintenance and N2+0
993 200-XFMR-014B IOM-REL-003 Pengajuan Job List TA 2022 3. Inspect and testing (Tan delta, index polarity, ratio
200-MCC-104B inspection LV Transformer Periodic Maintenance
test, winding resistant test and etc.)
4. Inspect and tighten all connection
5. Check and function protection device
1. Isolated of power supply and put in rack out position
2. Oil purifying and oil testing (DGA, BDV, water
content and etc.)
LV TRANSFORMER 6 - 0.42kV FOR Overhaul, periodic maintenance and N2+0
994 200-XFMR-015A IOM-REL-003 Pengajuan Job List TA 2022 3. Inspect and testing (Tan delta, index polarity, ratio
200-MCC-105A inspection LV Transformer Periodic Maintenance
test, winding resistant test and etc.)
4. Inspect and tighten all connection
5. Check and function protection device
1. Isolated of power supply and put in rack out position
2. Oil purifying and oil testing (DGA, BDV, water
content and etc.)
LV TRANSFORMER 6 - 0.42kV FOR Overhaul, periodic maintenance and N2+0
995 200-XFMR-015B IOM-REL-003 Pengajuan Job List TA 2022 3. Inspect and testing (Tan delta, index polarity, ratio
200-MCC-105B inspection LV Transformer Periodic Maintenance
test, winding resistant test and etc.)
4. Inspect and tighten all connection
5. Check and function protection device
1. Isolated of power supply and put in rack out position
2. Oil purifying and oil testing (DGA, BDV, water
content and etc.)
LV TRANSFORMER 6 - 0.42kV FOR Overhaul, periodic maintenance and N2+0
996 200-XFMR-016A IOM-REL-003 Pengajuan Job List TA 2022 3. Inspect and testing (Tan delta, index polarity, ratio
200-MCC-106A inspection LV Transformer Periodic Maintenance
test, winding resistant test and etc.)
4. Inspect and tighten all connection
5. Check and function protection device
1. Isolated of power supply and put in rack out position
2. Oil purifying and oil testing (DGA, BDV, water
content and etc.)
LV TRANSFORMER 6 - 0.42kV FOR Overhaul, periodic maintenance and N2+0
997 200-XFMR-016B IOM-REL-003 Pengajuan Job List TA 2022 3. Inspect and testing (Tan delta, index polarity, ratio
200-MCC-106B inspection LV Transformer Periodic Maintenance
test, winding resistant test and etc.)
4. Inspect and tighten all connection
5. Check and function protection device
1. Isolated of power supply and put in rack out position
2. Oil purifying and oil testing (DGA, BDV, water
content and etc.)
LV TRANSFORMER 6 - 0.42kV FOR Overhaul, periodic maintenance and N2+0
998 200-XFMR-017A IOM-REL-003 Pengajuan Job List TA 2022 3. Inspect and testing (Tan delta, index polarity, ratio
200-MCC-107A inspection LV Transformer Periodic Maintenance
test, winding resistant test and etc.)
4. Inspect and tighten all connection
5. Check and function protection device
1. Isolated of power supply and put in rack out position
2. Oil purifying and oil testing (DGA, BDV, water
content and etc.)
LV TRANSFORMER 6 - 0.42kV FOR Overhaul, periodic maintenance and N2+0
999 200-XFMR-017B IOM-REL-003 Pengajuan Job List TA 2022 3. Inspect and testing (Tan delta, index polarity, ratio
200-MCC-107B inspection LV Transformer Periodic Maintenance
test, winding resistant test and etc.)
4. Inspect and tighten all connection
5. Check and function protection device
1. Isolated of power supply and put in rack out position
2. Oil purifying and oil testing (DGA, BDV, water
content and etc.)
Overhaul, periodic maintenance and N2+0
1000 800-XFMR-011A LV TRANSFORMER A 6.3 - 0.42kV AT SS-800 IOM-REL-003 Pengajuan Job List TA 2022 3. Inspect and testing (Tan delta, index polarity, ratio
inspection LV Transformer Periodic Maintenance
test, winding resistant test and etc.)
4. Inspect and tighten all connection
5. Check and function protection device
1. Isolated of power supply and put in rack out position
2. Oil purifying and oil testing (DGA, BDV, water
content and etc.)
Overhaul, periodic maintenance and N2+0
1001 800-XFMR-011B LV TRANSFORMER B 6.3 - 0.42kV AT SS-800 IOM-REL-003 Pengajuan Job List TA 2022 3. Inspect and testing (Tan delta, index polarity, ratio
inspection LV Transformer Periodic Maintenance
test, winding resistant test and etc.)
4. Inspect and tighten all connection
5. Check and function protection device
1. Isolated of power supply and put in rack out position
2. Oil purifying and oil testing (DGA, BDV, water
content and etc.)
Overhaul, periodic maintenance and N2+0
1002 840-XFMR-011A LV TRANSFORMER A 6.3 - 0.42kV AT SS-840 IOM-REL-003 Pengajuan Job List TA 2022 3. Inspect and testing (Tan delta, index polarity, ratio
inspection LV Transformer Periodic Maintenance
test, winding resistant test and etc.)
4. Inspect and tighten all connection
5. Check and function protection device
1. Isolated of power supply and put in rack out position
2. Oil purifying and oil testing (DGA, BDV, water
content and etc.)
Overhaul, periodic maintenance and N2+0
1003 840-XFMR-011B LV TRANSFORMER B 6.3 - 0.42kV AT SS-840 IOM-REL-003 Pengajuan Job List TA 2022 3. Inspect and testing (Tan delta, index polarity, ratio
inspection LV Transformer Periodic Maintenance
test, winding resistant test and etc.)
4. Inspect and tighten all connection
5. Check and function protection device
1. Isolated of power supply and put in rack out position
2. Oil purifying and oil testing (DGA, BDV, water
content and etc.)
Overhaul, periodic maintenance and N2+0
1004 860-XFMR-011A LV TRANSFORMER A 6.3 - 0.42kV AT SS-860 IOM-REL-003 Pengajuan Job List TA 2022 3. Inspect and testing (Tan delta, index polarity, ratio
inspection LV Transformer Periodic Maintenance
test, winding resistant test and etc.)
4. Inspect and tighten all connection
5. Check and function protection device
1. Isolated of power supply and put in rack out position
2. Oil purifying and oil testing (DGA, BDV, water
content and etc.)
Overhaul, periodic maintenance and N2+0
1005 860-XFMR-011B LV TRANSFORMER B 6.3 - 0.42kV AT SS-860 IOM-REL-003 Pengajuan Job List TA 2022 3. Inspect and testing (Tan delta, index polarity, ratio
inspection LV Transformer Periodic Maintenance
test, winding resistant test and etc.)
4. Inspect and tighten all connection
5. Check and function protection device
1. Isolated of power supply and put in rack out position
2. Oil purifying and oil testing (DGA, BDV, water
content and etc.)
Overhaul, periodic maintenance and N2+0
1006 900-XFMR-011A LV TRANSFORMER A 6.3 - 0.42kV AT SS-900 IOM-REL-003 Pengajuan Job List TA 2022 3. Inspect and testing (Tan delta, index polarity, ratio
inspection LV Transformer Periodic Maintenance
test, winding resistant test and etc.)
4. Inspect and tighten all connection
5. Check and function protection device
1. Isolated of power supply and put in rack out position
2. Oil purifying and oil testing (DGA, BDV, water
content and etc.)
Overhaul, periodic maintenance and N2+0
1007 900-XFMR-011B LV TRANSFORMER B 6.3 - 0.42kV AT SS-900 IOM-REL-003 Pengajuan Job List TA 2022 3. Inspect and testing (Tan delta, index polarity, ratio
inspection LV Transformer Periodic Maintenance
test, winding resistant test and etc.)
4. Inspect and tighten all connection
5. Check and function protection device
1. Isolated of power supply and put in rack out position
2. Oil purifying and oil testing (DGA, BDV, water
content and etc.)
Overhaul, periodic maintenance and N2+0
1008 900A-XFMR-011A LV TRANSFORMER A 6.3 - 0.42kV AT SS-900A IOM-REL-003 Pengajuan Job List TA 2022 3. Inspect and testing (Tan delta, index polarity, ratio
inspection LV Transformer Periodic Maintenance
test, winding resistant test and etc.)
4. Inspect and tighten all connection
5. Check and function protection device

Finalisasi Job List TA-23 rev4 230518 4 OF 19


JOB LIST T/A TH. 2023 REV.4
JOB LIST TA-22 KILANG PT.TPPI TUBAN
PT. Trans Pasific Petrochemical Indotama
Turnaround - Relita Department
CRETERIA REFERENCE
NO. EQUIPMENT NO. SERVICE JOB LIST RECOMMENDATION-INSP/REL/PE REASON MAIN JOB TA-22
PI MI INSP OPT
NO. DESCRIPTION
1. Isolated of power supply and put in rack out position
2. Oil purifying and oil testing (DGA, BDV, water
content and etc.)
Overhaul, periodic maintenance and N2+0
1009 900A-XFMR-011B LV TRANSFORMER B 6.3 - 0.42kV AT SS-900A IOM-REL-003 Pengajuan Job List TA 2022 3. Inspect and testing (Tan delta, index polarity, ratio
inspection LV Transformer Periodic Maintenance
test, winding resistant test and etc.)
4. Inspect and tighten all connection
5. Check and function protection device
1. Isolated of power supply and put in rack out position
2. Check and re tighten all connection
1011 200-PB-001A BUS DUCT 6.3kV FOR 200-SWGR-011APeriodic maintenance and inspection bus duct x IOM-REL-003 Pengajuan Job List TA 2022 Periodic maintenance and inspection bus duct
3. Check and measure IR
4. Check and measure of contact resistance
1. Isolated of power supply and put in rack out position
2. Check and re tighten all connection
1012 200-PB-001B BUS DUCT 6.3kV FOR 200-SWGR-011BPeriodic maintenance and inspection bus duct IOM-REL-003 Pengajuan Job List TA 2022 Periodic maintenance and inspection bus duct
3. Check and measure IR
4. Check and measure of contact resistance
1. Isolated of power supply and put in rack out position
2. Check and re tighten all connection
1013 200-PB-011A BUS DUCT 6.3kV FOR 200-MCC-011A Periodic maintenance and inspection bus duct IOM-REL-003 Pengajuan Job List TA 2022 Periodic maintenance and inspection bus duct
3. Check and measure IR
4. Check and measure of contact resistance
1. Isolated of power supply and put in rack out position
2. Check and re tighten all connection
1014 200-PB-011B BUS DUCT 6.3kV FOR 200-MCC-011B Periodic maintenance and inspection bus duct IOM-REL-003 Pengajuan Job List TA 2022 Periodic maintenance and inspection bus duct
3. Check and measure IR
4. Check and measure of contact resistance
1. Isolated of power supply and put in rack out position
2. Check and re tighten all connection
1015 700-PB-101 BUS DUCT 420V FOR PDC Periodic maintenance and inspection bus duct IOM-REL-003 Pengajuan Job List TA 2022 Periodic maintenance and inspection bus duct
3. Check and measure IR
4. Check and measure of contact resistance
1. Isolated of power supply and put in rack out position
2. Check and re tighten all connection
1016 800-PB-001A BUS DUCT 11kV FOR 800-XFMR-001APeriodic maintenance and inspection bus duct IOM-REL-003 Pengajuan Job List TA 2022 Periodic maintenance and inspection bus duct
3. Check and measure IR
4. Check and measure of contact resistance
1. Isolated of power supply and put in rack out position
2. Check and re tighten all connection
1017 800-PB-001B BUS DUCT 11kV FOR 800-XFMR-001B Periodic maintenance and inspection bus duct IOM-REL-003 Pengajuan Job List TA 2022 Periodic maintenance and inspection bus duct
3. Check and measure IR
4. Check and measure of contact resistance
1. Isolated of power supply and put in rack out position
2. Check and re tighten all connection
1018 800-PB-001C BUS DUCT 11kV FOR 800-XFMR-001C Periodic maintenance and inspection bus duct IOM-REL-003 Pengajuan Job List TA 2022 Periodic maintenance and inspection bus duct
3. Check and measure IR
4. Check and measure of contact resistance
1. Isolated of power supply and put in rack out position
2. Check and re tighten all connection
1019 800-PB-011A BUS DUCT 6.3kV FOR SWGR BUS A Periodic maintenance and inspection bus duct IOM-REL-003 Pengajuan Job List TA 2022 Periodic maintenance and inspection bus duct
3. Check and measure IR
4. Check and measure of contact resistance
1. Isolated of power supply and put in rack out position
2. Check and re tighten all connection
1020 800-PB-011B BUS DUCT 6.3kV FOR SWGR BUS B Periodic maintenance and inspection bus duct IOM-REL-003 Pengajuan Job List TA 2022 Periodic maintenance and inspection bus duct
3. Check and measure IR
4. Check and measure of contact resistance
1. Isolated of power supply and put in rack out position
2. Check and re tighten all connection
1021 800-PB-101A BUS DUCT 420V FOR MCC BUS A Periodic maintenance and inspection bus duct IOM-REL-003 Pengajuan Job List TA 2022 Periodic maintenance and inspection bus duct
3. Check and measure IR
4. Check and measure of contact resistance
1. Isolated of power supply and put in rack out position
2. Check and re tighten all connection
1022 800-PB-101B BUS DUCT 420V FOR MCC BUS B Periodic maintenance and inspection bus duct IOM-REL-003 Pengajuan Job List TA 2022 Periodic maintenance and inspection bus duct
3. Check and measure IR
4. Check and measure of contact resistance
1. Isolated of power supply and put in rack out position
2. Check and re tighten all connection
1023 800-PB-101C BUS DUCT 420V FOR EDP NORMAL BUS
Periodic maintenance and inspection bus duct IOM-REL-003 Pengajuan Job List TA 2022 Periodic maintenance and inspection bus duct
3. Check and measure IR
4. Check and measure of contact resistance
1. Isolated of power supply and put in rack out position
2. Check and re tighten all connection
1024 800-PB-101D BUS DUCT 420V FOR EDP GENERATORPeriodic
BUS maintenance and inspection bus duct IOM-REL-003 Pengajuan Job List TA 2022 Periodic maintenance and inspection bus duct
3. Check and measure IR
4. Check and measure of contact resistance
1. Isolated of power supply and put in rack out position
2. Check and re tighten all connection
1025 840-PB-101A BUS DUCT 420V FOR MCC BUS A Periodic maintenance and inspection bus duct IOM-REL-003 Pengajuan Job List TA 2022 Periodic maintenance and inspection bus duct
3. Check and measure IR
4. Check and measure of contact resistance
1. Isolated of power supply and put in rack out position
2. Check and re tighten all connection
1026 840-PB-101B BUS DUCT 420V FOR MCC BUS B Periodic maintenance and inspection bus duct IOM-REL-003 Pengajuan Job List TA 2022 Periodic maintenance and inspection bus duct
3. Check and measure IR
4. Check and measure of contact resistance
1. Isolated of power supply and put in rack out position
2. Check and re tighten all connection
1027 860-PB-011A BUS DUCT 6.3kV FOR SWGR BUS A Periodic maintenance and inspection bus duct IOM-REL-003 Pengajuan Job List TA 2022 Periodic maintenance and inspection bus duct
3. Check and measure IR
4. Check and measure of contact resistance
1. Isolated of power supply and put in rack out position
2. Check and re tighten all connection
1028 860-PB-011B BUS DUCT 6.3kV FOR SWGR BUS B Periodic maintenance and inspection bus duct IOM-REL-003 Pengajuan Job List TA 2022 Periodic maintenance and inspection bus duct
3. Check and measure IR
4. Check and measure of contact resistance
1. Isolated of power supply and put in rack out position
2. Check and re tighten all connection
1029 860-PB-101A BUS DUCT 420V FOR MCC BUS A Periodic maintenance and inspection bus duct IOM-REL-003 Pengajuan Job List TA 2022 Periodic maintenance and inspection bus duct
3. Check and measure IR
4. Check and measure of contact resistance
1. Isolated of power supply and put in rack out position
2. Check and re tighten all connection
1030 860-PB-101B BUS DUCT 420V FOR MCC BUS B Periodic maintenance and inspection bus duct IOM-REL-003 Pengajuan Job List TA 2022 Periodic maintenance and inspection bus duct
3. Check and measure IR
4. Check and measure of contact resistance
1. Isolated of power supply and put in rack out position
2. Check and re tighten all connection
1031 900A-PB-101A BUS DUCT 420V FOR MCC BUS A Periodic maintenance and inspection bus duct IOM-REL-003 Pengajuan Job List TA 2022 Periodic maintenance and inspection bus duct
3. Check and measure IR
4. Check and measure of contact resistance
1. Isolated of power supply and put in rack out position
2. Check and re tighten all connection
1032 900A-PB-101B BUS DUCT 420V FOR MCC BUS B Periodic maintenance and inspection bus duct IOM-REL-003 Pengajuan Job List TA 2022 Periodic maintenance and inspection bus duct
3. Check and measure IR
4. Check and measure of contact resistance
1. Isolated of power supply and put in rack out position
2. Check and re tighten all connection
1033 900-PB-101A BUS DUCT 420V FOR MCC BUS A Periodic maintenance and inspection bus duct IOM-REL-003 Pengajuan Job List TA 2022 Periodic maintenance and inspection bus duct
3. Check and measure IR
4. Check and measure of contact resistance
1. Isolated of power supply and put in rack out position
2. Check and re tighten all connection
1034 900-PB-101B BUS DUCT 420V FOR MCC BUS B Periodic maintenance and inspection bus duct IOM-REL-003 Pengajuan Job List TA 2022 Periodic maintenance and inspection bus duct
3. Check and measure IR
4. Check and measure of contact resistance
1. Rack Out-Rack In Power
2. Lepas-Pasang Coupling
3. Overhaul - Inspection Motor (Winding, Isolasi,
Overhaul, periodic maintenance and Bearing)
1043 822-K-1101-M FORCE DRAFT FAN MTR IOM-REL-003 Pengajuan Job List TA 2022 Overhaul, periodic maintenance and inspection MV motor
inspection MV motor 4. Painting
5. Solo Run
6. Alignment
7. Test Run
1. Rack Out-Rack In Power
2. Lepas-Pasang Coupling
3. Overhaul - Inspection Motor (Winding, Isolasi,
Overhaul, periodic maintenance and Pengajuan job list TA 2022 dari sisi Bearing)
1044 200-P-005-M OWS pump IOM-REL-003 Periodic Maintenance (1st Inspection)
inspection LV motor Reliability 4. Painting
5. Solo Run
6. Alignment
7. Test Run

1. Rack Out-Rack In Power


2. Lepas-Pasang Coupling
3. Overhaul - Inspection Motor (Winding, Isolasi,
Overhaul, periodic maintenance and Pengajuan job list TA 2022 dari sisi Bearing)
1045 200-P-003-M Aromatics Sump Tank pump IOM-REL-003 Periodic Maintenance (1st Inspection)
inspection LV motor Reliability 4. Painting
5. Solo Run
6. Alignment
7. Test Run

1. Rack Out-Rack In Power


2. Lepas-Pasang Coupling
3. Overhaul - Inspection Motor (Winding, Isolasi,
Overhaul, periodic maintenance and IOM-REL-003 Bearing)
1046 201-P-002A-M HEAVY NAPHTHA OVERHEAD PUMP Pengajuan Job List TA 2022 Overhaul, periodic maintenance and inspection MV motor
inspection LV motor IOM-UOM-UTY-000 4. Painting
5. Solo Run
6. Alignment
7. Test Run

1. Rack Out-Rack In Power


2. Lepas-Pasang Coupling
3. Overhaul - Inspection Motor (Winding, Isolasi,
Overhaul, periodic maintenance and IOM-REL-003 Bearing)
1047 201-P-002B-M HEAVY NAPHTHA OVERHEAD PUMP Pengajuan Job List TA 2022 Overhaul, periodic maintenance and inspection MV motor
inspection LV motor IOM-UOM-UTY-000 4. Painting
5. Solo Run
6. Alignment
7. Test Run

1. Rack Out-Rack In Power


2. Lepas-Pasang Coupling
3. Overhaul - Inspection Motor (Winding, Isolasi,
CONDENSATE SPLITTER BOT.PUMP Overhaul, periodic maintenance and IOM-REL-003 Bearing)
1048 201-P-003A-M Pengajuan Job List TA 2022 Overhaul, periodic maintenance and inspection MV motor
A MTR inspection MV motor IOM-UOM-UTY-000 4. Painting
5. Solo Run
6. Alignment
7. Test Run

Finalisasi Job List TA-23 rev4 230518 5 OF 19


JOB LIST T/A TH. 2023 REV.4
JOB LIST TA-22 KILANG PT.TPPI TUBAN
PT. Trans Pasific Petrochemical Indotama
Turnaround - Relita Department
CRETERIA REFERENCE
NO. EQUIPMENT NO. SERVICE JOB LIST RECOMMENDATION-INSP/REL/PE REASON MAIN JOB TA-22
PI MI INSP OPT
NO. DESCRIPTION

1. Rack Out-Rack In Power


2. Lepas-Pasang Coupling
3. Overhaul - Inspection Motor (Winding, Isolasi,
CONDENSATE SPLITTER BOT.PUMP Overhaul, periodic maintenance and IOM-REL-003 Bearing)
1049 201-P-003B-M Pengajuan Job List TA 2022 Overhaul, periodic maintenance and inspection MV motor
B MTR inspection MV motor IOM-UOM-UTY-000 4. Painting
5. Solo Run
6. Alignment
7. Test Run

1. Rack Out-Rack In Power


2. Lepas-Pasang Coupling
3. Overhaul - Inspection Motor (Winding, Isolasi,
Overhaul, periodic maintenance and IOM-REL-003 Bearing)
1050 201-P-006A-M PRECUT COLUMN BOTTOMS PUMP Pengajuan Job List TA 2022 Overhaul, periodic maintenance and inspection MV motor
inspection MV motor IOM-UOM-UTY-000 4. Painting
5. Solo Run
6. Alignment
7. Test Run

1. Rack Out-Rack In Power


2. Lepas-Pasang Coupling
3. Overhaul - Inspection Motor (Winding, Isolasi,
Overhaul, periodic maintenance and IOM-REL-003 Bearing)
1051 201-P-006B-M PRECUT COLUMN BOTTOMS PUMP Pengajuan Job List TA 2022 Overhaul, periodic maintenance and inspection MV motor
inspection MV motor IOM-UOM-UTY-000 4. Painting
5. Solo Run
6. Alignment
7. Test Run

1. Rack Out-Rack In Power


2. Lepas-Pasang Coupling
3. Overhaul - Inspection Motor (Winding, Isolasi,
Overhaul, periodic maintenance and IOM-REL-003 Bearing)
1052 201-P-006C-M PRECUT COLUMN BOTTOMS PUMP Pengajuan Job List TA 2022 Overhaul, periodic maintenance and inspection MV motor
inspection MV motor IOM-UOM-UTY-000 4. Painting
5. Solo Run
6. Alignment
7. Test Run

1. Rack Out-Rack In Power


2. Lepas-Pasang Coupling
3. Overhaul - Inspection Motor (Winding, Isolasi,
Overhaul, periodic maintenance and IOM-REL-003 Bearing)
1053 201-E-007-M01 RESIDUE PRODUCT AIR COOLER Pengajuan Job List TA 2022 Overhaul, periodic maintenance and inspection MV motor
inspection LV motor IOM-UOM-UTY-000 4. Painting
5. Solo Run
6. Alignment
7. Test Run

1. Rack Out-Rack In Power


2. Lepas-Pasang Coupling
3. Overhaul - Inspection Motor (Winding, Isolasi,
Overhaul, periodic maintenance and IOM-REL-003 Bearing)
1054 201-E-007-M02 PESIDUE PRODUCT AIR COOLER Pengajuan Job List TA 2022 Overhaul, periodic maintenance and inspection MV motor
inspection LV motor IOM-UOM-UTY-000 4. Painting
5. Solo Run
6. Alignment
7. Test Run

1. Rack Out-Rack In Power


2. Lepas-Pasang Coupling
3. Overhaul - Inspection Motor (Winding, Isolasi,
Overhaul, periodic maintenance and IOM-REL-003 Bearing)
1055 201-P-007A-M DISTILLATE CO.BTM PUMP Pengajuan Job List TA 2022 Overhaul, periodic maintenance and inspection MV motor
inspection LV motor IOM-UOM-UTY-000 4. Painting
5. Solo Run
6. Alignment
7. Test Run

1. Rack Out-Rack In Power


2. Lepas-Pasang Coupling
3. Overhaul - Inspection Motor (Winding, Isolasi,
Overhaul, periodic maintenance and IOM-REL-003 Bearing)
1056 201-P-007B-M DISTILLATE CO.BTM PUMP Pengajuan Job List TA 2022 Overhaul, periodic maintenance and inspection MV motor
inspection LV motor IOM-UOM-UTY-000 4. Painting
5. Solo Run
6. Alignment
7. Test Run

(new motor, replace by revamp)


1. Rack Out-Rack In Power
2. Lepas-Pasang Coupling
3. Overhaul - Inspection Motor (Winding, Isolasi,
Overhaul, periodic maintenance and IOM-REL-003
1057 201-P-009A-M DIESEL PUMP Pengajuan Job List TA 2022 Overhaul, periodic maintenance and inspection MV motor Bearing)
inspection LV motor IOM-UOM-UTY-000
4. Painting
5. Solo Run
6. Alignment
7. Test Run

(new motor, replace by revamp)


1. Rack Out-Rack In Power
2. Lepas-Pasang Coupling
3. Overhaul - Inspection Motor (Winding, Isolasi,
Overhaul, periodic maintenance and IOM-REL-003
1058 201-P-009B-M DIESEL PUMP Pengajuan Job List TA 2022 Overhaul, periodic maintenance and inspection MV motor Bearing)
inspection LV motor IOM-UOM-UTY-000
4. Painting
5. Solo Run
6. Alignment
7. Test Run

(new motor replace by revamp)


1. Rack Out-Rack In Power
2. Lepas-Pasang Coupling
3. Overhaul - Inspection Motor (Winding, Isolasi,
Overhaul, periodic maintenance and IOM-REL-003
1059 203-P-005A-M CIRCULATING WATER PUMP Pengajuan Job List TA 2022 Overhaul, periodic maintenance and inspection MV motor Bearing)
inspection LV motor IOM-UOM-UTY-000
4. Painting
5. Solo Run
6. Alignment
7. Test Run

1. Rack Out-Rack In Power


2. Lepas-Pasang Coupling
3. Overhaul - Inspection Motor (Winding, Isolasi,
REGENERATION BLOWER MTR Overhaul, periodic maintenance and IOM-REL-003 Bearing)
1060 204-K-003-M Pengajuan Job List TA 2022 Overhaul, periodic maintenance and inspection MV motor
(POLE CHANGE) inspection MV motor IOM-UOM-UTY-000 4. Painting
5. Solo Run
6. Alignment
7. Test Run

1. Rack Out-Rack In Power


2. Lepas-Pasang Coupling
3. Overhaul - Inspection Motor (Winding, Isolasi,
REGENERATION COOLER BLOWER Overhaul, periodic maintenance and IOM-REL-003 Bearing)
1061 204-K-004-M Pengajuan Job List TA 2022 Overhaul, periodic maintenance and inspection MV motor
MOTOR inspection LV motor IOM-UOM-UTY-000 4. Painting
5. Solo Run
7. Alignment (by revamp)
8. Test Run (joint effort with revamp)

1. Rack Out-Rack In Power


2. Lepas-Pasang Coupling
3. Overhaul - Inspection Motor (Winding, Isolasi,
Overhaul, periodic maintenance and IOM-REL-003 Bearing)
1062 205-P-007A-M LEAN SOLVENT PUMP Pengajuan job list TA 2022 dari sisi Overhaul, periodic maintenance and inspection MV motor
inspection MV motor IOM-PROD-ARO-000 4. Painting
5. Solo Run
6. Alignment
7. Test Run

1. Rack Out-Rack In Power


2. Lepas-Pasang Coupling
3. Overhaul - Inspection Motor (Winding, Isolasi,
Overhaul, periodic maintenance and IOM-REL-003 Bearing)
1063 205-P-007B-M LEAN SOLVENT PUMP Pengajuan job list TA 2022 dari sisi Overhaul, periodic maintenance and inspection MV motor
inspection MV motor IOM-PROD-ARO-000 4. Painting
5. Solo Run
6. Alignment
7. Test Run
1. Rack Out-Rack In Power
2. Lepas-Pasang Coupling
3. Overhaul - Inspection Motor (Winding, Isolasi,
Overhaul, periodic maintenance and IOM-REL-003 Bearing)
1064 205-P-013-M Sulfolane sump tank Pengajuan job list TA 2022 dari sisi Overhaul, periodic maintenance and inspection MV motor
inspection LV motor IOM-PROD-ARO-000 4. Painting
5. Solo Run
6. Alignment
7. Test Run
(new motor replace by revamp)
1. Rack Out-Rack In Power
2. Lepas-Pasang Coupling
3. Overhaul - Inspection Motor (Winding, Isolasi,
Overhaul, periodic maintenance and IOM-REL-003
1065 205-P-002A-M Raffinate Wash Water Recycle Pump Pengajuan job list TA 2022 dari sisi Overhaul, periodic maintenance and inspection MV motor Bearing)
inspection LV motor IOM-PROD-ARO-000
4. Painting
5. Solo Run
6. Alignment
7. Test Run

Finalisasi Job List TA-23 rev4 230518 6 OF 19


JOB LIST T/A TH. 2023 REV.4
JOB LIST TA-22 KILANG PT.TPPI TUBAN
PT. Trans Pasific Petrochemical Indotama
Turnaround - Relita Department
CRETERIA REFERENCE
NO. EQUIPMENT NO. SERVICE JOB LIST RECOMMENDATION-INSP/REL/PE REASON MAIN JOB TA-22
PI MI INSP OPT
NO. DESCRIPTION

(new motor replace by revamp)


1. Rack Out-Rack In Power
2. Lepas-Pasang Coupling
3. Overhaul - Inspection Motor (Winding, Isolasi,
Overhaul, periodic maintenance and IOM-REL-003
1066 205-P-002B-M Raffinate Wash Water Recycle Pump Pengajuan job list TA 2022 dari sisi Overhaul, periodic maintenance and inspection MV motor Bearing)
inspection LV motor IOM-PROD-ARO-000
4. Painting
5. Solo Run
6. Alignment
7. Test Run

(new motor replace by revamp)


1. Rack Out-Rack In Power
2. Lepas-Pasang Coupling
3. Overhaul - Inspection Motor (Winding, Isolasi,
Overhaul, periodic maintenance and IOM-REL-003
1067 205-P-003A-M Raffinate Pump Pengajuan job list TA 2022 dari sisi Periodic maintenance Bearing)
inspection LV motor IOM-PROD-ARO-000
4. Painting
5. Solo Run
6. Alignment
7. Test Run

(new motor replace by revamp)


1. Rack Out-Rack In Power
2. Lepas-Pasang Coupling
3. Overhaul - Inspection Motor (Winding, Isolasi,
Overhaul, periodic maintenance and IOM-REL-003
1068 205-P-003B-M Raffinate Pump Pengajuan job list TA 2022 dari sisi Periodic maintenance Bearing)
inspection LV motor IOM-PROD-ARO-000
4. Painting
5. Solo Run
6. Alignment
7. Test Run

1. Rack Out-Rack In Power


2. Lepas-Pasang Coupling
3. Overhaul - Inspection Motor (Winding, Isolasi,
Overhaul, periodic maintenance and IOM-REL-003 Bearing)
1069 205-P-004A-M Stripper Bottom Pump Pengajuan job list TA 2022 dari sisi Overhaul, periodic maintenance and inspection MV motor
inspection LV motor IOM-PROD-ARO-000 4. Painting
5. Solo Run
6. Alignment
7. Test Run

1. Rack Out-Rack In Power


2. Lepas-Pasang Coupling
3. Overhaul - Inspection Motor (Winding, Isolasi,
Overhaul, periodic maintenance and IOM-REL-003 Bearing)
1070 205-P-004B-M Stripper Bottom Pump Pengajuan job list TA 2022 dari sisi Overhaul, periodic maintenance and inspection MV motor
inspection LV motor IOM-PROD-ARO-000 4. Painting
5. Solo Run
6. Alignment
7. Test Run

1. Rack Out-Rack In Power


2. Lepas-Pasang Coupling
3. Overhaul - Inspection Motor (Winding, Isolasi,
Overhaul, periodic maintenance and IOM-REL-003 Bearing)
1071 205-P-008A-M Water Stripper Bottom Pump Pengajuan job list TA 2022 dari sisi Overhaul, periodic maintenance and inspection MV motor
inspection LV motor IOM-PROD-ARO-000 4. Painting
5. Solo Run
6. Alignment
7. Test Run

1. Rack Out-Rack In Power


2. Lepas-Pasang Coupling
3. Overhaul - Inspection Motor (Winding, Isolasi,
Overhaul, periodic maintenance and IOM-REL-003 Bearing)
1072 205-P-008B-M Water Stripper Bottom Pump Pengajuan job list TA 2022 dari sisi Overhaul, periodic maintenance and inspection MV motor
inspection LV motor IOM-PROD-ARO-000 4. Painting
5. Solo Run
6. Alignment
7. Test Run

(new motor replace by revamp)


1. Rack Out-Rack In Power
2. Lepas-Pasang Coupling
3. Overhaul - Inspection Motor (Winding, Isolasi,
Overhaul, periodic maintenance and IOM-REL-003
1073 206-P-002A-M Benzene Column Bottom Pump Pengajuan job list TA 2022 dari sisi Overhaul, periodic maintenance and inspection MV motor Bearing)
inspection LV motor IOM-PROD-ARO-000
4. Painting
5. Solo Run
6. Alignment
7. Test Run

(new motor replace by revamp)


1. Rack Out-Rack In Power
2. Lepas-Pasang Coupling
3. Overhaul - Inspection Motor (Winding, Isolasi,
Overhaul, periodic maintenance and IOM-REL-003
1074 206-P-002B-M Benzene Column Bottom Pump Pengajuan job list TA 2022 dari sisi Overhaul, periodic maintenance and inspection MV motor Bearing)
inspection LV motor IOM-PROD-ARO-000
4. Painting
5. Solo Run
6. Alignment
7. Test Run

(new motor replacwe by revamp)


1. Rack Out-Rack In Power
2. Lepas-Pasang Coupling
3. Overhaul - Inspection Motor (Winding, Isolasi,
Overhaul, periodic maintenance and IOM-REL-003
1075 206-P-005A-M Toluene Column Bottoms Pump Pengajuan job list TA 2022 dari sisi Overhaul, periodic maintenance and inspection MV motor Bearing)
inspection LV motor IOM-PROD-ARO-000
4. Painting
5. Solo Run
6, Alignment
7. Test Run

(new motor replace by revamp)


1. Rack Out-Rack In Power
2. Lepas-Pasang Coupling
3. Overhaul - Inspection Motor (Winding, Isolasi,
Overhaul, periodic maintenance and IOM-REL-003
1076 206-P-005B-M Toluene Column Bottoms Pump Pengajuan job list TA 2022 dari sisi Overhaul, periodic maintenance and inspection MV motor Bearing)
inspection LV motor IOM-PROD-ARO-000
4. Painting
5. Solo Run
6, Alignment
7. Test Run

(new motor replace by revamp)


1. Rack Out-Rack In Power
2. Lepas-Pasang Coupling
3. Overhaul - Inspection Motor (Winding, Isolasi,
Overhaul, periodic maintenance and IOM-REL-003
1077 207-P-003A-M CHAMBER CIRCULATION PUMP Pengajuan job list TA 2022 dari sisi Overhaul, periodic maintenance and inspection MV motor Bearing)
inspection MV motor IOM-PROD-ARO-000
4. Painting
5. Solo Run
6, Alignment
7. Test Run

(new motor replace by revamp)


1. Rack Out-Rack In Power
2. Lepas-Pasang Coupling
3. Overhaul - Inspection Motor (Winding, Isolasi,
Overhaul, periodic maintenance and IOM-REL-003
1078 207-P-003B-M CHAMBER CIRCULATION PUMP Pengajuan job list TA 2022 dari sisi Overhaul, periodic maintenance and inspection MV motor Bearing)
inspection MV motor IOM-PROD-ARO-000
4. Painting
5. Solo Run
6, Alignment
7. Test Run

(new motor replace by revamp)


1. Rack Out-Rack In Power
2. Lepas-Pasang Coupling
3. Overhaul - Inspection Motor (Winding, Isolasi,
Overhaul, periodic maintenance and IOM-REL-003
1079 207-P-003C-M CHAMBER CIRCULATION PUMP Pengajuan job list TA 2022 dari sisi Overhaul, periodic maintenance and inspection MV motor Bearing)
inspection MV motor IOM-PROD-ARO-000
4. Painting
5. Solo Run
6, Alignment
7. Test Run
Overh
aul, 1. Rack Out-Rack In Power
perio 2. Lepas-Pasang Coupling
dic 3. Overhaul - Inspection Motor (Winding, Isolasi,
Overhaul, periodic maintenance and maint IOM-REL-003 Bearing)
1080 207-P-008A-M Desorbent Pump Pengajuan job list TA 2022 dari sisi Overhaul, periodic maintenance and inspection MV motor
inspection MV motor enanc IOM-PROD-ARO-000 4. Painting
e and 5. Solo Run
inspec 6. Alignment
tion 7. Test Run
MV
Overh
aul,
1. Rack Out-Rack In Power
perio
2. Lepas-Pasang Coupling
dic
3. Overhaul - Inspection Motor (Winding, Isolasi,
maint
Overhaul, periodic maintenance and IOM-REL-003 Bearing)
1081 207-P-008B-M Desorbent Pump enanc Pengajuan job list TA 2022 dari sisi Overhaul, periodic maintenance and inspection MV motor
inspection MV motor IOM-PROD-ARO-000 4. Painting
e and
5. Solo Run
inspec
6. Alignment
tion
7. Test Run
MV
motor

Finalisasi Job List TA-23 rev4 230518 7 OF 19


JOB LIST T/A TH. 2023 REV.4
JOB LIST TA-22 KILANG PT.TPPI TUBAN
PT. Trans Pasific Petrochemical Indotama
Turnaround - Relita Department
CRETERIA REFERENCE
NO. EQUIPMENT NO. SERVICE JOB LIST RECOMMENDATION-INSP/REL/PE REASON MAIN JOB TA-22
PI MI INSP OPT
NO. DESCRIPTION

1. Rack Out-Rack In Power


2. Lepas-Pasang Coupling
3. Overhaul - Inspection Motor (Winding, Isolasi,
Overhaul, periodic maintenance and IOM-REL-003 Bearing)
1082 207-P-005A-M Raffinate Bottom Pump Pengajuan job list TA 2022 dari sisi Overhaul, periodic maintenance and inspection MV motor
inspection LV motor IOM-PROD-ARO-000 4. Painting
5. Solo Run
6. Alignment
7. Test Run

1. Rack Out-Rack In Power


2. Lepas-Pasang Coupling
3. Overhaul - Inspection Motor (Winding, Isolasi,
Overhaul, periodic maintenance and IOM-REL-003 Bearing)
1083 207-P-005B-M Raffinate Bottom Pump Pengajuan job list TA 2022 dari sisi Overhaul, periodic maintenance and inspection MV motor
inspection LV motor IOM-PROD-ARO-000 4. Painting
5. Solo Run
6. Alignment
7. Test Run

1. Rack Out-Rack In Power


2. Lepas-Pasang Coupling
3. Overhaul - Inspection Motor (Winding, Isolasi,
Overhaul, periodic maintenance and IOM-REL-003 Bearing)
1084 207-P-013-M Desorbent sump tank Pengajuan job list TA 2022 dari sisi Overhaul, periodic maintenance and inspection MV motor
inspection LV motor IOM-PROD-ARO-000 4. Painting
5. Solo Run
6. Alignment
7. Test Run

1. Rack Out-Rack In Power


2. Lepas-Pasang Coupling
3. Overhaul - Inspection Motor (Winding, Isolasi,
Overhaul, periodic maintenance and IOM-REL-003 Bearing)
1085 207-P-009A-M Extrac Column Bottoms Pump Pengajuan job list TA 2022 dari sisi Overhaul, periodic maintenance and inspection MV motor
inspection LV motor IOM-PROD-ARO-000 4. Painting
5. Solo Run
6. Alignment
7. Test Run

1. Rack Out-Rack In Power


2. Lepas-Pasang Coupling
3. Overhaul - Inspection Motor (Winding, Isolasi,
Overhaul, periodic maintenance and IOM-REL-003 Bearing)
1086 207-P-009B-M Extrac Column Bottoms Pump Pengajuan job list TA 2022 dari sisi Overhaul, periodic maintenance and inspection MV motor
inspection LV motor IOM-PROD-ARO-000 4. Painting
5. Solo Run
6. Alignment
7. Test Run

(new motor replace by revamp)


1. Rack Out-Rack In Power
2. Lepas-Pasang Coupling
3. Overhaul - Inspection Motor (Winding, Isolasi,
Overhaul, periodic maintenance and IOM-REL-003
1087 209-P-002A-M Charge Pump Pengajuan job list TA 2022 dari sisi Overhaul, periodic maintenance and inspection MV motor Bearing)
inspection MV motor IOM-PROD-ARO-000
4. Painting
5. Solo Run
6, Alignment
7. Test Run
(new motor replace by revamp)
1. Rack Out-Rack In Power
2. Lepas-Pasang Coupling
3. Overhaul - Inspection Motor (Winding, Isolasi,
Overhaul, periodic maintenance and IOM-REL-003
1088 209-P-002B-M Charge Pump Pengajuan job list TA 2022 dari sisi Overhaul, periodic maintenance and inspection MV motor Bearing)
inspection MV motor IOM-PROD-ARO-000
4. Painting
5. Solo Run
6, Alignment
7. Test Run
(new motor replace by revamp)
1. Rack Out-Rack In Power
2. Lepas-Pasang Coupling
Overhaul, periodic maintenance and IOM-REL-003 3. Overhaul - Inspection Motor (Winding, Isolasi,
1089 209-P-003A-M Separator Pump Pengajuan job list TA 2022 dari sisi Overhaul, periodic maintenance and inspection MV motor
inspection LV motor IOM-PROD-ARO-000 Bearing)
4. Painting
5. Solo Run
6, Alignment
(new motor replace by revamp)
1. Rack Out-Rack In Power
2. Lepas-Pasang Coupling
Overhaul, periodic maintenance and IOM-REL-003 3. Overhaul - Inspection Motor (Winding, Isolasi,
1090 209-P-003B-M Separator Pump Pengajuan job list TA 2022 dari sisi Overhaul, periodic maintenance and inspection MV motor
inspection LV motor IOM-PROD-ARO-000 Bearing)
4. Painting
5. Solo Run
6, Alignment

1. Rack Out-Rack In Power


2. Lepas-Pasang Coupling
3. Overhaul - Inspection Motor (Winding, Isolasi,
Overhaul, periodic maintenance and IOM-REL-003 Bearing)
1091 209-P-008A-M Surface Condenser Condensate Pump Pengajuan job list TA 2022 dari sisi Overhaul, periodic maintenance and inspection MV motor
inspection LV motor IOM-PROD-ARO-000 4. Painting
5. Solo Run
6. Alignment
7. Test Run

1. Rack Out-Rack In Power


2. Lepas-Pasang Coupling
3. Overhaul - Inspection Motor (Winding, Isolasi,
Overhaul, periodic maintenance and IOM-REL-003 Bearing)
1092 209-K-001-P1-B-M Lube oil pump Pengajuan job list TA 2022 dari sisi Overhaul, periodic maintenance and inspection MV motor
inspection LV motor IOM-PROD-ARO-000 4. Painting
5. Solo Run
6. Alignment
7. Test Run

1. Rack Out-Rack In Power


2. Lepas-Pasang Coupling
3. Overhaul - Inspection Motor (Winding, Isolasi,
Overhaul, periodic maintenance and IOM-REL-003 Bearing)
1093 209-K-002A-M Combustion Air Fan for 209-H-001/2 Pengajuan job list TA 2022 dari sisi Overhaul, periodic maintenance and inspection MV motor
inspection LV motor IOM-PROD-ARO-000 4. Painting
5. Solo Run
6. Alignment
7. Test Run

1. Rack Out-Rack In Power


2. Lepas-Pasang Coupling
3. Overhaul - Inspection Motor (Winding, Isolasi,
Overhaul, periodic maintenance and IOM-REL-003 Bearing)
1094 209-K-002B-M Combustion Air Fan for 209-H-001/2 Pengajuan job list TA 2022 dari sisi Overhaul, periodic maintenance and inspection MV motor
inspection LV motor IOM-PROD-ARO-000 4. Painting
5. Solo Run
6. Alignment
7. Test Run

1. Rack Out-Rack In Power


2. Lepas-Pasang Coupling
3. Overhaul - Inspection Motor (Winding, Isolasi,
Overhaul, periodic maintenance and IOM-REL-003 Bearing)
1095 209-P-004A-M DEHEPTANIZER REBOILER PUMP Pengajuan job list TA 2022 dari sisi Overhaul, periodic maintenance and inspection MV motor
inspection MV motor IOM-PROD-ARO-000 4. Painting
5. Solo Run
6. Alignment
7. Test Run
1. Rack Out-Rack In Power
2. Lepas-Pasang Coupling
3. Overhaul - Inspection Motor (Winding, Isolasi,
Overhaul, periodic maintenance and IOM-REL-003 Bearing)
1096 209-P-004B-M DEHEPTANIZER REBOILER PUMP Pengajuan job list TA 2022 dari sisi Overhaul, periodic maintenance and inspection MV motor
inspection MV motor IOM-PROD-ARO-000 4. Painting
5. Solo Run
6. Alignment
7. Test Run

1. Rack Out-Rack In Power


2. Lepas-Pasang Coupling
3. Overhaul - Inspection Motor (Winding, Isolasi,
Overhaul, periodic maintenance and IOM-REL-003 Bearing)
1097 209-P-004C-M DEHEPTANIZER REBOILER PUMP Pengajuan job list TA 2022 dari sisi Overhaul, periodic maintenance and inspection MV motor
inspection MV motor IOM-PROD-ARO-000 4. Painting
5. Solo Run
6. Alignment
7. Test Run

1. Rack Out-Rack In Power


2. Lepas-Pasang Coupling
3. Overhaul - Inspection Motor (Winding, Isolasi,
Overhaul, periodic maintenance and IOM-REL-003 Bearing)
1098 209-P-005A-M DEHEPTANIZER BOTTOMS PUMP Pengajuan job list TA 2022 dari sisi Overhaul, periodic maintenance and inspection MV motor
inspection MV motor IOM-PROD-ARO-000 4. Painting
5. Solo Run
6. Alignment
7. Test Run

Finalisasi Job List TA-23 rev4 230518 8 OF 19


JOB LIST T/A TH. 2023 REV.4
JOB LIST TA-22 KILANG PT.TPPI TUBAN
PT. Trans Pasific Petrochemical Indotama
Turnaround - Relita Department
CRETERIA REFERENCE
NO. EQUIPMENT NO. SERVICE JOB LIST RECOMMENDATION-INSP/REL/PE REASON MAIN JOB TA-22
PI MI INSP OPT
NO. DESCRIPTION

1. Rack Out-Rack In Power


2. Lepas-Pasang Coupling
3. Overhaul - Inspection Motor (Winding, Isolasi,
Overhaul, periodic maintenance and IOM-REL-003 Bearing)
1099 209-P-005B-M DEHEPTANIZER BOTTOMS PUMP Pengajuan job list TA 2022 dari sisi Overhaul, periodic maintenance and inspection MV motor
inspection MV motor IOM-PROD-ARO-000 4. Painting
5. Solo Run
6. Alignment
7. Test Run

1. Rack Out-Rack In Power


2. Lepas-Pasang Coupling
3. Overhaul - Inspection Motor (Winding, Isolasi,
Overhaul, periodic maintenance and IOM-REL-003 Bearing)
1100 211-P-012A-M HEAVY AROMATICS COL.BOT.PUMP Pengajuan job list TA 2022 dari sisi Overhaul, periodic maintenance and inspection MV motor
inspection MV motor IOM-PROD-ARO-000 4. Painting
5. Solo Run
6. Alignment
7. Test Run

1. Rack Out-Rack In Power


2. Lepas-Pasang Coupling
3. Overhaul - Inspection Motor (Winding, Isolasi,
Overhaul, periodic maintenance and IOM-REL-003 Bearing)
1101 211-P-012B-M HEAVY AROMATICS COL.BOT.PUMP Pengajuan job list TA 2022 dari sisi Overhaul, periodic maintenance and inspection MV motor
inspection MV motor IOM-PROD-ARO-000 4. Painting
5. Solo Run
6. Alignment
7. Test Run

1. Rack Out-Rack In Power


2. Lepas-Pasang Coupling
3. Overhaul - Inspection Motor (Winding, Isolasi,
Overhaul, periodic maintenance and IOM-REL-003 Bearing)
1102 211-P-004A-M XYLENE RERUN COL.BOT. PUMP Pengajuan job list TA 2022 dari sisi Overhaul, periodic maintenance and inspection MV motor
inspection MV motor IOM-PROD-ARO-000 4. Painting
5. Solo Run
6. Alignment
7. Test Run
1. Rack Out-Rack In Power
2. Lepas-Pasang Coupling
3. Overhaul - Inspection Motor (Winding, Isolasi,
Overhaul, periodic maintenance and IOM-REL-003 Bearing)
1103 211-P-004B-M XYLENE RERUN COL.BOT. PUMP Pengajuan job list TA 2022 dari sisi Overhaul, periodic maintenance and inspection MV motor
inspection MV motor IOM-PROD-ARO-000 4. Painting
5. Solo Run
6. Alignment
7. Test Run

1. Rack Out-Rack In Power


2. Lepas-Pasang Coupling
3. Overhaul - Inspection Motor (Winding, Isolasi,
Overhaul, periodic maintenance and IOM-REL-003 Bearing)
1104 211-P-004C-M XYLENE RERUN COL.BOT. PUMP Pengajuan job list TA 2022 dari sisi Overhaul, periodic maintenance and inspection MV motor
inspection MV motor IOM-PROD-ARO-000 4. Painting
5. Solo Run
6. Alignment
7. Test Run
1. Rack Out-Rack In Power
2. Lepas-Pasang Coupling
3. Overhaul - Inspection Motor (Winding, Isolasi,
Overhaul, periodic maintenance and IOM-REL-003 Bearing)
1105 211-P-006A-M XYLENE SPLITTER BOT.PUMP Pengajuan job list TA 2022 dari sisi Overhaul, periodic maintenance and inspection MV motor
inspection MV motor IOM-PROD-ARO-000 4. Painting
5. Solo Run
6. Alignment
7. Test Run
1. Rack Out-Rack In Power
2. Lepas-Pasang Coupling
3. Overhaul - Inspection Motor (Winding, Isolasi,
Overhaul, periodic maintenance and IOM-REL-003 Bearing)
1106 211-P-006B-M XYLENE SPLITTER BOT.PUMP Pengajuan job list TA 2022 dari sisi Overhaul, periodic maintenance and inspection MV motor
inspection MV motor IOM-PROD-ARO-000 4. Painting
5. Solo Run
6. Alignment
7. Test Run

1. Rack Out-Rack In Power


2. Lepas-Pasang Coupling
3. Overhaul - Inspection Motor (Winding, Isolasi,
Overhaul, periodic maintenance and IOM-REL-003 Bearing)
1107 211-P-006C-M XYLENE SPLITTER BOT.PUMP Pengajuan job list TA 2022 dari sisi Overhaul, periodic maintenance and inspection MV motor
inspection MV motor IOM-PROD-ARO-000 4. Painting
5. Solo Run
6. Alignment
7. Test Run

1. Rack Out-Rack In Power


2. Lepas-Pasang Coupling
3. Overhaul - Inspection Motor (Winding, Isolasi,
Overhaul, periodic maintenance and IOM-REL-003 Bearing)
1108 211-P-006D-M XYLENE SPLITTER BOT.PUMP Pengajuan job list TA 2022 dari sisi Overhaul, periodic maintenance and inspection MV motor
inspection MV motor IOM-PROD-ARO-000 4. Painting
5. Solo Run
6. Alignment
7. Test Run

1. Rack Out-Rack In Power


2. Lepas-Pasang Coupling
3. Overhaul - Inspection Motor (Winding, Isolasi,
Overhaul, periodic maintenance and IOM-REL-003 Bearing)
1109 211-P-008A-M Parex Feed Pump Pengajuan job list TA 2022 dari sisi Overhaul, periodic maintenance and inspection MV motor
inspection LV motor IOM-PROD-ARO-000 4. Painting
5. Solo Run
6. Alignment (by revamp)
7. Test Run (joint with revamp)
1. Rack Out-Rack In Power
2. Lepas-Pasang Coupling
3. Overhaul - Inspection Motor (Winding, Isolasi,
Overhaul, periodic maintenance and IOM-REL-003 Bearing)
1110 211-P-008B-M Parex Feed Pump Pengajuan job list TA 2022 dari sisi Overhaul, periodic maintenance and inspection MV motor
inspection LV motor IOM-PROD-ARO-000 4. Painting
5. Solo Run
6. Alignment (by revamp)
7. Test Run (joint with revamp)
1. Rack Out-Rack In Power
2. Lepas-Pasang Coupling
3. Overhaul - Inspection Motor (Winding, Isolasi,
Combustion Air Fan Motor untuk Bearing)
1111 202-K-002B-M
202-H-001/H-002 dan 203-H-005 4. Painting
5. Solo Run
6. Alignment
7. Test run

1. Rack Out-Rack In Power


2. Lepas-Pasang Coupling
3. Overhaul - Inspection Motor (Winding, Isolasi,
Overhaul, periodic maintenance and IOM-REL-003 Bearing)
1112 211-K-001A-M Combustion Air Fan for 211-H-001 Pengajuan job list TA 2022 dari sisi Overhaul, periodic maintenance and inspection MV motor
inspection LV motor IOM-PROD-ARO-000 4. Painting
5. Solo Run
6. Alignment
7. Test Run

1. Rack Out-Rack In Power


2. Lepas-Pasang Coupling
3. Overhaul - Inspection Motor (Winding, Isolasi,
Overhaul, periodic maintenance and IOM-REL-003 Bearing)
1113 211-K-001B-M Combustion Air Fan for 211-H-001 Pengajuan job list TA 2022 dari sisi Overhaul, periodic maintenance and inspection MV motor
inspection LV motor IOM-PROD-ARO-000 4. Painting
5. Solo Run
6. Alignment
7. Test Run

1. Rack Out-Rack In Power


2. Lepas-Pasang Coupling
3. Overhaul - Inspection Motor (Winding, Isolasi,
Overhaul, periodic maintenance and IOM-REL-003 Bearing)
1114 211-K-002A-M Combustion Air Fan for 211-H-002 Pengajuan job list TA 2022 dari sisi Overhaul, periodic maintenance and inspection MV motor
inspection LV motor IOM-PROD-ARO-000 4. Painting
5. Solo Run
6. Alignment
7. Test Run

1. Rack Out-Rack In Power


2. Lepas-Pasang Coupling
3. Overhaul - Inspection Motor (Winding, Isolasi,
Overhaul, periodic maintenance and IOM-REL-003 Bearing)
1115 211-K-002B-M Combustion Air Fan for 211-H-002 Pengajuan job list TA 2022 dari sisi Overhaul, periodic maintenance and inspection MV motor
inspection LV motor IOM-PROD-ARO-000 4. Painting
5. Solo Run
6. Alignment
7. Test Run

1. Rack Out-Rack In Power


2. Lepas-Pasang Coupling
3. Overhaul - Inspection Motor (Winding, Isolasi,
Overhaul, periodic maintenance and IOM-REL-003 Bearing)
1116 211-K-003A-M Combustion Air Fan for 211-H-003 Pengajuan job list TA 2022 dari sisi Overhaul, periodic maintenance and inspection MV motor
inspection LV motor IOM-PROD-ARO-000 4. Painting
5. Solo Run
6. Alignment
7. Test Run

Finalisasi Job List TA-23 rev4 230518 9 OF 19


JOB LIST T/A TH. 2023 REV.4
JOB LIST TA-22 KILANG PT.TPPI TUBAN
PT. Trans Pasific Petrochemical Indotama
Turnaround - Relita Department
CRETERIA REFERENCE
NO. EQUIPMENT NO. SERVICE JOB LIST RECOMMENDATION-INSP/REL/PE REASON MAIN JOB TA-22
PI MI INSP OPT
NO. DESCRIPTION

1. Rack Out-Rack In Power


2. Lepas-Pasang Coupling
3. Overhaul - Inspection Motor (Winding, Isolasi,
Overhaul, periodic maintenance and IOM-REL-003 Bearing)
1117 211-K-003B-M Combustion Air Fan for 211-H-003 Pengajuan job list TA 2022 dari sisi Overhaul, periodic maintenance and inspection MV motor
inspection LV motor IOM-PROD-ARO-000 4. Painting
5. Solo Run
6. Alignment
7. Test Run

(new motor replace by revamp)


1. Rack Out-Rack In Power
2. Lepas-Pasang Coupling
3. Overhaul - Inspection Motor (Winding, Isolasi,
Overhaul, periodic maintenance and IOM-REL-003
1118 211-P-002A-M Reformate splitter OH pump Pengajuan job list TA 2022 dari sisi Overhaul, periodic maintenance and inspection MV motor Bearing)
inspection LV motor IOM-PROD-ARO-000
4. Painting
5. Solo Run
6. Alignment
7. Test Run

(new motor replace by revamp)


1. Rack Out-Rack In Power
2. Lepas-Pasang Coupling
3. Overhaul - Inspection Motor (Winding, Isolasi,
Overhaul, periodic maintenance and IOM-REL-003
1119 211-P-002B-M Reformate splitter OH pump Pengajuan job list TA 2022 dari sisi Overhaul, periodic maintenance and inspection MV motor Bearing)
inspection LV motor IOM-PROD-ARO-000
4. Painting
5. Solo Run
6. Alignment
7. Test Run
1. Rack Out-Rack In Power
2. Lepas-Pasang Coupling
3. Overhaul - Inspection Motor (Winding, Isolasi,
Overhaul, periodic maintenance and Bearing)
1120 861-P-002-M SERVICE WATER JOCKEY PUMP IOM-REL-003 Pengajuan Job List TA 2022 Overhaul, periodic maintenance and inspection MV motor
inspection LV motor 4. Painting
5. Solo Run
6. Alignment
7. Test Run

1. Rack Out-Rack In Power


2. Lepas-Pasang Coupling
3. Overhaul - Inspection Motor (Winding, Isolasi,
Overhaul, periodic maintenance and Bearing)
1121 834-P-004-M BFO PUMP MOTOR TO BERTH#3 IOM-REL-003 Pengajuan Job List TA 2022 Overhaul, periodic maintenance and inspection MV motor
inspection LV motor 4. Painting
5. Solo Run
6. Alignment
7. Test Run

1. Rack Out-Rack In Power


2. Lepas-Pasang Coupling
3. Overhaul - Inspection Motor (Winding, Isolasi,
Overhaul, periodic maintenance and Bearing)
1122 834-P-005-M BFO CLOSED DRAIN PUMP MOTOR IOM-REL-003 Pengajuan Job List TA 2022 Overhaul, periodic maintenance and inspection MV motor
inspection LV motor 4. Painting
5. Solo Run
6. Alignment
7. Test Run

1. Rack Out-Rack In Power


2. Lepas-Pasang Coupling
3. Overhaul - Inspection Motor (Winding, Isolasi,
Overhaul, periodic maintenance and Bearing)
1123 834-P-001-A-M CTG FUEL OIL PUMP A MOTOR IOM-REL-003 Pengajuan Job List TA 2022 Overhaul, periodic maintenance and inspection MV motor
inspection LV motor 4. Painting
5. Solo Run
6. Alignment
7. Test Run

1. Rack Out-Rack In Power


2. Lepas-Pasang Coupling
3. Overhaul - Inspection Motor (Winding, Isolasi,
Overhaul, periodic maintenance and Bearing)
1124 834-P-001-B-M CTG FUEL OIL PUMP B MOTOR IOM-REL-003 Pengajuan Job List TA 2022 Overhaul, periodic maintenance and inspection MV motor
inspection LV motor 4. Painting
5. Solo Run
6. Alignment
7. Test Run

1. Rack Out-Rack In Power


2. Lepas-Pasang Coupling
3. Overhaul - Inspection Motor (Winding, Isolasi,
Overhaul, periodic maintenance and Bearing)
1125 834-P-001-C-M CTG FUEL OIL PUMP C MOTOR IOM-REL-003 Pengajuan Job List TA 2022 Overhaul, periodic maintenance and inspection MV motor
inspection LV motor 4. Painting
5. Solo Run
6. Alignment
7. Test Run
1. Isolated of power supply and put in rack out position
2. Oil purifying and oil testing (DGA, BDV, water
content and etc.)
Overhaul Trafo include Replace gasket and
1263 700-XMFR-011 HV Transformer 36/6.3 KV x IOM-REL-003 Pengajuan Job List TA 2022 3. Inspect and testing (Tan delta, index polarity, ratio
bushing (oil leak)
test, winding resistant test and etc.)
4. Inspect and tighten all connection
5. Check and function protection device
1. Isolated of power supply and put in rack out position
2. Oil purifying and oil testing (DGA, BDV, water
content and etc.)
Overhaul Trafo include Replace gasket and
1264 980-XMFR-011 HV Transformer 36/6.3 KV x IOM-REL-003 Pengajuan Job List TA 2022 3. Inspect and testing (Tan delta, index polarity, ratio
bushing (oil leak)
test, winding resistant test and etc.)
4. Inspect and tighten all connection
5. Check and function protection device

Finalisasi Job List TA-23 rev4 230518 10 OF 19