Now undertake the JSA and record in the table below. Use prompts on JSA Prompt Sheet and Hazard Checklist PA-HSEC-02-040-002-F03.
Part 3: Contingency Plans. All work fronts will have a first aider c/w a first aid kit. The first aider will be responsible in the event of an
emergency/incident. The first response will then be activating DEL ERP!!!
Part 4: Review. After the job has been completed, JSA leader should note: any hazards, which were identified in the original JSA? Any practices
that need to be captured in the OMS? List action items, changes, and transfer any changes to the Change Management system.
File: 10.30
Heat Stress/Exhaustion
Pakistan Asset Team PA-HSEC-02-040-002-F01
BHP Billiton Page 4 of 7
JOB SAFETY ANALYSIS WORKSHEET
Unauthorized operator doing the job Only trained and authorized person will operate
the crane
Fire
No smoking policy on the site is mandatory. Fire
extinguisher(DCP) must be present in the area
Miscommunication
Proper communication must be present at the area
at all times. Only one man signal man rigger to
convey message to operator
Hand injury
6. Construction of new SWP & CWP No proper access and egress Ensure workers are wearing the hand gloves
Includes concreting and bricks Trips/falls Ensure that all area excavated was secured and
installation using mixer machine barricaded with scaffolding pipe.
No proper access and egress
Ensure that proper access was provided to worker
Back injury
Ensure that all area excavated was secured and
Pinch point hazard
barricaded with scaffolding pipe.
Dust
Ensure that proper access was provided to worker