Rulebook
Rulebook
Article 1.
This Rulebook shall prescribe the form, content and manner of keeping a Work Book (construction diary)
and Book of Quantity ( construction book)
Work Book is kept in the form of a book,A4 format with hard covers, containing cover page and
interconnected internal pages in which should include the following data:
1. The cover page: book number, name of construction, address of building, number and date of
construction permit, the institution that issued it, the title "Work Book ", name and surname or
title of the investors and his address (seat), name of the legal entity – designer with license
number, name and surname with authorization number of the main designer, name of the legal
entity- Contractor with tne number of licence, name and surname with authorization number
for the engineer for construction (Project Manager) who lead the construction, name of the
legal entity for performing supervision with license number, name and surname with the
authorization number of the supervisory Engineer, date of start of the construction, date of
completion of construction and duration (period) of construction. The date of the beginning of
construction is recorded in the first Work Book and date of the completion of construction is
recorded in the last Work Book, whereas in all others Work Books are recorded the period of
construction between first and last Work Book.
7.
10. and
11. Technical
12. Commitment for
number of working people on qualifications number and type of the involved transport means,
number and type of engaged in construction machinery.
In the records of the contractor entered into text and sketch the type, amount, manner of the
works, their disposition, data quantity, quality of apply and embedded building materials, all
changes incurred during the construction documentation and of participants in building, name,
in me and signature of the person who completed the diary, Name and signature of the anaging
engineer re vedba and the name and signature of the investor. In record the supervising
engineer, the designer's supervision and the inspector shall contain findings or observations of
the supervisory engineer, and the potential findings and observations of project supervision
Regarding the necessary design changes and notes the competent inspector in terms of quality
and way of performance of building, with their name, surname and signature.
Internal pages of the construction diary uniform and fill in two copies of carbonless paper, from
that on one sample individually reserve contractor and Supervisory engineer.
The form and content of the construction diary set out in Annex 1 which is an integral part of
this Regulation.
Article 3
The construction diary is kept every day from the beginning to completion of construction.
In the construction diary entry and the days or periods of no activity on the construction site, all
power performance of construction It works during construction, and the reasons that led to
their termination.
Article 4
Construction diary is kept in a way that enroll activities performed on site during the
performance construction works, in form and content that allows to prove reliability of
building, or compliance the conditions of the construction works, According to the project
solutions and requirements contained in basic design.
Article 5
Construction paper is kept in the form of a book format A4 with claims covers which contains
Home page and each other connected Home Pages in that are entered next data:
1. On the cover: book number, name of construction, building address, number and date of
approval for building and authority which it issued, title "Construction Book " name, or title
Of developer and his seat title of legal person – Designer with number of license, name and
surname number of franchise
the designer, name of the legal entity – contractor with number of License name and surname
with number of authorization Performance engineer managing the construction, title the legal
entity for supervision with license number, name and surname of the number of authorization
the supervision engineer, date of start of construction, date of completion of building and
period of construction. If the land book is more samples, the date of completion of construction
to writes only of latest book while in all remain
"Construction
book ", name of the building, the name of the contractor, name of oversight, book number,
month / date of
write
of
performed
things
title
of
developer
of
performed
things.
Of
end
from
page
are
entered
total
amounts
for
Transmission
of
all right
page
to
getting
of
overall
quantity
from
performed
affairs
certified with the name and signature of the artist, and the
Paper uniform
and
are
Article 6
construction products and equipment that are built into the structure
and basis for preparation of the interim situation
Article 7
Construction book
of construction.