Period Customer Orders

1 80
2 50
3 30
4 10

(A) Projected (C = A - B) Net (MPS + C)


Inventory from (B) Inventory Projected On-
Period Previous Period Requirements* Before MPS MPS* Hand Inventory
1 0 80 (80) 100 20
2 20 70 (50) 100 50
3 50 70 (20) 100 80
4 80 70 10 0 10

Starting Inv. = 0 1 2 3 4
Forecast 70 70 70 70
Customer orders 80 50 30 10
Projected on-hand inventory 20 50 80 10
MPS 100 100 100 0
ATP 20 50 60 0

Week 0 1 2 3 4
Forecast 70 70 70 70
Customer orders (committed) 80 50 30 10
Projected on-hand inventory 20 50 80 10
MPS 100 100 100 0
ATP 20 50 60 0
5 6 7 8

10 10 10 10