M/S.

Arenco Real Estate


P.O. BOX 122752
DUBAI (U.A.E)

OCT 27, 2023

PROJECT: EXISTING WARE HOUSE MODIFICATION - ARENCO - JEBEL ALI

SUBJECT: TENDER PROPOSAL-R0

REFERENCE: BNS – P540/T-R0/2023

We would like to thank you for inviting us to bid for the above project. We are pleased to submit
our competitive price according to your requirements and hope you will give us an opportunity
to serve you. We are committed to provide you professional service with our team of professional
qualified staff along with specialized subcontractors and suppliers.

A. PROJECT PRICE:
Our price based on the Specification, drawings, and in accordance with the mentioned comments
shall be AED 967,900.00 (AED Nine Hundred Sixty Seven Thousand Nine Hundred
Only) + 5% VAT as per applicable laws.

We trust you will find our offer satisfactory and in line with your requirements. For any queries
or clarifications, please feel free to contact us.

We look forward to hear from you soon and assure you our best services and attention always.

Yours truly,

For BNS Contracting L.L.C

Manish Bhatia

Managing Director
PROJECT: EXISTING WARE HOUSE MODIFICATION - ARENCO - JEBEL ALI

BILL OF QUANTITIES

CONTRACTOR: BNS CONTRACTING LLC

AMOUNT
S.NO ITEM DESCRIPTION UNIT QTY. RATE
Dirhams

A GENERAL REQUIREMENTS

Provide site temporary Covering, workshops,


secure storage areas, temporary external lighting,
A.1 Item 1 52,000.00 52,000.00
plant, and remove on completion, including that for
all Sub- Contractors.

Water and Electrocity Connections Supply by client


Not Including any kind of Authority charges or
Payments for Approvals

B PANELING WORK

Supply and Fixing 0.5mm GI + 50mm PIR + 0.5mm


GI Flat Slip Joint Profile. Multilow Ribbed for internal
B.1 m² 1,530.00 130.00 198,900.00
wall area with using necessary materials and
equipments

Sandwich panel considerd to be fixing in 5m


Height existing block work and balance area
free standing

Supply and Fixing 0.5mm GI + 50mm PIR + 0.5mm


B.2 GI Flat Slip Joint Profile. Multilow Ribbed for Ceiling m² 1,800.00 155.00 279,000.00
area with using necessary materials and equipments.

Ceiling panel directily fixing above the


Existing Roof Purlings.

C HVAC WORK

SITC OF Refrigeration system indoor complete and


C.1 motor, all accessories and controls factory assembled
and tested as under (+15 deg C) - 5 Sets

LS 1.00 438,000.00 438,000.00


SITC OF Refrigeration system outdoor complete
C.2 and motor, all accessories and controls factory
assembled and tested as under (+15 deg C) - 5 Sets

C.3 Accessories and Panels - 5 Sets

SCOPE OF ELECTRICAL WORK CONSIDER :-


ISOLATOR TO AC UNITS WIRING CONSIDER
DRAIN PIPE UP TO 3 METER

EXCLUSION:-
ELCTRICAL POWER SUPPLY NOT CONSIDER FORM
DB TO ISOLATORS FOR AC UNITS

DRAIN PIPE HEADER NOT CONSIDER


SCAFFOLDING/ MAN LIFT NOT CONSIDERED

ELECTRICAL POWER REQUIREMNETS

TOTAL POWER REQUIREMENT - 235 KW (ONLY


FOR AC UNITS)

TOTAL AMOUNT 967,900.00


Existing Room

WAREHOUSE -3
RUD 3.0MX4.0M

AIR CONDITIONED
1800 SQM