Professional Documents
Culture Documents
Mobily Tbpo Civil Specs
Mobily Tbpo Civil Specs
CIVIL SPECIFICATION
ETIHAD- ETISALAT
COMPANY MOBILY
CIVIL SPECIFICATION
(STRUCTURAL / ARCHITECTURAL)
ETIHADꞏETISALAT- MOBILY TBP&O
CIVIL SPECIFICATION
TABLE OF CONTENTS
2
ETIHADꞏETISALAT- MOBILY TBP&O
CIVIL SPECIFICATION
3
ETIHADꞏETISALAT- MOBILY TBP&O
CIVIL SPECIFICATION
DIVISION (1)
Definitions:
This section of the General Requirements defines certain terms used in the Specifications,
and explains the language abbreviations thereof, format and certain conversion used in the
specifications and associated contract documents.
A. The Owner/ The Engineer: referred in the Specifications shall mean Etihad-
Etisalat - Mobily, Kingdom of Saudi Arabia, SUPERVISION Engineer or his
authorized representative.
B. Project Site: The space available to the Contractor for the performance of the
work, either exclusively or in conjunction with others performing other work as part
of the project. The extent of the project site is shown on the drawings, and may or
may not be identical with the description of the land upon which the project is to
be built.
C. Construction Schedule: Before the work is started, the Contractor shall prepare
a detailed schedule of all construction operations involved indicating the
sequence of work, starting date and completion of each activity and installation;
schedule of equipment/manpower loading, cash flow, etc. as per the requirement
of owner or his representative.
The schedule shall be submitted to the Owner or his representative for review and
approval.
D. Progress Report: the contractor / consultant shall prepare daily, weekly and
monthly report which includes progress of work, manpower, cash flow etc..
Supported by photos from the site and shall be submitted to the owner for review
and following.
4
ETIHADꞏETISALAT- MOBILY TBP&O
CIVIL SPECIFICATION
Shop drawing acceptance shall be obtained prior to execution of the work detailed
on such submittal. Any work done prior to such acceptance shall be Contractor's
work. The Contractor shall maintain at the work site a complete file of all accepted
shop drawings. The file will be subject to Client's review and shall be provided to
Client at the time of inspection, tests, etc.
I. As Built drawings: Upon completion of all work, the Contractor shall submit three
(3) sets of "As-builr drawings (white line) and four (4) set of complete sets of
Computer (CD) Compact Disk for the entire project. These drawings/shop
drawings shall indicate all deviations from the contract drawings/shop drawings
including dimensions, quantities, materials and products.
Contractor shall designate one of his key personnel as Quality Control Supervisor.
It shall be the sole duty and responsibility of the Quality Control Supervisor and
his staff to organize, coordinate, conduct and otherwise implement the Quality
Control Plan as submitted by the Contractor and approved by the Owner (Client).
J. Codes and standard: they are the permanent reference for engineering, and
they are regulations and standards to be followed during design and
implementation.
END OF SECTION
5
ETIHADꞏETISALAT- MOBILY TBP&O
CIVIL SPECIFICATION
DIVISION (2)
Codes & References
Comply with the provisions of the following codes specifications and standards,
except as otherwise shown or specified.
- SBC-201 (Saudi Building Code-General).
- SBC-301 (Saudi Loading Code).
- SBC-302 (Saudi Construction Code).
- SBC-303 (Saudi Soils and Foundation Code).
- SBC-304 (Saudi Concrete Structures Code).
- SBC-306 (Saudi Steel Structure Code).
- Saudi Energy Efficiency center.
- ACI 318 (Building Code Requirements for Reinforced Concrete).
- ACI 315(Manual of Standard Practice for Detailing Reinforced Concrete
Structures).
- ACI 311 "Recommended Practice for Concrete Inspection".
- ASCE_Minimum_Design_Loads_and_Associated_Criteria_for_Buildings
- ASTM – American Society for Testing and Materials
- ASTM (C33) – Standard Specification for Concrete Aggregates
- ASTM (C39) – Standard Method of Test for Compressive Strength of
Cylindrical Concrete Specimens.
- ASTM (C94) – Specification for ready-mixed concrete
- ASTM (C150) – Specification for Portland cement.
- ASTM (C143)- American Standard Test Method for Slump
- ASTM (C31) - Standard Practice for Making and Curing Concrete Test
Specimens.
- PCI MNL-116 Prestressed Concrete Institute, "Manual for Quality Control"
- AISC "Specification for the Design, Fabrication, and Erection of Structural
Steel for Buildings," including "Commentary of the AISC Specifications."
- AISC "Specification for the Design of Cold-formed Steel Structural
Members."
- AWS D1.1 "Structural Welding Code" and "Welding Handbook."
- ASTM A615 "Deformed and Plain Billet-Steel Bars for Concrete
Reinforcement."
- ASTM A706 "Low Alloy Steel Deformed Bars for Concrete Reinforcement."
- SASO - Saudi Standards Organization
- SASO SSA 1068 “ Saudi Standards Organization Ready - mixed concrete”
- SASO 2 "Steel Bars for the Reinforcement of Concrete."
- SASO 223 "Method of Testing for Steel Fabric for Concrete Reinforcement."
- SASO 224 "Steel Fabric for Reinforcement of Concrete."
- NFPA No. 101 “National Fire Protection Association”.
- BHMA 1101 “Builders Hardware Manufacturers Association”.
- ANSI “The American National Standards Institute”.
- NFRC 500 “ National Fenestration Rating Council”
6
ETIHADꞏETISALAT- MOBILY TBP&O
CIVIL SPECIFICATION
7
ETIHADꞏETISALAT- MOBILY TBP&O
CIVIL SPECIFICATION
DIVISION (3)
Site Preparation
3.1 Site Protection & Safety Requirements
‐ Protect existing work to remain in place by temporary fence, covers, shoring,
bracing, and supports. Repair such items that are damaged during performance
of the work or replace with new material. Do not overload structural elements.
Provide new supports or reinforcement for existing construction which is
weakened by demolition or removal work.
‐ The site should be safe during the construction and the contractor shall take all
necessary steps to prevent accidents, injuries, occupational illness and property
damage. For the avoidance of doubt, such responsibility includes responsibility
for subcontractors and suppliers, and must comply with all applicable health and
safety laws and regulations, including those dealing with labor hygiene. In
addition, contractors must promptly comply with any specific instructions or
directions regarding HSE matters issued by Mobily.
‐ The contractor must ensure that immediate and proper first-aid and/or
medical/hospital treatment will be provided for every work-related injury. All
accidents and incidents occurring on site must be reported to the management,
even where there is no injury involved. Mobily and the appropriate authorities
must be informed immediately if the accident results in serious injuries or fatality
8
ETIHADꞏETISALAT- MOBILY TBP&O
CIVIL SPECIFICATION
‐ The extent of site work shall be determined by visual observation of the site.
‐ The work includes but is not limited to, trash or debris, if any; and removal of
Remove existing improvements, both above-grade and below grade to the extent
indicated or as otherwise required to permit new construction.
‐ Restore damaged work to the condition existing prior to the start of work, unless
otherwise directed.
‐ Cleaning products from site clearing shall not be deposited on or in any type of
water-body or wetland. Spoil and excess topsoil shall be disposed of at the
approved Sanitary Landfill facility.
9
ETIHADꞏETISALAT- MOBILY TBP&O
CIVIL SPECIFICATION
‐ Contractor shall not start any demolition work until procedures authorizing such
work, have been approved by the Client, in writing.
‐ The contractor should be submitted for review and approval a Soil Treatment
INSPECTION AND TEST PLAN (ITP) reflecting the requirements of these
specifications and approved submittals before commencement of construction.
‐ The ITP shall address sequence, method and control of application and criteria
for acceptance of work.
10
ETIHADꞏETISALAT- MOBILY TBP&O
CIVIL SPECIFICATION
‐ The ITP shall include procedures for sampling and testing of the soil by chemical
extraction to determine the content of the termiticide solution residual in the soil
before and after treatment. The results of these tests shall constitute the control
sample. Sampling and testing shall be done by an Independent Testing
Laboratory approved by the owner.
‐ If any initial test fails, three additional retests shall be taken in the same TEST
AREA, at locations directed by the Engineer. If any of the three retests fail, the
entire TEST AREA shall be retreated and retested in compliance with this
specification and the approved ITP. If all three tests pass only the location of
original failure shall be retreated and retested.
1- Any initial test result which is less than 90% of the result of the respective
control sample shall be considered to fail.
2- Any retest result which is less than 95% of the result of the respective control
sample shall be considered to fail.
3.4.2 SAFETY
‐ The Contractor shall post warning signs in Arabic and English in areas of
application to inform workers and the public that hazardous soil treatment
(poison) has been applied. Remove signs only when treated areas are
adequately covered by concrete.
‐ The Contractor shall treat all empty containers and other contaminated materials
as hazardous waste and properly dispose in designated areas. Keep all such
waste in one area, marked as hazardous (poisonous) material until it can be
properly disposed. Do not allow such material to become mixed into other trash
or waste materials.
‐ Workers shall wear protective clothing and other apparatus recommended by the
manufacturer.
‐ In addition to requirements listed, the Contractor shall comply with all safety
recommendations made by the manufacturer or required by the Engineer.
3.4.3 Warranty
‐ The Contractor shall furnish a written warranty certifying that the applied soil
termiticide treatment will prevent infestation of subterranean termites for a period
of ten (10) years from the date of initial acceptance, signed by the Contractor and
the Applicator.
‐ The warranty shall require the Contractor to provide additional treatment if there
is any evidence of termite infestation during the warranty period. Additional
11
ETIHADꞏETISALAT- MOBILY TBP&O
CIVIL SPECIFICATION
treatment will be carried out in compliance with the specifications for post-
construction termite treatment.
‐ The warranty shall also require the Contractor to repair to the satisfaction of the
Engineer or furnish equal or better replacements for damage caused by termite
infestation during the warranty period.
3.4.4 Products
3.4.5 Execution
‐ Do not apply soil treatment solution until excavating, filling and grading
operations are completed, except as otherwise required in construction operation.
Reapply soil treatment solution to areas disturbed by construction operations
following application of soil treatment termiticide solution.
12
ETIHADꞏETISALAT- MOBILY TBP&O
CIVIL SPECIFICATION
3.5 Grading
This section covers the requirements filling and backfilling for the building.
This section consist of furnishing labor, material and equipment required to
complete all earthwork shown on the drawings.
‐ Test and approve sub -grades and fill layers before further construction
work is performed. Testing and approval of each layer shall be done to
demonstrate conformance to compaction and other requirements.
Perform tests in accordance with the following:
1- Backfill and Fill------ Type of Test is Classification Sieve Analysis/
Liquid Limit Plastic / Limit Classification (every 1000 m3 filling).
2- Compacted Fill-------- Type of Test is Density in Place & Moisture
Density (Every 2000 m2 for each layer compacted).
‐ The contractor should be consider If excavations over 1.5 meters in
depth will be sheeted and shored, submit working drawings and
calculations for the design of the sheeting and shoring.
‐ All materials suitable for use as backfill material shall be free from
organic matter, expansive clay, rubbish, debris, coral or any other
deleterious materials of any kind.
‐ The Contractor shall be responsible for locating suitable fill and backfill
material sources and for obtaining, supplying, and transporting material
to the site in sufficient quantities to complete the work.
13
ETIHADꞏETISALAT- MOBILY TBP&O
CIVIL SPECIFICATION
‐ The select fill material shall be tested by laboratory sieve analysis in accordance
with ASTM C 136 and shall conform to any of the grading specified in AASHTO
M 147.
‐ Backfill and Fill Material Types: Material shall be of the types listed
below. All materials shall be free of debris, waste, organic material, and
other deleterious matter. Except where specified otherwise, all
materials shall be free of rock or gravel larger than 100 mm. in any
dimension. The portion of the materials passing the No. 200 sieve size
(0.074 mm.) shall be non-plastic as defined in accordance with ASTM
D 4318.
Type I: Graded sands and gravel, gravel-sand / silty-sand mixtures, crushed graded rock;
little or no fines, no well-defined moisture versus maximum density relationship (GW, SW,
GP, SP).
Plasticity Index – NP to 5
Gradation – Less than 12% passing No. 200 sieve.
Type II: Clayey gravels and sands, poorly graded mixture of sand, gravel and clay, clays
(inorganic) of low to medium plasticity, sandy clays, silty clays, lean clays (CM, SM, GC, SC,
CL).
Liquid limit – 20 – 50
Plasticity Index – 5 to 22 maximum
‐ The following tests shall be used to ensure the fill meets the above requirements:
ASTM D1557 Maximum Density & Optimum Moisture Content of soils
ASTM D2487 Classification of soils for Engineering Purposes
ASTM D422 Particle-size analysis of soils
ASTM D423 Liquid limit of soils
ASTM D424 Plastic limit and plasticity – Index of soils
14
ETIHADꞏETISALAT- MOBILY TBP&O
CIVIL SPECIFICATION
3.5.3 Compaction:
‐ Place backfill and fill materials in layers not more than 200 mm. in loose depth,
unless compaction equipment can accomplish uniform specified density for
thicker layers, as demonstrated by a test strip.
‐ Compact each layer to required percentage of maximum density (95%) or relative
density for each area classification. Do not place additional layers if the previous
layers have not attained the required compaction.
‐ Material Type I shall be tested using ASTM D4253 and D4254 as laboratory
standards to determine the maximum and minimum density. At least three tests
shall be carried out and the mean value used as a standard. Following this, the
field density shall be determined using ASTM D1556 (sand-cone method),),
ASTM D2922 (Nuclear Methods) for the test strip. At least five tests shall be
carried out and the minimum relative density shall be calculated from laboratory
tests. This shall equal or exceed the specified value (e.g. 75% relative density).
‐ Percentage of Maximum Density Requirements: Compact soil to not less than the
following:
1- Structures: Compact top 300 mm. of sub-grade and each layer of backfill or
fill material to 95%maximum dry density or 75% relative density.
2- Building Slabs and Steps: Compact top 300 mm. of sub-grade and each
layer of backfill or fill material to 95% of maximum dry density or 75% relative
density.
3- Under Pavements and Shoulders: Compact top 300 mm. of sub-grade and
each 200 mm. loose layer of base course fill and each layer of sub-grade fill
to 100% maximum dry density or 78% relative density
4- Walkways: Compact top 150 mm. of sub-grade and each layer of backfill or
fill material to 95% of maximum dry density or 75% relative density.
3.5.4 Excavation
Excavation includes removal and disposal of pavements and other
obstructions on ground surface, underground structures and utilities indicated
to be demolished and removed, and all other materials encountered.
15
ETIHADꞏETISALAT- MOBILY TBP&O
CIVIL SPECIFICATION
‐ Shoring and Bracing: Provide materials for shoring and bracing, such as sheet
piling, uprights, stringers, and cross-braces, in good serviceable condition.
‐ Maintain shoring and bracing in excavations. Carry down shoring and bracing as
excavation progresses.
16
ETIHADꞏETISALAT- MOBILY TBP&O
CIVIL SPECIFICATION
‐ Coat forms with a non-staining, clear, form release agent which will not discolour
or deface the surface of the concrete.
‐ Concrete Mix, Design, And Testing: Design the mix to produce standard-weight
concrete consisting of Portland cement, aggregate and water to produce the
following properties:
‐ Check completed formwork for grade and alignment to the following tolerances:
Top of forms, not more than 3 mm in 3 meters.
Vertical face on longitudinal axis, not more than 6 mm in 3
meter.
‐ Clean forms after each use, and coat with form release agent as often as
required to ensure separation from concrete without damage.
17
ETIHADꞏETISALAT- MOBILY TBP&O
CIVIL SPECIFICATION
‐ Curing: Protect and cure finished concrete curbs and gutters complying with
applicable requirements of Division 3 sections.
‐ If the section is not indicated, the width to be excavated shall be 300 mm (12")
either sides of the outside edges of the elements.
‐ Units shall have longitudinal reinforcement and shall be cast with dowel/dowel
holes in the ends.
‐ After barrier curbs have been laid, steel forms shall be erected behind the
elements and continuous concrete backing poured and The backing concrete
shall be as specified in Section 3 .
‐ For barrier curbs without tiling to back face, the concrete backing shall extend to
a height of 50 mm (2" +, -) below the top of the curb.
END OF SECTION
18
ETIHADꞏETISALAT- MOBILY TBP&O
CIVIL SPECIFICATION
DIVISION (4)
Concrete
4.1 Concrete Form Work
The work of this section includes furnishing, fabricating, and placing of formwork for
cast-in- place concrete as indicated on the drawings.
‐ Codes and Standards: Comply with the provisions of the following codes
specifications and standards, except as otherwise shown or specified.
ACI 347 "Recommended Practice For Concrete Formwork."
ANSI A199.1 "Construction and Industrial Plywood."
‐ The contractor should be Before concrete placement to be check the lines and
levels of erected formwork. Make corrections and adjustments to ensure proper
size and locations of concrete members and stability of forming systems.
‐ During concrete placement check formwork and related supports to ensure that
forms are not displaced and that completed work will be within specified
tolerances.
‐ Design, erect, support, brace, and maintain formwork so that it will safely support
vertical and lateral loads that might be applied, until such loads can be supported
by the concrete structure. Carry vertical and lateral loads to ground by formwork
system and in place construction that has attained adequate strength for the
purpose. Construct formwork so that concrete members and structures are of
correct size, shape, alignment, elevation and position.
19
ETIHADꞏETISALAT- MOBILY TBP&O
CIVIL SPECIFICATION
‐ USE shores and struts with positive means of adjustment capable of taking up
formwork settlement during concrete placing operations, using wedges or jacks
or a combination thereof. Use trussed supports when adequate foundations for
shores and struts cannot be secured.
‐ Provide temporary openings in wall forms, column forms and at other locations
necessary to permit inspection and clean-out.
‐ Formwork not supporting concrete, such as sides of beams, walls, columns, and
similar parts of the work, may be removed after 24 hours after placing concrete,
provided concrete is sufficiently hard to not be damaged by form removal
operation, and provided that curing and protection operations are maintained.
‐ Formwork supporting weight of concrete, such as beam soffits, joists, slabs, and
other structural elements may not be removed until concrete has attained its
design compressive strength.
20
ETIHADꞏETISALAT- MOBILY TBP&O
CIVIL SPECIFICATION
The work of this Section includes furnishing, fabrication and placement of un-
coated reinforcement for cast-in-place concrete, including bars, welded wire
fabric, ties and supports.
‐ Codes and Standards: Comply with the provisions of the following codes,
specifications, and standards, except as otherwise shown or specified:
AWS D12.1 "Recommended Practices for Welding Reinforced Steel,
Metal Inserts and Connections in Reinforced Concrete Construction."
CRSI "Manual of Standard Practice."
ACI 301 "Specifications for Structural Concrete for Buildings."
ACI 315 "Manual of Standard Practice for Detailing Reinforced Concrete
Structures."
ACI 318 "Building Code Requirements for Reinforced Concrete."
ASTM A615 "Deformed and Plain Billet-Steel Bars for Concrete
Reinforcement."
ASTM A706 "Low Alloy Steel Deformed Bars for Concrete
Reinforcement."
SASO 2 "Steel Bars for the Reinforcement of Concrete."
SASO 223 "Method of Testing for Steel Fabric for Concrete
Reinforcement."
SASO 224 "Steel Fabric for Reinforcement of Concrete."
‐ The contractor Submit shop drawings for fabrication bending, and placement of
concrete reinforcement. Comply with ACI 315 "Manual of Standard Practice for
Detailing Reinforced Concrete Structures." Show bar schedules, stirrup spacing,
diagrams of bent, bars, arrangements and assemblies, as required for the
fabrication and placement of concrete reinforcement.
4.2.2 Materials:
‐ Steam reinforcing bars shall be ASTM A 615 grade 60 with ultimate tensile
strength,
Fy = 420 MPA.
‐ Steel wire fabric shall be ASTM A 185, grade 40 in flat sheet with ultimate tensile
strength, Fy = 280 MPA.
‐ Support for reinforcement: Bolster, chairs, spacers and other devices for spacing,
supporting and fastening reinforcement in place shall be provided.
21
ETIHADꞏETISALAT- MOBILY TBP&O
CIVIL SPECIFICATION
4.2.3 Installation:
‐ Comply with the CRSI recommended practice for "Placing Reinforcing Bars," for
details and methods of reinforcement placement and supports, and as herein
specified.
‐ Clean reinforcement to remove loose rust and mill scale, earth, and other
materials which reduce or destroy bond with concrete.
22
ETIHADꞏETISALAT- MOBILY TBP&O
CIVIL SPECIFICATION
‐ This Section establishes general criteria for materials, mixes and placement of
concrete as required for this and other related sections of these specifications.
‐ The work also includes constructing expansion joints, construction joints, water
stops and corrosion protection for cast-in-place concrete.
‐ Unless otherwise noted, all reinforced concrete exterior surfaces below finish
grade shall be protected by suitable water proofing (Refer to division thermal and
moisture protection).
‐ Comply with the provisions of the following codes, specifications and standards,
except as otherwise shown or specified.
Saudi Arabia Building Codes.
ACI 301 "Specifications for Structural Concrete for Buildings".
ACI 318 "Building Code Requirements for Reinforced Concrete".
ACI 304 "Recommended Practice for Measuring, Mixing, Transporting
and Placing Concrete.
‐ Portland Cement:
Provide type 1 cement or approved equal for above grade concrete
beams.
23
ETIHADꞏETISALAT- MOBILY TBP&O
CIVIL SPECIFICATION
‐ Aggregate:
Fine Aggregate: Clean, sharp, natural sand free from loam, clay, lumps,
or other deleterious substances and with rounded or sub-rounded
particles. Fine aggregate shall be selected to comply with the
requirements of ASTM C33 (Natural sand may need to be washed with
potable water to achieve these requirements)
Coarse Aggregate: Clean, uncoated, processed aggregate containing no
clay, mud, loam or foreign matter, as follows: Crushed stone, processed
from natural rock or stone & washed gravel, either natural or crushed.
Maximum aggregate size: No larger than one-fifth of the narrowest
dimension between sides of forms, one-third of the depth of slabs, nor
three-fourths of the minimum clear spacing between individual reinforcing
bars or bundles of bars.
‐ Water:
In any case that potable water is not available, the use of water with chemical
contents in according with SASO SSA 1068, shall not exceed the following limits:
24
ETIHADꞏETISALAT- MOBILY TBP&O
CIVIL SPECIFICATION
‐ Admixtures:
The contractor should be Continue curing for at least 7 days by using one
of below:
Impervious Sheeting: ASTM C 171
Burlap cloth made from jute or kenaf, weighing approximately 290
grams/m2 and complying with AASHTO M182, Class 3.
Water: Potable water
‐ Each class of concrete may consist of one or more mixes determined by the
maximum size of aggregate, slump and type of admixtures of special aggregates
used.
‐ All structural concrete embodied in the structures shall have a minimum ultimate
compressive strength of 30 MPa at 28 days unless a higher strength is indicated
on the drawings. Lean or blinding concrete shall be 17 MPa at 28 days.
‐ All concrete used for electrical and telecom duct banks (except at road crossings)
shall be lean concrete, 17 MPa strength at 28 days.
‐ Water Content: Use the minimum net water content necessary to properly place
the concrete mixture.
25
ETIHADꞏETISALAT- MOBILY TBP&O
CIVIL SPECIFICATION
‐ Water-Cement Ratio: Maximum Free Water/Cement ratio shall not exceed 0.4
(by weight) for structural concrete and shall not exceed 0.5 (by weight) for lean or
blinding concrete.
‐ Compressive strength developed at 7 days and 28 days, from not less than 4 test
cylinders cast for each 7 and 28 day test and for each design mix.
‐ Unit Weight: Unit weight of fresh concrete shall not be less than 2400 kg/m3 as
determined by ASTM C138.
‐ Slump: ASTM C143; one test for each concrete load at point of discharge.
‐ Compression Test Specimens: ASTM C31; two sets of 4 standard cylinders for
each compressive strength test, unless otherwise directed. Cast and store one
set of cylinders for laboratory cured test specimens and one set of field- cured
test specimens as specified in ASTM C31.
‐ Testing laboratory shall report test results in writing to the Engineer and
Contractor on the same day that tests are made. Reports of compressive
strength tests shall contain the project identification name and number, date of
concrete placement, name of Contractor, name of concrete supplier and truck
number, name of concrete testing service, concrete type and class, location of
concrete batch in the structure, design compressive strength at 28 days, concrete
mix proportions and materials; compressive breaking strength and type of break
for both 7 day tests and 28 day tests.
‐ The unconfined free fall distance of concrete shall not exceed one meter.
26
ETIHADꞏETISALAT- MOBILY TBP&O
CIVIL SPECIFICATION
‐ Do not use concrete which becomes non-plastic and unworkable, or does not
meet the required quality control limits, or which has been contaminated by
foreign materials. Remove rejected concrete from the project site and dispose of
it in an acceptable location.
‐ Bring slab surfaces to the correct level with a straight edge and strike off. Use
bull floats or derbies to smooth the surface, leaving it free of humps or hollows.
Do not sprinkle water on the plastic surface. Do not disturb the slab surfaces
prior to beginning finishing operations.
1- Construction Joints:
‐ In walls: at not more than 18 m in any horizontal direction; at top of footings; at
top of slabs on ground; at top and bottom of door and window openings or as
required to conform to architectural details as directed by the Engineer and at the
underside of the deepest beam or girder framing into wall.
‐ In columns or piers,: at the top of footing; at the top of slabs on ground; and at the
underside of the deepest beam or girder framing into the column or pier.
‐ Top slab : Slabs wider than 4 m should have longitudinal joint down the center
and corresponding cross joints.
‐ Place construction joints perpendicular to the main reinforcement. Continued all
reinforcement across construction joints.
2- Waterstops:
‐ Provide waterstops in construction joints as shown on the drawings. Submit
drawings showing locations. Install waterstops to form a continuous diaphragm in
each joint. Make provisions to support and protect waterstops during the progress
of the work. Fabricate field joints in waterstops in accordance with manufacturer's
printed instructions. Protect waterstop material from damage where it protrudes
from any joints.
27
ETIHADꞏETISALAT- MOBILY TBP&O
CIVIL SPECIFICATION
grade beams, and elsewhere as indicated. Joint filler and sealant materials are
specified in Division (6).
‐ Form control joints by inserting a pre molded hardboard or fiberboard strip into
the fresh concrete until the top surface of the strip is flush with the slab surface.
After the concrete has cured for at least 7 days, remove inserts and clean groove
of loose debris. Joint sealant material is specified in Division (6).
5- Expansion joint:
‐ Aluminum Retainers: Extruded aluminum alloy 6063-T5. Aluminum retainers
shall be chemically treated to prepare surfaces for complete adhesion of the
sealant.
6- Steel Grating:
‐ Steel gratings shall be galvanized at exterior locations or shall be standard shop
coat at interior locations. Gratings exposed to weather such as parking garages
or other open buildings are considered exterior locations.
‐ Submit shop drawings showing complete information for the fabrication and
installation of precast concrete units. Indicate member dimensions and cross-
28
ETIHADꞏETISALAT- MOBILY TBP&O
CIVIL SPECIFICATION
‐ Provide location and details of anchorage devices that are to be embedded in this
and other construction. Furnish templates if required for accurate placement.
‐ Panels shall be designed As a minimum, the effects of all wind loads, seismic
loads, vertical live and dead loads, and loads due to restrained volume changes
such as creep, shrinkage, and temperature changes shall be considered
‐ Panels shall not be erected earlier than 28 days after
casting.
4.5 Screed
‐ Topping as backing for floor, roof and gutter etc. to receive tiles and other
finishes shall be composed of one part cement to two parts of sand to four parts
of coarse aggregates by volume, finished even and true to exact line, level or falls
required.
29
ETIHADꞏETISALAT- MOBILY TBP&O
CIVIL SPECIFICATION
‐ Topping for paving shall be slightly adjusted in thickness to allow for different
adjacent floor finishes to finish at the same level.
‐ Comprehensive Strength (28 Days): Not less than 250 kg/cm2, cylinders for
screeds over 70 mm.
END OF SECTION
30
ETIHADꞏETISALAT- MOBILY TBP&O
CIVIL SPECIFICATION
DIVISION (5)
Masonary
The work under this section consists of furnishing and installation of all
concrete unit masonry and accessories as indicated on the drawings or as
specified herein.
5.1 Quality Assurance
‐ Construction Tolerances: Lay-up all walls and partitions plumb and true with
courses level and accurately spaced and coordinated with other work. Variations
from plumb, true or level of more than 3 mm in 2400 mm in any direction are
unacceptable.
‐ Type N1, load bearing concrete hollow blocks, with Ultimate compressive
strength at 28 days fm = 10 MPa .
‐ Hollow Load-bearing: Provide units complying with ASTM C90 type I normal
weight.
‐ Portland cement: ASTM C150, Type I. Provide natural color or white cement as
required to produce the required mortar color.
‐ Type Sand: ASTM C144, except for joints less than 6 mm, use aggregate graded
with 100% passing the No. 16 sieve.
‐ Water: Potable.
31
ETIHADꞏETISALAT- MOBILY TBP&O
CIVIL SPECIFICATION
Truss type fabricated with single pair of 4.00 mm (9 gage) side rods
and 4.00 mm (9 gage) continuous diagonal cross-rods spaced not
more than 400 mm on center.
For use with hollow masonry units laid with cells vertical, provide
rectangular shaped ties.
For use with solid masonry units, provide ties with ends bent to 90
degree angles to form hook not less than 50 mm long.
For interior walls, fabricate from steel wire with mill galvanized
finish.
For exterior walls, fabricate from steel wire with hot dip zinc
coating, ASTM A153 Class B2, or fabricate from steel wire with not
less than
0.18 mm (7-mil) copper coating, ASTM B227, Grade 30 HS.
Provide straps, bars, bolts and rods fabricated from not less than
1.52 mm (16 gage) sheet metal or 9 mm diameter rod stock,
unless otherwise indicated.
32
ETIHADꞏETISALAT- MOBILY TBP&O
CIVIL SPECIFICATION
5.5 Execution
‐ All masonry units shall be laid true to lines and levels with joints of
uniform thickness. All surface corners shall be straight and plumb.
‐ Lintels, plates, bolts and the like shall be cut or pinned or built-in.
‐ Masonry units shall be filled solid with grout at the following locations:
All cells with reinforcing.
The first two cells of unit abutting door frames.
Where embedment of anchors, bolts, bearing of wood or steel
Members, etc. occurs.
5.6 Curing
END OF SECTION
33
ETIHADꞏETISALAT- MOBILY TBP&O
CIVIL SPECIFICATION
DIVISION (6)
Metals fabrications
The work of this Section includes items fabricated from iron and steel shapes, plates,
bars strips, tubes, pipes, and castings which are not directly a part of structural steel
or other metal systems in these specifications.
6.1 Quality Assurance
‐ Codes and Standards: Comply with the applicable provisions of the following
codes, standards, and specifications, except as otherwise shown and specified.
‐ Shop Assembly: Pre Assembled items in the shop to the greatest extent possible
to minimize field splicing, welding, and assembly.
‐ The contractor / Supplier shall be submitted Samples before erection: Submit sets
of representative samples of materials and finishes for products exposed to view.
The review will be for colour, texture, style, and finish of metal fabrications.
6.2 Materials
The steel materials fabricated shall be according to the following standards:
‐ Steel Plates, Shapes and Bars: ASTM A36.
‐ Steel Plates to be Bent or Cold-formed: ASTM A283, Grade C.
‐ Steel Bars and Bar-size Shapes: ASTM A663 or ASTM A675, Grade 65, or
ASTM A36.
‐ Steel Tubing: ASTM A501, Hot-formed, welded or seamless, including square,
rectangular, round, and special shapes.
‐ Cold-finished Steel Bars: ASTM A108, grade as selected by the fabricator.
34
ETIHADꞏETISALAT- MOBILY TBP&O
CIVIL SPECIFICATION
‐ Fabricate ladders for the locations shown, with dimensions, spacings, details, and
anchorages as indicated. Comply with the requirements of ANSI A14.3, except
as otherwise indicated.
‐ Fit rungs in centreline of side rails, plug weld and grind smooth on outer
rail faces.
‐ Support each ladder at top and bottom and at intermediate points spaced not
more than 1500 mm on center. Provide anchors for embedding in concrete use
welders or bolted steel brackets, designed for adequate support and anchorage,
and to hold the ladder clear of the wall surface with a minimum of 175 mm
clearance from wall to centreline of rungs. Extend rails 1000 mm above top rung,
and return rails to wall or structure unless other secure handholds are provided.
If the adjacent structure does not extend above the top rung, goose-neck the
extended rails back to the structure to provide secure ladder access.
‐ Anodize all ladders, brackets, and fasteners.
35
ETIHADꞏETISALAT- MOBILY TBP&O
CIVIL SPECIFICATION
details of fabrication and support. Use the type of materials shown or specified
for the various components of the work.
‐ Metal Bar Grating: Comply with NAAMM "Metal Bar Grating Manual" and as
herein specified.
‐ Steel Finish: Hot-dip galvanized after fabrication.
6.2.4 Steel Grating
‐ Fabricate pipe railings and hadnrails to dimensions and details shown, with
smooth bends and welded joints ground smooth and flush.
‐ Adjust railings prior to anchoring to ensure matching alignment at butting joints.
Space posts not more than 2400 mm on centers, unless otherwise shown.
‐ Secure handrails to walls with wall brackets and end fittings. Provide brackets
with not less than 75 mm clearance from inside face to handrill to the finish wall
surface. Drill wall plate portion of bracket to receive bolt,
‐ Galvanize all steel railings, including pipe, fittings, brackets, fasteners, and other
ferrous metal components.
‐ Coating : Hot-dip galvanized on according with ASTM A123
‐ Red lead mixed pigment, alkyd varnish, linseed oil paint or red lead iron oxide,
raw linseed oil, alkyd paint, complying with Steel Structures Painting Council
(SSPC) Paint 2-64; or basic lead silico chromate base iron oxide, linseed oil,
alkyd paint.
‐ Primer paint selected must be compatible with the required finish coats of paint.
Coordinate selection of metal primer with finish paint requirements specified in
Section 09900.
‐ Galvanizing Repair and Primer Paint: Zinc dust or zinc oxide, alkyd paint.
‐ The coating system shall be applied by spray equipment to get a uniform
calibrated coating. Allow at least 24 hrs drying time between coats and 5 days
before any top coating.
‐ Protection using fire resistant system, the paint shall have the following:
1 hour Fire resistance (thermal insulation and bum through protection).
Adhesive to prime and bare substrate.
Flexible.
Crack resistance under vibrating conditions.
Rapid fire test according to ASTM E-199 (UI263).
6.4 Execution
‐ Examine the areas and conditions under which metal fabrication items are to be
installed.
‐ Coordinate setting drawings, diagrams, templates, instructions, and directions for
installation of anchor- age such as concrete inserts, anchor bolts, and
miscellaneous items having integral anchors, which are to be embedded in
concrete or masonry construction. Coordinate the delivery of such items to the
affected trades for installation.
36
ETIHADꞏETISALAT- MOBILY TBP&O
CIVIL SPECIFICATION
‐ Field Welding:
Comply with AWS Code for procedures of arc welding, appearance and
quality of welds made, and methods used in correcting welding work.
Do not weld, cut, or abrade exposed surfaces which cannot be completely
restored in the field.
Testing Of Welds : The Contractor shall make radiographic examination
of butt welds in accordance with Section 8 of American Petroleum
Industry (API) Standard
‐ BOLTS:
Bolts, including friction –grip bolts, nuts and washers shall be hot-dip
galvanized.
END OF SECTION
37
ETIHADꞏETISALAT- MOBILY TBP&O
CIVIL SPECIFICATION
DIVISION (7)
Thermal and Moisture Protection
The work under this section consists of furnishing and application of bituminous damp
proofing over surfaces of structural members and also the thermal insulation to provide
resistance to:
38
ETIHADꞏETISALAT- MOBILY TBP&O
CIVIL SPECIFICATION
‐ Deliver materials to the site in original containers with seals unbroken, labeled
with manufacturer's name, product brand name and type, date of manufacture,
shelf life, and directions for storing and mixing with other components.
‐ Remove and replace material that cannot be applied within its stated shelf life.
7.1.2 Execution
‐ Commence work only after sleeves, vents, curbs, inserts, drains, and other
projections through have been completed and proceed only after any substrate
defects, including honeycombs, voids, and cracks, have been repaired.
39
ETIHADꞏETISALAT- MOBILY TBP&O
CIVIL SPECIFICATION
‐ The concrete surface shall be dry and shall be cleaned of all dust and debris.
‐ Cracks shall be sealed using an approved sealant using depth to width ratio as
recommended by sealant manufacturer.
-Sub-structure i.e., foundations, walls, columns, tie beams, lift, water tanks
and other pits and the like which are in direct contact with soil saturated with
ground water or areas which experience fluctuations in local ground water
table raising to the levels of the sub-structure, shall be protected as follows:
-Two layer of 4mm thick SBS Modified Bituminous membrane 180 g/sqm.
Torch bonded with reinforcing strips at all junctions and corners. The
membrane shall be protected from damage by Brick Wall thickness 12 cm to
all vertical surfaces and 50 mm thick cement / sand screed to all horizontal
surfaces.
40
ETIHADꞏETISALAT- MOBILY TBP&O
CIVIL SPECIFICATION
‐ Remove and replace material that cannot be applied within its stated shelf life.
7.2.2 Execution
‐ The concrete surface shall be dry and shall be cleaned of all dust and debris.
‐ Cracks shall be sealed using an approved sealant using depth to width ratio as
recommended by sealant manufacturer.
‐ Apply 2 or 3 coats of bitumen emulsion using brushes, rollers or sprayers at a rate
of about 2 kg/m2 to produce a uniform seamless dry film thickness approved by
the Engineer but not less than 1.3 mm. Allow time for complete drying between
coats.
‐ Before the application of protection layer, all horizontal application shall be flood
tested with a minimum of 50 mm head of clean water for 72 hours.
‐ If leaking is found, water shall be removed and leaking areas shall be repaired with
new waterproofing materials as directed by the Engineer.
41
ETIHADꞏETISALAT- MOBILY TBP&O
CIVIL SPECIFICATION
‐ Engage a testing agency to perform field inspections, test materials being used,
observe flood test and report whether tested work conforms to or deviates from
requirements.
‐ The work of this Section includes furnishing and installation of thermal insulation
for buildings and related structures.
‐ Where thermal resistance ("R" value) is specified or shown for insulation, the
thickness shown on the drawings shall be nominal. Use only insulation with actual
thickness that is not less than that required to provide the thermal resistance
specified.
‐ Where "R" value is not specified for insulation, the thickness shown on the
drawings shall be used.
42
ETIHADꞏETISALAT- MOBILY TBP&O
CIVIL SPECIFICATION
‐ Flame Spread Rating: Where required to comply with flame spread rating (ASTM
E84), provide material which has been tested and certified by the manufacturer
for compliance. Except as otherwise shown, provide flame spread rating of 25 or
less.
7.4.2 Materials
A- Extruded Polystyrene Plastic Board Insulation:
43
ETIHADꞏETISALAT- MOBILY TBP&O
CIVIL SPECIFICATION
2- Foil Faced Blanket: Reflective aluminum foil and asphalt vapor barrier
laminated to one face, with 25 mm flanges on long edges; vapor
transmission not more than 0.5 perms.
7.4.3 Installation
‐ Insulation manufacturer’s instructions shall be complied with products and
application indicated. If printed instructions are not available or do not apply to
project conditions, consult manufacturer’s technical representative for specific
recommendations before proceeding with installation of insulation.
‐ Insulation shall be cut to fit angles, corners or irregular spaces. Adjoining pieces
of insulation shall be closely butted except at expansion joint.
‐ Insulation shall not be installed which is damaged, wet, and soiled.
‐ Rigid insulating units shall be installed with joints close and flush, in regular
courses and with cross joints broken.
‐ Blanket insulation shall be installed with tight joints and filling framing void
completely. Seal cuts, tears, and unlapped joints with tape.
‐ Insulation shall be fit tight against adjoining construction and penetrations, unless
specified otherwise.
‐ The minimum level of airborne sound resistance for dividing walls or floors
between homes is 45- 55dB (decibels) in new builds. This level should easily cut
out normal levels of speech, TV and music playing.
44
ETIHADꞏETISALAT- MOBILY TBP&O
CIVIL SPECIFICATION
‐ We can achieve the requirements by using the suitable insulation that give us the
Allowable sound resistance by using double wall masonary or insulated walls or
using rock wool in the partitions or using the special sound insulation as per
design drawings.
‐ Generator room minimum level of airborne sound resistance for dividing walls or
floors is 57- 62 dB (decibels).
45
ETIHADꞏETISALAT- MOBILY TBP&O
CIVIL SPECIFICATION
46
ETIHADꞏETISALAT- MOBILY TBP&O
CIVIL SPECIFICATION
47
ETIHADꞏETISALAT- MOBILY TBP&O
CIVIL SPECIFICATION
48
ETIHADꞏETISALAT- MOBILY TBP&O
CIVIL SPECIFICATION
‐ The work of this Section includes high performance polymer modified bituminous
sheet membrane protected by insulation and covered by thermal insulation and
other finishing layers.
‐ The extent of protected (inverted) roofing system and the integral accessories
related to the system installation as indicated on Drawings and as specified herein.
49
ETIHADꞏETISALAT- MOBILY TBP&O
CIVIL SPECIFICATION
‐ Weather: Proceed with roofing work when the existing and forecasted weather
conditions permit work to be performed in accordance with the manufacturer's
recommendations and warranty requirements
7.6.2 Submittals:
‐ Product Data: Submit specifications, installation instructions, and general
recommendations from the roofing materials manufacturer for each type of
roofing product required. Include the manufacturer's data substantiating that the
materials used are in compliance with the requirements.
‐ Mock-up Samples: Submit samples of each roofing system material for the
Engineer's approval.
‐ Shop Drawings: Submit complete shop drawings showing roof configurations and
sheet layout, perimeter details as well as special conditions.
Roofing Membrane:
High performance polymer modified bituminous sheet membrane reinforced with
a 200 g/m² non-woven polyester fabric and complying with the following
requirements:
Softening Point: 155oC as per ASTM D 36
Penetration at 25oC: 20 - 30 mm as per ASTM D 5
Heat Resistance, 2 hours at 120oC: No flow
Tensile Strength:
50
ETIHADꞏETISALAT- MOBILY TBP&O
CIVIL SPECIFICATION
Elongation:
* Longitudinal: 55 percent as per ASTM D 828
* Transverse: 60 percent as per ASTM D 146
Tear Resistance:
* Longitudinal: 195 N per DIN 53859
* Transverse: 210 N as per DIN 53859
Water Absorption: Less than 0.12 percent as per ASTM D 570 and ASTM
D 471
‐ Roofing membrane shall be applied single ply, 4 mm thick, fully bonded, torch applied
to the primed substrate.
‐ Roofing Membrane Accessories shall include but not limited to the following:
Separation Layer:
- Non-woven polyester fabric of a minimum density of 180 g/m² and to be laid
above the roof insulation.
Protection Layer:
- High density polyethylene sheeting conforming to ASTM E 154, 150 microns
thick.
Flashing Materials:
- Manufacturer's Metal system compatible with the roofing membrane.
Roof Topping:
- Provide one of the following roof toppings as indicated on Drawings:
51
ETIHADꞏETISALAT- MOBILY TBP&O
CIVIL SPECIFICATION
7.6.4 Execution:
Roof waterproofing works shall be executed by a specialized Sub-Contractor
recommended by the waterproofing membrane manufacturer and approved by the
Engineer.
4. Substrate shall be smooth, hard dry and free from high spots and
depressions. Substrate shall be swept clean and free from dust, loose
cement scale, oil, grease, foreign substances and debris.
5. Starting at the low point of the slab, apply the waterproofing membrane
loosely laid for horizontal areas with minimum 50 mm overlap. All the joints
shall be welded with hot air.
9. Extend insulation full thickness over entire area to be insulated. Cut and
fit tightly around obstructions and fill voids with insulation. Remove
projection interfering with placement.
52
ETIHADꞏETISALAT- MOBILY TBP&O
CIVIL SPECIFICATION
10. Lay non-woven polyester fabric separation layer over insulation prior to
installation of roof topping (Terrazzo tiles or gravel).
The extent of joint filler and sealants work is shown on the drawings, and is hereby
defined to include all such work not specified in other sections of these
specifications (for work forming joint surfaces).
- Size and Shape: Provide the sizes and shapes of units as shown or, if not
shown, as recommended by the manufacturer for the joint size and condition
shown. Wherever joint movement is a factor in the determination of size,
consult with the Engineer to determine the nature and magnitude of
anticipated joint movements for the temperature and condition of the project
at the time of installation.
53
ETIHADꞏETISALAT- MOBILY TBP&O
CIVIL SPECIFICATION
Bituminous and Fiber Joint Filler (BF-JF): Provide resilient and non-
extruding type premolded bituminous impregnated fiberboard units
complying with ASTM D1751 and AASHTO M213.
54
ETIHADꞏETISALAT- MOBILY TBP&O
CIVIL SPECIFICATION
55
ETIHADꞏETISALAT- MOBILY TBP&O
CIVIL SPECIFICATION
7.7.7 Installation:
Install sealant backer rod for liquid elastomeric sealants, except where
shown to be omitted or recommended to be omitted by sealant
manufacturer for the application shown.
Employ only proven installation techniques which will ensure that sealants
will be deposited in uniform, continuous ribbons without gaps or air pockets;
with complete "wetting" of the joint bond surfaces equally on opposite sides.
Except as otherwise indicated, fill sealant rabbet to a slightly concave
surface, slightly below adjoining surfaces. Where horizontal joints are
between a horizontal surface and a vertical surface, fill joint to form a slight
cove, so that joint will not trap moisture and dirt.
For normal moving joints sealed with elastomeric sealants, but not subject
to traffic, fill joints to a depth equal to 50% of joint width, but not more than
12 mm deep or less than 6 mm deep.
56
ETIHADꞏETISALAT- MOBILY TBP&O
CIVIL SPECIFICATION
After nominal cure of exterior joint sealants which are exposed to the
weather, test for water leaks. Flood the joint exposure with water directed
from a 20 mm garden hose held perpendicular to wall face, 600 mm from
joint, connected to a water system with 200 KPa minimum normal water
pressure. Move stream of water along joint at an approximate rate of 6
meters per minute.
END OF SECTION
57
ETIHADꞏETISALAT- MOBILY TBP&O
CIVIL SPECIFICATION
DIVISION (8)
Doors and Windows
8.1 Steel doors and frames:
The extent of standard steel doors and frames is shown on the drawings.
8.1.1 Quality Assurance:
- - Provide standard steel doors and frames manufactured by a single firm
specializing in production of this type of work, unless otherwise
acceptable to the Engineer.
- Fabricate side panels and transom panels to match doors in all respects
unless otherwise indicated.
- Provide doors and frames complying with the Steel Door Institute
"Recommended Specifications, Standard Steel Doors and Frames" (SDI-
100), and as herein specified.
- Submit shop drawings for fabrication and installation of steel doors and
frames. Include details of each frame type, elevations of door design types,
conditions at openings, details of construction, location and installation
requirements of finish hardware and reinforcements, and details of joints
and connections. Show anchorage and accessory items.
- Provide schedule of doors and frames using same reference numbers for
details and openings as those on contract drawings.
8.1.2 Materials:
A. Hot-rolled Steel Sheets and Strip: Commercial quality carbon steel, pickled and oiled,
complying with ASTM 569 and ASTM A568.
B. Cold-rolled Steel Sheets: Commercial quality carbon steel, complying with ASTM
A366 and ASTM A568.
58
ETIHADꞏETISALAT- MOBILY TBP&O
CIVIL SPECIFICATION
G. Shop-applied Paint: For steel surfaces, use rustinhibitive enamel or paint, either air-
drying or baking, suitable as a base for specified finish paints.
59
ETIHADꞏETISALAT- MOBILY TBP&O
CIVIL SPECIFICATION
rated door pairs shall be provided with astragal intumescent protection strip unless
otherwise shown. Fire rated doors and frames shall be as per manufacturer
instructions and recommendations as per the Engineer approval.
J. Metal Louvers Doors:
Manufacturer's standard sight-proof (and light-proof Manufacturer's standard
sight-proof (and light-proof where called for) 18 gauge steel louvers of
sizes indicated shall be provided as required.
Louvers shall have 18 gauge steel channel frames which shall be
fully concealed behind face sheets of doors.
There shall be no overlapping of face sheets with louver blades on
frames.
L. The doors should be guaranteed for a minimum of 5 years starting from the
project's contractual completion date.
A. Provide metal frames of the types and styles indicated on drawings or schedules and
complying with SDI-100 for minimum materials and construction requirements.
C. Plaster Guards: Provide 0.55 mm thickness steel plaster guards or mortar boxes,
welded to frame, at back of finish hardware cutouts where mortar or other materials
might obstruct hardware operation.
8.1.5 Installation:
A. General: Install hollow metal units and accessories in accordance with final shop
drawings and manufacturer's data, and as herein specified.
B. Placing Frames:
60
ETIHADꞏETISALAT- MOBILY TBP&O
CIVIL SPECIFICATION
3. In masonry construction, locate 3 wall anchors per jamb at hinge and strike
levels. Build-in of anchors and grouting of frames is specified in the 04 Series
section.
6. In metal stud partitions, install at least 3 wall anchors per jamb at hinge and
strike levels. In open steel stud partitions, place studs in wall anchor notches
and wire tie. In closed steel stud partitions attach studs to wall anchors with
tapping screws.
C. Door Installations:
1. Fit hollow metal doors accurately in their respective frames, within clearances
specified in SDI-100.
2. Place fire-rated doors with clearances as specified in NFPA Standard No. 80.
3. Check and readjust operating finish hardware items in hollow metal work prior to final
inspection. Leave work in complete and proper operating condition. Remove and
replace defective work, including doors or frames which are wraped, bowed or
otherwise damaged.
4. Prime Coat Touch-up: Immediately after erection, sand smooth any rusted or
damaged areas of prime coat and apply touch-up of compatible air-drying primer.
61
ETIHADꞏETISALAT- MOBILY TBP&O
CIVIL SPECIFICATION
8.2.2 Materials:
- All doors shall be fabricated to the quality standards of AWl and shall be 50 mm thick
unless otheJWise indicated.
- All doors shall be assembled with type Waterproof adhesives.
‐ All doors other than fire-rated doors, sound insulating doors, and hollow core doors,
shall be solid core doors, 50 millimeters thick as follows:
Core shall be type SRC [stile and rail solid core].
Face shall be premium grade faces.
Pairs of doors shall have matched grain face veneers.
Doors shall have matching hardwood edge strips laminated to the stiles.
Where glazing panels or louvers are indicated, openings in non-fire rated doors
shall be edged with matching hardwood.
-Fire rated doors shall be Underwriters Laboratories labeled fire doors as follows
for the label scheduled on the drawings.
Fire rated doors in corresponding fire rated frames shall be installed in accordance
with the requirements of NFPA publication no. 80, "Standard for Fire Doors and
Windows".
Installation is covered in Section 06100, ROUGH CARPENTRY .
Sound insulating doors shall be type SR with face veneer to match that of solid core
flush doors.
Thickness shall be 45 millimeters [1-3/4 inches] with a sound transmission
- manufacturers: SIDCO, FADEN, approved equal.
- the contractor shall not delivered until the entire building has been free from dampness
due to plastering or other work for at least ten (10) days.
- Doors shall be delivered to job site completely enveloped in protective cover to prevent
damage due to moisture or other elements that might stain the surfaces.
- Protect all doors against dampness, store in dray and well-ventilated area, and do not
subject to extreme changes of temperature or humidity.
- After the doors are installed in their openings, provide adequate protection to prevent
damage due to other construction operations and movement of materials,
equipment, and people through the openings.
- Furnish wood doors with the door manufacturer's warranty covering defects in materials
and workmanship. Duration of warranty shall be as follows: Solid core door, interior
or lifetime. Solid core doors, exterior - two (2) years.
62
ETIHADꞏETISALAT- MOBILY TBP&O
CIVIL SPECIFICATION
8.2.3 Installation:
A. Fit to the following tolerance :
3.0 mm (1/8") on each vertical side.
3.0 mm (1/8") on top.
5.0 mm (1/5") on bottom except when hardware requirements, floor finishes
require otherwise, or where undercuts are indicated.
Bevel lock edge 3.0 mm (1/8") in 50 mm (2").
C. Sand all surface planed or cut during fitting and installation of hardware.
4- Shop Drawings: Before delivery, submit shop drawings for aluminum windows.
Shop drawings shall show elevations of units, full-size sections, thicknesses,
fastening, methods of installation and anchorage, size and spacing of anchors,
method of glazing, locations of operating hardware, mullion details, method and
material for weatherstripping, method of attaching screens, details of installation,
connections with other work and window schedules showing locations of each
window unit.
63
ETIHADꞏETISALAT- MOBILY TBP&O
CIVIL SPECIFICATION
8.3.2 Materials:
- Material shall conform to the requirements of Master Specification Part A
(Architectural) of AAMA 302.9.
64
ETIHADꞏETISALAT- MOBILY TBP&O
CIVIL SPECIFICATION
8.3.3 Installation:
- Comply with manufacturer's specifications and recommendations for the
installation of window units, hardware, operators, and other components of
the work
- Set units, plumb, level and true to line, without warp or rack of frames or
sash. Anchor securely in place. Where aluminum surfaces are in contact
with or fastened to dissimilar materials, except stainless steel or zinc, the
aluminum surface shall be protected from dissimilar materials as specified in
the appendix of AAMA 302.9. Surfaces in contact with sealant after
installation shall not be coated with any type of protective material.
65
ETIHADꞏETISALAT- MOBILY TBP&O
CIVIL SPECIFICATION
2. Locksets and Latchsets: Locksets and latchsets shall meet the requirements of ANSI
A 156.2 and shall be the series, types, grades, and functions as specified and
scheduled. [Locks shall have (interchangeable cylinders) (or) (removable core)
removable and replaceable by use of special control keys.] Lock cylinders shall have
not less than (6) pin tumblers. Lock cylinders shall be permanently inscribed with a
number that identifies the key-change combination to the building, lock manufacturer,
key-control symbol, and manufacturer's trademark. Only manufacturer's name or
trademark shall be visible after installation.
3. Auxiliary Locks: Auxiliary locks shall meet the requirements of ANSI A 156.5 and shall
be the series, types, grades, and functions as specified and scheduled. Locks shall
have (interchangeable cylinders) (or) (removable cores) removable and replaceable
by use of special control keys. Lock cylinders shall have not less than (6) pin tumblers.
(Provide locks with escutcheons.)
4. Exit Devices: Exit devices shall meet the requirements of ANSI A156.3, grade 1, of
types and functions scheduled. All units shall have lock down device except labelled
fire doors.
5. Door Closing Devices: Shall meet the requirements of ANSI 156.4, Grade 1, (surface or
Concealed) type and function, as specified and scheduled. The sweep period of the
closer shall be adjusted so that from an open position of 70 degree, the door will take at
lease 3 seconds to move to a point 75 mm from the latch, measured to the leading edge
of the door.
6. Push-pull Plates: Plates shall meet the requirements of ANSI A156.6. Push-pull plates
shall be provided with cutouts for cylinders or keys on doors requiring locks. Push-pull
plates for doors not requiring locks shall not have cutouts.
66
ETIHADꞏETISALAT- MOBILY TBP&O
CIVIL SPECIFICATION
7. Thresholds: Thresholds shall be ANSI A 156.3, auxiliary item (AI) where scheduled for
panic exit device installation, and ANSI A156.4, type scheduled for floor pivot
installations. Other thresholds as scheduled are ANSI A156.6 product type J 600.
8. Door Stops: Door stops shall be provided and located to prevent contact between door
hardware, door, or both and adjacent wall surfaces. Provide hold open device for out-
swinging exterior doors.
9. Door Silencers: Silencers shall meet the requirements of Builder's Hardware (A 156.
16). Provide three on strike jamb of frames for single doors; two on head frame for double
doors, and four on strike jamb of frames for dutch doors.
10. Padlocks: Padlocks shall be 7-lever, key type with minimum 63.5 mm case size,
galvanized. Shackle shall be case-hardened.
11. Keys shall be permanently inscribed with a number that identifies the cylinder number,
lock manufacturer and the key symbol. Keys shall be appropriately tagged. Keys shall
be provided as follows:
8.4.3 Installation:
- General: Finish hardware items shall be installed in a neat, workmanlike
manner according to the manufacturer's recommendations unless otherwise
specified herein.
67
ETIHADꞏETISALAT- MOBILY TBP&O
CIVIL SPECIFICATION
- Fire Exit (Panic) Device: Locate so that centerline of lock strike is 1024 mm
(nominal) above bottom of door frame. (Where knob, pull, or pull with thumb
piece is used as outside trim with panic devices, height of strike will
determine position of outside trim.)
- Door Pulls: Locate so that centerline of grip, or of bar where single bar is
used, is 1067 mm (nominal) above bottom of door frame.
Top Hinge: Not over 300 mm from inside of frame rabbet at heat to
centerline of hinge.
8.5 Glass:
8.5.1 Quality Assurance:
Comply with the applicable provisions of the following codes and standards,
except as otherwise shown and specified:
- Flat Glass Marketing Association (FGMA) "Glazing Sealing Systems
Manual" and "Glazing Manual."
68
ETIHADꞏETISALAT- MOBILY TBP&O
CIVIL SPECIFICATION
- Glass shall be identified by the manufacturer's labels for grade and quality.
The labels shall not be removed until authorized by the Engineer.
8.5.3 Materials:
- Clear Plate or Float Glass: Polished plate or float glass; 6 mm thick, except
as otherwise indicated.
69
ETIHADꞏETISALAT- MOBILY TBP&O
CIVIL SPECIFICATION
- Clear Sheet Glass: Clear sheet glass; double strength, except as otherwise
indicated, 3 mm minimum thickness.
- Tempered Glass: Either float (plate) glass, or sheet glass; which has been
heat-strengthened by manufacturer's standard process (after cutting to final
size), to achieve a flexural strength of 4 times normal glass strength; clear
or tinted, except as otherwise indicated. Tint shall be as selected by the
Engineer. Provide 6 mm or 4.76 mm thick glass as per drawings.
70
ETIHADꞏETISALAT- MOBILY TBP&O
CIVIL SPECIFICATION
- Vinyl Foam Glazing Tape: Closed cell, flexible, self- adhesive, non-
extruding, polyvinyl chloride foam tape; recommended by manufacturer for
exterior, exposed, watertight installation of glass, with only nominal
pressure in the glazing channel; comply with ASTM D 1667.
8.5.5 Installation:
- Watertight and airtight installation of each piece of exterior glass is required.
Each installation must withstand normal regional temperature changes,
wind loading, impact loading (for operating sash and doors) without failure
of any kind including loss or breakage of glass, failure of sealants or gaskets
to remain watertight and air-tight, deterioration of glazing materials and
other defects in the work.
- Comply with ANSI Z 97.1 for safety glazing materials at the location shown,
specified, and as required.
- Wash and polish glass on exposed faces not more than 4 days prior to
Engineer's acceptance of the work in each area. Comply with glass
manufacturer's recommendations.
71
ETIHADꞏETISALAT- MOBILY TBP&O
CIVIL SPECIFICATION
Wind Loads:
Seismic Loads:
72
ETIHADꞏETISALAT- MOBILY TBP&O
CIVIL SPECIFICATION
73
ETIHADꞏETISALAT- MOBILY TBP&O
CIVIL SPECIFICATION
- Air Infiltration: Maximum air leakage through fixed glazing and framing
areas of 0.7 L/s per sq. m of fixed wall area as determined according to
ASTM E 283 at a minimum static-air-pressure differential of 300 Pa.
74
ETIHADꞏETISALAT- MOBILY TBP&O
CIVIL SPECIFICATION
- the supplier should be submitted Samples for Initial Selection: For units
with factory-applied color finishes.
8.6.3 Materials:
- Extrusions shall be 6063-T5 Alloy and Temper. Fasteners, where exposed
shall be Aluminum, Stainless steel or Zinc plated steel in accordance with
ASTM A164. Perimeter anchors shall be Aluminum or Steel providing the
Steel is properly isolated from the Aluminum.
8.6.4 Installation:
- Framing shall be installed, glazed and adjusted by experienced workmen
in accordance with the manufacturer's installation instruction and/or
approved shop drawings.
END OF SECTION
75
ETIHADꞏETISALAT- MOBILY TBP&O
CIVIL SPECIFICATION
DIVISION (9)
Finishes
9.1 Portland Cement Plaster:
The work under this section consists of furnishing and installing all portland cement plaster
and accessories as indicated in the drawings and as specified herein, including but not limited
to the following:
- The work shall be executed and tested in accordance with the current
editions of the following standards:
AASHTO Quality of water to be used in concrete
PCA Portland Cement Association
ANSI A42.2 Portland Cement and Portland Cement-Lime
Plastering, Exterior (Stucco) and Interior," except where more
detailed or stringent requirements are indicated.
ASTM American Society for Testing and Materials
E. Accessories : Corner beads, control joints, cornered, metal lath and other
plaster accessories shall be as specified in this section and approved by
Engineer.
76
ETIHADꞏETISALAT- MOBILY TBP&O
CIVIL SPECIFICATION
9.1.3 Execution
- Clean all surfaces to be plastered of dust, loose mortar and traces of salt.
- Apply wash of sand and cement in equal parts to form bond coat.
- Install accessories.
- Size batches for complete use within a maximum of one hour after mixing
and to set within a maximum of four hours.
- All finish surfaces shall be evenly applied and properly troweled to finish or
texture indicated or desired.
- For color plastering: Surfaces shall be uniform in color, free from stains,
marks and defects straight-edged, plumb and level in every direction, with
all angles straight, true and perfect.
- Protect each coat of Portland cement plaster work from dry-out for a period
of 20 to 24 hours after placement (or until curing operation will not
damage surface), and moisture-cure not less than 48 hours after time of
placement. Moisture-cure by maintaining in a moist condition, by frequent
fog-spraying with water and by protecting from fast dry-out with covering
of polyethylene film or similar enclosure. Dry each coat to a uniform
77
ETIHADꞏETISALAT- MOBILY TBP&O
CIVIL SPECIFICATION
ANSI A 108.1 “Standard Specification for Ceramic Tile Installed in Dry Set
Portland Cement Mortar”.
ANSI A 137.1 “merican National Standards Institute for Ceramic Tile.
TCA Tile Council of America "Handbook for Ceramic Tile Installation"
- when the tile works are exposed to direct sunlight and moisture, it is
recommended to install expansion joints in the tiles every 3.5 m and in
78
ETIHADꞏETISALAT- MOBILY TBP&O
CIVIL SPECIFICATION
9.2.2 Materials
- Ceramic Wall Tile: Toilet and kitchen tiles shall manufactured by any
approved similar in pattern and equal in quality, and All external comers
shall be formed with bullnose units and all internal corners shall be
square.
- Grout filling: use the high quality material like Mapei grouting
9.2.3 Execution
- Remove efflorescence, laitance, dirt and other loose material by thoroughly
dry brushing.
- Remove deposits of oil, grease and other materials incompatible with the
bedding using a suitable emulsion cleaner then washing with clean water
- Jointing Pattern: Unless otherwise shown, lay tile in grid pattern. Align
joints when adjoining tiles on floor, base, walls, and trim are the same size
or proportional size. Layout title work and center tile fields both directions
in each space or on each wall area. Adjust to minimize tile cutting.
Provide uniform joint widths, unless otherwise shown.
- Use commercial cement grout for grouting tile wall joints, unless otherwise
shown.
79
ETIHADꞏETISALAT- MOBILY TBP&O
CIVIL SPECIFICATION
- Metal Edge Strips: Provide where shown and where exposed edge of
ceramic tile flooring is to meet carpet, wood resilient floor covering, or
other flooring material where marble thresholds are not shown. Install in
continuous metal strips adequately anchored into substrate to resist
impact.
- Clean grout and setting materials from face of tile while materials are
workable. Leave tile face clean and free of all foreign matter.
- Prohibit foot and wheeled traffic from using tiled floors for at least 3 days,
preferably 7 days.
- Samples of the tiles shall be submitted to the Engineer for approval prior to
ordering same.
- The tiles are to be laid on a cement and sand screed to make up the total
floor thickness as stated herein or as shown on the drawings.
- Wherever differing floor finishes about each other, they are to be finished
with a fair square cut edge and separated by means of a dividing strip.
The dividing strip shall be formed of Brass of aluminium sections or
Marble price to the Engineer's approval.
- When the tile works are exposed to direct sunlight and moisture, it is
recommended to install expansion joints in the tiles every 3.5 m and in
indoor areas every 6-8 m.
80
ETIHADꞏETISALAT- MOBILY TBP&O
CIVIL SPECIFICATION
9.3.1 Materials
- Water: Potable.
- Sand
81
ETIHADꞏETISALAT- MOBILY TBP&O
CIVIL SPECIFICATION
- Submit shop drawing details at full scale for unusual conditions relating to
the construction of the gypsum ceiling systems.
9.4.2 Materials
Hanger Anchorages: Comply with ANSI A42.4 for concrete inserts, clips,
bolts, screws and other devices applicable to the indicated method of
structural anchorage for ceiling hangers. Size devices for 3 x calculated
load supported, except size direct-pull concrete inserts for 5 x calculated
load.
- Gypsum board of 12mm thick for ceiling and 16 mm for walling and
complying with ASTM Standard (normal / waterproof / fire rated).
9.4.3 Execution
- Examine and inspect surfaces to which gypsum board is to be applied. All
defects will be remedied prior to installation of drywall under the
applicable section of the specifications.
82
ETIHADꞏETISALAT- MOBILY TBP&O
CIVIL SPECIFICATION
number of end joints occur. Boards will be brought into contact with each
other will not be located so that no end joint will align with edges of
opening. End joints will be staggered, and joints on opposite sides of a
partition will not occur on the same stud.
- Drywall screws will be spaced not to exceed 400 mm (16") o.c. on
sidewalls, Where studs are spaced 600 mm (24") sidewall screw spacing
will not exceed 300 mm (12") o.c.
- Gypsum Ceiling boards: Furnish concrete inserts, steel deck hanger clips,
and similar devices to other trades for installation well in advance of time
needed for coordination with other work.
- Submit 300 mm square samples for each acoustical tile required. In each
set of samples show the full range of exposed color and texture to be
expected in the completed work.
- Cosmos 20mm inch thick reveal type with trim or similar approved equal.
- Do not store or install material in the building until all glazing has been
completed, all exterior openings have been closed in.
83
ETIHADꞏETISALAT- MOBILY TBP&O
CIVIL SPECIFICATION
9.5.3 Execution
- Pre-Installation Conference: Prior to the start of acoustical ceiling
installation, meet at the project site with the installers of related work,
including lighting, ductwork and similar work in the ceiling plenum. Review
areas of potential interference and resolve conflicts before proceeding
with the work. Coordinate ceiling layout with the layout of other work
which penetrates or is supported by the ceiling in each space of the
building.
- Do not support ceilings directly for permanent metal forms; furnish inserts
and extend hangers through forms into concrete inserts.
- Install acoustical ceiling in a true and even plane, in straight line course
laid out symmetrically about center lines of ceiling. Apply border tile not
less than 200 millimetres wide. Unless otherwise shown, border tiles on
parallel sides shall be equal in width.
84
ETIHADꞏETISALAT- MOBILY TBP&O
CIVIL SPECIFICATION
9.6 Carpeting:
The work under this section consist of furnishing and installation of all
carpet tile and carpet flooring finishes.
9.6.1 Quality Assurance
- This work shall be tested and executed in accordance with the current
edition of the following standards:
ASTM 0418 Woven & tufted pile floor covering .
ASTM 01335 Tuft bind of pile floor covering.
ASTM 02401 Service change of appearance of pile floor covering
ASTM 02646 Testing backing fabrics
ASTM 0 2859 Flammability of finished materials-textile floor covering.
- Manufacturers technical data and installation instructions.
9.6.2 Materials
- Adhesives must provide a firm and durable bond. The adhesive should
have no harmful effect on the floor covering, underlay or base and after
use must be odourless. Consideration shall be given to softening points of
adhesive as they may be required to withstand high temperature.
9.6.3 Execution
- The floor screed shall be finished with a trovel and shall be free from
trovel marks, laitance, dust and surface moisture. The tolerance in level
over a 2 m length shall not exceed +/- 3 mm. If the surface has trovel
marks or other imperfections which are likely to show to laid floor then the
Contractor shall level or smooth the surface with filling or leveling
compound or by grinding. Vacuum cleaning of the base before laying and
fixing is essential.
85
ETIHADꞏETISALAT- MOBILY TBP&O
CIVIL SPECIFICATION
in the same direction. The carpet rolls are to be placed in accordance with
the product serial number.
- The contractor shall be submitted Specifications and other data for each
type of marble required.
- Marble Building Stone Standard: ASTM C 503 & Granite Building Stone
Standard: ASTM C 615. & SASO 1026/1995 Methods of test for tiles of
natural marble.
9.7.1 Materials
- Marble or granite shall be first quality, consistent In color and texture, free
from voids, earth veins and lamination or structural weakness and of an
approved texture and color. Pattern of slabs shall be as shown on the
Drawings, or approved shop drawings. Minimum thickness of flooring
shall be 25mm.
- All granite of marble tiles shall be painted on their rear sides and edges
with an approved clear non-yellowing penetrative protective sealant
(water repellent). Mortar for fixation shall be done using OPC.
86
ETIHADꞏETISALAT- MOBILY TBP&O
CIVIL SPECIFICATION
- Marble granite to be obtained from one quarry with consistent color range
and texture throughout the work.
9.7.2 Execution
- Clean marble before setting by scrubbing with fiber brushes and
thoroughly drenched with clear water.
- Apply slush coat of cement grout over surface of concrete sub-base about
15 minutes prior to placing setting bed. Limit area of slush coat to avoid
drying out prior to placement of setting bed and apply by towel or brush.
Do not exceed 2 mm thickness for cement slush coat.
- Set stone before initial set of cement bed occurs. Do not set stone on dry
bed. Apply a thin layer of neat cement paste 0.75 mm to 2 mm thick by
brushing or towling over setting bed, or apply to bottom stone. Tap stone
for complete contact with setting bed. Set level each unit immediately. Do
not set large areas and later level. Set immediately. Set stone in pattern
shown with uniform joints of the width shown, or if not shown, provide
joints not more than 6 mm wide.
87
ETIHADꞏETISALAT- MOBILY TBP&O
CIVIL SPECIFICATION
9.8 Painting:
The work of this Section includes the finish painting of interior and exterior exposed items
and surfaces as indicated.
The term "paint" as used herein means all coating systems which include primers,
emulsions, enamels, stains, sealers, fillers, and other applied coating materials whether
used as prime, intermediate, or finish coats.
9.8.1 Quality Assurance
- Provide finish coats which are compatible with the prime paints used.
- All paint and finishes used shall have class A rating in accordance with
ASI/ASTM E 84.
- Do not apply exterior paint during sand storms, rain, or fog. Do not apply
paint when the relative humidity exceeds 85%, or to damp or wet
surfaces, unless permitted by the paint manufacturer's printed
instructions.
88
ETIHADꞏETISALAT- MOBILY TBP&O
CIVIL SPECIFICATION
9.8.2 Materials
- Color Pigments: Pure, non-fading types to suit the substrates and service
indicated. Lead content in pigment, if any, shall not exceed more than
0.5% lead, based on the total non-volatile, dry-film, of the paint by weight.
This limitation shall extend to all interior surfaces and those exterior
surfaces, such as stairs, decks, porches, railings, windows, and doors
which are readily accessible to children under seven years of age.
- Primers for Aluminum: Surfaces which are not shop primed and are
scheduled for finish painting shall be solvent cleaned and primed with a
zinc-phosphate, alkyd primer complying with SSPC-Paint 20.
- Exterior Work :
Iron and Steel:
One coat of zinc chromate primer when unprimed.
Touch up for primer surfaces.
Two coats larcoloid enamel, alkyd, oil-base.
Concrete Block:
One coat acrylic binder containing mineral type filler
containing aggregate.
89
ETIHADꞏETISALAT- MOBILY TBP&O
CIVIL SPECIFICATION
- Interior work :
Plaster (flat):
One coat primer sealer.
Two coats interior flat wall paint.
Plaster (semi-gloss):
Wood to be painted :
Epoxy paint:
90
ETIHADꞏETISALAT- MOBILY TBP&O
CIVIL SPECIFICATION
9.8.3 Execution
- Remove all hardware, hardware accessories, machined surfaces, plates,
lighting fixtures, and similar items not to be painted, or provide surface-
applied protection prior to surface preparation and painting operations.
Remove, if necessary, for the complete painting of the items and adjacent
surfaces. Following completion of painting of each space or area, reinstall
the removed items by workmen skilled in the trades involved.
- Do not paint over dirt, rust, scale, grease, moisture, scuffed surfaces, or
conditions otherwise detrimental to the formation of a durable paint film.
- All paint shall be applied by brush except plastered surfaces which may
be applied by roller or spray. Lacquered paint finish as specified in the
drawings shall be by spray.
- Final coats shall be free from holidays, laps, runs, sags, brush marks, and
other surface imperfections. Make edges of paint adjoining other materials
or colors sharp and neat, without overlapping.
END OF SECTION
91
ETIHADꞏETISALAT- MOBILY TBP&O
CIVIL SPECIFICATION
DIVISION (10)
Mobily Specialties Specs
10.1 Civil requirements:
10.1.1 Design criteria in technical buildings:
- The design should be compatible with latest versions of SBC code and
international codes (ACI) as below:
I. Saudi code of practice for design and construction of reinforced
concrete structures (SBC-304).
II. Saudi code of practice for loading and forces on structures (SBC-301).
III. Saudi code of practice for soil mechanics and foundation design &
construction (SBC-303).
IV. The building code requirements for structural concrete (ACI 318).
V. ASCE 7 code for wind load design.
VI. ASCE 7 code for seismic load design.
- for structural live loads we should be consider all actual loads in design
specially the loads of power rooms, data centre, Battery rooms and
mechanical equipment.
- the Lateral loads (wind & seismic) should be consider in the design.
92
ETIHADꞏETISALAT- MOBILY TBP&O
CIVIL SPECIFICATION
II. Deformed welded wire reinforcing (WWR) sheets: ASTM A497 (fy=
317 MPa).
- All reinforcing bars details shall be supported in Conformance with the
manual of standard practice for detailing reinforced concrete structure
(ACI 315 latest edition).
- The masonry walls shall be non-load bearing and the external walls shall
be insulated and obtain the R value according to the code.
- The soil report should be ready during the design stage to consider the
suitable type of foundation and check the ground water table.
- The shop drawings should be Comply with ACI 315 "Manual of Standard
Practice for Detailing Reinforced Concrete Structures.“
- During close out the project the contractor shall be preparing the following
documents:
I. As built drawings.
II. Certificates.
III. Hand over with key persons using the official forms.
IV. Rectifying all the snags
93
ETIHADꞏETISALAT- MOBILY TBP&O
CIVIL SPECIFICATION
94
ETIHADꞏETISALAT- MOBILY TBP&O
CIVIL SPECIFICATION
- The minimum clear height for data rooms (Racks area) is 4.50 m from
slab to slab or 3.60 m above raised floor.
95
ETIHADꞏETISALAT- MOBILY TBP&O
CIVIL SPECIFICATION
- For raised floor type recommended Tate access floor, and the supplier
should be submitted all tests (loading, burn,……etc)
- The finishing of main entrance, stairs, offices staff, and corridors are
recommended Porcelain tiles 600X600mm, and for toilets and kitchen
ceramic tiles 300X300 mm.
END OF SECTION
96