Bill of Quantity & Specification Additional

ADDITIONAL WORK Work


Project: G+3 Mixed Use Building Contractor No: AMBPCA/BC-01/2010
Location: Adola Woyu Town Kilta Eba(03) Kebele
Client: Meda Buna Anferara Cooperative
Contractor: Tarakegne Zeleke B.C
Ite Quanti
Description Unit Rate Amount
m ty
1. PAINTING
Apply three coats emulsion paint to Bank Room internal
1.10 m² 90.00 140.00 12,600.00
plastered wall surface.
To Concrete ceiling and exposed beams,columns for Bank Room. m² 24.00 140.00 3,360.00
Total carried to Summary.................................................. 15,960.00
2. ELECTRICAL WORKS
2.1 DISTRIBUTION BOARDS
Supply and install flush mounting main distribution board,
MDB,with lockable doors and including bus bars of 35A /3P
rating and consisting of :-(SDB-GF)
ACB of 16A/1P No 1.00 7,000.00 7,000.00
ACB of 25A/1P No 1.00 7,000.00 7,000.00
2.2 ELECTRICAL INSTALATION
PVC of 50mm diameter. Ml 50.00 120.00 6,000.00
2.3 LIGHT POINTS
Flush mounted light points fed through PVC insulated conductors
of 3x2.5mm² inside PVC conduits of 16mm diameter, including No 45.00 350.00 15,750.00
junction boxes with covers insulating screw cap connectors.
2.4 SOCKET OUTLET
16A/1P socket outlet fed through PVC insulated conductors of
3x2.5 mm² inside PVC conduits of 16mm diameter including
No 16.00 750.00 12,000.00
junction boxes with covers,and insulating screw cap connectors
all for flush mounting .
2.5 LIGHT FITTING AND LAMPS
(Specified or Equivalent)
a)Philips TMS, 01.2/40 With 1x40W Flourescent lamp. No 8.00 1,500.00 12,000.00

b)Incandescent lamp with reflection cover 60w. No 8.00 750.00 6,000.00

Total carried to Summary.................................................. 65,750.00

Grand Total of 1+2 ................................................. 81,710.00