Download as pdf or txt
Download as pdf or txt
You are on page 1of 45

CLIENT

M/S. ARRJAVV Builder Pvt Ltd

NAME OF THE WORK


PILING WORK FOR NADIA HOUSE BY ARRJAVV
AT 2, BRIGHT STREET,BALLYGUNGE KOLKATA-700019

ANCHOR LOAD TEST ON 1000 MM DIA PILE

SARITHA INFRA & GEOSTRUCTURES:


Registered Office :
#50-27-18, 2nd Floor, TPT Colony, Seethammadhara
Visakhapatnam – 530 013, Andhra Pradesh, India
Tel: +91 891 2556566 + 91 8008 696 666
Email: sarithainfra@gmail.com
PROJECT: CLIENT:
“Piling Work at Nadia House “ M/S ARRJAVV Builder Pvt Ltd

INTIAL PILE LOAD TEST ON 1000 MM DIA PILES


(BY ANCHOR PILE METHOD)
METHOD STATEMENT

PROJECT

INSTALLATION OF BORED CAST-IN-SITU PILES OF 1000MM DIA BY HYDRAULIC ROTARY


RIG FOR NADIA HOUSE BY ARRJAVV AT 2, BRIGHT STREET ,BALLYGUNGE KOLKATA -
700019

CONTRACTOR

SARITHA INFRA & GEOSTRUCTURES


VISAKHAPATANAM
PROJECT: CLIENT:
“Piling Work at Nadia House “ M/S ARRJAVV Builder Pvt Ltd

TABLE OF CONTENTS

1. PREAMBLE .......................................................................................................................................

2. TEST METHOD ..................................................................................................................................

3. REFERENCE DOCUMENTS ...............................................................................................................

4. PILE DETAILS: ...................................................................................................................................


PROJECT: CLIENT:
“Piling Work at Nadia House “ M/S ARRJAVV Builder Pvt Ltd

1. PREAMBLE

This Method Statement is prepared for conducting the Initial Anchor Pile Load

Test to be carried out on 1000mm diameter piles installed .Pile shall be tested for

2.5 times the designed pile capacity of 600MT.

2. TEST METHOD

a) Pile head Preparation:-

The area around the pile was excavated to expose the pile head. Top of the Pile- pile

head - chipping shall be done to remove the contaminated concrete till the good

concrete is observed.

Exposed reinforcement of 1000mm Dia Pile was cut and the top surface of the pile was

made to a horizontal level using cement sand mortar,

b) Platform:-
The platform which offers resistance to the jack when load is applied on the pile is

made of structural steel beams (main beam and secondary beams) in both the

directions, erected such that the center of the platform coincides with the center of

the pile. The main beam (8.00Mx1.60mX2.50m) is fixed 1m high from test pile (1000mm

Ø) head top and the end sides are rested on the concrete solid blocks (2 No’s) top.

The secondary beams (2 No’s each of 8.00mX1.50mX0.90m) are rested on the main

beam and the ends of secondary beams are connected by the anchor piles

reinforcement, the reinforcement of anchor piles are inserted into the secondary beam

end sides and arrested by welding with cover plates (4 No’s).


PROJECT: CLIENT:
“Piling Work at Nadia House “ M/S ARRJAVV Builder Pvt Ltd

c) Apparatus:-
A bearing plate made of steel was placed on top of the pile and hydraulic jacks

(4No’s jacks of 500T capacity) set up at the center of the pile such that the load

transformed to the pile uniformly/centrally. The gap between the ram of the jack

and bottom of the main girder shall be filled with necessary steel plates

Datum bars, 2 no’s, shall be fixed with independent supports on both sides of the pile

and the dial gauges placed on periphery of the plate to measure the settlement on

four corners of the pile.

Noted the initial readings of all the dial gauges.

d) Maintained Load Method: -

The Maintained Load Test Method shall be carried on the test piles selected for conducting
the Initial vertical load test to find out whether the design assumptions does match with the
site practices on 1000 mm diameter pile.

The following is the procedure for the Maintained Static Load Test where the load is
applied in increment of 20% of the design load (600 Ton) up to 2.5 times the design load.

Incremental loading shall be carried out at each stage by applying a series of vertical
incremental load and each increment being of about 20 percent of design load i.e.,120MT
on the pile. Each loading maintained as per the criterion given below:

 Dial gauge reading taken at regular interval of 2, 15,30& 60 minutes.


 Each Load increment maintained for 60 minutes during loading based on the
criteria and 30 minutes for each unloading.
 2.5 times design load shall be maintained for 24 hours
CLIENT:
PROJECT: Date 22.01.2024
PILING WORK FOR NADIA HOUSE M?S ARRJAVV Builder Pvt Ltd

 Readings were recorded before and after applying increment/decrement


of load.

Final 1500MT Ton shall be maintained for 24 hours and readings shall be

recorded hourly. Readings are tabulated and enclosed.

3. PILE DETAILS: -
Each test piles details shall be provided under this column.

 Test Pile no:- TP-1


 Pile Depth – 54.00 m from COL
 Pile diameter – 1000 mm
 Grade of concrete – M50

 Anchor Piles-4 Nos


 Pile Depth – 50.00 m from COL
 Pile diameter – 1000 mm
 Grade of concrete – M30

Load Test Record:

Load Vs Settlement Curve Graph is drawn and enclosed


CLIENT:
PROJECT:
Date: 22.01.2024
PILING WORK FOR NADIA HOUSE M/S ARRJAVV BUILDERS PVT LTD

4. CONCLUSION:-

WITH REFERENCE TO the FILED OBSERVATIONS TEST LOAD GIVEN WAS 1156.80 Tons AND THE
GROSS SETTLEMENT IS ABOUT 19.20mm.

AS PER IS 2911 (Part 4) : 2013)

7.1.5

The safe vertical load on single pile for the initial test should be

For piles more than 600 mm diameter:

1)Two-thirds of the final load at which the total displacement

attains a value of 18mm or maximum of 2 percent pile d i a m e t e r

w h i c h e v e r i s l e s s u n l e s s otherwise required in each case on the basis

of nature and type of structure in w h i c h c a s e , t h e s a f e l o a d s h o u l d b e

c o r r e s p o n d i n g t o t h e s t a t e d t o t a l displacement permissible.

In this case with reference to the field observations we have attained 18mm

deflection at a load of 1156.80MT. So pile safe capacity is 2/3rd of 1156.80MT is

771.20MT.

As per the design consideration safe capacity of pile is 600MT this is less than the

above value.

So we can consider the safe bearing capacity of pile is 600MT Only.


CLIENT:
PROJECT: Date: 22.01.2024
PILING WORK FOR NADIA HOUSE ARRJAVV BUILDERS PVT LTD
GEOTECHNICAL ENGINEERING DIVISION
DEPARTMENT OF CIVIL ENGINEERING
COLLEGE OF ENGINEERING, ANDHRA UNIVERSITY
VISAKHAPATNAM-530 003, ANDHRA PRADESH
E Mail: cnvsreddy@gmail.com
Mob: 98491 00310
ISO 9001-2015 Certified

Dr. C.N.V. Satyanarayana Reddy


M.Tech. (Geotech.-IITMadras), M.E (Strs.-AU), Ph.D (NIT, Warangal)
Visakhapatnam
CE, FIGS, FIE, MISSMGE, MIRC, MICI, MISTE
Date: 17.11.2023
Professor
Name of the Work : Design of Reaction piles for loading Test pile of 1000mm dia. and 54m length
of 600t anticipated safe load capacity- Proposed G+34 storied building at Nadia
House, 2, Bright Street, Kolkata.
Client : M/s. AARJAVV Builder Pvt. Ltd., Kolkata.
Agency : M/s Sarita Infra and Geostructures, Visakhapatnam
***
DESIGN OF REACTION PILE

Design of reaction piles is done as per IS 10270 -1983 (reaffirmed in 2003) for generating reactive force
to perform initial load test on 1000mm diameter pile with anticipated allowable load as 600t. The subsoil
at test location based on Borelog data submitted by the client (prepared by M/s J P Geo Consultants,
Kolkata is observed to be comprised of Very soft clay, Soft clay, stiff to very stiff clay followed by Hard
clay. The weighted average N values of very soft clay, soft clay and stiff to very stiff clay are taken based
on borelog details as 2, 4 and 19 respectively. The average thicknesses of very soft clay, Soft clay and
stiff to very stiff clay are considered as 5m, 8m and 27m respectively. The weighted average value of N
from 40m to 50m depth is taken as 40 and the value of N below 50m depth is taken as 50. 4 Nos. of
bored cast- in-situ concrete piles of 1000mm diameter are proposed with pile length of 50m to derive
reaction for loading test pile through skin friction from subsoil strata. The design details are presented
below.
FN

1. Details of Loading

Details of loading on Test Pile


Anticipated safe load on Pile = 600t
As per IS 2911 part 4- 1985, Test load on Pile= 2.5 times anticipated safe load = 1500t
Load capacity required from reaction piles for the test = 1.25x1500 = 1875t
Load on each reaction pile = 1875/4= 468.75t
Department of Civil Engineering,
College of Engineering, Andhra University,
Visakhapatnam-530003
SO 9001-2015 Certified
Andhra Pradesh
------------------------------------------------------------------------------------------------------------------------------------------

2.0 Load capacity of Reinforcing bars

Dia. of reaction pile=1000mm

Considering 24 tor steel bars of 25mm diameter of Fe 500 steel in top portion of pile, Ultimate load
capacity of bars = 589 t > 468.75t

3.0 Capacity in Soil Bond Criterion

The ultimate load capacity in skin friction of reaction pile is determined as

Qs = ∑ .
Where,
rs is allowable side socket shear resistance in component layer
As is Surface area of pile in component layer

From Table 2 of section B-3.4 of IS 2911 part 1 Section 2 (2010), static cone penetration resistance
(kN/m2) of very soft clay /soft to medium clay and stiff to very stiff /hard clay strata are deduced from
Standard Penetration resistance (N) as 150N and 200N respectively. Ultimate skin friction resistance (rs)
in very soft clay /soft clay, stiff to very stiff clay and hard clay layers (kN/m2) are determined as qc/25,
qc/75 and qc/100 respectively as per Table 1 of Section B-3.3. The ultimate skin friction resistances in
very soft clay, soft clay, stiff to very stiff clay and hard clay strata are determined considering to N values
of 2, 4, 19 and 40 are determined as 1.2t/m2, 2.4t/m2, 5.1 t/m2 and 8 t/m2 respectively. The skin friction
contribution in top 5m depth is ignored.

Ultimate capacity of reaction pile in skin friction = πx1 [8x 2.4 + 27x 5.1 + 10 x 8] = 744.2t

For a factor of safety of 1.5, safe load capacity in tension/ uplift = 496.1 + 59.7 (submerged weight of
pile) = 555.8 > 468.75t.

Capacity of 4 reaction piles in skin friction / soil bond = 2223t > 1875t

4.0 Capacity in concrete bond Criterion

As per IS 456-2000, Allowable bond strength is taken as 1.5MPa for M30 concrete

Required bond length = 195.3/(πx25x1.5) = 1.7m

Provide a bond length of 12 m for 24 Nos. of 25mm dia. bars.

2|Page
Department of Civil Engineering,
College of Engineering, Andhra University,
Visakhapatnam-530003
SO 9001-2015 Certified
Andhra Pradesh
------------------------------------------------------------------------------------------------------------------------------------------

Hence, provide 24 Nos. of reinforcing bars of 25mm diameter in top 12 m portion of the reaction pile and
12 Nos. of reinforcing bars of 25mm diameter in the remaining portion.

Recommendations:

1. 4 Nos. of Reaction piles of 1000mm diameter and 50m length of M30 concrete shall be used to
load test pile of 1000mm diameter and 54m length with anticipated safe load capacity of 600t.
2. 24 Nos. of 25mm dia. reinforcing bars shall be provided in reaction pile in top 12m length with
12 Nos. of 25mm dia. reinforcing extending to full length of pile.
3. 8mm diameter helical ties with bars 150mm spacing shall be provided with stiffener rings of
16mm dia. spaced at 2 m intervals.

Prof. C.N.V. Satyanarayana Reddy

3|Page
SARITHA INFRA & GEOSTRUCTURES
PROJECT: PILING WORK FOR NADIA HOUSE BY ARRJAVV BUILDERS PVT LTD

INITIAL PILE LOAD TEST BY ANCHOR METHOD


1 DATE OF CASTING 16-12-2023
2 DATE OF TESTING 19.01.2024
3 DIA OF PILE 1000mm
4 PILE DEPTH FROM GL 54.00 mtr
5 PILE REF.NO TP-01
6 CONCRETE GRADE M 50

7 REINFORCMENT USED 0.0 to 16 MTR ,32MM,18nos

8 MAIN RODS 16 to 32 mtr,25mm,18 nos,32 to 54 mtr 18 nos

9 INNER RING 16mm,1500mm SPACING


10 SPRIL RINGS 08mm,200mm SPACING
11 PRESSURE GAUGE LEAST COUNT 20kg/cm2
12 RANGE OF PRESSURE GAUGE 0-700kg/cm2
13 NO OF DIAL GAUGE 4 nos
14 DIAL GAUGE RANGE & LEAST COUNT 0.01mm & 0-50mm
15 DIA OF THE JACK RAM 342mm/34.2cm
16 JACK CAPACITY 500 MT
17 NO OF JACKS 4 nos
18 AREA OF THE RAM FOR ONE JACK 918.167SQ.CM
19 TOTAL AREA OF THE RAM 3.672SQ.CM
20 DESIGN LOAD 600MT
21 TEST LOAD (2.5 TIMES Design load) 1500MT
SARITHA INFRA & GEOSTRUCTURES
PROJECT:NODIA HOUSE TYPE OF TEST: INITIAL PILE LOAD TEST BY ANCHOR METHOD
PILE LOCATION: TEST PILE DATE OF TEST: 19.01.2024 JACK CAPACITY:500 TON
CLIENT:ARRJAVV BUILDERS PVT LTD DESIGN LOAD:600MT NO OF JACKS:04
DATE OF CASTING: 16/12/2023 RAM AREA :918.167SQ.CM
TOTAL RAM
GRADE OF CONCRETE:M50 TEST LOAD:1500MT AREA:3672SQ.CM
DIA OF PILE:1000mm DIA OF THE JACK
PILE DEPTH:54.00MTR RAM:342mm/34.2cm
THEORITICAL LOAD
THEORITICAL THEORITICAL ACTUAL
SL NO ACTUAL LOAD(MT) NO OF DIV REMARKS
LOAD(MT) PRESSURE(kg/cm2) PRESSURE(kg/cm2)
1 120 32.68 40 146.88 2
2 240 65.36 70 257.04 3.5
3 360 98.04 100 367.2 5
4 480 130.72 130 477.36 6.5
5 600 163.40 170 624.24 8.5
6 720 196.08 200 734.4 10
7 840 228.76 230 844.56 11.5
8 960 261.44 270 991.44 13.5
9 1080 294.12 300 1101.6 15
10 1200 326.80 330 1211.76 16.5
11 1320 359.48 370 1358.64 18.5
12 1440 392.16 400 1468.8 20
13 1500 408.50 410 1505.52 20.5
SARITHA INFRA & GEOSTRUCTURES
PROJECT: PILING WORK FOR NADIA HOUSE FOR ARRJAVV TYPE OF TEST: INITIAL PILE LOAD TEST BY ANCHOR METHOD
PILE LOCATION :TEST PILE DATE OF TEST: 19.01.2024 JACK CAPACITY:500 TON
DESIGN LOAD:600 MT NO OF JACKS:04
CLIENT:ARRJAVV BUILDERS PVT LTD
TEST LOAD:1500MT DIA OF THE JACK RAM:342mm/34.2cm
DATE OF CASTING: 16/12/2023 AREA OF :THE RAM FOR ONE JACK:918.167SQ.CM
DIA:1000mm GRADE OF CONCRETE:M50
TOTAL AREA OF THE RAM:3672 SQ.CM
PILE DEPTH: 54.00mtr from EGL

DATE TIME PRESSURE Kg/Cm2 LOAD(MT) DIAL GAUGE READING IN MM AVERAGE(mm) REMARKS

DG1 DG2 DG3 DG4

19.01.2024 12.00pm 0 0 0 0 0 0 0

0.00
12.10 pm 40 146.88 1.31 0.03 1.8 0.785
0.00
5mins 12.15pm 1.32 0.03 1.81 0.79
0.00
15mins 12.25pm 1.34 0.04 1.81 0.7975
0.00
30 mins 12.40pm 1.34 0.04 1.81 0.7975
0.00
1hr 1.10pm 1.34 0.04 1.81 0.7975

1.10 pm 70 257.04 2.6 0.75 0.78 3 1.7825

5mins 1.15pm 2.6 0.76 0.78 3.01 1.7875

15mins 1.25pm 2.64 0.76 0.79 3.01 1.8

30 mins 1.40 pm 2.68 0.76 0.79 3.01 1.81

1hr 2.10pm 2.71 0.76 0.79 3.03 1.8225

2.10 pm 100 367.2 4.06 2.01 2.02 4.4 3.1225

5mins 2.15pm 4.1 2.03 2.03 4.44 3.15

15mins 2.25pm 4.14 2.05 2.05 4.45 3.1725

30 mins 2.4pm 4.2 2.05 2.05 4.47 3.1925

1hr 3.10pm 4.5 2.37 2.37 4.8 3.51

CLIENT SIGNATURES CONSULTANT SIGNATURES CONTRACTOR SIGNATURES


SARITHA INFRA & GEOSTRUCTURES

PROJECT: PILING WORK FOR NADIA HOUSE FOR ARRJAVV TYPE OF TEST: INITIAL PILE LOAD TEST BY ANCHOR METHOD

PILE LOCATION :TEST PILE DATE OF TEST: 19.01.2024 JACK CAPACITY:500 TON

DESIGN LOAD:600 MT NO OF JACKS:04


CLIENT:ARRJAVV BUILDERS PVT LTD
TEST LOAD:1500MT DIA OF THE JACK RAM:342mm/34.2cm

DATE OF CASTING: 16/12/2023 AREA OF :THE RAM FOR ONE JACK:918.167SQ.CM

DIA:1000mm GRADE OF CONCRETE:M50


TOTAL AREA OF THE RAM:3672 SQ.CM
PILE DEPTH: 54.00mtr from EGL

DATE TIME PRESSURE Kg/Cm2 LOAD(MT) DIAL GAUGE READING IN MM AVERAGE(mm) REMARKS

DG1 DG2 DG3 DG4

3.10pm 130 477.36 6.21 3.82 3.88 6.55 5.115

5mins 3.15pm 6.26 3.86 3.91 6.59 5.155

15mins 3.25pm 6.34 3.88 3.92 6.66 5.2

30 mins 3.40pm 6.38 3.89 3.92 6.68 5.2175

1 Hr 4.10pm 6.48 3.89 3.92 6.74 5.2575

4.10pm 170 624.24 8.51 5.75 5.91 8.9 7.2675

5mins 4.15pm 8.54 5.77 5.93 8.94 7.295

15mins 4.25pm 8.6 5.81 5.97 8.99 7.3425

30 mins 4.40pm 8.72 5.83 5.99 9.15 7.4225

1 Hr 5.10pm 8.78 5.89 6.05 9.2 7.48

5.10pm 170 624.24

5mins 5.15pm

15mins 5.25pm
30 mins 5.40pm 8.82 5.9 6.05 9.23 7.5
1 Hr 6.10pm 8.86 5.91 6.05 9.27 7.5225

CLIENT SIGNATURES CONSULTANT SIGNATURES CONTRACTOR SIGNATURES


SARITHA INFRA & GEOSTRUCTURES
PROJECT: PILING WORK FOR NADIA HOUSE FOR ARRJAVV TYPE OF TEST: INITIAL PILE LOAD TEST BY ANCHOR METHOD
PILE LOCATION :TEST PILE DATE OF TEST: 19.01.2024 JACK CAPACITY:500 TON
DESIGN LOAD:600 MT NO OF JACKS:04
CLIENT:ARRJAVV BUILDERS PVT LTD
TEST LOAD:1500MT DIA OF THE JACK RAM:342mm/34.2cm
DATE OF CASTING: 16/12/2023 AREA OF :THE RAM FOR ONE JACK:918.167SQ.CM
DIA:1000mm GRADE OF CONCRETE:M50
TOTAL AREA OF THE RAM:3672 SQ.CM
PILE DEPTH: 54.00mtr from EGL
DATE TIME PRESSURE Kg/Cm2 LOAD(MT) DIAL GAUGE READING IN MM AVERAGE(mm) REMARKS
DG1 DG2 DG3 DG4
6.10pm 200 734.4 10.8 7.61 7.89 11.3 9.4
5mins 6.15pm 10.85 7.63 7.9 11.35 9.4325
15mins 6.25pm 10.9 7.66 7.94 11.39 9.4725
30 mins 6.40pm 10.95 7.68 7.96 11.45 9.51
1 Hr 7.10pm 11.02 7.69 7.97 11.5 9.545

7.10pm 230 844.56 12.36 8.89 9.27 12.9 10.855


5mins 7.15pm 12.42 8.9 9.29 12.96 10.8925
15mins 7.25pm 12.48 8.92 9.31 13.04 10.9375
30 mins 7.40pm 12.49 8.93 9.33 13.04 10.9475
1 Hr 8.10pm 12.53 8.94 9.34 13.08 10.9725

8.10pm 270 991.44 15.24 11.03 11.56 15.9 13.4325


5mins 8.15pm 15.24 11.03 11.55 15.9 13.43
15mins 8.25pm 15.24 11.03 11.56 15.9 13.4325
30 mins 8.40pm 15.25 11.06 11.57 15.9 13.445
1 Hr 9.10pm 15.25 11.07 11.57 15.91 13.45

CLIENT SIGNATURES CONSULTANT SIGNATURES CONTRACTOR SIGNATURES


SARITHA INFRA & GEOSTRUCTURES
PROJECT: PILING WORK FOR NADIA HOUSE FOR ARRJAVV TYPE OF TEST: INITIAL PILE LOAD TEST BY ANCHOR METHOD
PILE LOCATION :TEST PILE DATE OF TEST: 19.01.2024 JACK CAPACITY:500 TON
DESIGN LOAD:600 MT NO OF JACKS:04
CLIENT:ARRJAVV BUILDERS PVT LTD
TEST LOAD:1500MT DIA OF THE JACK RAM:342mm/34.2cm
DATE OF CASTING: 16/12/2023 AREA OF :THE RAM FOR ONE JACK:918.167SQ.CM
DIA:1000mm GRADE OF CONCRETE:M50
TOTAL AREA OF THE RAM:3672 SQ.CM
PILE DEPTH: 54.00mtr from EGL
DATE TIME PRESSURE Kg/Cm2 LOAD(MT) DIAL GAUGE READING IN MM AVERAGE(mm) REMARKS
DG1 DG2 DG3 DG4
9.10pm 300 1101.6 18.07 13.36 14.04 18.92 16.0975
5mins 9.15pm 18.07 13.36 14.04 18.92 16.0975
15mins 9.25pm 18.02 13.29 13.98 18.88 16.0425
30 mins 9.40pm 18 13.29 13.98 18.85 16.03
1 Hr 10.10pm 18 13.29 13.98 18.83 16.025

10.10pm 315 1156.8 19.41 14.52 15.27 20.23 17.3575


5mins 10.15pm 19.41 14.52 15.27 20.23 17.3575
15mins 10.25pm 19.41 14.48 15.23 20.36 17.37
30 mins 10.40pm 19.43 14.48 15.23 20.38 17.38
1 Hr 11.10pm 19.44 14.46 15.23 20.41 17.385

OBSERVATION
20.01.2024
1hr 12.10am 19.45 14.46 15.22 20.42 17.3875

2hr 1.10am 18.58 14.65 15.15 19.89 17.0675

3hr 2.10am 18.53 14.69 15.25 19.89 17.09

CLIENT SIGNATURES CONSULTANT SIGNATURES CONTRACTOR SIGNATURES


SARITHA INFRA & GEOSTRUCTURES
PROJECT: PILING WORK FOR NADIA HOUSE FOR ARRJAVV TYPE OF TEST: INITIAL PILE LOAD TEST BY ANCHOR METHOD
PILE LOCATION :TEST PILE DATE OF TEST: 19.01.2024 JACK CAPACITY:500 TON
DESIGN LOAD:600 MT NO OF JACKS:04
CLIENT:ARRJAVV BUILDERS PVT LTD
TEST LOAD:1500MT DIA OF THE JACK RAM:342mm/34.2cm
DATE OF CASTING: 16/12/2023 AREA OF :THE RAM FOR ONE JACK:918.167SQ.CM
DIA:1000mm GRADE OF CONCRETE:M50
TOTAL AREA OF THE RAM:3672 SQ.CM
PILE DEPTH: 54.00mtr from EGL
DATE TIME PRESSURE Kg/Cm2 LOAD(MT) DIAL GAUGE READING IN MM AVERAGE(mm) REMARKS
DG1 DG2 DG3 DG4

4hr 3.10am 18.51 14.72 15.28 19.89 17.1

5hr 4.10am 18.5 14.74 15.34 19.89 17.1175

6hr 5.10am 18.47 14.75 15.34 19.89 17.1125

7hr 6.10am 18.45 14.75 15.37 19.9 17.1175

8hr 7.10am 18.45 14.75 15.37 19.9 17.1175

9hr 8.10am 18.41 14.75 15.38 19.9 17.11

10hr 9.10am 18.35 14.75 15.38 19.87 17.0875

11hr 10.10am 18.34 14.75 15.38 19.86 17.0825

12hr 11.10am 18.32 14.75 15.38 19.84 17.0725

13hr 12.50pm 315 1156.8 20.92 16.23 17.35 22.32 19.205

CLIENT SIGNATURES CONSULTANT SIGNATURES CONTRACTOR SIGNATURES


SARITHA INFRA & GEOSTRUCTURES
PROJECT: PILING WORK FOR NADIA HOUSE FOR ARRJAVV
TYPE OF TEST: INITIAL PILE LOAD TEST BY ANCHOR METHOD
PILE LOCATION :TEST PILE DATE OF TEST: 19.01.2024 JACK CAPACITY:500 TON
DESIGN LOAD:600 MT NO OF JACKS:04
CLIENT:ARRJAVV BUILDERS PVT LTD
TEST LOAD:1500MT DIA OF THE JACK RAM:342mm/34.2cm
DATE OF CASTING: 16/12/2023 AREA OF :THE RAM FOR ONE JACK:918.167SQ.CM
DIA:1000mm GRADE OF CONCRETE:M50
TOTAL AREA OF THE RAM:3672 SQ.CM
PILE DEPTH: 54.00mtr from EGL
DATE TIME PRESSURE Kg/Cm2 LOAD(MT) DIAL GAUGE READING IN MM AVERAGE(mm) REMARKS
DG1 DG2 DG3 DG4
1.50pm 300 1101.6 20.91 16.14 17.27 22.31 19.1575
2.30pm 270 991.44 21.05 16.87 16.9 22.23 19.2625
3.00pm 21.09 16.85 16.88 22.36 19.295
3.30pm 230 844.56 19.99 14.57 15.46 21.07 17.7725
4.00pm 19.99 14.57 15.46 21.07 17.7725
4.30pm 200 734.4 18.62 13.28 14.06 19.62 16.395
5.00pm 18.59 13.24 14.04 19.59 16.365
5.30pm 170 624.24 17.19 11.9 12.64 18.11 14.96
6.00pm 17.18 11.88 12.63 18.11 14.95
6.30pm 130 477.36 15 9.89 10.58 15.89 12.84
7.00pm 14.98 9.87 10.56 15.89 12.825
7.30pm 100 367.2 13.25 8.33 9 14.17 11.1875
8.00pm 13.25 8.29 8.97 14.15 11.165
8.30pm 70 257.04 11.14 6.5 7.16 12.09 9.2225
9.00pm 11.12 6.46 7.14 12.07 9.1975
9.30pm 40 146.88 9.93 4.57 5.24 9.93 7.4175
10.00pm 9.9 4.54 5.21 9.87 7.38
10.30pm 0 0 4.15 3.19 3.44 5.72 4.125
15min 10.45pm 3.49 2.61 3.25 4.44 3.4475
30min 11.30pm 3.33 2.57 3.2 4.29 3.3475
1 hr 12.30am 3.2 2.54 3.19 4.19 3.28

GROSS SETTLEMENT 19.205 mm


NET SETTLEMENT 3.28 mm
REBOUND 15.925 mm

CLIENT SIGNATURES CONSULTANT SIGNATURES CONTRACTOR SIGNATURES


Anchor Pile Uplift Observation Sheet
SARITHA INFRA & GEOSTRUCTURES
NADIA HOUSE 2, BRIGHT STREET KOLKATA
Sl.no Pressure Time Anchor-1 Anchor-2 Anchor-3 Anchor-4 Average Load in MT

1 Initial 12.00pm 750 750 750 750 750 0

2 40 12.10pm 750 750 750 750 750 146.88

3 70 1.10pm 750 750 750 750 750 257.04

4 100 2.10pm 750 750 750 750 750 367.2

5 130 3.10pm 750 750 750 750 750 477.36

6 170 4.10pm 750 750 750 750 750 624.24

7 200 6.10pm 747 748 749 750 748.5 734.4

8 230 7.10pm 746 747 748 749 747.5 844.56

9 270 8.10pm 744 746 746 748 746 991.44

10 300 9.10pm 741 745 743 745 743.5 1101.6

11 315 10.10pm 739 745 741 745 742.5 1156.8

12 315 12.10pm 739 745 741 745 742.5 1156.8

13 315 1.10am 739 745 742 745 742.75 1156.8

14 315 2.10am 739 745 742 745 742.75 1156.8

15 315 3.10am 739 745 742 745 742.75 1156.8

16 315 4.10pm 739 745 742 745 742.75 1156.8

17 315 6.10am 739 745 742 745 742.75 1156.8

18 315 7.10am 739 745 742 745 742.75 1156.8

19 315 8.10am 740 745 742 745 743 1156.8

20 315 9.10am 740 745 742 745 743 1156.8

21 315 10.10am 740 745 742 745 743 1156.8

22 315 11.10am 740 742 742 742 741.5 1156.8

23 315 12.50am 739 742 740 742 740.75 1156.8

24 270 2.00pm 738 741 740 743 740.5 991.44

25 230 2.30pm 738 741 740 743 740.5 844.56

26 200 3.00pm 738 741 740 743 740.5 734.4

27 170 3.30pm 738 741 740 743 740.5 624.24

28 130 4.00pm 740 741 741 745 741.75 477.36

29 100 4.30pm 741 741 743 747 743 367.2

30 70 5.00pm 743 742 744 748 744.25 257.04

31 40 5.30pm 743 742 745 748 744.5 146.88

32 0 6.00pm 745 745 746 749 746.25 0

33 0 6.15pm 745 745 747 750 746.75 0

34 0 6.30pm 745 745 747 750 746.75 0

35 0 7.00pm 745 745 747 750 746.75 0


GROSS SETTLEMENT = 19.205mm
NET SETTLEMENT = 3.280mm
REBOUND 15.925mm
Compression
Avg.
Uplift
Avg.
LOAD VS SETTLEMENT
LOAD LOAD
Settlement Settlement 1200.00 1200.00
0.00 0.000 0.00 0.00
146.88 0.797 146.88 750.00
257.04 1.822 257.04 750.00 1000.00 1000.00
367.2 3.510 367.2 750.00
477.36 5.257 477.36 750.00
624.24 7.480 624.24 750.00 800.00 800.00
624.24 7.522 624.24 750.00
734.4 9.545 734.4 748.50
844.56 10.972 844.56 747.50 600.00 600.00
991.44 13.445 991.44 746.00
1101.6 16.025 1101.6 743.50
1156.8 17.385 1156.8 742.50 400.00 400.00

1156.8 17.090 1156.8 742.75


1156.8 19.205 1156.8 740.75
1101.6 19.16 1101.6 740.75 200.00 200.00

991.44 19.30 991.44 740.50


844.56 17.772 844.56 740.50
734.40 16.37 734.40 740.50 0.00 0.00
0.00 200.00 400.00 600.00 800.00 1000.00 1200.00
624.24 14.95 624.24 740.50
477.36 12.83 477.36 741.75 0.000 2.000 4.000 6.000 8.000 10.000 12.000 14.000 16.000 18.000 20.000
367.20 11.19 367.20 743.00
257.04 9.222 257.04 744.25 Compression
Legend:
146.88 7.380 146.88 744.50 Uplift or Reaction
0.00 3.280 0.00 746.75
PILING WORK FOR NADIA HOUSE BY ARRJAVV

ANCHOR PILE LOAD TEST

Avg.
LOAD LOAD VS SETTLEMENT
Settlement
0.00 0.000 1400.00
146.88 0.797
257.04 1.822
1156.8
1156.8 1156.8
367.2 3.510 1200.00
1101.6 1101.6
477.36 5.257
624.24 7.480 991.44 991.44
624.24 7.522 1000.00
734.4 9.545 844.56 844.56
844.56 10.972
800.00 734.4 734.40
991.44 13.445
LOAD IN MT

1101.6 16.025
624.24 624.24
1156.8 17.385
600.00
1156.8 17.090
477.36 477.36
1156.8 19.205
1101.6 19.16 367.2 367.20
400.00
991.44 19.30
844.56 17.772 257.04 257.04

734.40 16.365 146.88 146.88


200.00
624.24 14.950
477.36 12.825
0.00 0.00
367.20 11.165 0.00
257.04 9.222 0.000 5.000 10.000 15.000 20.000 25.000
146.88 7.380 SETTLEMENT IN MM
0.00 3.280

You might also like