S-000-1630-007!00!0010 (Detailed Field Material Control Procedure)
S-000-1630-007!00!0010 (Detailed Field Material Control Procedure)
PMT OPRNS
THIS DRAWING AND THE INFORMATION CONTAINED HEREIN ARE THE SOLE PROPERTY OF SAUDI ARAMCO. NO REPRODUCTION IN FULL OR IN PART SHALL BE OBTAINED FROM THIS DOCUMENT WITHOUT THE WRITTEN CONSENT OF ITS OWNER.
ENGG CERT
E.S.H
K.K
FOR
STEEL STRUCTURE
JO/EWO
10-01055
FOR CONSTRUCTION
19-APR-113
DATE
INTERNAL USE
NO.
REV
00
DISCIPLINE
ENGINEER
K.Kamiya
15-APR-13
DATE:
PROJECT
ENGINEER
E.S.HAN
15-APR-13
DATE:
CERTIFIED
E.S.HAN
15-APR-13
DATE:
CONSTRUCTION
AGENCY
DATE:
OPERATIONS
APPROVAL/CERTIFICATION REQUIREMENTS,
THIS INDICATES THAT REV. NO.__________
CERTIFICATE
PROJECT SPECIFICATION DWG.TYPE PLANT NO. INDEX DRAWING NO. SHT.NO. REV.NO.
REVISION
IN D R-20A
G
13
- A U S-000-1630-007-00
02
Saudi Aramco 2616-ENG (03/99)
PMT OPRNS
THIS DRAWING AND THE INFORMATION CONTAINED HEREIN ARE THE SOLE PROPERTY OF SAUDI ARAMCO. NO REPRODUCTION IN FULL OR IN PART SHALL BE OBTAINED FROM THIS DOCUMENT WITHOUT THE WRITTEN CONSENT OF ITS OWNER.
ENGG CERT
TABLE OF CONTENTS
E.S.H
1 SCOPE ................................................................................................................ 3
4 PREPARATION................................................................................................... 3
8 STORAGE ........................................................................................................... 4
9 ISSUANCE .......................................................................................................... 5
9.1 Material Request .......................................................................................... 5
9.2 Material to be issued to Subcontractor on Back Charge Basis .................... 5
JO/EWO
10-01055
ATTACHMENTS
NO.
REV
00
DISCIPLINE
Attachment-1: Material Handling Flow Chart 6
ENGINEER Attachment-2: Receiving Inspection Report (RIR) 7
K.Kamiya Attachment-3: Overage, Shortage and Damage Report (OSD) 8
15-APR-13
DATE: Attachment-4: Material Receiving Report (MRR) 9
PROJECT
ENGINEER Attachment-5: Construction Material Issue Voucher (CMIV) 10
E.S.HAN Attachment-6: Material Back Charge Register (MBCR) 11
DATE:
15-APR-13 Attachment-7: Construction Material Return Voucher (CMRV) 12
CERTIFIED
E.S.HAN
15-APR-13
DATE:
CONSTRUCTION
AGENCY
DATE:
OPERATIONS
DATE:
CONTROL NUMBER
VERIFICATION
EDSD
DATE:
BY:
REVISIONCERTIFICATION
APPROVAL/CERTIFICATION REQUIREMENTS,
THIS INDICATES THAT REV. NO.__________
CERTIFICATE
PROJECT SPECIFICATION DWG.TYPE PLANT NO. INDEX DRAWING NO. SHT.NO. REV.NO.
REVISION
IN D R-20A
G
13
- A U S-000-1630-007-00
02
Saudi Aramco 2616-ENG (03/99)
PMT OPRNS
THIS DRAWING AND THE INFORMATION CONTAINED HEREIN ARE THE SOLE PROPERTY OF SAUDI ARAMCO. NO REPRODUCTION IN FULL OR IN PART SHALL BE OBTAINED FROM THIS DOCUMENT WITHOUT THE WRITTEN CONSENT OF ITS OWNER.
1 SCOPE
ENGG CERT
E.S.H
This Procedure covers handling and control of Steel Structure at site of Jazan
Project in Kingdom of Saudi Arabia.
K.K
2 REFFERENCE DOCUMENTS
(1) S-000-1630-001 Field Material Control Procedure
(2) S-000-1630-002 Material Exception Reporting Procedure
FOR INTERNAL USE
DESCRIPTION
4 PREPARATION
F-CAMCS shall be received Cargo Delivery Advice with Packing List from
Vendor prior to arrival at Site. After receiving the information, F-CAMCS shall
prepare unloading and storage location at site.
JO/EWO
10-01055
00
DATE:
CONTROL NUMBER
VERIFICATION
EDSD
DATE:
BY:
REVISIONCERTIFICATION
APPROVAL/CERTIFICATION REQUIREMENTS,
THIS INDICATES THAT REV. NO.__________
CERTIFICATE
PROJECT SPECIFICATION DWG.TYPE PLANT NO. INDEX DRAWING NO. SHT.NO. REV.NO.
REVISION
IN D R-20A
G
13
- A U S-000-1630-007-00
02
Saudi Aramco 2616-ENG (03/99)
PMT OPRNS
THIS DRAWING AND THE INFORMATION CONTAINED HEREIN ARE THE SOLE PROPERTY OF SAUDI ARAMCO. NO REPRODUCTION IN FULL OR IN PART SHALL BE OBTAINED FROM THIS DOCUMENT WITHOUT THE WRITTEN CONSENT OF ITS OWNER.
ENGG CERT
6.1 Receiving Inspection By F-CAMCS
E.S.H
(1) Receiving inspection shall be conducted by F-CAMCS as per Packing List.
F-CAMCS shall verify received quantity compared with Packing List and
K.K
existence of damage.
After inspection, Contractor Amalgamate QC shall put his signature on RIR and
submit to F-CAMCS for register. If any damage or off-spec is found, Contractor
Amalgamate QC shall put down in RIR and F-CAMCS shall prepare MER.
JO/EWO
10-01055
distributed with attached Packing List to the concern discipline for their reference
00
DATE:
(2) Small size accessories such as bolts, nuts, washers, and etc., shall be
bagged or put on box. Those materials shall be separated from similar
CONTROL NUMBER
VERIFICATION
DATE:
BY:
REVISIONCERTIFICATION
APPROVAL/CERTIFICATION REQUIREMENTS,
THIS INDICATES THAT REV. NO.__________
CERTIFICATE
PROJECT SPECIFICATION DWG.TYPE PLANT NO. INDEX DRAWING NO. SHT.NO. REV.NO.
REVISION
IN D R-20A
G
13
- A U S-000-1630-007-00
02
Saudi Aramco 2616-ENG (03/99)
PMT OPRNS
THIS DRAWING AND THE INFORMATION CONTAINED HEREIN ARE THE SOLE PROPERTY OF SAUDI ARAMCO. NO REPRODUCTION IN FULL OR IN PART SHALL BE OBTAINED FROM THIS DOCUMENT WITHOUT THE WRITTEN CONSENT OF ITS OWNER.
ENGG CERT
(3) Bolts, nuts, and washers must be assembled for issuance effectively.
E.S.H
9 ISSUANCE
K.K
(2) Steel structure supervisor shall check to ensure the requisition is correct.
He may cancel the requested items or amend quantity if necessary. After
JO/EWO
10-01055
00
DISCIPLINE On the date of actual material transaction, to finalize the transaction, Store
ENGINEER Keeper shall sign as the issuing party and the Recipient
K.Kamiya
15-APR-13
acknowledgement.
DATE:
PROJECT
ENGINEER (4) Upon completion of transaction the copy of the issue voucher shall be
E.S.HAN handed over to the recipient Sub-subcontractor. The original copy of issue
DATE:
15-APR-13 voucher shall be kept by F-CAMCS for record and filing purposes.
CERTIFIED
E.S.HAN 9.2 Material to be issued to Sub-subcontractor on Back Charge Basis
15-APR-13
DATE: In principle, materials will be correctly issued to Sub-subcontractor based on
CONSTRUCTION
AGENCY
official requirement only. However, if additional material is required due to Sub-
subcontractor’s negligence, such as misuse, losses, damage etc., Sub-
DATE:
subcontractor shall prepare “Material Back Charge Register (MBCR)” (see
OPERATIONS Attachment-6) for material request. Document flow shall be same as CMIV,
section 9.1.
DATE: 10 RETURN OF MATERIAL
CONTROL NUMBER
VERIFICATION
PROJECT SPECIFICATION DWG.TYPE PLANT NO. INDEX DRAWING NO. SHT.NO. REV.NO.
REVISION
IN D R-20A
G
13
- A U S-000-1630-007-00
02
Saudi Aramco 2616-ENG (03/99)
PMT OPRNS
THIS DRAWING AND THE INFORMATION CONTAINED HEREIN ARE THE SOLE PROPERTY OF SAUDI ARAMCO. NO REPRODUCTION IN FULL OR IN PART SHALL BE OBTAINED FROM THIS DOCUMENT WITHOUT THE WRITTEN CONSENT OF ITS OWNER.
Attachment-1
ENGG CERT
E.S.H
Delivery from
Vendor
Delivery
Notice
FOR INTERNAL USE
DESCRIPTION
BY Vendor
Receiving
BYF-CAMCS
MCS
RIR
JO/EWO
10-01055
BY MCS By QC
Contractor Amalgamate QC
F-CAMCS RIR
NO.
REV
00
15-APR-13 BYF-CAMCS
MCS
DATE:
CONSTRUCTION
By MCS
F-CAMCS
AGENCY
Request
CMIV
DATE: Material
OPERATIONS
BY Subcon
Sub-subcontractor BY Subcon
Sub-subcontractor
DATE: Checking CMIV
RIR : Receiving Inspection Request
CONTROL NUMBER
VERIFICATION
BY JAL Category SV
F-CAMCS MER : Material Exception Report
EDSD
to Site
BY:
BY MCS
F-CAMCS
REVISIONCERTIFICATION
APPROVAL/CERTIFICATION REQUIREMENTS,
THIS INDICATES THAT REV. NO.__________
CERTIFICATE
PROJECT SPECIFICATION DWG.TYPE PLANT NO. INDEX DRAWING NO. SHT.NO. REV.NO.
REVISION
IN D R-20A
G
13
- A U S-000-1630-007-00
02
Saudi Aramco 2616-ENG (03/99)
PMT OPRNS
THIS DRAWING AND THE INFORMATION CONTAINED HEREIN ARE THE SOLE PROPERTY OF SAUDI ARAMCO. NO REPRODUCTION IN FULL OR IN PART SHALL BE OBTAINED FROM THIS DOCUMENT WITHOUT THE WRITTEN CONSENT OF ITS OWNER.
Attachment-2
ENGG CERT
E.S.H
Attachment :
JO/EWO
10-01055
Inspected Date
19-APR-113
DATE
Inspection Type
NO.
REV
00
DATE:
OPERATIONS
DATE:
CONTROL NUMBER
VERIFICATION
Section MCS
F-CAMCS Section QC Section MCS
F-CAMCS
Name Name Name
DATE:
BY:
APPROVAL/CERTIFICATION REQUIREMENTS,
THIS INDICATES THAT REV. NO.__________
CERTIFICATE
PROJECT SPECIFICATION DWG.TYPE PLANT NO. INDEX DRAWING NO. SHT.NO. REV.NO.
REVISION
IN D R-20A
G
13
- A U S-000-1630-007-00
02
02 -
IN A
D U
EDSD REV
G
REVISION CERTIFICATE
REVISIONCERTIFICATION VERIFICATION NO. DATE JO/EWO DESCRIPTION ENGG CERT PMT OPRNS
DATE:
DATE:
DATE:
DATE:
DATE:
THIS INDICATES THAT REV. NO.__________
00 19-APR-113 10-01055 FOR INTERNAL USE K.K E.S.H
OF THIS DRAWING IS COVERED, FOR ALL
CONTROL NUMBER
13
R-20A
APPROVAL/CERTIFICATION REQUIREMENTS,
AGENCY
BY:
PROJECT
E.S.HAN
E.S.HAN
BY DRAWING COMPLETION CERTIFICATE
ENGINEER
K.Kamiya
ENGINEER
15-APR-13
DISCIPLINE
CERTIFIED
15-APR-13
15-APR-13
OPERATIONS
CONSTRUCTION
(DCC) NO. _____________________ DATE:
Attachment-3
DETAILED
JAZAN
OVERAGE, SHORTAGE AND DAMAGE REPORT (OS&D)
JAZAN PROJECT
Saudi Arabia : Manifa Profect DATE :
FIELD
Saudi Aramco 2616-ENG (03/99)
MATERIAL
MATERIAL QUANTITY RECEIVED
PROJECT SPECIFICATION
P.O QC
Code Size DESCRIPTION UNIT Packing List REMARKS
CONTROL
DOC
DWG.TYPE
SAUDI ARABIA
JO / EWO:
J95
PLANT NO.
INDEX
SAUDI ARABIAN OIL COMPANY
10-01055-0012
DATE C Conformant
DRAWING NO.
NAME NV Not Verified
SIGNATURE NC Not Comformance
8
OF
12
SHT.NO.
00
S-000-1630-007-00
REV.NO.
THIS DRAWING AND THE INFORMATION CONTAINED HEREIN ARE THE SOLE PROPERTY OF SAUDI ARAMCO. NO REPRODUCTION IN FULL OR IN PART SHALL BE OBTAINED FROM THIS DOCUMENT WITHOUT THE WRITTEN CONSENT OF ITS OWNER.
02 -
IN A
D U
EDSD REV
G
REVISION CERTIFICATE
REVISIONCERTIFICATION VERIFICATION NO. DATE JO/EWO DESCRIPTION ENGG CERT PMT OPRNS
DATE:
DATE:
DATE:
DATE:
DATE:
THIS INDICATES THAT REV. NO.__________
00 19-APR-113 10-01055 FOR INTERNAL USE K.K E.S.H
OF THIS DRAWING IS COVERED, FOR ALL
CONTROL NUMBER
13
R-20A
APPROVAL/CERTIFICATION REQUIREMENTS,
AGENCY
BY:
PROJECT
E.S.HAN
E.S.HAN
BY DRAWING COMPLETION CERTIFICATE
ENGINEER
K.Kamiya
ENGINEER
15-APR-13
DISCIPLINE
CERTIFIED
15-APR-13
15-APR-13
OPERATIONS
CONSTRUCTION
(DCC) NO. _____________________ DATE:
Attachment-4
DETAILED
JAZAN
Saudi Arabia : Manifa Profect
Job Code : 0-5000-20-0000
JAZAN PROJECT
FIELD
Saudi Aramco 2616-ENG (03/99)
Ref. No.
PO #
Date
Shipment #
MATERIAL
Vendor
PROJECT SPECIFICATION
CONTROL
DOC
DWG.TYPE
SAUDI ARABIA
JO / EWO:
J95
PLANT NO.
INDEX
SAUDI ARABIAN OIL COMPANY
10-01055-0012
DRAWING NO.
Witness by : Appearance (G) : Good Reported by :
Signature : of Package (D) : Damaged
(S) : Shortage
9
OF
12
JAL Material Controller (O) : Overage JAL Material Controller
SHT.NO.
(E) : Incorrect Material
00
S-000-1630-007-00
REV.NO.
THIS DRAWING AND THE INFORMATION CONTAINED HEREIN ARE THE SOLE PROPERTY OF SAUDI ARAMCO. NO REPRODUCTION IN FULL OR IN PART SHALL BE OBTAINED FROM THIS DOCUMENT WITHOUT THE WRITTEN CONSENT OF ITS OWNER.
Saudi Aramco 2616-ENG (03/99)
PMT OPRNS
THIS DRAWING AND THE INFORMATION CONTAINED HEREIN ARE THE SOLE PROPERTY OF SAUDI ARAMCO. NO REPRODUCTION IN FULL OR IN PART SHALL BE OBTAINED FROM THIS DOCUMENT WITHOUT THE WRITTEN CONSENT OF ITS OWNER.
Attachment-5
ENGG CERT
E.S.H
K.K
Requested By : Sub-subcontractor
Subcontractor : For MCS Use Only
Requestor : Ref : CMIV -
Date Requested: Date :
FOR INTERNAL USE
DESCRIPTION
Req'd Issued
No. Structure ID Member ID Description Remarks
Qty Qty
JO/EWO
10-01055 19-APR-113
NO. DATE
REV
00
DISCIPLINE
ENGINEER
K.Kamiya
15-APR-13
DATE:
PROJECT
ENGINEER
E.S.HAN
15-APR-13
DATE:
CERTIFIED
E.S.HAN
15-APR-13
DATE:
CONSTRUCTION
AGENCY
DATE:
CONTROL NUMBER
VERIFICATION
Issued by : Received by :
EDSD
JGC Material
Material Controller
Controller Subcon Requestor
Sub-subcontractor
DATE:
Date : Date :
BY:
REVISIONCERTIFICATION
APPROVAL/CERTIFICATION REQUIREMENTS,
THIS INDICATES THAT REV. NO.__________
CERTIFICATE
PROJECT SPECIFICATION DWG.TYPE PLANT NO. INDEX DRAWING NO. SHT.NO. REV.NO.
REVISION
IN D R-20A
G
13
- A U S-000-1630-007-00
02
Saudi Aramco 2616-ENG (03/99)
PMT OPRNS
THIS DRAWING AND THE INFORMATION CONTAINED HEREIN ARE THE SOLE PROPERTY OF SAUDI ARAMCO. NO REPRODUCTION IN FULL OR IN PART SHALL BE OBTAINED FROM THIS DOCUMENT WITHOUT THE WRITTEN CONSENT OF ITS OWNER.
Attachment-6
ENGG CERT
E.S.H
K.K
Requested By : Sub-subcontractor
Subcontractor : For MCS Use Only
Requestor : Ref : MBCS -
Date : Date :
FOR INTERNAL USE
DESCRIPTION
Req'd Issued
No. Symbol/Part No. Description of Material Size Remarks
Qty Qty
19-APR-113
NO. DATE
REV
00
DISCIPLINE
ENGINEER
K.Kamiya
15-APR-13
DATE:
PROJECT
ENGINEER
E.S.HAN
15-APR-13
DATE:
CERTIFIED
E.S.HAN
15-APR-13
DATE:
CONSTRUCTION
AGENCY
DATE:
OPERATIONS
DATE:
Issued by : Received by :
BY:
Material
JGC Controller
Material Controller Sub-subcontractor
Subcon Requestor
REVISIONCERTIFICATION
APPROVAL/CERTIFICATION REQUIREMENTS,
THIS INDICATES THAT REV. NO.__________
CERTIFICATE
Date : Date :
(DCC) NO. _____________________
PROJECT SPECIFICATION DWG.TYPE PLANT NO. INDEX DRAWING NO. SHT.NO. REV.NO.
REVISION
IN D R-20A
G
13
- A U S-000-1630-007-00
02
Saudi Aramco 2616-ENG (03/99)
PMT OPRNS
THIS DRAWING AND THE INFORMATION CONTAINED HEREIN ARE THE SOLE PROPERTY OF SAUDI ARAMCO. NO REPRODUCTION IN FULL OR IN PART SHALL BE OBTAINED FROM THIS DOCUMENT WITHOUT THE WRITTEN CONSENT OF ITS OWNER.
Attachment-7
ENGG CERT
E.S.H
K.K
Date :
DESCRIPTION
00
DISCIPLINE
ENGINEER
K.Kamiya
15-APR-13
DATE:
PROJECT
ENGINEER
E.S.HAN
15-APR-13
DATE:
CERTIFIED
E.S.HAN
15-APR-13
DATE:
CONSTRUCTION
AGENCY
Note :
DATE:
OPERATIONS
DATE:
CONTROL NUMBER
Returned by : Received by
VERIFICATION
Subcontractor : Name :
EDSD
Sub-subcontractor
Name : Material Controller
JGC Material Controller
DATE:
Date : Date :
BY:
REVISIONCERTIFICATION
APPROVAL/CERTIFICATION REQUIREMENTS,
THIS INDICATES THAT REV. NO.__________
CERTIFICATE
PROJECT SPECIFICATION DWG.TYPE PLANT NO. INDEX DRAWING NO. SHT.NO. REV.NO.
REVISION
IN D R-20A
G
13
- A U S-000-1630-007-00
02