Vincent Project

You might also like

Download as pdf or txt
Download as pdf or txt
You are on page 1of 99

MODERN SHOPPING MALL AT LIDA

BY;

WEKESA VINCENT WANJALA

INDEX; 731101/1145

A PROJECT PROPORTIAL SUBMITTED IN PARTIALFULFILLMENT OF


THE REQUIREMENT FOR THE AWARD OF DIPLOMA IN CIVIL
ENGINEERING

MAWEGO TECHNICAL TRAINING INSTITUTE

NOV/DEC 2021
DECLARATION
DECLARATION BY THE STUDENT
This project proposal is my original work and has not been submitted for
the award of diploma in any institution.

NAME: WEKESA VINCENT WANJALA


INDEX: 731101/1145
SIGN: ……………………………………….
DECLARATION BY THE SUPERVISOR
I confirm that the work that is reported in this proposal was carried out by
the candidate under my supervision
NAME: MR. WYCLIFF AKATCH
SIGN: …………………………………….
DATE: ………………………………
DEDICATION
I dedicate this project to my family for the extra pair of shoulders they offered to
me all along my project work. Secondly, I would like to dedicate this work to my
classmates and friends for staying supportive all along.
I would like to dedicate this project to my very dedicated and supportive project
supervisor for the assistance and guidance. Finally, this project is dedicated to all
the Mawego Technical Training Institute lectures and student’s fraternity for the
provision of resources and ample time till the completion of this project.
ACKNOWLEDGEMENT

My sincere gratitude goes to the Almighty God for the life and good health He has
granted me throughout the project duration. I would also like to express my special
thanks to several individuals for supporting me throughout my study.
Special appreciation goes to my supervisor, Mr. Akach Wickliffe for his
enthusiasm, patience, insightful comments, helpful information, practical advice
and unceasing ideas that has helped me tremendously in my research and writing
of this thesis. His immense knowledge profound experience and professional
expertise in structural design, architectural works and measurements has helped
me complete this research successfully.
Secondly my utmost thanks goes to my family. Without their support and guidance
this project would not have been possible. I could not have imagined of having a
better family than them throughout my studies.
Finally I wish to express my sincere thanks to my friends, classmates and the
entire Mawego TTI fraternity for allowing me into their program, their ample time
and facilitation of resources. I will always be indebted to their immense support.
ABSTRACT
In the era of globalization, increasing the nation’s industrial competitiveness and
production value is a challenge to every country. Therefore Kenya must strive for
innovation, increase the added value of its products and enhance industrial competitiveness.
Today, shopping malls are not developed for a single functional purpose. The
contemporary shopping malls demonstrate diverse manifestations of creativity and culture.
Relative to the shopping avenues of the past, today’s shopping malls have more complex
and rich cultural functions.
The functional aspect of shopping mall serves to satisfy the economic model that connects
commercial entities and buyers
Another function is to provide a fascinating place that presents visitors with a culturally
creative and unique impression through its architectural and interior design
As an experiential place, a shopping mall must have a unique and special place that is
suitable for socialization
To attain such functions the spaces of a shopping mall must not be placeless.

The need for a shopping mall at Lida was as a result of the growth of the Lida market and
increase in population, therefore, creating a need for one stop shopping mall to help solve
the problem accessing all the required goods and services under one roof. Moreover the
relationship between the local culture of Luo people and shopping also influenced the need
for a mall.
The modern shopping mall is to be constructed on a 100 square meters piece of land and is
almost one kilometer from Mawego TTI.
The modern mall is to comprise of a basement parking for saloon cars with a general size of
30M by 20M wide. The height of the basement is 2.8m high. ground floor comprises of a
supermarket and rental stalls for tenants. The supermarket is big enough with a size of 30m
by 30m wide. The stall units for tenants are 6m by 5m wide large enough to accommodate
any tenant. It also has a washroom and eye clinic with a pharmacy.
The first floor also has an electrical and electronic accessories supermarket. The size of the
electronic supermarket is 31m by 20m wide. The first floor has a business college, a
conference hall and a cafeteria. It also has rental units of size 6m by 5m and a control room
for security use.
Contents

DECLARATION ....................................................................................................................................... 2

DEDICATION .......................................................................................................................................... 3

ACKNOWLEDGEMENT ......................................................................................................................... 4

CHAPTER ONE........................................................................................................................................ 8

1.1 INTRODUCTION: .............................................................................................................................. 8

1.2 BACKGROUND OF STUDY ............................................................................................................. 8

1.3 PROBLEM STATEMENT .................................................................................................................. 9

1.4 OBJECTIVES OF THE PROJECT ...................................................................................................... 9

1.5 SIGNIFICANCE OF THE PROJECT .................................................................................................. 9

1.6 CO OPERATIONAL DEFINITION OF TERMS............................................................................... 10

2.0 CHAPTER TWO ............................................................................................................................... 11

LITERATURE REVIEW ........................................................................................................................ 11

2.1 Kenya Vision 2030. ............................................................................................................................ 11

2.2 Millennium Development Goals ......................................................................................................... 12

2.3 The city Metro 2030. .......................................................................................................................... 12

2.4 Constitution ....................................................................................................................................... 13

CHAPTER THREE: METHODOLOGY ................................................................................................. 14

3.1: SURVEY .......................................................................................................................................... 14

3.1.1 Site selection ................................................................................................................................... 14

3.1.2 Marking of obstacles ....................................................................................................................... 14

3.1.3 Noting of obstacles.......................................................................................................................... 14

3.1.4 Pre-existing features ......................................................................................................................... 15

3.1.5 Running survey lines....................................................................................................................... 15

3.1.6 Taking notes.................................................................................................................................... 15

3.1.7 Problems encountered ..................................................................................................................... 15

3.1.9 Contouring. ..................................................................................................................................... 16

SURVEY FIELD BOOK-LEVELING..................................................................................................... 17

3.2: SOIL MECHANICS ......................................................................................................................... 18


3.2.0SOIL INVESTIGATION ................................................................................................................. 18

3.2.1 Procedure ........................................................................................................................................ 19

3.2.2 Bearing Capacity Tests (CBR) ......................................................................................................... 20

3.2.3 DRAINAGE WORK....................................................................................................................... 22

3.2.2.2 : ARCHITECTURAL DESIGN AND DRAWINGS ..................................................................... 23

3.2.2.3: MEASUREMENTS .................................................................................................................... 24


............................................................................................................................................ 27
3.2.2.4.BILLS OF QUANTITIES ............................................................................................................ 42

3.3 SITE ORGANISATION & ADMINISTRATION .............................................................................. 70

3.4 REFERENCE .................................................................................................................................... 73


CHAPTER ONE

1.1 INTRODUCTION:
The latest emerging trend in the corporate world is the emergence of shopping malls. The
first thing that comes into our minds about shopping malls is that it is a big enclosed
building housing a variety of shops and products. According to historical evidences
shopping malls came into existence in the middle age, though it was not called so. The
concept of departmental stores came up in the 19th century with the industrial revolution.
Consumers wanted a better shopping experience and this demand gave rise to the
emergence of shopping malls. Originally the first of the shopping malls was opened in
Paris. Then the trend followed in metros over the world.
The concept of shopping was altered completely with the emergence of shopping malls.
Shopping has no longer been limited to a mere buying activity- it has become synonymous
with splurging time and resources. People simply go about roaming through the shopping
mall in order to peep through the window of the shop and often end up buying they like.

1.2 BACKGROUND OF STUDY


Shopping malls are also called retail parks or out of town shopping centers. Through this
market research project, I have made an attempt to address a few of the issues stated earlier.
The target population constitutes the people of Lida town in Rachuonyo sub-county.
I have studied a sample of 200 people to have a comprehensive view of the problem; I have
used various research methodologies to present the findings of my research.
I have made use of both primary and secondary research methods for data collection so as
to have an insight into the fact how my research report can form a source of information the
need for a shopping mall in the Lida market to create an employment opportunity and help
solve the problem of easy access to services and products.
1.3 PROBLEM STATEMENT
The success of a shopping mall depends on many factors, the major one being the mall
attractiveness which determines preference by both the potential tenants and consumers.it is
argued that the shopping mall attractiveness is an important consideration to the tenants,
developers and visiting customers. An attractive location and differentiation from
competitors are important to the developers that chose the site of a shopping mall and thus
preference of locating a mall and not any other thing.
With the advent of major shopping malls in Kenya, mall preference decisions by retailers
and consumers have emerged as an important domain of study. Over the last decade there
has been substantial research on the success factors of malls in the overseas countries.
However the research in the area of shopping mall is very limited in Kenya. This is the
knowledge gap that this project tries to fill. This study tries to establish the critical
dimensions that tenants/ retailers evaluate when making choices as to where to locate their
businesses among the various options available.

1.4 OBJECTIVES OF THE PROJECT


The objectives of this study include:
To determine the influence of the location on the tenant preference of modern shopping
mall in Lida.
To asses to what extent tenant mix influence modern shopping mall in Lida.

1.5 SIGNIFICANCE OF THE PROJECT


This research is worthwhile undertaking as the findings may be of benefit to developers and
mall managers in ensuring a successful mall development in this competitive retail
environment. This research offers shopping mall developers an understanding of mall site
selection and development that will help them gain competitive advantage over other
competing firms. The study may also be important to store owners/ mall tenants in
determining the choice of their business location.
1.6 CO OPERATIONAL DEFINITION OF TERMS
DWG: Drawing
FL: Floor Level
GC: General Constructor
IN: Inch
LL: Live Load
MH: Man Hole
QTY: Quantity
RC: Reinforced Concrete
BOQ: Bill Of Quantity
FFL: Floor Finish Level
PC: Precast Concrete
BS8110: British Standard Cord
MM: Millimeter
M: Meters
CONC: Concrete
2.0 CHAPTER TWO

LITERATURE REVIEW
The modern shopping mall at Lida is a three storey building with a basement parking for
saloon cars with a height of 2.8 meters. Ground floor building has a size of 40M length by
30M wide. It has a general supermarket and several rental units of standard size 7M by 4M
wide. It also has a standard restaurant and eye clinic. The ground floor has a two stairs, one
from the basement parking to the ground floor and another one from the ground floor to the
next floor which is the first floor.
It has water closet and showers on both ground and first floor on the left and right hand
sides. It would consist of wide strip foundation. The foundation is in filled with handpicked
quarry hardcore with 150mm thick stone dust to receive the slab concrete. The basement
walling then commences from the basement slab with a height of 2.8 M.
Thereafter the ground floor slab is constructed of size 40 by 30 m wide. Waterproofing in
the basement is a key element and care has to be done.
It has superstructure wall made of natural Stone 200mm thick at height of 3.5 from ground
floor to the beam under the slab. The slab is 150mm thick reinforced concrete held by a
450mm reinforced beam at ratio 1:2:4.
The wall above the first floor is 3.5m high and 200mm thick natural Stone. The roof
consists of steel trusses and purlins at an angle of 30degrees covered by galvanized iron
sheet gauge 28.
Its ground and first floors has a25mm thick floor finish and 12mm thick internal wall finish
at both ground and first floor walls. The outer wall of both ground and floor are pointed at
stone joints and rendered at their column and beams.
Both internal and external finishes are painted in three coats of different colors at specified
places. It has ceiling made of gypsum at the first floor which improves its appearance and
also cover electrical and plumbing services also to reduce the volume of the room
enhancing its air conditioning

2.1 Kenya Vision 2030.


This is a new National development strategy that was developed for the period of
2008-2030.It aims at developing the Kenya Economy and Employment levels by the year
2030. Its goal is to transform Kenya into a newly industrializing, middle income country
providing a high quality of life to all its citizens in a clean and secure environment. The
vision targets to attain MDGS that were given a time limit to 2015.The vision has three
pillars: Economic, social and political governance. Economic pillar aims at achieving an
economic growth rate of 10% per annum. This vision has flagship projects to address the
same which are in various sectors such as agriculture, education, water and environment.
The vision envisages a country firmly interconnected through network of roads, railways,
ports, airports and waterways. It envisages that by 2030, it will become impossible to refer to
any region of the country as remote and so the focus would be oninvesting in the nation’s
infrastructure.
For Kenya to achieve a middle economy status it has to invest in its road network that
conforms to article 70 of constitution on environmental issues and article 43 on economic
and social rights among others by following these actions:
To upgrade road links in order to reduce traffic congestion and improve accessibility and
mobility to cope with increasing road traffic
To expand the road network by construction of new roads
To construct to paved standards all economically viable major urban arterials.

2.2 Millennium Development Goals


The eight Millennium Development Goals (MDGs) provide a framework to plan and
implement development, and include time-bound targets and indicators by which progress
can be measured over the period from 1990 until 2020 when the targets are expected to be
met. Particular interest is given to the goal number seven which is to ensure environmental
sustainability. Target seven aims at integrating the principles of sustainable development into
country’s policies and programs and reduce loss of environmental resources. The
development project will take into account these principles and will ensure that the sources
of the materials used do not hamper environmental sustainability.

2.3 The city Metro 2030.


It takes into account that more than 57% of world population will be living in cities hence
there will be need for efficient transportation system. It envisages transport as a key
component in promoting a competitive business environment as well as a viable means in
which other economic and social objectives can be attained. This therefore creates the need
for an efficient transport system which minimizes travel times and distance.
City Metro was formulated in line with the vision 2030 key development agenda which
include: rapid economic growth, employment and balanced wealth creation, poverty
alleviation. Policy concurs with the fact that efficient transport minimizes travel time. The
policy document has measures dealing with transportation:
Mass rapid transit
Traffic management structures
Traffic law enforcement
Demand management
Road transportation and infrastructure measures.
Legal framework
2.4 Constitution
The Constitution classifies land as public land, private land and community land. The
Constitution also gives guidelines on how land is to be used equitably, efficiently,
productively and sustainably, Article 60(1). The State is given the authority to regulate the
use of land or any interest on or over land as stated in Article 66, for reasons as defense,
public safety, public order, land use planning, public morality and public health. The
Constitution states that all land in the country belongs to the state therefore any mineral
within the land is owned by the state.
The Constitution also requires that there is environmental conservation without which there
would be legal consequences.
The constitution stipulates that all Kenyans with any disability are entitled to reasonable
access to all places, public transport and information. This implies that traffic congestion
must be alleviated in order to promote accessibility. Traffic jams impedes accessibility.
Draft Integrated National Transport Policy Of 2003
The transport policy provides strategies that can be used to manage transport planning in the
country to facilitate movement and accessibility. This policy provides guidelines on the
linkages that should be established in the country. It aims at providing integrated, efficient,
reliable and sustainable road transport infrastructure that meets national and regional
passenger and freight transport goals. It envisions a transport system that is effective and
efficient in which there is a faster flow of goods and people while being environmentally and
economically sustainable.
CHAPTER THREE: METHODOLOGY

3.1: SURVEY
I adopted grid method as the method of taking survey points and also during the coming up
of contours. This is because it is easy and the most comprehensive considering availability
of survey equipment which had to be shared in groups.
Survey had to be carried out in order to;
Conduct the necessary field survey work to determine the best alignment.
Carry out engineering survey on the chosen alignment in order to obtain data for the design
of the horizontal and vertical alignment.
Survey procedures carried out were;
Reconnaissance survey
Chain survey
Leveling
Contouring Reconnaissance survey
th
This activity was carried out on 12 May 2021 by a team which I led.
The activities carried out include;
Site selection.
Marking of obstacles.
Noting of obstacles.
Pre-existing features identification.
Running the survey lines.
Taking notes.

3.1.1 Site selection


Based on the clients’ requirements of the construction of modern shopping mall at Lida,
The project was to be constructed at Lida Market, one kilometer from Mawego TTI. The
project was to be set up in a 100 by 100m piece of alnd

3.1.2 Marking of obstacles


Being selected as the team leader, I lead my team to the site to be able to identify obstacles
that might hinder our process of survey work.

3.1.3 Noting of obstacles


Identified obstacles are noted down for easy re-identification during the process of surveying
and also to be able to find alternative methods and lines of sight without obstruction.
3.1.4 Pre-existing features
Features such as heaps of soil will be moved away. Also, trees will be cut down in order to
allow for the construction works to run out smoothly.
3.1.5 Running survey lines
The survey lines started from the east. Our baseline was on the eastern end and run across
northwards. The survey lines run through 64 points in total. The grid was made up of grids
measuring 10m by 10m on a 150m by 200m land.

3.1.6 Taking notes


All my team members each had to take notes on the procedures. The materials needed were:
a. Field book.
b. Pencil.
c. Tape.
d. Hammers.
e. Ranging rods.
f. Dumpy level.
g. Staff

3.1.7 Problems encountered


1. Misunderstandings among colleagues because some of them were unfamiliar with the
surveying method used.
2. Early tiresomeness among colleagues hence lack of concentration.
3. Unfavorable weather condition, hot sun all day long.
4. Inexperienced reading of the dumpy level among members hence taking a lot of time.
Chain surveying.
Linear measurements were taken using a tape measure. A skeleton framework was made
consisting of a number of lines forming a regular shaped square on the proposed site. The
intervals between the lines were 10m and the whole proposed site was 150mby 200m
rectangle. Materials used include:
Tape measure.
Pangas.
Hammers and mallets.
Ranging rods.
Pegs
3.1.8 Leveling.
The grids were established on the day of chaining. This was a 10m by 10m grid. They were
marked using wooden pegs. During leveling, the dumpy level was used to take the readings
on the leveling staff taking readings of each point on the grid. An assumed datum of
100.00m was used to calculate the reduced levels of all 64 points surveyed. Field levels
were taken as follows:

3.1.9 Contouring.
After reducing the levels of each of the grid points which is at the intersections, the levels
were then put into excel format in a systematic manner to help with the coming up of
contours using AutoCAD which is a computer software used in the most civil engineering
projects. I being competent and well conversant with AutoCAD operation, I came up with the
contour lines without any difficulty. The reduced levels were as follows;
SURVEY FIELD BOOK-LEVELING

I leveled the site using rise & fall method as shown in the table below in reference to the
temporary Bench Mark and establish information required in the drawing.
The table below shows booking for the data obtained by the reduced level of bench mark
tone 100.00m and peg intervals to be 20m.

Stations Back Site Intermediate Fore site Rise Fall Reduce Remark s
sight levels
0 2.140 100.00 BM
20 1.024 1.116 101.116
40 2.403 0.820 0.204 101.320 CP
60 1.704 0.669 102.019
80 2.061 0.357 101.662
100 1.426 2.325 0.264 101.398 CP
120 2.098 0.672 100.726
140 2.954 2.258 0.160 100.566 CP
160 2.291 0.663 101.229
180 1.124 1.167 102.398
200 1.270 0.462 0.662 103.058 CP
220 0.763 0.507 103.565
240 1.423 0.660 102.905 LRL
Total 10.193 7.288 5.018 2.113

Arithmetic checks:
Sum of back sight – sum of fore sight = sum of rise – sum of fall 10.193 – 7.288 = 2.113
2.905 = 2.905
3.2: SOIL MECHANICS

3.2.0SOIL INVESTIGATION
This is aimed at determining the characteristics of the soil at the proposed site in order to
carry out soil tests.
I took the samples of soil from the site at a distance of 20m interval and took them to the soil
mechanics laboratory in Mawego Technical Training Institute to test and get the correct
data to be used in design.
Soil sampling was done from different trial pits. These tools were required:
Two spades.
Tamping rod.
Moisture bags.
The following soil tests were conducted:
Sieve analysis (grading).
Plasticity index.
Moisture content test (proctor).
Bearing capacity test (CBR). Purpose of soil tests.
To provide the necessary data in order to come up with a structurally safe and economical
structure.
To come up with the best construction methods.
To be able to predict any possibilities of challenges and how to deal with them.
To be able to classify soil according to their appearance and physical characteristics
Sieve Analysis (Grading)
Purpose: to determine the grain size distribution in soils. Apparatus:
Riffle box
Weighing balance
Assorted sieve sizes
Procedure
The sample is passed through the riffle box to obtain the required quantity.
Weigh the sample to be sieved
The sample is soaked in a solution containing 2g of Sodium Hexameter Phosphate for
24hours. It is then washed and left to dry.
The sieves are then assembled in a descending order.
The dry sample is placed on the topmost sieve followed by shaking of the sieves.
The weights of the retained sample through each sieve size are taken.
A graph of percentage retained against sieve size is then plotted and then checked against
specification given.
Plasticity index.
The purpose of this test is to determine the plasticity of fine soil. Apparatus:
Casagrande
Groove
Wash bottle
Glass plate
Weigh balance
Palette knives
Pestle and mortar
Trough
Receiver
Sieve-425um

3.2.1 Procedure
Sample is crushed using pestle and mortar then passed through the sieve.
Water is added to the sample that passed through the sieve and mixed thoroughly using
palette knives on the glass plate to form a uniform paste.
A portion of the collected material is placed in the Casagrande which is the grooved leaving
a gap in the center.
The sample in the Casagrande is then hit with specified number of blows 50,40,30,20 and 10
till the grooved portions meet.
A portion of the wet sample for each number of blows is taken for moisture content
determination.
For shrinkage limit, the sample is hit through 25 blows then placed in a 140mm long trough
and air dried for 24hrs. The length of the dried sample is measured for the shrinkage limit
determination.

For plastic limit, the sample of the 50th blow is used after drying to make rolls that are used
in moisture content determination.
The higher the number of blows, the lesser the amount of moisture thus, soil is added to the
wet sample on the glass plate followed by thorough mixing.
A graph of moisture content against the number of blows is then plotted to determine the
liquid limit.
Moisture content test (proctor)
Purpose: To determine optimum moisture content maximum dry density of the soil.
Apparatus
Sieve 20
Mould, base plate and collar.
Measuring cylinder.
Rammer (2.5kg for field).
Weighing balance.
Straight edge chisel
Mixing plate Procedure
2500g of sample passed through the sieve 20 is weighed.
Using the measuring cylinder, the lowest amount of water is added to the soil sample then
mixed to achieve a homogeneous product.
The 2.5 rammer is used with the sample placed in three layers with 27 bows at each layer.
The collar is then removed from the mould and excess material trimmed using the straight
edge.
The sample is then weighed plus the mould and the base plate.
A portion of the compacted sample is then taken for moisture content determination.
The above processes are repeated with different amount of water till the optimum moisture
content is achieved.

3.2.2 Bearing Capacity Tests (CBR)


The purpose of the test is to determine the strength and stability of the soil material for
pavement construction.
It involves penetration of model soil sample with a cylindrical plunger at a constant
1mm/min.
The force corresponding to penetration of 2.5mm and 5.0mm are used to determine the
strength and stability of the soil.
MDD and OMC that were obtained in proctor test are used to calculate the mass of wet soil
and the mass of the dry soil and water content required.
Mass of wet soil= 0.95x23.0xMDDx (OMC x 100)1000
Dry soil= (wet soil+500) (PMC+100)
100
Amount of water =(PMC-OMC) x Dry soil
10

Apparatus
Mixing plate
Mould, base plate and collar
Weighing balance
Measuring cylinder
Spacer disc
2.5kg rammer
Swell disc
Procedure
Using the obtained proctor results, weigh the dry sample and measure the amount of water
then mix to obtain the wet material.
Take the portion of wet material for moisture content determination.
From the proctor result calculations, weigh the required wet material to be mould.
-For dynamic method, three moulds are used placing the materials in three layers compacting
each layer with 62 blows for the first mould, 25 blows for the second and 10 blows for the
last mould.
-in static method, the wet material is placed in CBR mould then using a jack, the material is
compressed in the mould.
Placing a swell disc on top of the mould, the initial swell readings are taken.
Place the mould in water for 4days in case of neat material.
After soaking, the final swell readings are taken.
The mould is left to d3rain then placed in CBR penetration machine penetrating the top and
bottom. The penetration readings are taken at intervals of 0.25 up to 5.00.

To obtain the strength, the values at 2.5mm and 5.0mm are multiplied by the ring factor for
both the top and the bottom then average.
Compaction factor = dry density x 100
MDD
3.2.3 DRAINAGE WORK
The main aim of the drainage pattern in the proposed site is to ensure that the rain water and
the surface water is removed from the road so that it cannot affect the pavement and the
structure in general.
Existing drainage system /Recommended and proposed drainage system.
There is an existing drainage system on the pavement and around the entrance of The lagoon
which collects all the rain water and the surface water which is directed along the main
pavement. The drainage gently slopes hence water moves by use of gravity. The new
structure will require some improvement on the drainage system since all the water
collected from elevated interchange will be directed to the main pavement drainage system.
Design of an economical channel
The principle used was the wetted perimeter; maximum discharge depends on the wetted
perimeter, given the coefficient of roughness and slope.
Manning` Roughness Coefficient
Channel material Roughness coefficient
Metals 0.010-0.024
Glass 0.009-0.013
Concrete 0.011-0.017
Wood 0.012-0.016
Clay 0.013-0.016
Grave 0.020-0.033

Drainage area Impermeability


Concrete/Bitumen surface 0.8-0.9
Gravel/Macadam surface 0.4-0.7
Base/Impervious soil 0.4-0.7
Impervious soil with turf 0.3-0.6
Slightly pervious soil with turf 0.2-0.4
Pervious soil 0.1-0.3
Wooden area 0.1-0.3
Rainfall intensity obtained from the meteorological department of Kenya is 120mm per hour
3.2.2.2 : ARCHITECTURAL DESIGN AND DRAWINGS
Involves, the pictorial drawings of the proposed project. The drawings include:
Floor Plans
Elevations
Cross -sections.
More details about the drawings are shown on the plan
3.2.2.3: MEASUREMENTS
MEASUREMENT

T D S DESCRIPTION

TAKING OFF QUANTITIES


MODERN SHOPPING MALL AT LIDA
DRAWING NO 15/09/2021
SUBSTRUCTURE WORKS
ALL PROVISIONAL

Checklist

i. Site clearance

ii. Excavation of the topsoil.

iii. Disposal of excavated soil.

iv. Excavation of basement

v. Setting off the column base.

vi. Planking and strutting.

vii. Dewatering.

viii. Surface treatment.

ix. Formwork.

x. Compaction.

xi. Concrete foundation.

xii. Hardcore.

xiii. Blinding.

xiv. Wall.

xv. Slab.

xvi. Concrete in column base.

xvii. D.P.C
SITE CLEARANCE

L= 40

W= 30
ADD
ALLOWANCE
2/1.5

L = 40 + 3.0 = 43.0

W = 30+3 = 33.0

43.0 Clear site of all bushes and shrubs including small trees
and burn on site or cart away the arising debris
33.0
EXCAVATION TOPSOIL

L= 40

W=30

ADD FDN SPREAD 2/0.2 = 0.4

ADD WORKING ALLOWANCE 2/ 0.5 =1.0


L = 41.4

W =31.4

Excavation of the top soil up to 0.15m depth startingfrom


41.4
the strip level.
31.4 {Remove all the excavated soil 100m from the site.}

UNDERGROUNG BASEMENT EXCAVATION


Depth 3m
Less stripping = 0.15m = 2.85m
Length of basement =30m 30.6
Add working space 2/ 0.3 0.6
Width of the basement =20m
Add working space 2/0.3 =0.6 =20.6

30.6
Excavate top soil not exceeding 4.5 m in red soil from
20.6 the strip level and return fill and ram
Remove all the excavated soil and deposit away from
site.
SETTING OFF THE COLUMN BASE

120

400 1200

400

L = 1200

W= 1200

D= 200
Ditto

For blinding core, column base does not need


32/ 1.2
formwork.
1.2

0.2

RAINFOCEMENT FOR THE COLUMN BASE

Provide 5 Y 20 for the column base

Main bars 5 Y 20 at 110mm Length=

1200

Width= 1200

Less 2/25

L= 1150

W= 1150
32/ 1.150
Use 20Ø high yield bars at 110mm
32/ 1.150
c/c with tying wires and space blocks

FORMWORK FOR THE COLUMN

Y8

Y 10 at 400mm

5y20L=

400

W= 400

H= 3500
32
0.4 Provide soft sawn timber for formwork nailed well.
0.4

3.5

CONCRETE FOR COLUMN

BASE

L= 1200
W= 1200

D= 200

Provide a mix in concrete in ratio 1:2:4 well mixed and


compacted.

CONCRETE FOR THE COLUMN


L= 400

W= 400

H= 3500

Provide concrete in ratio 1:2:4 and well compacted.


32 0.4

0.4

3.5

COMPACTION OF THE BASE

30.6 Compact with a roller to ensure maximum strengthis


obtained.
20.6

FOUNDATION SLAB

i. Hardcore
30.6 Provide hardcore well laid and compacted to detail. 300mm
thick handpicked hardcore from an approved quarry
20.6

ii. Lime

Provide lime well compacted to attain strength


30.0 655(32/200) from column

20.0

0.20
D.P.C
30.0
Provide D.P.C for all the slab
20.0
30.6
Wire mesh
20.6
Provide wire mesh for the base of the concrete
655(32/200)

30.6 Concrete

20.6 Provide concrete well compacted to attain


maximum strength, concrete mix in ratio
1:2:4

30.6

20.6 iv. Bitumen


Provide bitumen for the slab well compacted less
for the column.

(32/200 )

FORMWORK FOR

THE SLAB

30.0 L= 2/200000
20.
W= 2/12000
0 Depth= 200
Provide soft sawn timber for formwork of the
elevated slab.

30.0 Metal sheet boards for floor deck to support slab

20.0
Side support soft sawn timber or metal sheet
20.0 boards

0.55

20.0 Side support for slab

0.55
166.7/
2.8 Soft sawn timber round poles for support props

Soft sawn timber for folding wedges


166.7
1

PLANKING AND STRUTTING

Planking and
strutting

t-support

Allow for planking and strutting to the side of the


Item columns to act as a retaining wall to prevent the
collapse of the elevated slab.

Allow for the removal of water.


Item
Allow for the surface treatment before laying of
Item the hardcore.
GROUND FLOOR SLAB

L =40.00

W =30.00

Less ext walls 2/0.275

L =39.45

W =29.45

Reinforced insitu concrete1:3:6 horizontal work


39.5 in structures n.e 300mm thick
29.5 &

Mesh reinforcement ref A 252 weighing 3.95kgs


/m2 with 150mm minimum side laps

&

1200mm gauge polythene horizontal damp proof


membrane exceeding 500mm wide

& 50mm thick insulation lain on concrete


TAKING OFF ALL QUANTITIES

MODERN SHOPPING MALL AT

LIDA DRAWING NO 15/09/2021

SUPERSTRUCTURE WORKS

1. BLOCKWORK

MEAN GIRTH
External dimensions
Length= mean girth
Width= height of wall
Mean girth
27.30
27.30
40.30
40.30
7.30
7.30
Total= 149.80
Less corners
8/0.5/2/0.20= 1.6
Total =148.20

INTERNAL DIMENSIONS
HORIZONTAL WALLS
4.70 X 4
9.70 X 2
9.70
14.70
3.39
6.65 X3
4.7 X 3
TOTAL= 100.9

VERTICAL WALLS
1 X 7.30
1 X 22.70
2 X 19.60
4 X 46.95
TOTAL= 87.98
TOTAL INTERNAL DIMENSIONS
Horizontal dimensions + vertical dimensions
100.9 + 87.98
Total =188.07

TOTAL MEAN GIRTH


INTERNAL + EXTERNAL DIMENSIONS
148.20 + 188.07
TOTAL = 336.27

200mm thick natural stoned walling bedded and


336.27 joined in cement sand mortar 1:4 forming a
3.6 stretcher bond and including stainless steel
twisted wire wall ties.

DEDUCT
Deduct block work as before described.
OPENINGS

Glass openings
L= 4.7 X 3
W= 3.0

3/ 4.7 Deduct glass openings as before described.


3.0
DOORS

L=2.00
H=2.4M
18/ 2.00
2.4

2/
3.0 Deduct door openings from block work as before
2.4 described.

WINDOWS

L=2.00
W=1.5
23/ 2.0
Deduct window openings from block work as
1.5 before described.

Ddt ditto
4/ 0.61
0.5
WINDOWS
WINDOW TYPE D2 [36 IN NUMBER]
AS PER DRAWING NO 15/09/2021
MODERN SHOPPING MALL AT LIDA OF 20 TH
OCTOBER 2021.

PREAMBLE
Supply and fix the following metal casement
windows as per steel fabricators or equal and
approved complete with all necessary fastener
window stays and one coat of red lead oxide
primer and all open able panels have a 50mm vent

CASEMENT (NO)
1 Metal casement overall size 2000x1500mm high
36/
comprises of 4 no bottom fixed panels size
500x450mm, 4 no middle fixed panels size
500x500mm and top size hung open able panels
size 500x500mm

PANES (M2)
Bottom =0.45x0.5=0.15m2
Middle 0.5x 0.5=0.25m2
Top 0.5x0.5=0.25m2
Assume 4mm thick clear glass
36/4 0.45
0.5
4mm thick clear glass sheet fixed to metal
36/4 0.5
casement window with putty 0.1 to 0.5m2
0.5
36/4 0.5
0.5

GRILL (NO)
36/ Burglar proofing grill overall size 1.5mx2.0m
1
comprising of 12mm welded bars vertically at
150mm centers and 12mm welded horizontally
at150mm centers welded to steel casement
windows

PELMET BOXES
Total length 2.0+0.3m=2.3m
36/ 2.3 50x50mm Cypress bearer plugged to concrete
beam
175x25mm cypress front nailed to cypress top
36/ 2.3

36/ 175x25mm cypress nailed to cypress bearer


2.3

36/2 175x175x25mm cypress boxed ends to top and


1
nailed to top and front end

Curtain rail

L=23.5-0.05=2.25

36/ Aluminum I section or 25mm diameter tube fixed


2.25 to cypress top with hooks including all the
necessary rollers, stops and overlaps.

36/ 2.1 Precast concrete 1:2:4 window sill 175mm wide


by 50mm to 25mm thick bedded and jointed in
natural stone wall an cement and mortar 1.4
weathered and throated
3
2.1
WINDOW BOARD (LM)
150X25mm camphor window board plugged into
natural stone

PAINTING CASEMENT(M2)
36/ 2.1 Prepare and apply one under coat and two finished
`1.5 coats of oil paint to surfaces of burglar proofing
grill measured both surfaces

36/ PELMET BOXES(LM)


2.15 Knot, prime and stop and apply one undercoat and
36/ two finishing coats of oil paints to timber surfaces
1.80
100-200mm girth
TAKING OFF QUANTITIES
MODERN SHOPPING MALL AT LIDA
DRAWING (NO) 15/09/2021
SUPERSTRUCTURE WORKS
ROOF
Notes;
(a) Trusses are spaced at 2.0m centers and are in
second grade cypress
(b) Purlins are spaced at 1.2m centers
(c) Collars are 75x50mm
(d) Roof covering is G.C.I gauge 26 with 75mm
end laps and 50mm side laps
(e) Bolts are spaced at 1.5m centers
(f) Use 30 degrees pitch

Soffit of slab
L =2100 =21.0
Less - ½ x 8 04 = 1.6
Beam 19.4
W = 19800 = 19.8
Less ½ x 8 x 0.2 1.6
18.2 Beams 18.2
0 Sawn soffit to
15.30 slab Ddt ditto
13.00 Conc (1:2:4) to suspended

21.00 slab. Ddt Ditto

105 19.80 Roof


105 structure.
0.10
Wall plate
15.30
L = (2 x 19.86) + (5.3 x 2) + (13.0) + (2 x 4000)
13.00
= 1099
0.10

109.90 100 x50mm wall plate to ring


49
2/2/ beams Rafters
4/
Length of rafters on plan
2,4/
Half span = 2000

Wall thickness =

200 Overhang =

600

2800 =2.80

3.233 L = 2.80 = 3.233m


m
Cos 30
m

3.2
L 3.233m
33
300
L= 5-300 x 3.233 = 1.6165m
100 x50 king

posts Purlin.

100 x 50mm

1.62

19.80
21.0 Roof covering cancel ridge

46.4

15.30
GL Iron
16.23
Roof covering
15.30

3.23 Galvanized iron sheets

15.80 100 x 50mm

3.23 Roof covering

Iron sheets
3.2.2.4.BILLS OF QUANTITIES
UNIT AMOUNT
ITEM DESCRIPTION QTY UNIT RATE (Kshs)
(Kshs)
PRELIMINARIES

A Construction and maintenance of site office


to project manager’s details.

B Site location clause

C Firm price contract clause

D Performance bond of 7% of contract sum and


bid Bond of 2% of tender sum clause

E Adherence to Government Legislation and


Regulations

F Insurance company Fees

G Samples and Materials Generally clause and


cost of testing

H The contractor is drawn to the legal notice in


the Finance Act part 3 section 21(b) which
requires VAT payments on all contracts. The
tenderer to include in their prices VAT of
16% in all rates.
I
Allow for electricity and water on site for use
J
Allow for erection of sign post to PM
approval
K
Allow for relocation of existing sewer line
and water reticulation

Total Carried to Collection


Allow a provisional sum Ksh Two Hundred
Thousands for the Project Management stationery

Allow a provisional sum Ksh One Million Five


Hundred Thousands for the Project Management
costs

Allow sum for the contractor’s administrative cost


for all the preliminaries

Allow attendance on mechanical and electrical


sub-contractors

Total to collection below

Collection from page B1………………………

From above …………………………………

UNIT AMOUNT
DESCRIPTION QTY UNIT RATE (Kshs)
ITEM (Kshs)
A
200,000

B
1,500,000

Total Preliminaries Carried to Main Summary


UNI AMOUN
DESCRIPTI QTY UNIT T T
ITEM ON RAT (Kshs)
E
(Kshs)

1.0 SUBSTRUCTURE

A Site clearance

Clear site off grass, shrubs, and small trees and 1419 M2
grub up roots and burn debris.
1278.2
B M2
TOPSOIL EXCAVATION

Excavate over site to remove vegetable top soil


average 200mm deep and cart away.
1796.53 M
3

C UNDER GROUND EXCAVATION

Excavations including maintaining and supporting


sides of excavation from fallen soil, mud or sub-
surface water by baling, pumping or otherwise.
D SETTING OF THE COLUMN BASE 9.288 M3

Excavate column base commencing

from basement level and not

exceeding 4.5

E REINFORCEMENT FOR THE COLUMN BASE 36.8 LM

Use 20mm diameter high yield bars at 110mm


center with tying wires and space blocks

F FORMWORK FOR THE COLUMN 179. SM

Provide soft sawn timber for formwork nailed 2


well

G CONCRETE FOR COLUMN BASE

Vibrated reinforcement concrete 1:2:4 well mixed


and compacted.
CONCRETE FOR COLUMN 17.92
H M2
Provide concrete in 1:2:4 and well compacted.

COMPACTION OF THE BASE 630.3


I M2.
Compact the base of the basement to ensure it 6
gains maximum strength with a roller

FOUNDATION SLAB 630.3


J M2
6
Hardcore
Ja
Provide 300mm thick handpicked hard core from
the approved quarry well laid and compacted.

Murram blinding
Jb 630.3
50mm thick stored dust or sand blinding on
hardcore to receive the slab 6
M2

Treatment
Jc
Insecticide treatment to blinded surface
ITEM

Termite nest
Jd
Remove and cutaway all termite nests
ITEM

Lime 630.3

Je Provide 200mm thick well compacted to attin 6 M2


strength 655 (32/200)from column

630.3
D.P.C
Jf Provide 200mm thick asphalt matic tanking to all 6
sides of the slab
M2
B.R.C Mesh 630.3
Jg Provide B.R.C mesh size A 142 M2
6

Concrete for slab 630.3


Jh M2
150mm thick reinforced concrete slab in 1:2:4 20mm 6
aggregate

Bitumen 630.3
K M2
Provide bitumen for tanking on the slab 50mm thick 6
on layers

Formwork for the slab 102.4


L M2
Provide soft sawn timber for formwork of the 8
basement floor slab

Planking and strutting


M ITEM

Allow for planking and strutting to the side of the


walls to act as the retaining wall to prevent the
collapse of the side

Dewatering
N
Protect the excavation from water by bailing and
pumping ITEM

Basement wailing
O 268.3 SM
200mmide and thick natural stoned wailing bedded
and joined in cement sand motor 1;4 forming cavity
in holl walls 50mm wide and including stainless
steel twisted wall ties.
p Concrete walling 268.3
300mm thick vertical concrete work reinforced
SM

Total Carried to collection


UNIT AMOUNT
DESCRIPTION QTY UNIT RATE (Kshs)
ITEM (Kshs)
Imported filling

300mm thick hardcore filling to make up levels


handpacked and well compacted in 150mm thick
layers to Structural Engineer's approval.
1364 SM
50mm Thick murram blinding spread over
hardcore bed and ram over while moist for proper
consolidation.
1364 SM
Anti-termite treatment

Chemical anti- termite treatment as "Gladiator


TC" or other equal and approved termicide
sprayed over surfaces of hardcore bed and walls.
1364 SM
Damp proof membrane.

500 Gauge polythene sheeting damp proof


membrane spread over hardcore bed and walls
with 300mm side laps and end laps (measured net
with no allowance for overlaps).
1364 SM
Concrete Works
Mass concrete class 15/20 aggregate as described
in:-
50mm thick blinding under strip footing

Ditto under column bases

Reinforced concrete class 20/20 aggregate as 178 SM


described in:- 282 SM

Strip footing 40 CM

Column bases and columns 111 CM

150mm Thick ground floor slab SM


1364

Total Carried to collection


UNIT AMOUNT
DESCRIPTION QTY UNIT RATE (Kshs)
ITEM (Kshs)

Reinforcement

B.R.C Mesh Reinforcement


A Fabric Mesh reinforcement to Ref. A142 laid in
slab with minimum 300mm side and end laps
(measured net with no allowance for overlaps) 1364 SM

High tensile square twisted bar reinforcement to


B.S 4461 supplied, cut, bent and fixed;
B
8mm diameter bars 599 KG
C
10mm Ditto 1834 KG
D
12mm ditto 4211 KG
E
16mm ditto 59 KG
F
20mm ditto 1064 KG
G
25mm ditto 1973 KG

Formwork

H Sawn formwork as described to:-

Edges of floor slab 75- 150mm girth 245 SM


I
Sides of column bases 300-450mm girth. 214 SM
J
Sides of strip footing 137 SM
K
Sides of vertical column 224 SM

Total Carried to collection


UNIT AMOUNT
DESCRIPTION QTY UNIT RATE (Kshs)
ITEM (Kshs)

Foundation Walling

Approved natural stone built in courses of


cement/sand (1:3) mortar mix as described in:-
A 200mm Thick natural stone walling reinforced at
each alternate course with and including 24gauge
25mm galvanized mild steel hoop iron. 954 SM

B Damp Proof Course.

150mm Wide 3 ply bituminous felt or equally


approved damp proof course laid under walls with
and including 20mm thick cement/sand (1:3) 720 LM
C setting screed.

Plinth finishes

Cement/sand (1:3) render as described to:-


D
20mm Thick render to plinths. 132 SM

Prepare and apply three coats of black bituminous


paint on rendered walls externally 132 SM

Paving slabs
Excavations

Excavate vegetation soil average 150mm deep and 270 SM


cart away

Filling in aprons

150mm thick hardcore filling compacted in layers. 270 SM

Total Carried to collection


ITEM DESCRIPTION QTY UNIT UNIT AMOUNT
RATE (Kshs)
(Kshs)

ELEMENT NO.2: SUPERSTRUCTURE

Walls
Approved natural stone walling, fine chisel dressed one
side the other butchered to receive plaster or render
(m/s) bedding and jointing in cement sand mortar (1:4)
A
External 150mm walling reinforced at each alternate
course with and including 24gauge 25mm galvanized 2107 SM
mild steel hoop iron.
B
Extra over for fair face and neat horizontal and vertical 2107 SM
joints all brushed neat to approval.

Approved concrete blocks walling bedded and jointed


in cement sand mortar reinforced with hoop iron at
C alternate course
4128 SM
D Walls 150mm
1750 SM
E
Walls 100mm

150mm thick precast concrete lourve block walling in 88 SM


F
cement sand 1:4 mortar joining

Damp Proof Course


BS 743 type A bitumen hessian base 150mm laps. No
allowance made for laps
150mm wide bedded in cement sand mortar (1:3) 882 LM
Total Carried to Collection
UNIT AMOUNT
DESCRIPTION QTY UNI RATE (Kshs)
ITEM T (Kshs)

Insitu vibrated concrete mix class 20/20 in:

A Beams 280 CM

B Ring beams 70 CM

C Columns 107 CM

D 150mm suspended slab 3250 SM

E Staircase threads and risers and waist 11 CM


ramp

Reinforcement
High yield square twisted bar reinforcement to BS
4461; including bends, hooks, tying wire, distance
blocks and spacers.
F
8mm diameter bars
G 7821 KG
10mm diameter bars
H 37975 KG
12mm diameter bars
I 2668 KG
16mm diameter bars
J 5299 KG
20mm diameter bars
K 14210 KG
25mm diameter bars
15219 KG
L Expansion Joint
22mm thick flexile in expansion joint
25x12mm mastic sealant 180 SM

Total Carried to collection B23


ITEM DESCRIPTION QTY UNIT UNIT AMOUNT
RATE (Kshs)
(Kshs)

Sawn formwork

A Sides and soffits of beam 2905 SM

B Sides and soffits of ring beam 650 SM

C Sides of columns 2072 SM

D Soffits of suspended slab 3250 SM

E Vertical edges of slab over 150mm but not 371 SM


exceeding 225mm high

Total Carried to Collection


ITEM DESCRIPTION QTY UNIT UNIT AMOUNT
RATE (Kshs)
(Kshs)

ROOFING
Approved concrete tiles size
400x250x25mm laid in accordance to
pertinent drawings and with manufacturers
printed instructions on and including
treated 50x25mm sawn timber batterns and
iron sheets underlay (m/s) as instructed.
A
Roof covering(concrete tiles shall be
supplied by the client)
1644 SM
B
Ridge and hip tiles 260 LM
C
Raking cutting to hips or and valleys. 154 LM

GI Sheets Underlay

D Galvanized steel corrugated iron sheets


gauge 30 with small corrugations fixed to
E timber purlins(m/s) 1644 SM

F Ridge cap 186 LM

Valley; 900mm girth twice bent to profile. 40 LM


Structural timber
G
Cypress prime grade, pressure impregnated.
H

I 75x50mm purlin 1722 LM

J 100x50mm struts and underpurlins 2646 LM

K 150X50mm rafters and ties 3929 LM

150x25mm support beam/collar plates 1489 LM

Total Carried to Collection


ITEM DESCRIPTION QTY UNIT UNIT AMOUNT
RATE (Kshs)
(Kshs)
BOARDING

Wought cypress prime grade, pressure impregnated

A 225x25mm thick fascia board 744 LM

Closed Eaves
B 50x50mm treated timber as Cypress brandering
complete Pvc ceiling including pvc cornies and
fixing accessories. 485 SM

Ceiling.
C
12mm chipboards on 75x50mm treated timber
brandering at 600mm centers including 75mm 1296 SM
cypress timber cornies as applicable.

Rain Water Goods


D
150mm half round gutter PVC gutter complete with
PVC brackets to slope 532 LM
E
100mm heavy gauge grey PVC down pipes
including all bends and connections to storm water
drains or and main line to underground tank. 200 LM
F
Excavate to slope depth not exceeding 900mm deep,
compact surface, lay 100mm golden brown PVC
pipe to underground water tank, haunch with mass
concrete to slope all to engineers approval. 957 LM
G
Inspection chambers, 750x750mm in masonry walls
on mass concrete complete with concrete covers to
20 No
H detail

Apply one coat undercoat and two finishing coats as


Crown or equivalent on general timber and ceiling 1599 SM

Total Carried to Collection


DESCRIPTION QTY UNIT UNIT AMOUNT
ITEM RATE (Kshs)
(Kshs)
Windows

Window Cills
A 275x75mm thick cill weathered throated molded to
architectural details.
Windows 336 LM

Windows made from 25x25x2mm Z sections,


25x25x2mm Tee sections, 25x2mm flat bars complete
with all necessary ironmongery to architectural detail
steel for glazing with putty lugs to two jamps, cutting
and pinning to concrete or block work, fixing to head
and sill with screws and plugging
B
Window size 1700x1200mm, W1 120 LM
C
Window size 800x1200mm, W2 32 No
D
Window size 900x1200mm, W3 4 No
E
Window size 1000x1200mm, W4 32 No
F Glass in openings to windows
4mm thick clear glass and glazing in and including
G glazing putty. 448 SM
Ditto; obscure
H 133 SM
Window boards with one labour plagged size
150x25mm 287 LM
I
Standard adjustable window curtain rods complete
with all necessary fittings to approval 120 No

J Stand window curtain in heavy duty cotton printed


material and blinder to approval by the Project 240 No
Manager
1800mm high x 1200mm width fixed in curtain rods

Total Carried to Collection


DESCRIPTION QTY UNIT UNIT AMOUNT
ITEM RATE (Kshs)
(Kshs)

Doors

Purpose made doors made from RHS 50x25x2mm


welded together complete with fan light and all the
necessary ironmongery to architectural details.
A 1600 x 2400mm double leaf doors.
4 No
B
1200 x 2400mm single leaf doors
16 No
C
900 x 900mm double leaf doors
4 No
D
Purpose made standard steel casement doors as
emergency exit 2400 x 2400mm four leaf doors 6 No

45mm thick semi solid core standard flush door faced


both sides with mahogany veneer and hardwood lipped
all round complete with 100mm heavy duty brass
hinges,150x50mm approved hardwood frame as rose
wood with fanlight and padlock lockable aldrop
externally and pad bolt internally with three coats of 1st
grade varnish as Crown or equivalent with all other
E necessary ironmongery;

F 900x2400mm doors 108 No

G 1100x2100 double swing action hinges 8 No

H 900x1800mm high without fanlight 64 No

900x2100mm high without fanlight 64 No


I
Clear Glass
4mm clear glass and glazing to metal with putty in
panels not exceeding 0.1 square metres 67 SM

Supply and fix 38mm door stoppers 124 No

Total Carried to Collection


ITEM DESCRIPTION QTY UNIT UNIT AMOUNT
RATE (Kshs)
(Kshs)
Floor Finishes
Screed, cement and sand (1:4) with approved
integral dust proofing additive wood float
finish to
A receive floor tiles (m/s)
30mm thick. 2764 SM
Approved non-slip ceramic floor tiles to
regular
pattern, bedding, jointing and pointing in
cement
B nil complete with grouting and finished clean
to
approval;
300x300x8mm thick, butt joints both ways to
cement sand backing screed (m/s) 2764 SM

C Ditto skirting 100mm high 1650 LM


Polished white cement based terrazzo
32mm thick cement sand screed (1:4)
including
20x4mm thick plastic terrazzo strips to
approved
pattern to receive terrazzo; 1470 SM
D
10mm terrazzo laid on screed (m/s) including 1470 SM
polishing to smooth .

E Ditto but 100mm high skirting 1120 LM


Ditto for 300mm threads 85 LM
F Ditto for 150mm risers 91 LM

G Ditto for landing 27 SM

I
Total Carried to Collection B23
DESCRIPTION QTY UNIT UNIT AMOUNT
RATE (Kshs)
(Kshs)
Wall finishes
15mm thick plaster applied internally with
cement
sand (1:4) finished smooth with white lime
using steel
A float to;
Walls internally steel troweled 11310 SM

Concrete work 1120 SM


B
Ditto coloured tyrolean rendering 75 SM
Ring beam 372 SM
C Soffits of suspended slab 3250 SM
Soffits of landings 27 SM

D Sloping soffits of staircase 40 SM


15mm thick plaster applied externally with 66 SM
cement
sand (1:3) wood float finished to;
E
Columns 78 SM
F Beams 360 SM
G Approved 250x200x6mm thick coloured
ceramic wall
tiles glazed to regular pattern, bedding, jointing
and
pointing in cement nil, grouting joints with
matching
H cement butt joints both ways to cement sand
backing
(m/s) 672 SM
I

J
Total Carried to Collection
ITE DESCRIPTION QTY UNIT UNI AMOUN
M T
T (Kshs)
RAT
E
(Kshs)
Underground Water Tank
A Supply materials, construct, and test
and commission 150M3 underground
water tank as described all to approval
of structural engineer;
Class 25/15 concrete.
200mm thick base slab, vertical wall
and top slab.
Reinforcement in 8, 10 and 12mm
diameter bars at between 150to 200
centers on base slab, vertical wall and
to slab. All these complete with 1 ITEM
5x2x2m deep reinforced concrete
settlement tank and 2x1x1m deep
R.C screen with galvanized screen 2No.

B
Balustrades
37x3mm CHS welded 1000mm high,
bottom fish tailed and set in
concrete,50x3mm CHS hand rail
welded to balusters and 4No. R16 bars
as horizontal members at 200 centers, 305 LM

all with one coat red oxide primer


before fixing and three coats of 1st
grade gloss paint all as per architectural
details.

Total Carried to Collection


ITEM DESCRIPTI QTY UNIT UNI AMOUN
ON T T
RAT (Kshs)
E
(Kshs)
FIXTURES AND FITTINGS
(All Provisional)
Washroom worktops

A Insitu vibrated reinforced concrete mix


(1:2:4) grade 20/20 in 50mm thick
worktop including Y8 reinforcement at 156 SM
100 c/c, and all the necessary formworks.
Allow for forming openings for lab sinks 128 No
B
Walling
100mm thick concrete block, bedded in
cement sand mortar mix (1:3) complete
with 12mm plaster finished smooth with 109 SM
lime on both sides of wall
C
10mm Terrazzo finish on worktops and sides
including 20x4mm pvc terrazzo strips to
approved colour including polishing smooth 156 SM
on 20mm thick cement sand(1:4) backing.
D
Approved coloured ceramic tiles glazed to
regular pattern, bedding and pointing in
E cement grouting joints with matching
cement 218 SM
250x200x6mm wall tiles butt joints both
ways to cement sand backing m/s
F

Total Carried to Collection


complete with all necessary framing and
25x25x2mm hardwood lipping with three
coats of
gloss paint to approval. Drawing No.04 208 No

Student wardrobes all as described drawing


No.01
Complete with three coats of 1st grade gloss 208 No.
paint
Fabricate student study chairs as
described in
drawing 05. All with one coat primer
gloss paint
and two finishing 1st grade gloss paint to
approval.
420 No
Ditto but 4 chairs fixed together with
50x25x2mm
RHS 150 Sets

Total Carried to Collection


ITEM DESCRIPTION QTY UNIT UNIT AMOUN
RAT T
(Kshs)
E
(Kshs)

Wash rooms
Insitu vibrated reinforced concrete mix
class 20/20 in;
50mm thick worktop including Y8
A
reinforcement at 100mm centres
48 SM
including all necessary formworks
B Allow for forming openings
1 Item
Walling
C
100mm thick concrete block, bedded in
cement sand mortar mix (1:3) complete
with 12mm plaster finished smooth with
320 LM
lime on both sides of wall.
D
10mm terrazzo finish on worktops and
sides including 20x4mm PVC strips to
approved colour and polishing smooth
on 15mm thick cement sand backing 60 SM
E
Relocate temporary kitchen and store.
Build 4m x4m kitchen with 3No.
firewood kitchen hoods and 4mx4m
store. All in masonry and concrete tiles
on timber roof, floor screed finish,
painted walls, 2 No. 1200x2100mm steel
casement doors, 2No. 1200x1200mm 1 Item
steel casement window including all
necessary works
Total Carried to Collection
ITE DESCRIPTION QTY UNIT UNI AMOUN
M T T
(Kshs)
RAT
E
(Kshs)

A Supply and fix 4 No. 42 inch


Television as
SONY or equivalent all connected to
DSTV
with a one year premium subscription
from the
B date of handover of the
project all including the steel TV cages 4 Sets

Supply and fix cloth line from CHS


C 50mmx3mm spaced
at 2m centers with galvanized cloth line 75 LM

Catalina chairs from 25x25x2mm steel


frame
D with heavy 50mm cushion covered with
heavy
duty recsin 50 No
E
Cantilever stainless steel frame chairs
with
heavy duty cushion to project
managers
F approval 50 No

Hostels officer’s boardroom tables from


veneer
block board with hardwood lipping
round with
all necessary ironmongery for 1 set
50capacity
boardroom

Supply and fix aluminum framework and


6mm
plain glass on office partitions at the
administration block 2nd floor including
doors
with closers and all necessary SM
ironmongery to Project Managers 200
approval

Total Carried to Collection


ITE DESCRIPTION QTY UNIT UNI AMOUN
M T T
(Kshs)
RAT
E
(Kshs)
PAINTING AND DECORATION

On metal work.
Prepare and apply one approved
primer, one
undercoat and two finishing coats as
Crown
SOLO or other approved equivalent
A supper
gloss paint.
564 SM
General window and door surfaces

Prepare and apply three coats of 1st


B Grade
emulsion paint as Crown including
filling
with approved wall care to;
C 1131 SM
0
Plastered walls, beams and column
surfaces
3250 SM
D
Plastered slab soffits
36 SM
Suspended landings
27 SM
Stair waist internally
936 SM
E Plastered beams and columns
externally
F

Total Carried to Collection

3.3 SITE ORGANISATION & ADMINISTRATION


Contract Programs

Operation Operation Duration


No. Of Days
1 Hoarding 3
2 Site clearance 4
3 Removal of vegetable soil 3
4 Site Investigation 1
5 Setting Out of the Building 1
6 Excavation of foundation trenches and bases 4
7 Foundation treatment 1
8 Plunking and Strutting 1
9 Blinding 1

10 Reinforcement of column bases and foundation trenches 2


11 Conc to foundation & column bases 1
12 200mm natural stone foundations wall 2
13 Formwork to sides of the column 1
14 Conc to columns 1
15 Backfilling 1
16 Hardcore filling 3
17 Marram Blinding 2
18 Ant termite 1
19 DPM laying 1
20 Steel fabric laying 1
21 Formwork to edges of the slabs 1
22 Casting to floor slab 3
23 Casting to column kickers 2
24 Building of brick wall 6
25 Formworks to soffits of beams and slabs and sides of 10
beams
26 Reinforcement to beams and slabs 14
27 Concrete to beams and slabs 3
28 Roofing 4
29 Doors and Windows Fixing 12
30 32 Glazing of Windows and Doors 10 3
33 Painting and Decoration 5

Wall Finishes
31 Floor Finishes 5
3.4 REFERENCE

 The codes which were adopted for the design work include.
 The BS8110 for concrete work
 The standard method of measurement (SMM)
 Research was also included
 The price quotation used in the BQ was obtained from standard prices of
building materials.
?.5
€r

CquL"LtL ATi oN r:trrPdT


Ccu'o

4DO r.rnr1 I

Pn*".Jut'e-g
r\ r,Le*V= ie lLr-
)
hL.*"'G"" r* ar Yr,.n ttl- J.I", irr WilrCmarnmaJ
l
t:.I.
r,I/.._---.. ryri vr(- ft"- r* ,'. f.IIc Lr.'Ls
t-LoTP" -"

t\ f L^uoc-,k.iq,1.c: S
)
L-C t\ 5c t'\ \

\
-F
,/,

Ctotnrn

604 rnr\1

f-leirr

It

)
\*

t.r
*x

t
B.

\ a

ntS
(-
r

E
a

85

D'4x L\( *t

tc \Goooo 5G

1 (* ?s rnrn

Lr,

,.\ a
E

hbu rnrn .

40urnn^

.lf a-

( kN \r\ft
"
i., '
I
EF

=to

,O X ;\
' r-)

qbl€ ?.\

\.4 x e,

cQt Lt--l

8.4'

x+. :33("
'.5"1c. "t?4s
r- ku lns
Prp C+\r--C-ul iA'J".i?rl-i 1 . Du-i-rur
itts 3.-toer-..f 6,rr{e',nr) L.^-l',.-"* wvrnre,nt-5,
J
:7ffif D.\\L\
z t-).ll X?sXs = l'3-+s ta*rin'r

A+ en r+ Eup pn's\ ullirn-le= d,eo. #,y.ca


I
f\,i]S F\
l

(
r\D . +5 x tt+,q T ) : BS [,a e, *s.-l
\"* 8qe,,u*L fi*.,hrio.\
t
rr\-\$rnc.\<, .BLe-r
A{c:r&
o,6 rl

C\ s,,"rse 5:S A.es"-, rne So rnrfl .\i*.r.ujo- L*r' *


Bo: Si ze- = krnnnfl
Ct.tlrS C,
<"ts 1 1.2 Nlu. **) fYlax:illilrf1 .R\r7€ aq d?titreotre"< 4;5**
6ctt$ e
JJu"
B3 E^r* c.rJ\iftsns €e s,re r€. 6z*tel =l$ftnnm

ASu;.r*re ffiinirvr.rrf\ C'rrr,."r .\- {y\^on qle',r, \


.z z{Dn1fi\
Fp.rr*lnre - Jo=,il^
ll
C \c'l-rrs€ J *(':'Goi - l+e *ED) = 5+orntur
B'il j3 fl.=e"rrne. e5 r\arm Jio*rrL.. L.. * Err\ r
I
rvrcr \rt Skc i L.l t- ti,z r,- p t. 5 $n rY\

EXVo*rv€ c5r"a*li.Ls^ .Ser€re z fipmffl


Et. {Esi:;'}-o.xo Z i\ ?'?omffl
a

L.C.ri C)

o -&-

3z+: rt"

,5,33 D

o5-l,553 xtO

f
jl
I

e5 fr\

ff\tfl

?xru

t/+O < tss{nrYr

B&r, CI6x tD

[-**

= 0"DB

D-S+ D"es- V

41 *,*
*Z

D '5 ,t531 e1 "s mrn

= Q5 +tB =&tryfl

D.ls ( D"s+ to rei

5* t
O o1S
,c ?
- e. ts€ o x4CIoXSA
b'rs x to

5*I ED

5 mrn
z

:o
I

ztboxf=

o
( n

=?y
3
I'

?x4oo
xtt

ho. Y ?

A h 4 Eoru
i
5a

e
R.EN c- ffi{Dtr15 CIdl-RrT
CI,OU L r^),iJ

[ocA.: tocx lc-e"a' ,


= u"6)'
b'*: \^ ^thr-.o)cbOn

$ni..innti,n A s {?arf,re)
t;
* n,f-} LIX h .!a--

teo
e-
b. bk vltr\cX 6rrc
rr) o
t aB? r\^rrP
,"{kf .\er.Lre t_..t\ te *..e.*\Cr.
l}

C1.,,* *Ti.,rre'..
s € reincDrc€hne '. {
I
3.lD:5.3,
L_ .Y------
o0 :

Loo
: D isxaot xt u$D
toe
G on rrn rnQ
{
l\^i-:- \= or-rileJ \n.-Ue si.rt slr" I
.--\^,,s.r....<
J-- r
Cto^rs e (a o r rlotl
B'la"^ t n AI "J
\rGer isr Strp eo. \s

t +

lrs.lot a crDt\fY1fil
(

E
z
o,lsx
L> R*
\

'= 4a krt

1y o
J,l.'h -=$

I ,cx
Drt>Et r( t , ?,f,s :

= o.

1.=q. 3

IV\i nimunn ll" 7ton''.

= tsorrYln

g
I

L=

?= D
= li

o.

5 xlo (
0 ..lS X 4ba Xl1f,-)

rl I
=>

L
it
(1ce
--\Jr
'a St

= o.\-s D .l.s

\:
A ?'aa=r.e- =

i'' -

3"b

I
'^:1 i

ct= \ * -s'n
\ -rs rn
\<.q

I \

I
f)'-
o< -\ '< f :1 \znr I

I
L-*,\r".\ fr> rr,, C>, -S" Y Ql", ,* ..-*l) t c
a .\i
I

.,,

€o,', \ !J.,..LJ \,n L-,rl-.L.tr'. Q-, L \,/.< '1r Y' \ *


';
a 1

rnr n^r,<-r,,f o1\ r€ -.., \g\ , ^.\


_)

3
5 "25

$,.l , ?5'1
,5i=5

.{
I

o_. .l

c{a a
h.
t\o t

i>c'\

t<- C;,ns'i

r2
t, ,/- I rn-

L,fr ,

t
aLJ

= \\ 3, zrz kr\
5

.5

Vr-C"<;ye."c .Yl.a s\i c \-: DU


_)

h \.

u1- \ "5

,3X tB

e, s3l

e.
S-02

S-02
S-02

North Elevation North Elevation North Elevation


40.300 40.350
40.300 31.816 8.534
30.300 0.300 0.300 0.300
0.300 4.700 0.300 4.700 0.300 4.700 0.300 4.700 0.300 1.057 0.7321.015 0.6380.9210.545
0.807 0.300 2.660 0.300 3.229 0.300 3.211 0.300 4.700 0.300 0.300 4.700 0.300 4.700 0.300 5.000 4.700 0.300 4.700 0.300 2.660 0.300 3.229 0.300 0.027 8.534
30.300 0.610 0.610 0.610 0.610 0.662
1.649 2.000 2.993 2.000 2.906 2.000 3.519 2.000 1.549 0.681 2.000 0.978 2.000 1.235 3.000 5.435 1.779 2.000 2.541 2.000 3.722 2.000 2.814 2.000 2.046 1.500 1.500 1.102 2.000 4.150 8.534
0.300 4.700 0.300 4.700 0.300 4.700 0.300 4.700 0.300 4.700 0.300 4.700 0.300

0.150
0.150
0.150

0.300
0.150
0.150

0.300

0.300
0.300
0.300
0.300

0.350
1.805
BOYS SHOP WINE AND SPIRIT
GIRLS SHOP

2.000

4.644
4.644
4.644
GIM HOUSE rental

4.695
TOYS SHOP rental

4.494
4.700

4.695
rental

6.648

0.300 0.049
0.002
0.002
0.002
0.049
0.049
2.993
0.300
0.300

0.300

0.300
0.300
RENTAL

0.586

1.508
SECURITY REFRESHMENT
CHECK SHOP

15.000
LADIES

2.000

2.000
4.705
RENTAL

2.000
S-01 BOTIQUE S-01 conference hall

4.700

1
2

3
4
5
6
7

4.705

4.705
4.705
4.520
15 x 0 .18 7 = 2 .80 0

S-01 S-01 S-01

1
2

3
4

5
6
7

17.601
15 x 0 .18 7 = 2 .8 00

1.197
15
14

12
11
10
2.906

13

2.993

20.300
15
14

13
12

10

0.300
11

0.300
SHOPING AREA

0.300

0.300

Elevation0.300
0.300
0.400
East Elevation
BOOKSHOP

1.681
ELECTRONICS

West Elevation
RENTAL
West Elevation

Elevation
2.000

2.000
MEN'S

4.700
EYE CLINIC

4.700
BOTIQUE

4.600

2.000
4.700
27.300

27.300

East
27.000
27.000
27.300

27.300

27.300

27.300
27.000

West
27.000

1.466

6.952
2.117

7.301
8

0.300

2.920
0.300
0.300

2.000

0.300
1.692
2.301
7 9

KINYOZI
6 10

PHARMACY

0.700
5 11

15 x 0 .1 87 = 2 .80 0

2.301
4 12

CAFETERIA
3 13

0.300
2 14
1 15

2.000 0.750

0.008
0.300
0.300

5.350
4.850
4.850

0.300
ENTRY

1.300
0.300
EXIT CONTROL

2.099

2.448

2.099
0.300
9 x 0.2 53 = 2.2 74

3.525
0.300

0.300
0.875
RESTAURANT

1.500
SUPERMARKET

9.391

9.399
RAMP

9.699
STORE

7.230
TO

6.700
BASEMENT PARKING
7.000
7.000

2.000
2.087
7.000
6.700
school of business

6.700
1.500

2.874
0.150
0.150
0.150

0.300

1.038
0.300 4.700 0.679 2.000 4.395 2.000 1.227 2.631 2.000 0.419 2.000 2.650 1.265 2.000 3.385 2.000 3.389 2.000 1.261
0.150

0.150
0.150
0.150

0.300
5.300 4.700 0.300 4.700 0.300 4.700 0.300 1.750 1.500 1.450 1.700 0.300 2.700 0.300 0.300 4.700 0.300 9.700 0.300 4.700 0.300 4.700 0.300 14.700 0.300

0.300

0.300
0.300 4.700 10.300 9.700 15.300 0.300
0.300 4.700 0.300 4.700 0.300 4.700 0.300 4.700 0.300 0.150 4.550 0.300 1.700 0.300 2.700 0.300 3.179 0.610 1.211 1.350 2.000 2.475 2.000 1.875 0.300 0.650 4.000 0.543 4.507 1.155 1.5 00 0.555 2.000 0.990 1.500 4.139 2.000 1.461 0.050
5.300 4.700 0.300 4.700 0.300 4.700 0.300 4.700 0.300 1.700 0.300 2.700 0.300 40.300
0.300 4.700 0.300 9.700 0.300 9.700 0.300 14.700 0.300 0.050
30.300 5.000 0.300 9.700 0.300 9.700 15.300 0.050

South Elevation 40.350

S-02
South Elevation
South Elevation
S-02

GROUND DETAILS

S-02
0. Ground Floor 1:525.31 roof pitch 300
-1. Story 1:516.06 1. Story 1:508.60 makepermanent vent above
all openings along the
external wall
all pipe works to be atleast
450mm below grround level
formation
all the construction to comply
to the local authority bylaws
and regulations

LAYOUT ID
Ground floor plan
first, second and third floor plan
3 building across section s-o1
and s-02
East Elevation 1:279.00 North Elevation 1:291.57 roof plan
4 elevations

PERSONAL DETAILS
STUDENT NAME:
WANJALA VINCENT WEKEZA
SUPERVISOR:
HARON OUMA

SERIES: NOV/DEC 2021


INDEX: 7311011145
PAPER CODE: 2707/305A
CENTRE NAME:
MAWEGO TECHNICAL TRAINING
INSTITUTE
PROJECT NAME:
PROPOSED MODERN SHOPPING
MALL AT LIDA

West Elevation 1:252.20


South Elevation 1:266.06

You might also like