Project Name: Proposed 3 Bedroom Residential Date Starts: September 30, 2019 Date Finish: March 9, 2020
ACTIVIT DESCRIPTION START END % DURATION WEEK 1
Y DONE (DAYS)
30 01 02 03 04 05 06
M T W T F S S
A Site Setting and Clearing 0 3 5
B Layout and Fabrication of Steel Rebar 0 3 3
C Excavation ,Demolition and Earthworks 0 2 3
D Installation of Footing Rebar and Framework 0 3 4
E Concrete Pouring for Footing 0 3 7
F Installation of Tie Beam Rebar and Framework 5 3 5
G Installation of Formwork for Tie Beam 5 3 5
H Concrete Pouring for Tie Beam 5 3 7
I Installation of Column Rebar and Framework 0 3 4
J Installation of Formwork for Column 0 4 8
K Concrete Pouring for Column 0 5 7
L Installation of Roof Beam Rebar and Framework 0 3 5
M Installation of Formwork for Roof Beam 0 4 7
N Concrete Pouring for Roof Beam 8 3 7
O Removing for Formworks for Column and Tie Beam 0 4 15
P Backfill and Compaction 0 3 5
Q Laying of CHB 1 4 12
R Finishing of CHB Joints 1 3 4
S Plumbing Works and Installation of Septic Tank 12 5 9
T Removing of Formworks form for Roof Beam 12 4 7
U Fabrication of Trusses 0 3 6
V Installation of Scaffolding 0 3 6
W Installation of Trusses 0 3 5
X Installation of Gutter and Roofing and Ceiling Joist 0 3 8
Y Electrical Works 7 2 5
Z Installation of Doors and Windows 28 2 6
A’ Plastering 7 5 9
B’ Installation of Floor Slab Rebar and Framework 0 5 10
C’ Concrete Pouring for Floor Slab 0 3 7
D’ Installation of Ceiling 7 2 4
E’ Installation of Water Closet, Lavatory, Faucet, and Waterline 0 3 8
F’ Painting 7 5 9
G’ Tiles Work 0 6 30
H’ Cleaning 0 5 10