PRODUCTION REPORT

DATE : 14/01/2024
TARGET FOR THE MONTH OF JAN 2024 405000 TE
REQUIRED TRIP PER DAY 160 TRIP
PRODUCTION FOR THE MONTH
1ST PRO (Te) 2ND PRO (Te) MAINTENACE Shift (Te) DAY (Te) MONTH (Te) LEVEL FILL %
3780 2520 4140 10440 149130 I 81.53%
Till Date Total
64890 45540 38700
CUMULATIVE PRODUCTION 2023-24 TILL DATE
TARGET FOR THE FY 2023-24 4400000 TE
TOTAL ROM TILL DATE 2870910 TE
FULFILLMENT (%) 85