Pathsattya,
As per 2024.January.17 #57 weekly coordination meeting, PVR team Mr. Chea Srun has mentioned that
“From start work until now I wait already 1 month”. To clarify this ART would like to mention the actual
submission and request for inspection by PVR as below:
3. Site inspection
To speed up the site installation ART has agreed with PVR to:
Inspected the setting out line of the partition wall and stiffener in 2024.January.06(12days
ago) (first inspection for location that not impacted to defect works that not yet finish by
PVR) and 2024.January.16 (second inspection for MEP room) (see attached WIR.ARC.001.C)
On 2023.January.12(6days ago), ART has refused PVR WIR.ARC.002.A inspection of
stiffener and curb rebar and concrete work due to unclear MOS of door installation from
PVR refer to SI.039 issued by ART in 2024.January.08.
4. Matter to discuss
PVR has officially refused to submit MOS door installation in #56 weekly coordination
meeting on 2024.January.10 and ART has clearly replied to “PVR to reply on SI.039 and ART
will seek for client design constancy assistance for the matter”
PVR sent replied to SI.039 on 2024.January.15 (3days ago) that “Method for installation of
door/window and filling the gap between tie beam/lintel/stiffener and door/window
frame is not PVR's scope”.
ART has sought for client’s design consultancy, got confirmed, and replied to PVR “The door
and window supplier team will be responsible for the installation of their frame to
concrete stiffener and lintel as long as all the openings are correct as per the approved FC
drawing and schedule. In addition to this, PVR can install stiffener and lintel based on the
approved shop drawing” on 2024.January.18”.
5. Conclusion