HERITAGE INFRASPACE INDIA LTD

DAILY PROGRESS REPORT FOR DIAPHRAGM WALL & PILLING


Division : SOUTH DIVISION Date of Report: 22.01.2024
Name of the Project: BYPN DEPOT PHASE 2A Date of Starting Work as per Work Order

Place: BANGALORE Actual Date of Starting Work 25.10.2023

Date of Completion the Work as per Work Order

Name of the Client: J KUMAR-AICIPL JV Expected Date of Completion

DETAILS OF DIAPHRAGM WALL PANELS Hindrance if any


Sr. Reasons for Work
Date Thickness Previous Today Total Remarks
No. Length Depth in Scope in Balance in Hampered Reasons for
Number Type /Width in Shape Completed in Completed in Completed in NIL Progress
in RM RM Nos Nos.
mm Nos. Nos. Nos.

Dw-78 Grabbing Completed, Cage &


1 21.01.2024 Dw-78 0 1000 Regular 5.50 20.00 46.00 38 1 39 7 Stop-end Lowerd & Concrete
Completed.

DETAILS OF GUIDE WALL Hindrance if any


Sr. Reasons for Work
Date Previous Today Total Remarks
No. Thickness/ Width in Balance in Hampered Reasons for
Type Length in RM Scope in RM Completed in Completed in Completed in
mm RM NIL Progress
RM RM RM

2 21.01.2024 - 1050 0 248.495 228 0 228 20.495

DETAILS OF PILE Hindrance if any


Sr. Reasons for Work
Date Previous Today Total Remarks
No. DIA in Scope in Balance in Hampered Reasons for
Number Location Type Depth in RM Completed in Completed in Completed in NIL Progress
mm Nos Nos.
Nos. Nos. Nos.

3 21.01.2024 0 EDS-2 800mm ROUTINE 0.00 25.4 80 44 0 44 36

DETAILS OF ANCHOR
Sr. Hindrance/Work
Date Remarks
No DIA in Fixed Free Previous Today Total Hampered
Number Location LVL. Scope Balance
mm Length Length Completed Completed Completed

DW-17 L-01/03 Anchor Grouting


4 21.01.2024 1 SBL-02 200MM 1 12 15 600 6 1 7 593
Completed.

NOTE:
A. Resources available at Site like D Wall Rig B-200/ Pilling Rig, Crane 100T, Crane75T Crane40T, JCB, Compressor, DG, Anchor Rig (C6) etc.
B. Requirement of Manpower:
C. Manpower: Steel fabrication Manpower 30 Nos. Concrete Manpower 22 Nos & Anchor works Man Power 11 Nos. Total Manpower 51 Nos. Skilled 30 Nos & 21 Nos Unskilled.

Foreman Engineer Site In-charge Project Manager