PLASTER

PAS.BATA
0.30 CORAN

TULANGAN
0.25
TANAH URUG
0.15

CORAN 0.18 X PANJANG PARIT ( 32.9 ) = 5.92 x Rp. 150.000 = Rp. 888.000
BATA 0.60 X PANJANG PARIT ( 32.9 ) = 19.74 X Rp. 65.000 = Rp 1.154.000
TANAH URUG 0.25 X PANJANG PARIT ( 32.9 ) = 8.225 X Rp. 50.000 = Rp. 411.000
GALIAN Rp. 12.750.000
SAFETY TANK
TOTAL Rp 15.250.000 3.20 M X 1.70 M = 5.44 M2
PENCAPAIAN KERJAAN 45 % PASANG BATA = Rp. 150.000 X 2.72 M2 = Rp. 408.000
TOTAL = Rp. 6.862.500 BONGKAR = Rp. 150.000 X 5.44 M2 = Rp. 816.000
COR LANTAI DAK = Rp. 65.000 X 5.44 M2 X 2 = Rp. 353.000
BONGKAR PASANG PIPA SAFETY TANK = Rp. 500.000
TOTAL = Rp. 2.077.000

TOTAL TAGIHAN = RP. 8.939.500