CPM Exercise

Questions
▪ Q1: Calculate CP
▪ Q2: Calculate float of activities
Answer 1
I. Start-A-B-C-D-Finish
II. Start-E-F-G-D-Finish
III. Start-E-F-G-H-Finish
IV. Start-I-J-G-D-Finish
V. Start-I-J-G-H-Finish
VI. Start-I-J-K-Finish
Answer 2

I. Start-A-B-C-D-Finish Duration 29 days


II. Start-I-J-G-H-Finish Duration 29 days
Critical Path Shortcut (Q1)
Path Durations Total
Start-A-B-C-D-Finish 16+3+7+3 29
Start-E-F-G-D-Finish 2+5+9+3 19
Start-E-F-G-H-Finish 2+5+9+10 26
Start-I-J-G-D-Finish 6+4+9+3 22
Start-I-J-G-H-Finish 6+4+9+10 29
Start-I-J-K-Finish 6+4+1 11

5
Float Calculation Shortcut (Q2)
Activity On Critical Path? Float
A Yes 0
B Yes 0
C Yes 0
D Yes 0
E No 3
F No 3
G Yes 0
H Yes 0
I Yes 0
J Yes 0
K No 18