Master Schedule (or Level 1 Schedule; Management Level Schedule; Major Milestone
Schedule; Top Management Report Schedule) is a simplest detailed project schedule that
shows and highlights major project activities and milestones on an entire project calendar,
and usually developed on the one page and used a bar chart or Gantt chart technique.
Project Summary Schedule (or Level 2 Schedule) is a high level integrated project
schedule for the entire project time frame that is used for high level internal and external
management reporting by summarizing to the management summary schedule (Master
Schedule (Level 1 Schedule). The Project Summary Schedule shows the project
milestones of engineering, procurement, construction, and start-up activities by network
logic, identifies critical path, key deliverables divided by units and system facilities
includes key critical activities and units or systems. The Project Summary Schedule is
developed, usually, as a summarization of the Level 3 Project Schedule (Project Control
Schedule).
The Project Control Level Schedule shows detail and individual work tasks and clearly
defined works by discipline or responsibility. This is a first level of detailed schedule
that a meaningful critical path management can be performed to monitor and manage the
overall project work accurately, and usually basis of a look ahead or window schedules
for the project schedule control and management.