NAME : RAKHUL D DETAILED ESTIMATE DATE:03.04.

2023
ROLL NO: 2001075
EXP.NO:01

S.NO DESCRIPTION NOS LENGTH WIDTH DEPTH or TOTAL UNIT REMARKS


3 2
(m) (m) HEIGHT QUANTITY (m /m
3 2
(m) (m /m /m) /m)
GROUNDFLOOR

1 Earthwork excavation
IN X-DIRECTION
3
Short wall 3 9.46 1.2 1.33 45.29 m 9.46
3
staircase wall 2 4.43 1.2 1.33 14.14 m 4.43
IN Y-DIRECTION
3
Long wall 3 10.52 1.2 1.33 50.37 m 10.52
3
Total Quantity 109.80 m

2 PCC For walls


IN X-DIRECTION
3
Short wall 3 9.46 1.2 0.15 5.11 m
3
staircase wall 2 4.43 1.2 0.15 1.59 m
IN Y-DIRECTION
3
Long wall 3 10.52 1.2 0.15 5.68 m
3
Total Quantity 12.38 m

3 RR masonry
STEP-1
IN X-DIRECTION
3
Short wall 3 9.36 1.1 0.15 4.63 m 9.36
3
staircase wall 2 4.33 1.1 0.15 1.43 m 4.33
IN Y-DIRECTION
3
Long wall 3 10.92 1.1 0.15 5.41 m 10.92
STEP-2
IN X-DIRECTION
3
Short wall 3 9.06 0.8 0.6 13.05 m 9.06
3
staircase wall 2 4.03 0.8 0.6 3.87 m 4.03
IN Y-DIRECTION
Long wall 3 8.66 0.8 0.6 12.47 12.12
STEP-3
IN X-DIRECTION
3
Short wall 3 8.66 0.4 0.6 6.24 m 8.66
3
staircase wall 2 3.63 0.4 0.6 1.74 m 3.63
IN Y-DIRECTION
3
Long wall 3 8.66 0.4 0.6 6.24 m 13.72
3
Total Quantity 55.07 m

4 Plinth beam
IN X-DIRECTION
3
Short wall 3 8.49 0.23 0.23 1.35 m 8.49
3
staircase wall 2 3.46 0.23 0.23 0.37 m 3.46
IN Y-DIRECTION
3
Long wall 3 14.4 0.23 0.23 2.29 m 14.4
3
Total Quantity 4.00 m

Page 1 of 14
NAME : RAKHUL D DETAILED ESTIMATE DATE:03.04.2023
ROLL NO: 2001075
EXP.NO:01

S.NO DESCRIPTION NOS LENGTH WIDTH DEPTH or TOTAL UNIT REMARKS


3 2
(m) (m) HEIGHT QUANTITY (m /m
3 2
(m) (m /m /m) /m)

Brickwork from plinth to


5 the lintel
IN X-DIRECTION
3
Short wall 3 8.49 0.23 2.57 15.06 m 8.49
3
staircase wall 2 3.46 0.23 2.57 4.09 m 3.46
IN Y-DIRECTION
3
Long wall 3 14.4 0.23 2.57 25.54 m 14.4
3
Net Quantity 44.68 m

DEDUCTIONS :
3
staircase wall opening 1 1.8 0.23 2.57 1.06 m
3
main door MD 1 1.2 0.23 2.1 0.58 m
3
door D 3 1 0.23 2.1 1.45 m
3
door D1 3 0.9 0.23 2.1 1.30 m
3
opening AO 1 1 0.23 2.1 0.48 m
3
window W 3 1.2 0.23 1.2 0.99 m
3
window W1 3 1.8 0.23 1.2 1.49 m
Net Quantity 7.36 m3
3
Total Quantity 37.32 m

6 Fixing of joineries
main door MD 1 1.2 - 2.1 2.52 m2
door D 3 1 - 2.1 6.30 m2
door D1 3 0.9 - 2.1 5.67 m2
ventilator V 2 0.6 - 0.6 0.72 m2
window W 3 1.2 - 1.2 4.32 m2
window W1 3 1.8 - 1.2 6.48 m2
TOTAL Quantity 26.01 m2

7 Lintel beam
IN X-DIRECTION
3
Short wall 3 8.49 0.23 0.15 0.88 m 8.49
3
staircase wall 2 3.46 0.23 0.15 0.24 m 3.46
IN Y-DIRECTION
3
Long wall 3 14.4 0.23 0.15 1.49 m 14.4
3
Total Quantity 2.61 m

Deduction
Staircase wall opening 1 1.8 0.23 0.15 0.06
3
NET QUANTITY 2.55 m
3
sunshade -W 3 1.66 0.6 0.075 0.22 m 1.66
3
-W1 3 2.26 0.6 0.075 0.31 m 2.26
3
0.53 m
3
TOTAL QUANTITY 3.07 m

Page 2 of 14
NAME : RAKHUL D DETAILED ESTIMATE DATE:03.04.2023
ROLL NO: 2001075
EXP.NO:01

S.NO DESCRIPTION NOS LENGTH WIDTH DEPTH or TOTAL UNIT REMARKS


3 2
(m) (m) HEIGHT QUANTITY (m /m
3 2
(m) (m /m /m) /m)
Brickwork from Lintel to
8 roof slab
IN X-DIRECTION
3
Short wall 3 8.49 0.23 1.2 7.03 m 8.49
3
staircase wall 2 3.46 0.23 1.2 1.91 m 3.46
IN Y-DIRECTION
3
Long wall 3 14.4 0.23 1.2 11.92 m 14.4

Deduction
3
Staircase wall opening 1 1.8 0.23 1.2 0.50 m
3
Ventilator 2 0.6 0.23 0.6 0.17 m
3
TOTAL QUANTITY 20.20 m

9 Partition wall
partition wall of CM(1:5)
Along x direction
1.Toilet-Bedroom 1 4.8 0.15 3.22 2.32
3
2.Pooja room-Dining 1 1.8 0.15 3.22 0.87 m
Along y direction
3
1.Toilet-Toilet 1 1.65 0.15 3.22 0.80 m
3
2.Pooja room 1 1.15 0.15 3.22 0.56 m

deductions :
3
door D1 2 0.9 0.15 2.1 0.57 m
3
TOTAL Quantity 3.97 m

10 Sand fillings
3
kitchen 1 3 3 0.3 2.70 m
3
Hall 1 4.8 4.8 0.3 6.91 m
3
pooja and dining 1 3 4.8 0.3 4.32 m
3
bed room 2 3 4.8 0.3 8.64 m
3
Toilet 2 2.325 1.65 0.3 2.30 m
3
sitout 1 4.8 1.5 0.3 2.16 m
3
stair 1 3 1.8 0.3 1.62 m
3
portico 1 4.8 3.3 0.3 4.75 m
3
net quantity 33.41 m

11 PCC flooring
3
kitchen 1 3 3 0.15 1.35 m
3
Hall 1 4.8 4.8 0.15 3.46 m
3
pooja and dining 1 3 4.8 0.15 2.16 m
3
bed room 2 3 4.8 0.15 4.32 m
3
Toilet 2 2.325 1.65 0.15 1.15 m
3
sitout 1 4.8 1.5 0.15 1.08 m
3
stair 1 3 1.8 0.15 0.81 m
3
portico 1 4.8 3.3 0.15 2.38 m
3
TOTAL Quantity 16.70 m

Page 3 of 14
NAME : RAKHUL D DETAILED ESTIMATE DATE:03.04.2023
ROLL NO: 2001075
EXP.NO:01

S.NO DESCRIPTION NOS LENGTH WIDTH DEPTH or TOTAL UNIT REMARKS


3 2
(m) (m) HEIGHT QUANTITY (m /m
3 2
(m) (m /m /m) /m)
12 Vitrified tile flooring
2
kitchen 1 3 3 - 9.00 m
2
Hall 1 4.8 4.8 - 23.04 m
2
pooja and dining 1 3 4.8 - 14.40 m
2
bed room 2 3 4.8 - 28.80 m
2
Toilet 2 2.325 1.65 - 7.67 m
2
sitout 1 4.8 1.5 - 7.20 m
2
stair 1 3 1.8 - 5.40 m
2
portico 1 4.8 3.3 - 15.84 m
2
Net quantity 111.35 m
deductions :
2
partition wall x direction 1 1.8 0.15 - 0.27 m
2
partition wall y direction 1 1.3 0.15 - 0.20 m
2
net quantity 0.47 m
2
Total quantity 110.89 m
2
13 tiles for bathroom 2 7.95 - 2.1 33.39 m 7.95
2
deductions : 2 0.9 - 2.1 3.78 m
2
Net quantity 29.61 m

3
14 RCC slab M20(1:1.5:3) 1 8.49 15.55 0.125 16.50 m
Deduction:
3
Staircase area 1 3.23 2.03 0.125 0.82 m
3
Net quantity 15.68 m
15 Ceiling plastering
2
kitchen 1 3 3 - 9.00 m
2
Hall 1 4.8 4.8 - 23.04 m
2
pooja and dining 1 3 4.8 - 14.40 m
2
bed room 2 3 4.8 - 28.80 m
2
Toilet 2 2.325 1.65 - 7.67 m
2
sitout 1 4.8 1.5 - 7.20 m
2
portico 1 4.8 3.3 - 15.84 m
2
Net quantity 105.95 m
16 Inner plastering
Along X direction
2
1. Main wall 5 7.8 - 3.42 133.38 m 7.8
2
2. Stair wall 3 3.23 - 3.42 33.14 m
Along Y direction
2
1.Side wall 2 14.4 - 3.42 98.50 m 14.4
2
2.Middle wall 2 12.6 - 3.42 86.18 m 12.6
Partition wall
Along x direction
2
1.Toilet-Bedroom 2 4.8 - 3.42 32.83 m
2
2.Pooja room-Dining 2 1.65 - 3.42 11.29 m
Along y direction
2
1.Toilet-Toilet 2 1.65 - 3.42 11.29 m
2
2.Pooja room 2 1.15 - 3.42 7.87 m
2
Opening in dining 2 0.23 - 2.1 0.97 m
2
Net quantity 415.44 m

Page 4 of 14
NAME : RAKHUL D DETAILED ESTIMATE DATE:03.04.2023
ROLL NO: 2001075
EXP.NO:01

S.NO DESCRIPTION NOS LENGTH WIDTH DEPTH or TOTAL UNIT REMARKS


3 2
(m) (m) HEIGHT QUANTITY (m /m
3 2
(m) (m /m /m) /m)

Deductions
2
main door 1 1.2 - 2.1 2.52 m
2
door D 6 1 - 2.1 12.60 m
2
door D1 6 0.9 - 2.1 11.34 m
2
window W 3 1.2 - 1.2 4.32 m
2
window W1 3 1.8 - 1.2 6.48 m
2
ventilator 2 0.6 - 0.6 0.72 m
2
Opening 2 1 - 2.1 4.20 m
2
Bathroom tiles 1 7.95 - 2.1 16.70 m
2
net quantity 58.88 m
2
Net quantity 356.56 m
17 Outer plastering
Along x direction
2
1.Long wall 1 8.49 - 4.045 34.34 m
2
2.short wall 1 3.46 - 4.045 14.00 m

Along y direction
2
1.Outer wall 2 15.55 - 4.045 125.80 m
2
Sunshade m
2
Window W1 3 2.66 0.6 - 4.79 m
2
Window W 3 1.66 0.6 - 2.99 m
2
net quantity 181.91 m
2
Deductions m
2
window W 3 1.2 - 1.2 4.32 m
2
window W1 3 1.8 - 1.2 6.48 m
2
ventilator 2 0.6 - 0.6 0.72 m
2
net quantity 11.52 m
2
Net quantity 170.39 m
18 Staircase
3
1.Waist slab 2 2.64 0.9 0.17 0.81 m
3
2.Landing 1 1 1.8 0.17 0.31 m
3
3.Brickwork for stairs 22 0.2 0.9 0.16 0.63 m
3
Net quantity 1.75 m
2
19 Hand rail 2 3 - 1 6.00 m
20 Plastering for staircase
2
1.Waist slab 2 2.64 0.9 - 4.75 m
2.Landing slab(top and
2
bottom) 2 1 1.8 - 3.60 m
2
Net quantity 8.35 m
21 Painting
2
1.Ceiling of house 105.95 m
2
2.Inner wall plastering 356.56 m
2
3.Outer wall plastering 170.39 m
2
4.Stair case painting 8.35 m
2
Net quantity 641.25 m

Page 5 of 14
NAME : RAKHUL D DETAILED ESTIMATE DATE:03.04.2023
ROLL NO: 2001075
EXP.NO:01

S.NO DESCRIPTION NOS LENGTH WIDTH DEPTH or TOTAL UNIT REMARKS


3 2
(m) (m) HEIGHT QUANTITY (m /m
3 2
(m) (m /m /m) /m)
FIRST FLOOR

Brickwork upto lintel


22 beam
IN X-DIRECTION
3
Short wall 3 8.49 0.23 2.12 12.42 m 8.49
3
staircase wall 2 3.46 0.23 2.12 3.37 m 3.46
IN Y-DIRECTION
3
Long wall 3 14.4 0.23 2.12 21.06 m 14.4
3
Net quantity 36.86 m
DEDUCTIONS :
3
staircase wall opening 1 1.8 0.23 2.12 0.88 m
3
main door MD 1 1.2 0.23 2.1 0.58 m
3
door D 3 1 0.23 2.1 1.45 m
3
door D1 3 0.9 0.23 2.1 1.30 m
3
opening AO 1 1 0.23 2.1 0.48 m
3
window W 3 1.2 0.23 1.2 0.99 m
3
window W1 3 1.8 0.23 1.2 1.49 m
Deduction
Quantity 7.18 m3
3
Total Quantity 29.68 m

23 Fixing of joineries
main door MD 1 1.2 - 2.1 2.52 m2
door D 3 1 - 2.1 6.30 m2
door D1 3 0.9 - 2.1 5.67 m2
ventilator V 2 0.6 - 0.6 0.72 m2
window W 3 1.2 - 1.2 4.32 m2
window W1 3 1.8 - 1.2 6.48 m2
TOTAL Quantity 26.01 m2

24 Lintel beam
IN X-DIRECTION
3
Short wall 3 8.49 0.23 0.15 0.88 m 8.49
3
staircase wall 2 3.46 0.23 0.15 0.24 m 3.46
IN Y-DIRECTION
3
Long wall 3 14.4 0.23 0.15 1.49 m 14.4
3
Total Quantity 2.61 m

Deduction
Staircase wall opening 1 1.8 0.23 0.15 0.06
3
NET QUANTITY 2.55 m
3
sunshade -W 3 1.66 0.6 0.075 0.22 m 1.66
3
-W1 3 2.26 0.6 0.075 0.31 m 2.26
3
Net quantity 0.53 m
3
TOTAL QUANTITY 3.07 m

Page 6 of 14
NAME : RAKHUL D DETAILED ESTIMATE DATE:03.04.2023
ROLL NO: 2001075
EXP.NO:01

S.NO DESCRIPTION NOS LENGTH WIDTH DEPTH or TOTAL UNIT REMARKS


3 2
(m) (m) HEIGHT QUANTITY (m /m
3 2
(m) (m /m /m) /m)
Brickwork from lintel to
25 roof slab
IN X-DIRECTION
3
Short wall 3 8.49 0.23 1.2 7.03 m 8.49
3
staircase wall 2 3.46 0.23 1.2 1.91 m 3.46
IN Y-DIRECTION
3
Long wall 3 14.4 0.23 1.2 11.92 m 14.4
Deduction
3
Staircase wall opening 1 1.8 0.23 1.2 0.50 m
3
Ventilator 2 0.6 0.23 0.6 0.17 m
3
TOTAL QUANTITY 20.20 m

26 partition wall
partition wall of CM(1:5)
Along x direction
3
1.Toilet-Bedroom 1 4.8 0.15 3.47 2.50 m
3
2.Pooja room-Dining 1 1.8 0.15 3.47 0.94 m
Along y direction
3
1.Toilet-Toilet 1 1.65 0.15 3.47 0.86 m
3
2.Pooja room 1 1.15 0.15 3.47 0.60 m
deductions :
3
door D1 2 0.9 0.15 2.1 0.57 m
3
TOTAL Quantity 4.33 m

27 Vitrified tile flooring


2
kitchen 1 3 3 - 9.00 m
2
Hall 1 4.8 4.8 - 23.04 m
2
pooja and dining 1 3 4.8 - 14.40 m
2
bed room 2 3 4.8 - 28.80 m
2
Toilet 2 2.325 1.65 - 7.67 m
2
stair 1 3 1.8 - 5.40 m
2
Balcony 1 4.8 4.8 - 23.04 m
2
Net quantity 111.35 m
deductions :
2
partition wall x direction 1 1.8 0.15 - 0.27 m
2
partition wall y direction 1 1.3 0.15 - 0.20 m
2
net quantity 0.47 m
2
Total quantity 110.89 m

2
28 Tiles for bathroom 2 7.95 - 2.1 33.39 m 7.95
2
deductions : 2 0.9 - 2.1 3.78 m
2
Net quantity 29.61 m

3
29 RCC slab M20(1:1.5:3) 1 8.49 15.55 0.125 16.50 m
Deduction:
3
Staircase area 1 3.23 2.03 0.125 0.82 m
3
Net quantity 15.68 m

Page 7 of 14
NAME : RAKHUL D DETAILED ESTIMATE DATE:03.04.2023
ROLL NO: 2001075
EXP.NO:01

S.NO DESCRIPTION NOS LENGTH WIDTH DEPTH or TOTAL UNIT REMARKS


3 2
(m) (m) HEIGHT QUANTITY (m /m
3 2
(m) (m /m /m) /m)
30 Ceiling plastering
2
kitchen 1 3 3 - 9.00 m
2
Hall 1 4.8 4.8 - 23.04 m
2
pooja and dining 1 3 4.8 - 14.40 m
2
bed room 2 3 4.8 - 28.80 m
2
Toilet 2 2.325 1.65 - 7.67 m
2
Balcony 1 4.8 4.8 - 23.04 m
2
Net quantity 105.95 m

31 Inner plastering
Along X direction
2
1. Main wall 5 7.8 - 3.42 133.38 m 7.8
2
2. Stair wall 3 3.23 - 3.42 33.14 m
Along Y direction
2
1.Side wall 2 14.4 - 3.42 98.50 m 14.4
2
2.Middle wall 2 12.6 - 3.42 86.18 m 12.6
Partition wall
Along x direction
2
1.Toilet-Bedroom 2 4.8 - 3.42 32.83 m
2
2.Pooja room-Dining 2 1.65 - 3.42 11.29 m
Along y direction
2
1.Toilet-Toilet 2 1.65 - 3.42 11.29 m
2
2.Pooja room 2 1.15 - 3.42 7.87 m
2
Opening in dining 2 0.23 - 2.1 0.97 m
net quantity 415.44 m2
Deductions
2
main door 1 1.2 - 2.1 2.52 m
2
door D 6 1 - 2.1 12.60 m
2
door D1 6 0.9 - 2.1 11.34 m
2
window W 3 1.2 - 1.2 4.32 m
2
window W1 3 1.8 - 1.2 6.48 m
2
ventilator 2 0.6 - 0.6 0.72 m
2
Opening 2 1 - 2.1 4.20 m
2
Bathroom tiles 1 7.95 - 2.1 16.70 m
2
net quantity 58.88 m
2
Net quantity 356.56 m

32 Outer plastering
Along x direction
2
1.Long wall 1 8.49 - 3.595 30.52 m
2
2.short wall 1 3.46 - 3.595 12.44 m

Along y direction
2
1.Outer wall 2 15.55 - 3.595 111.80 m
2
Sunshade m
2
Window W1 3 2.66 0.6 - 4.79 m
2
Window W 3 1.66 0.6 - 2.99 m
2
net quantity 162.54 m

Page 8 of 14
NAME : RAKHUL D DETAILED ESTIMATE DATE:03.04.2023
ROLL NO: 2001075
EXP.NO:01

S.NO DESCRIPTION NOS LENGTH WIDTH DEPTH or TOTAL UNIT REMARKS


3 2
(m) (m) HEIGHT QUANTITY (m /m
3 2
(m) (m /m /m) /m)
2
Deductions m
2
window W 3 1.2 - 1.2 4.32 m
2
window W1 3 1.8 - 1.2 6.48 m
2
ventilator 2 0.6 - 0.6 0.72 m
2
net quantity 11.52 m
2
net quantity 151.02 m
33 Staircase
3
1.Waist slab 2 2.64 0.9 0.17 0.81 m
3
2.Landing 1 1 1.8 0.17 0.31 m
3
3.Brickwork for stairs 22 0.2 0.9 0.16 0.63 m
3
Net quantity 1.75 m

2
34 Hand rail 2 3 - 1 6.00 m

35 Plastering for staircase


2
1.Waist slab 2 2.64 0.9 - 4.75 m
2.Landing slab(top and
2
bottom) 2 1 1.8 - 3.60 m
2
Net quantity 8.35 m

36 Painting
2
1.Ceiling of house 105.95 m
2
2.Inner wall plastering 356.56 m
2
3.Outer wall plastering 151.02 m
2
4.Stair case painting 8.35 m
2
Net quantity 621.88 m

SECOND FLOOR

Brickwork upto lintel


37 beam
IN X-DIRECTION
3
Short wall 3 8.49 0.23 2.12 12.42 m 8.49
3
staircase wall 2 3.46 0.23 2.12 3.37 m 3.46
IN Y-DIRECTION
3
Long wall 3 14.4 0.23 2.12 21.06 m 14.4
3
Net quantity 36.86 m
DEDUCTIONS :
3
staircase wall opening 1 1.8 0.23 2.12 0.88 m
3
main door MD 1 1.2 0.23 2.1 0.58 m
3
door D 3 1 0.23 2.1 1.45 m
3
door D1 3 0.9 0.23 2.1 1.30 m
3
opening AO 1 1 0.23 2.1 0.48 m
3
window W 3 1.2 0.23 1.2 0.99 m
3
window W1 3 1.8 0.23 1.2 1.49 m
Net Quantity 7.18 m3
3
Total Quantity 29.68 m

Page 9 of 14
NAME : RAKHUL D DETAILED ESTIMATE DATE:03.04.2023
ROLL NO: 2001075
EXP.NO:01

S.NO DESCRIPTION NOS LENGTH WIDTH DEPTH or TOTAL UNIT REMARKS


3 2
(m) (m) HEIGHT QUANTITY (m /m
3 2
(m) (m /m /m) /m)
38 Fixing of joineries
main door MD 1 1.2 - 2.1 2.52 m2
door D 3 1 - 2.1 6.30 m2
door D1 3 0.9 - 2.1 5.67 m2
ventilator V 2 0.6 - 0.6 0.72 m2
window W 3 1.2 - 1.2 4.32 m2
window W1 3 1.8 - 1.2 6.48 m2
TOTAL Quantity 26.01 m2

39 LINTEL BEAM
IN X-DIRECTION
3
Short wall 3 8.49 0.23 0.15 0.88 m 8.49
3
staircase wall 2 3.46 0.23 0.15 0.24 m 3.46
IN Y-DIRECTION
3
Long wall 3 14.4 0.23 0.15 1.49 m 14.4
3
Total Quantity 2.61 m
Deduction
Staircase wall opening 1 1.8 0.23 0.15 0.06
3
NET QUANTITY 2.55 m
3
sunshade -W 3 1.66 0.6 0.075 0.22 m 1.66
3
-W1 3 2.26 0.6 0.075 0.31 m 2.26
3
Net quantity 0.53 m
3
TOTAL QUANTITY 3.07 m

Brickwork from lintel to


40 roof slab
IN X-DIRECTION
3
Short wall 3 8.49 0.23 1.2 7.03 m 8.49
3
staircase wall 2 3.46 0.23 1.2 1.91 m 3.46
IN Y-DIRECTION
3
Long wall 3 14.4 0.23 1.2 11.92 m 14.4
Deduction
3
Staircase wall opening 1 1.8 0.23 1.2 0.50 m
3
Ventilator 2 0.6 0.23 0.6 0.17 m
3
TOTAL QUANTITY 20.20 m

41 partition wall
partition wall of CM(1:5)
Along x direction
3
1.Toilet-Bedroom 1 4.8 0.15 3.47 2.50 m
3
2.Pooja room-Dining 1 1.8 0.15 3.47 0.94 m
Along y direction
3
1.Toilet-Toilet 1 1.65 0.15 3.47 0.86 m
3
2.Pooja room 1 1.15 0.15 3.47 0.60 m
deductions :
3
door D1 2 0.9 0.15 2.1 0.57 m
3
TOTAL Quantity 4.33 m

Page 10 of 14
NAME : RAKHUL D DETAILED ESTIMATE DATE:03.04.2023
ROLL NO: 2001075
EXP.NO:01

S.NO DESCRIPTION NOS LENGTH WIDTH DEPTH or TOTAL UNIT REMARKS


3 2
(m) (m) HEIGHT QUANTITY (m /m
3 2
(m) (m /m /m) /m)

42 PCC flooring
3
kitchen 1 3 3 0.15 1.35 m
3
Hall 1 4.8 4.8 0.15 3.46 m
3
pooja and dining 1 3 4.8 0.15 2.16 m
3
bed room 2 3 4.8 0.15 4.32 m
3
Toilet 2 2.325 1.65 0.15 1.15 m
3
stair 1 3 1.8 0.15 0.81 m
3
Balcony 1 4.8 4.8 0.15 3.46 m
3
TOTAL Quantity 16.70 m

43 Vitrified tile flooring


2
kitchen 1 3 3 - 9.00 m
2
Hall 1 4.8 4.8 - 23.04 m
2
pooja and dining 1 3 4.8 - 14.40 m
2
bed room 2 3 4.8 - 28.80 m
2
Toilet 2 2.325 1.65 - 7.67 m
2
stair 1 3 1.8 - 5.40 m
2
Balcony 1 4.8 4.8 - 23.04 m
2
Net quantity 111.35 m
Deductions :
2
partition wall x direction 1 1.8 0.15 - 0.27 m
2
partition wall y direction 1 1.3 0.15 - 0.20 m
2
net quantity 0.47 m
2
Total quantity 110.89 m

2
44 tiles for bathroom 2 7.95 - 2.1 33.39 m 7.95
2
deductions : 2 0.9 - 2.1 3.78 m
2
Net quantity 29.61 m

3
45 RCC slab M20(1:1.5:3) 1 8.49 15.55 0.125 16.50 m
Deduction:
3
Staircase area 1 3.23 2.03 0.125 0.82 m
3
Net quantity 15.68 m

46 Ceiling plastering
2
kitchen 1 3 3 - 9.00 m
2
Hall 1 4.8 4.8 - 23.04 m
2
pooja and dining 1 3 4.8 - 14.40 m
2
bed room 2 3 4.8 - 28.80 m
2
Toilet 2 2.325 1.65 - 7.67 m
2
Balcony 1 4.8 4.8 - 23.04 m
2
Net quantity 105.95 m

47 Inner plastering
Along X direction
2
1. Main wall 5 7.8 - 3.42 133.38 m 7.8
2
2. Stair wall 3 3.23 - 3.42 33.14 m

Page 11 of 14
NAME : RAKHUL D DETAILED ESTIMATE DATE:03.04.2023
ROLL NO: 2001075
EXP.NO:01

S.NO DESCRIPTION NOS LENGTH WIDTH DEPTH or TOTAL UNIT REMARKS


3 2
(m) (m) HEIGHT QUANTITY (m /m
3 2
(m) (m /m /m) /m)
Along Y direction
2
1.Side wall 2 14.4 - 3.42 98.50 m 14.4
2
2.Middle wall 2 12.6 - 3.42 86.18 m 12.6
Partition wall
Along x direction
2
1.Toilet-Bedroom 2 4.8 - 3.42 32.83 m
2
2.Pooja room-Dining 2 1.65 - 3.42 11.29 m
Along y direction
2
1.Toilet-Toilet 2 1.65 - 3.42 11.29 m
2
2.Pooja room 2 1.15 - 3.42 7.87 m
2
Opening in dining 2 0.23 - 2.1 0.97 m
net quantity 415.44
Deductions
2
main door 1 1.2 - 2.1 2.52 m
2
door D 6 1 - 2.1 12.60 m
2
door D1 6 0.9 - 2.1 11.34 m
2
window W 3 1.2 - 1.2 4.32 m
2
window W1 3 1.8 - 1.2 6.48 m
2
ventilator 2 0.6 - 0.6 0.72 m
2
Opening 2 1 - 2.1 4.20 m
2
Bathroom tiles 1 7.95 - 2.1 16.70 m
2
net quantity 58.88 m
2
Net quantity 356.56 m

48 Outer plastering
Along x direction
2
1.Long wall 1 8.49 - 3.595 30.52 m
2
2.short wall 1 3.46 - 3.595 12.44 m
Along y direction
2
1.Outer wall 2 15.55 - 3.595 111.80 m
2
Sunshade m
2
Window W1 3 2.66 0.6 - 4.79 m
2
Window W 3 1.66 0.6 - 2.99 m
2
net quantity 162.54 m
2
Deductions m
2
window W 3 1.2 - 1.2 4.32 m
2
window W1 3 1.8 - 1.2 6.48 m
2
ventilator 2 0.6 - 0.6 0.72 m
2
net quantity 11.52 m
2
Net quantity 151.02 m

49 Staircase
3
1.Waist slab 2 2.64 0.9 0.17 0.81 m
3
2.Landing 1 1 1.8 0.17 0.31 m
3
3.Brickwork for stairs 22 0.2 0.9 0.16 0.63 m
3
Net quantity 1.75 m

2
50 Hand rail 2 3 - 1 6.00 m

Page 12 of 14
NAME : RAKHUL D DETAILED ESTIMATE DATE:03.04.2023
ROLL NO: 2001075
EXP.NO:01

S.NO DESCRIPTION NOS LENGTH WIDTH DEPTH or TOTAL UNIT REMARKS


3 2
(m) (m) HEIGHT QUANTITY (m /m
3 2
(m) (m /m /m) /m)

51 Plastering for staircase


2
1.Waist slab 2 2.64 0.9 - 4.75 m
2.Landing slab(top and
2
bottom) 2 1 1.8 - 3.60 m
2
Net quantity 8.35 m

52 Painting
2
1.Ceiling of house - - - - 105.95 m
2
2.Inner wall plastering - - - - 356.56 m
2
3.Outer wall plastering - - - - 151.02 m
2
4.Stair case painting - - - - 8.35 m
2
Net quantity 621.88 m

TERRACE

Brickwork for parapet


53 wall
3
Along X direction 1 1 8.49 0.23 1 1.95 m
3
Along X direction 2 1 5.03 0.23 1 1.16 m
3
Along Y direction 1 1 15.55 0.23 1 3.58 m
3
Along Y direction 2 1 13.29 0.23 1 3.06 m
3
net quantity 9.74 m

54 Brickwork for Headroom


3
Along X direction 2 3.46 0.23 2.5 3.98 m
3
Along Y direction 2 2.26 0.23 2.5 2.60 m
deduction
3
Grill door 1 1.8 0.23 2.1 0.87 m
3
net quantity 5.71 m

55 Fixing of joineries Grill door 1 1.8 2.1 3.78 m2

56 Outer plastering
parapet wall
2
Along X direction 1 1 8.49 1.1 9.34 m
2
Along X direction 2 1 5.03 1.1 5.53 m
2
Along Y direction 1 1 15.55 1.1 17.11 m
2
Along Y direction 2 1 13.29 1.1 14.62 m
Headroom
2
Along X direction 2 3.46 2.5 17.30 m
2
Along Y direction 2 2.26 2.5 11.30 m
Deduction
2
Grill door 1 1.8 2.1 3.78 m
net quantity 71.42 m2

Page 13 of 14
NAME : RAKHUL D DETAILED ESTIMATE DATE:03.04.2023
ROLL NO: 2001075
EXP.NO:01

S.NO DESCRIPTION NOS LENGTH WIDTH DEPTH or TOTAL UNIT REMARKS


3 2
(m) (m) HEIGHT QUANTITY (m /m
3 2
(m) (m /m /m) /m)
57 Inner plastering
Parapet wall
2
Along X direction 1 1 8.03 1 8.03 m
2
Along X direction 2 1 4.8 1 4.80 m
2
Along Y direction 1 1 15.09 1 15.09 m
2
Along Y direction 2 1 13.06 1 13.06 m
Headroom
2
Along X direction 2 3.23 2.27 14.66 m
2
Along Y direction 2 1.8 2.27 8.17 m
deduction
2
Grill door 1 1.8 2.1 3.78 m
net quantity 60.04 m2
58 painting
2
Inner plastering 60.04 m
2
outer plastering 71.42 m
2
Net quantity 131.46 m
2
59 Weathering coarse 1 7.8 14.4 0.075 8.42 m
deduction
2
stair area 1 3 1.8 0.075 0.41 m
2
net quantity 8.02 m
60 Roof tiles 1 8.03 15.09 121.17 m2
deduction
2
stair area 1 3.23 2.03 6.56 m
2
net quantity 114.62 m

Page 14 of 14