SOP 018-08 Issue 2
SOP 018-08 Issue 2
Safety Instruction:
1. Before starting the job, always be aware of the safety instructions.
2. Employees shall be worn the safty PPE such as googles, gloves, helmet & safety shoes while perfoming all the below activites.
3. Safty check points to be verified by the machine operator prior to operating the machine as per DOC 011-05(Operation Maintenance Check list) and
filled.
1.) Check the cleanness of the 3.) Load the program to the machine 4.) Load(move) the job box(JB) inside
machine the machine till the sound of lock is
While power voltage is off 2.) Check the cleanness of the re-coater heard
Prepared By: Fayez Al-Ahmadi Reviewed & Approved By: MOHAMMED ABU OSS
Position: Development Engineer Position: HEAD - ENGINEERING, R&D
Date: 12.November.2022 Date: 12.November.2022
Issue: 2 DCR/A: 663
Page 01 of 03
STANDARD OPERATING PROCEDURE (SOP 018-08)
9.) Check the recycled sand level 10.) Check Binder level. 11.) Check Cleaner level 12.) Check Activator level
“Material B” “45 kg and above “ “45 kg and above “ “5000g and above”
13.) Check the air pressure level which 14.) Press on “Process”
must be > 6.0 bar 16.) Monitor the first 40 layers to
15.) Press on “Start” make sure there is no printing issue.
(cavity not acceptable)
17.) Press on “print Test image” 18.) Check the test image and make sure 19.) After print completion, leave Job box
there is no major gap in any of the 12 inside the machine for two hrs. 20.) Move the Job box out of the
modules. machine
21.) Extract the printed items from job 24.) Arrange printed parts properly on
box carefully. Suck the loose sand by 22.) Clean the printed items using air 23.) Inspect printed items & test bar pallet.
sand extractor to reload into reloading pressure of 1 bar. dimension. Hardness test to be
container conducted on the test bar to ensure core
strength. If not meeting the specification,
scrap the complete job box. LOI need to
check
Page 02 of 03
Prepared By: Fayez Al-Ahmadi Reviewed & Approved By: MOHAMMED ABU OSS
Position: Development Engineer Position: HEAD - ENGINEERING, R&D
Date: 12.November.2022 Date: 12.November.2022
Issue: 2 DCR/A: 663
STANDARD OPERATING PROCEDURE (SOP 018-08)
END OF PROCEDURE
Prepared By: Fayez Al-Ahmadi Reviewed & Approved By: MOHAMMED ABU OSS
Position: Development Engineer Position: HEAD - ENGINEERING, R&D
Date: 12.November.2022 Date: 12.November.2022
Issue: 2 DCR/A: 663
STANDARD OPERATING PROCEDURE (SOP 018-08)
Page 03 of 03
Prepared By: Fayez Al-Ahmadi Reviewed & Approved By: MOHAMMED ABU OSS
Position: Development Engineer Position: HEAD - ENGINEERING, R&D
Date: 12.November.2022 Date: 12.November.2022
Issue: 2 DCR/A: 663