Client : Dubai Holding Real Estate Project Name: MH-0025-Warsan First-Landscape Work
Consultant: Parsons Second-Road and Infrastructure Works Date: 22/01/2024
Contractor: Green Scapes Location: Dubai, UAE
Hours Worked:
Shift: Day Staff Day Work: 8:00AM to 5:00PM Weather: Sunny
Labour Day Work: 6:30AM to 5:00PM
Manpower (Staff) No. Total Hours Major Equipment No. Total Hours
Construction Manager 1 8 JCB 8 10
Project Manager 1 8 Mini Excavator 5 10
Planning Engineer 1 8 Bobcat 6 10
NOC Engineer 1 8 3Ton Pick up 1 10
Safety Engineer 1 8 Tipper 1 10
Lab Technician 1 8 Shovel 2 10
Electrical Engineer 1 8 Big Excavator 1 0
Draftman 2 8 Six Wheel 1 10
Surveyor 2 8 Roller Operator 1 10
QS 1 8 Asphalt Cutter 1 0
QC 1 8 Hi-ab Crane 1 10
Secretary 1 8 Boom Loader 1 10
Storekeeper 1 8
Total Staff 15
Manpower (Labour)
Foreman 5 10
Asst. Surveyor 4 10
Asst. Safety 2 10
Labour 105 10
Pick up Driver 1 10
Operator 27 10
Mason 3 10
Helper 3 10
Carpenter 4 10
Sub-contractor's Equipment
Manpower
(Sub-contractor's Labour)
Sub-contractor 10 10
Labour 188 10
Foreman 8 10
Page 5 of 11
CONTRACTOR DAILY REPORT
DESCRIPTION OF WORK PERFORMED TODAY
1 Working on Hardscapes in Warsan 2
2 Formation Level for Kerb Stone, Heel Kerb & Interlock - Warsan 2
3 Road Base for Flush Kerb & Heel Kerb - Warsan 2
4 Formation for Hardscape and Landscaping - Warsan 1
5 Formation of Hardscape at SIKKA Area - Warsan 1
6 Subgrade for Moving Heel Kerb & Kerb Stone - Warsan 2
7 Formation Level for Heel Kerb & Kerb Stone - Warsan 2
8 Shuttering Formwork for Heel Kerb & Kerb Stone - Warsan 2
9 FDP Test for Warsan 2
10 Casting of PCC for the Heel Kerb & Moving Edge - Warsan 2
11 Formation Level for the Heel Kerb & Moving Edge Activity - Warsan 2
12 Fixing the Interlock, Heel Kerb & Flush Kerb - Warsan 2
13 Fixing the Heel Kerb - Warsan 1
Total Quantity
Total Quantity
Page 6 of 11
CONTRACTOR DAILY REPORT
PROGRESS POTOGRAPHS
PHOTO
WARSAN 1 WARSAN 1
PHOTO
WARSAN 1 WARSAN 1
WARSAN 1 WARSAN 1
Page 7 of 11
CONTRACTOR HSE DAILY PROGRESS REPORT
TOOL BOX TALK POTOGRAPHS
Description: Daily Tool Box Talk Description: Daily Tool Box Talk
Location: Al Warsaan-02 Area-04 Location: Al Warsaan-02, Area-04
Description: Daily Tool Box Talk Description: Daily Tool Box Talk
Location: Al Warsaan-02 Area-04 Location: Al Warsaan-01, Area-02
Description: Daily Tool Box Talk Description: Daily Tool Box Talk
Location: Al Warsaan-01, Area-02 Location: Al Warsaan-01, Area-02
Page 8 of 11
CONTRACTOR HSE DAILY PROGRESS REPORT
DAILY INSPECTION OF EQUIPMENT POTOGRAPHS
Page 9 of 11
CONTRACTOR HSE DAILY PROGRESS REPORT
SITE OBSERVATION REPORT
Description:Operator did not wear the safety jacket Description:immeditely conduct TBT and warning to
him
Location:Al Warsaan-02 , Area 04 Location: Al Warsaan-02 , Area 04
Description: Description:
Location: Location:
Page 10 of 11
Leading Indicators Today Previous Total
HSE Meetings (Toolbox, Pre-shift meetings, etc..) 1 116 117
HSE Audits 0 0 0
Inspections / Safety Walks 0 1 1
Emergency Drills 0 0 0
Training / Inductions 0 296 296
Observations 2 97 99
Near Misses 0 15 15
Awareness campaigns 0 4 4
Management Site Walk 0 1 1
REMARKS BY CONTRACTOR (Delays, Interruptions, Deviations, Extra Work Activities, Conferences, etc. Relevant to Today's Work).
Site Maintenance and cleaning