CONTRACTOR DAILY REPORT

Client : Dubai Holding Real Estate Project Name: MH-0025-Warsan First-Landscape Work
Consultant: Parsons Second-Road and Infrastructure Works Date: 29/01/2024
Contractor: Green Scapes Location: Dubai, UAE

Contract No.:0086 – Warsan Report No: DPR No. 351654-GSL-


First & Second PAR-DPR-00120_R00

Hours Worked:
Shift: Day Staff Day Work: 8:00AM to 5:00PM Weather: Sunny
Labour Day Work: 6:30AM to 5:00PM

Manpower (Staff) No. Total Hours Major Equipment No. Total Hours
Construction Manager 1 8 JCB 8 10
Project Manager 1 8 Mini Excavator 5 10
Planning Engineer 1 8 Bobcat 6 10
NOC Engineer 1 8 3Ton Pick up 1 10
Safety Engineer 1 8 Tipper 1 10
Lab Technician 1 8 Shovel 2 10
Electrical Engineer 1 8 Big Excavator 1 0
Draftman 2 8 Six Wheel 1 10
Surveyor 2 8 Roller Operator 1 10
QS 1 8 Asphalt Cutter 1 0
QC 1 8 Hi-ab Crane 1 10
Secretary 1 8 Boom Loader 1 10
Storekeeper 1 8
Total Staff 15

Manpower (Labour)
Foreman 5 10
Asst. Surveyor 4 10
Asst. Safety 2 10
Labour (GS) 99 10
Pick up Driver 1 10
Operator 27 10
Mason 3 10
Helper 3 10
Carpenter 4 10

Total (GS Labour) 148


Total (Manpower) 163 Total (Equipment) 29

Sub-contractor's Equipment
Manpower
(Sub-contractor's Labour)
Sub-contractor 10 10
Labour 77 10
Foreman 8 10

Total (Sub-C. Labour) 95

Total 258 No.s

CONTRACTOR DAILY REPORT


DESCRIPTION OF WORK PERFORMED TODAY
1 Working on Hardscapes in Warsan 2

Page 5 of 11
2 Formation Level for Kerb Stone, Heel Kerb & Interlock - Warsan 2
3 Road Base for Flush Kerb & Heel Kerb - Warsan 2
4 Formation for Hardscape and Landscaping - Warsan 1
5 Formation of Hardscape at SIKKA Area - Warsan 1
6 Subgrade for Moving Heel Kerb & Kerb Stone - Warsan 2
7 Formation Level for Heel Kerb & Kerb Stone - Warsan 2
8 Shuttering Formwork for Heel Kerb & Kerb Stone - Warsan 2
9 FDP Test for Warsan 2
10 Casting of PCC for the Heel Kerb & Moving Edge - Warsan 2
11 Formation Level for the Heel Kerb & Moving Edge Activity - Warsan 2
12 Fixing the Interlock, Heel Kerb & Flush Kerb - Warsan 2
13 Fixing the Heel Kerb - Warsan 1

S.No Date Day Work Description Quantity BoQ Ref; Remarks


1

Total Quantity

PLANNED ACTIVITIES FOR 24 HOURS

1 Working on Hardscapes in Warsan 2


2 Formation Level for Kerb Stone, Heel Kerb & Interlock - Warsan 2
3 Road Base for Flush Kerb & Heel Kerb - Warsan 2
4 Formation for Hardscape and Landscaping - Warsan 1
5 Formation of Hardscape at SIKKA Area - Warsan 1
6 Subgrade for Moving Heel Kerb & Kerb Stone - Warsan 2
7 Formation Level for Heel Kerb & Kerb Stone - Warsan 2
8 Shuttering Formwork for Heel Kerb & Kerb Stone - Warsan 2
9 FDP Test for Warsan 2
10 Casting of PCC for the Heel Kerb & Moving Edge - Warsan 2
11 Formation Level for the Heel Kerb & Moving Edge Activity - Warsan 2
12 Fixing the Interlock, Heel Kerb & Flush Kerb - Warsan 2
13 Fixing the Heel Kerb - Warsan 1

S.No Date Day Work Description Quantity BoQ Ref; Remarks


1

Total Quantity

CONTRACTOR DAILY REPORT


PROGRESS POTOGRAPHS

Page 6 of 11
PHOTO
PHOTO

WARSAN 1 WARSAN 1

PHOTO

WARSAN 1 WARSAN 1

WARSAN 1 WARSAN 1

CONTRACTOR HSE DAILY PROGRESS REPORT


TOOL BOX TALK POTOGRAPHS

Page 7 of 11
Description: Daily Tool Box Talk Description: Daily Tool Box Talk
Location: Al Warsaan-02 Area-04 Location: Al Warsaan-02, Area-04

Description: Daily Tool Box Talk Description: Daily Tool Box Talk
Location: Al Warsaan-01 Area-02 Location: Al Warsaan-01, Area-02

Description: Daily Tool Box Talk Description: Daily Tool Box Talk
Location: Al Warsaan-01, Area-02 Location: Al Warsaan-01, Area-02

Page 8 of 11
CONTRACTOR HSE DAILY PROGRESS REPORT
DAILY INSPECTION OF EQUIPMENT POTOGRAPHS

Description: Equipment's Daily Inspection Description: Equipment's Daily Inspection


Location: Al Warsaan-02 , Area 04 Location: Al Warsaan-02 , Area 04

Description: Equipment's Daily Inspection Description: Equipment's Daily Inspection


Location: Al Warsaan-01 , Area 02 Location: Al Warsaan-01 , Area 02

Description: Equipment's Daily Inspection Description: Equipment's Daily Inspection


Location: Al Warsaan-01 , Area 02 Location: Al Warsaan-01 , Area 02

Page 9 of 11
CONTRACTOR HSE DAILY PROGRESS REPORT
SITE OBSERVATION REPORT

Description:Board are fall down Description:immeditely rectify.


Location:Al Warsaan-01 , Area 02 Location: Al Warsaan-01 , Area 02

Description:stop the work and inform the foreman to


Description: Electrical socket is bad condition
rectify
Location: Al Warsaan-01, Area 02
Location: Al Warsaan-1 , Area 02

Description: Description:
Location: Location:

CONTRACTOR DAILY REPORT


HEALTH, SAFETY & ENVIRONMENT

Leading Indicators Today Previous Total


HSE Meetings (Toolbox, Pre-shift meetings, etc..) 1 122 123
HSE Audits 0 0 0
Inspections / Safety Walks 0 1 1

Page 10 of 11
Emergency Drills 0 0 0
Training / Inductions 0 303 303
Observations 2 114 116
Near Misses 1 17 18
Awareness campaigns 0 4 4
Management Site Walk 0 1 1

Lagging Indicators Today Previous Total


Lost Time Injury cases (LTIC) 0 0 0
Restricted workday cases (RWC) 0 0 0
Medical treatment cases (MTC) 0 0 0
First aid cases (FAC) 1 1 2
Fire/Explosion 0 0 0
Property Damage 0 0 0
Environmental Incident 0 0 0
Dangerous Occurrence 0 0 0
Vehicle Incident 0 0 0
HSE Violations 0 0 0

REMARKS BY CONTRACTOR (Delays, Interruptions, Deviations, Extra Work Activities, Conferences, etc. Relevant to Today's Work).
Site Maintenance and cleaning

CONTRACTOR'S AUTHORIZED REPRESENTATIVE (Signature)


HSE Engineer DATE 29/01/2024

CONTRACTOR'S AUTHORIZED REPRESENTATIVE (Signature)


Project Manager DATE 29/01/2024

POL COMMENTS AND/OR EXCEPTIONS

POL RESIDENT ENGINEER DATE

(Signature)

Page 11 of 11