Professional Documents
Culture Documents
Electricity Sector Assessment in Nigeria The Post-Liberation Era
Electricity Sector Assessment in Nigeria The Post-Liberation Era
Electricity Sector Assessment in Nigeria The Post-Liberation Era
To cite this article: Olubayo Babatunde, Elutunji Buraimoh, Oluwatobi Tinuoye, Clement
Ayegbusi, Innocent Davidson & Desmond Eseoghene Ighravwe (2023) Electricity sector
assessment in Nigeria: the post-liberation era, Cogent Engineering, 10:1, 2157536, DOI:
10.1080/23311916.2022.2157536
© 2023 The Author(s). This open access article is distributed under a Creative Commons
Attribution (CC-BY) 4.0 license.
Page 1 of 24
Babatunde et al., Cogent Engineering (2023), 10: 2157536
https://doi.org/10.1080/23311916.2022.2157536
and presented using documents and recent literature on the Nigerian electricity
sector. Findings from the study show that infrastructural deficits and administrative
lapses dominated the pre-liberation era. The privatization of electricity led to
organizational structure and infrastructure improvements. The sector was
unbundled into the GenCos, TransCo, Discos, and the regulatory bodies assigned
well-defined tasks. The generation capacity has increased to 16,384 MW against the
pre-liberation figure of approximately 6000 MW. As against the approximate figure
of 10,000 km covered by the transmission infrastructure, an additional 10,000 km
has been added to the existing transmission facilities. Although there have been
improvements in service deliveries, there are still more grounds to cover to stabilize
the Nigerian electricity sector. It is proposed that stakeholders harmonize the
various policies and structural changes to make the necessary improvements.
Subjects: Energy Policy; Energy policy and economics; Energy Industries & Utilities
1. Introduction
In the last three decades, many developed and developing economies have directed intense
efforts at various electricity sector reforms to stabilize the sector. These reforms are necessary
due to the different emerging themes that have emanated from the electricity market. Some of
these include the inclusion of renewable energy in the electricity mix, change of ownership
structure, market competition, and the sector’s decentralization to meet SDG 7 (Babatunde
et al., 2018). With a specific emphasis on developing economies, these reforms are triggered by
consumers’ dissatisfaction in countries whose electricity sectors are based on the inefficient,
traditional model (monopolistic). Also, successes recorded in many developed countries’ electricity
sectors are another motivation behind adopting electricity reforms in developing economies.
However, although electricity reforms in developed countries aim to improve comparatively effi
cient market performance, the narrative is totally different in developing countries (especially the
global south). In developing countries, many electricity sectors are plagued with vandalization,
weak networks, non-cost reflective tariffs, high technical and non-technical losses, and inadequate
coverage (Eberhard & Shkaratan, 2012; Babatunde et al., 2020). Moreover, in the wake of global
economic recessions, the budgets of many governments of developing economies are no longer
capable of the state-supported electricity sector. In addition, significant reforms will open up and
suitably position a monopolistic government-funded electricity sector in developing countries for
much-needed competition and investments (Rehermann & Shi, 2016). As such, many power sector
reforms in Africa are stimulated by the states’ needs in accessing credits from international
financing institutions (Wamukonya, 2003).
Nigeria’s federal government enacted a decree as part of efforts intended to improve the
Nigerian power sector in the early 1970s. This decree led to the merger of the Niger Dams
Authority (NDA) and the Electricity Corporation of Nigeria (ECN) to create National Electric Power
Authority (Oluseyi et al., 2012). Until deregulation, the public-owned utility company operated
a vertically integrated government-funded model. With a considerable transmission and distribu
tion infrastructure deficit, it could only generate a total power of about 6200 MW (four thermal and
two hydropower plants). The deficit in the generation, transmission, and distribution infrastruc
tures ensured that the market’s demand side was severely underserved, with commodities char
acterized by brownouts, blackouts, and unscheduled load shedding. The utility could not reduce
technical and non-technical losses on the supply side, adequate maintenance, timely expansion,
and a reasonable collection rate. Seeing the underfunded state-owned Nigerian power sector’s
poor condition and the need for significant restructuring for increased efficiency, the FGN
Page 2 of 24
Babatunde et al., Cogent Engineering (2023), 10: 2157536
https://doi.org/10.1080/23311916.2022.2157536
promulgated the National Electric Power Policy in 2001 (Ayamolowo et al., 2019b). The policy
aimed to unbundle the Nigerian power sector for private sector participation and create enabling
structures to sustain the Nigerian electricity market. This was followed by the enactment of the
Electric Power Sector Reform (EPSR) and the creation of the Nigerian Electricity Regulatory
Commission (NERC) in 2005 (Ayamolowo et al., 2019b). Based on the EPSR, the Nigerian electricity
sector was finally unbundled and allowed private sector participation in 2013. However, the much-
expected service delivery improvements are far from being achieved, with electrification rates in
Nigeria standing at 45% (Rural: 36% Urban: 55%; USAID-United States Agency for International
Development, 2019). Apart from the fact that electricity demand far exceeds the installed and
available capacity, the transmission and distribution capacity is also grossly below the required
capacity.
With the privatization of the last distribution facility concluded in 2014, various milestones and
drawbacks have been experienced within the Nigerian electricity sector. Passed as a law almost
20 years ago, the Electric Power Sector Reforms Bill was expected to, among other issues, develop
and guarantee an efficient, reliable, affordable, safe, and cost-effective system of electricity
generation, transmission, distribution, and marketing in the NESI (Isola, 2016). Various works of
literature have been dedicated to appraising the progress or otherwise of Nigeria’s deregulated
electricity market. (E. Ogunleye, 2017) presented a political economy aspect of the Nigerian power
sector reform. The author identified regulatory uncertainty and policy inconsistencies as major
challenges in the industry. The challenges and possible solutions to the challenges of power sector
reforms in Nigeria have also been discussed in the literature (Oladipo et al., 2018; Onochie et al.,
2015). While (Oladipo et al., 2018) suggested proper funding of GENCOs as a key solution to
improving power generation in Nigeria, (Onochie et al., 2015) opined that implementing the
existing policies would go a long way in improving the NESI. Also (Gatugel Usman et al., 2015)
concludes that transforming the NESI for sustainable growth and development mitigation of
energy poverty and corruption is critical and must be pursued. Other aspects of the NESI that
have been discussed in the literature include power sector laws (Usman & Abbasoglu, 2014),
decentralization of the grid (Alao & Awodele, 2018), policy analysis (Audu et al., 2017), and
productivity analysis (Barros et al., 2014). Based on this literature, the efficacy of the reforms in
improving the Nigerian power sector has remained ambiguous. Although the network capacities
have been relatively increased, the electrification access (percentage) post-liberation era has not
significantly improved. Many consumers are still exposed to long hours and multiple national
blackouts. This paper summarizes the Nigerian power sector by improving the existing literature,
emphasizing the trends, challenges, and future perspectives. The contribution of the paper
includes the following
● Aggregation, comprehensive review of state-of-the-art and documentation of the NESI. The current
power sector market structure, market regulations, and policies and reforms were aggregated and
discussed
● Identification of the various challenges of the Nigerian Power Sector and discussion of potential
solutions to the challenges; a unique approach for improving the Nigerian Electricity Sector was
proposed in this study
This review is expected to act as a navigating compass for stakeholders in the industry in terms of
the present state of the sector and what needs to be done to improve the sustainability of the
Nigerian Electricity Supply Industry (NESI). Accordingly, the review is organized as follows:
Section 2 focuses on the current power sector market structure, Section 3 discusses market
regulations available in the NESI, Section 4 is dedicated to government-motivated policies and
reforms, and Section 5 highlights the present challenges in the NESI, Section offer some solutions
to the challenges identified in the study, while Section 7 concludes the study by discussing the
various findings drawn from the review.
Page 3 of 24
Babatunde et al., Cogent Engineering (2023), 10: 2157536
https://doi.org/10.1080/23311916.2022.2157536
2.1. Generation
There are four major categories of power generation in Nigeria; these include (a) transmission-grid
connected generation, (b) embedded generation (usually connected to the distribution line), (c)
off-grid generation, and (d) captive generation (Nigerian Electricity Regulatory Commission, 2020).
To operate the first three categories of generation options, a valid license is required from NERC. In
contrast, the last power generation option only involves obtaining a permit from NERC. With the
implementation of the EPSR Act of 2005, the generation part of the former state-owned PHCH was
unbundled into six privatized GenCos, National Integrated Power Project (NIPP), and Independent
Power Producers (IPPs; Nigerian Electricity Regulatory Commission, 2020). From these three
sources, the Nigerian electricity network has 23 grid-connected generators with a total installed
capacity of 12,522 MW (Hydro: 19%, Thermal: 81%; USAID-United States Agency for International
Development, 2019). However, due to various challenges, only about 58% of the total installed
Page 4 of 24
Babatunde et al., Cogent Engineering (2023), 10: 2157536
https://doi.org/10.1080/23311916.2022.2157536
capacity is available (Hydro: 1,060 MW, Thermal: 4,996 MW; Bamisile et al., 2020). Therefore, NERC
periodically licenses IPPs who meet the specified conditions to improve electricity generation. Also,
the commission proposed Bulk Procurement Guidelines to systematically and effectively procure
bulk power.
2.2. Transmission
Nigeria’s transmission network is managed and operated by the state-owned Transmission
Company of Nigeria (TCN). TCN, incorporated in 2005, is responsible for expanding and improving
the transmission network’s reliability. TCN serves as a transmission service provider, system
operator, and market operator. The TCN is saddled with providing the necessary infrastructure
for wheeling electric power generated by the GENCOs to the DISCOs. The Nigerian transmission
network consists of approximately 20,000 km of 132kV lines, 330kV lines, and high voltage
Page 5 of 24
Babatunde et al., Cogent Engineering (2023), 10: 2157536
https://doi.org/10.1080/23311916.2022.2157536
substations with a theoretical wheeling capacity of about 7.5GW (Nigerian Electricity Regulatory
Commission, 2020). At present, the operational generation capacity (3,879.MW) is less than the
transmission wheeling capacity (5,300 MW); however, if the total installed generation capacity
(12,522 MW) were to be evacuated into the transmission network, there is likely to be a system
collapse. The network is also reported to suffer from transmission losses (7.4%), which are above
the average (figure 2 –6%) for emerging countries (Nigerian Electricity Regulatory Commission,
2020). The highest power to be evacuated to the transmission grid to date is 5,420.3 MW; this was
achieved in August 2020–7 years after the privatisation process was completed (Okafor, 2020).
Without redundancies, the Nigerian transmission network is radial and as such susceptible to poor
reliability and frequent collapse.
2.3. Distribution
Nigeria’s power distribution network operates majorly on low voltage (11kV) and medium voltage
(33kV). The distribution network spans approximately 366,363 km serving more than 8,645,000
customers across the 36 states of Nigeria (Ley et al., 2015).
The distribution network is radial, grossly under-maintained, and records an average technical
loss of approximately 13% (Ley et al., 2015). With few customers being metered, the non-technical
loss on the Nigerian distribution network is very high. In addition, Nigeria’s electricity sector’s
privatization in 2013 gave rise to 11 privately run (DisCos), which serve consumers across the
country’s six geo-political zones, as shown in Figure 3.
Figure 3. 11 Distribution
Companies (DisCos).
Page 6 of 24
Babatunde et al., Cogent Engineering (2023), 10: 2157536
https://doi.org/10.1080/23311916.2022.2157536
2020). Apart from individual and corporate efforts in the off-grid generation, governments at
various levels are also dedicated to improving electricity access through several off-grid electrifi
cation schemes. Through the Nigerian Rural Electrification Agency (REA), Nigeria’s federal govern
ment is responsible for remote and unserved communities’ electrification through the Nigeria
Electrification Project (NEP). The REA is also responsible for administering the rural electrification
fund and coordinating rural electrification programs through various private and public sector
participation. The NEP includes the Energizing Education Programme (EEP), which targets clean
and affordable energy for 7 University Teaching Hospitals and 37 federal universities across
Nigeria. Apart from this, REA also has the responsibility of providing clean electricity access for
clusters of economic hubs (shopping malls, agricultural and agro-processing, and markets)
through private sector partnerships (The Nigeria Electrification Project (NEP)—Rural Electrification
Agency, 2020).
3. Market regulation
Page 7 of 24
Babatunde et al., Cogent Engineering (2023), 10: 2157536
https://doi.org/10.1080/23311916.2022.2157536
Online Updates, 2020). The cost-reflective tariff is proposed to be replaced by the future service-
reflective tariff. NERC regulates and sets electricity tariffs, emphasizing the achievement of cost-
reflective tariffs over a given period. At the dawn of electricity industry privatization, tariffs were
ordinarily non-cost-reflective, implying the initial under-recovering investment. However, the tariffs
were intended to increase to an economic level that eventually led investors to over-recover their
initial and generate significant profit needed to promote competition and continuous investment.
The NERC aims to migrate from a solely cost-reflective tariff approach and sculpting idea to
a service-reflective method in the nearest future. Consequently, NERC’s emphasis on ensuring
that tariffs are enough to meet costs and provide fair investment returns will ensure that tariffs
reflect service delivery quality.
The MYTO implements a building block technique to set distribution and transmission tariffs that
offer price controls and incentives advantages by integrating all associated electricity costs into
a standardized financial system. The first two blocks are the return on invested capital (ROIC):
market and asset depreciation-based. The last is the overhead and resourceful running cost.
Finally, long-run marginal cost (LRMC) is the incremental cost incurred by a generating station
when all inputs are variable. Hence, The generation tariff is estimated with the most financially
viable new market entrants’ LRMC standard.
The retail electricity price to consumers consists of four units, as shown in Figure 4. MYTO
provides a simple segmentation and evaluation of required operational expenses, overhead, and
a real investment return to create transparent tariffs with credibility and widespread acceptance.
DisCos service evaluation criteria include hours of electricity supply, supply reliability determined
by disruption frequency and length, and power quality (operating voltage magnitude and fre
quency specified by grid code). Future tariff adjustments will be based now on negotiations and
agreements between DisCos and consumer clusters. If DisCos not meet performance goals,
incentives will be used to reimburse consumers.
Page 8 of 24
Babatunde et al., Cogent Engineering (2023), 10: 2157536
https://doi.org/10.1080/23311916.2022.2157536
E
D
C
B
A
0 4 8 12 16 20 24
MYTO regime specifies wholesale and retail tariff services, including charges for power transmis
sion. The base cost of the electricity tariff defined by the generation cost module is 36.36% of the
retail tariff, as shown in Figure 4. This is the wholesale price that the bulk buyer, NBET, purchased
electricity from GenCos and IPP before selling to DisCos. GenCos and IPPs can recover their capital
return, operating, and overhead costs under the cost generation module. The GenCos decide their
respective wholesale electricity price with NBET through a PPA authorised by NERC. However, the
IPPs are prohibited from recovering their capital or capital return. This is because the IPPs are paid
only for their cost of operation and not for investment in gas power plants. This module is critical
as it determines the generation lucrativeness to private investment. The government also con
siders it significant, as it is, in reality, among the few tools to encourage competition in the market
hitherto dominated by natural monopolies. As inflation shifts, exchange rates, and gas prices
changes, the wholesale tariff is also adjusted.
The transmission cost module, also known as the “grid charge” or Transmission Use of System
(TUoS) Charge, is the second layer of the electricity tariff in Nigeria, contributing 8.16 % of the retail
Page 9 of 24
Babatunde et al., Cogent Engineering (2023), 10: 2157536
https://doi.org/10.1080/23311916.2022.2157536
tariff by the DisCos to TCN. Using the TCN’s transmission infrastructure to transmit power to
substations under DisCo ownership for distribution is the cost. The TUoS enables TCN to recover
current and projected capital costs and effective operational costs and make capital return and
maintenance provisions. However, NERC controls the TUoS, which is uniform across the country
and susceptible to inflation and the exchange rate.
The smallest and third module of the electricity tariff is the service and VAT, which amounts to
6.86%. The service and VAT consist of the agency running cost of NERC and NBET regulating and
operating the NESI.
The distribution cost is the highest and last layer and accounts for 48,62% of the overall price for
electricity which is charged by the DisCos. The cost is different in the eleven DisCo networks, as
shown in the year 2020 average tariff depicted in Figure 7. Hence the tariff at the distribution level
depends on the type of customer: residential, commercial, industrial, street lighting, and special
tariff. The customer categories are further subdivided into groups based on the number of phases,
voltage level, and demands.
Page 10 of 24
Babatunde et al., Cogent Engineering (2023), 10: 2157536
https://doi.org/10.1080/23311916.2022.2157536
50
40
30
20
10
0
Yola Ibadan Port Jos Ikeja Benin Abuja Eko Kano Kaduna Enugu
Harcourt
allows renewable energy companies to sell electricity to the grid at prices significantly above those
producing energy via traditional gas, coal, and hydro sources: the NBET’s assured electricity
procurement and a five-year exclusion from renewable energy investment tax. As shown in
Figure 8, the apparent challenges negatively affecting businesses have necessitated the reform’s
conception as depicted.
It must be noted that moderate progress was made in executing the power sector reform. First
of all, the former NEPA and later PHCN were unbundled, and 11 distribution firms, six generating
firms, and one transmission company were born. Secondly, a cost-reflective tariff (MYTO) is
introduced to make the industry attractive to domestic and international investors. Third, many
IPPs with 2,500 MW aggregated capacity have been added to the system. Fourthly, NERC was
created. Fifthly, considerable efforts are underway to develop the gas-to-power plan, the country’s
biggest electricity supply bottleneck amidst pipeline vandalism and gas pricing policies. Finally,
many policies and market rules have been formulated to govern the evolving privatised electricity
sector at various reform phases.
Page 11 of 24
Babatunde et al., Cogent Engineering (2023), 10: 2157536
https://doi.org/10.1080/23311916.2022.2157536
& Chikuni, 2007). With the creation of the National Electric Power Policy in 2001, the change was
given a further policy drive. This policy resulted from a survey conducted by the government in
1999 to identify the power sector’s challenges and provide guidelines to transform the sector. This
policy provided the foundation for the reform plan and signified the birth of Nigeria’s modern
power sector. In 2005, the reform was given great impetus by the Electric Power Sector Reform Act
(EPSRA), introduced to provide legal support for the reform and implement the strategy. The
reform’s overall purpose is to improve the productivity, transparency, reliability, standard, and
affordability of electricity supply to spur economic transformation, growth, and development. The
former NEPA was transformed into PHCN and subsequently unbundled following the procedures
drawn in the EPSRA. Key policies since 2001 are shown in Figure 9.
The system has designed many policy measures, proclamations, and reports to steer the power
sector’s reform process. The Nigeria Energy Commission established and adopted the 2003
National Energy Policy (NEP) for the energy sector. The target of 75% electrification by 2020
encompasses all forms of electricity, including renewable energy, energy conservation, and rural
electrification. The 2007 National Energy Master Plan (NEMP) lays out the National Energy Policy
(NEP) structure for implementation. The government approved the National Electric Power Policy
Page 12 of 24
Babatunde et al., Cogent Engineering (2023), 10: 2157536
https://doi.org/10.1080/23311916.2022.2157536
(NEPP) in 2001 to set out the power sector’s basic structure. Roadmap for Power Sector Reform in
2010 was leveraged on the Electricity Master Plan (EMP) of 2008 and 2013 to identify the critical
barriers affecting the power sector’s full liberalisation and energy sufficiency. The 2015 National
Renewable Energy and Energy Efficiency Policy (NREEEP) conceptualizes energy efficiency and
renewable energy strategy. The Energy Commission of Nigeria (ECN), along with the United
Nations Development Programme (UNDP) 2006, developed the Renewable Energy Master Plan
(REMP), which was reviewed in 2012. The structure and goals for the rural electrification program
are set out in the Rural Electrification Policy Paper (REPP), approved by the government in 2009,
which targets 10% of the energy mix for renewable sources by 2025. The Electric Power Sector
Reform Act (EPSRA) empowers the Rural Electrification Agency (REA) to develop its operational
plan and strategy. However, this must be done in consultation with the NERC and ratified by the
government.
The NREEEP, which was officially approved in 2015, is the power sector policy pool. The policy
seeks to implement programs to achieve sustainable and inclusive development by effectively
using energy resources in the country. The policy seeks to tackle various renewable energy
concerns: planning and policy implementation, regulations, research and innovation; enforcement
and rules; supply and use; funding and pricing; training and technical; performance and sustain
ability; execution of initiatives; gender; and climate change.
Over the past two decades, the successive government has tried to find a solution to generation
capacity issues by assuming a monopoly role in generating, transmitting, and distributing power
where billions of the country’s hard-earned resources have been invested in power with meagre
improvement.
In August 2010, the power sector reform roadmap was launched to lay the groundwork for
transferring the private sector’s power utilities’ operations. Finally, in 2013, six (6) power-
generation plants and 11 distribution companies unbundled from Nigeria’s power holding com
pany were sold to private investors. (Challenges facing the Nigerian power sector, 2016),
(Ayamolowo et al., 2019a). This new transformation raised expectations as it was assumed that
the new investors would rapidly end frequent power outages and meet up with the populace’s
power demands. However, the initiative has brought little improvement as numerous issues still
hamper the electricity growth in Nigeria. Below is the graph shows the energy sent out from 2016
to 2019. The analysis shows that there is still a large deficit. This write-up aims to look at the
challenges hampering the power sector fulfillment and resolve this deficit.
Page 13 of 24
Babatunde et al., Cogent Engineering (2023), 10: 2157536
https://doi.org/10.1080/23311916.2022.2157536
a service level agreement will run into chaos. Its operations will be unstable; value creation will be
limited or nonexistent.
The Nigerian national grid’s design capacity is about 7500 MW, and power generated and
supplied to the grid instantly has never been up to 6000 MW. (Nigerian Electricity Regulatory
Commission, 2020). One tends to ask the question, why? The shortage of gas has rendered most of
the thermal power plants idle. There is no accountability because there is no agreement and,
therefore, no efficiency in service delivery. This has hampered our economy. Table 1 below shows
the status of the Gas Supply Agreement for the various power plants.
● Duration of PPA is a 20 years tenor by NBET standard and provides clauses to take care of early
termination due to either party’s default.
● Tariff Structure—makes available the guide on how NBET will make payment for the duration
of PPA
● Resolution of Conflict—defines the processes for resolving conflict as regards disputes or issues on
the invoice.
● Metering—clarify the metering and metering code rules supersedes the conflict between PPA
provision and metering code.
● Allocation of Risk—captures all the risk related to the project and allocate these risks to the best
party who can bear them.
● Testing and Commissioning—gives detail of the testing and commissioning of the power plant.
● Operation and Maintenance—provides the details of the private investor’s operation and mainte
nance responsibilities throughout the PPA duration.
● Precedent Conditions—indicates all the prerequisite conditions that either party must fulfill before
the PPA can become active.
● Liability and indemnity—highlight the parties responsible for specific types of failures and provide
both parties’ indemnity.
● Project Document—states all the documents connected to the PPA, such as the design, procure
ment, construction, Gas Transport Agreement, Gas Supply Agreement, and Finance documents.
● Force Majeure—Provides the scenario’s details to be considered a force majeure and the payments
to be made in the occurrence. https://nbet.com.ng/our-customers/generation/key-parts-of-ppa/
Page 14 of 24
Babatunde et al., Cogent Engineering (2023), 10: 2157536
https://doi.org/10.1080/23311916.2022.2157536
Table 1. PPA power plants statuses (Nigerian Electricity Regulatory Commission, 2020)
S/N Power GenCo Installed PPA Status GSA Status Remarks
Plant Type Capacity
Name (MW)
1 Shiroro hydro 600 Not active Hydro No
Guarantee
2 Jebba hydro 578.4 Not active Hydro No
Guarantee
3 Kainji hydro 760 Not active Hydro No
Guarantee
4 Afam thermal 300 Not active Hydro No
Guarantee
5 Delta thermal 765 Not active Not active No
Guarantee
6 Geregu thermal 435 Not active Not active No
Guarantee
7 Sapele thermal 720 Not active Not active No
Guarantee
8 Egbin thermal 1320 Not active Not active No
Guarantee
9 Omotosho 1 thermal 336.8 Full active Not active No
PPA Guarantee
10 Olorunsogo 1 thermal 336 Full active Not active No
PPA Guarantee
11 Omotosho 2 NIPP 500 Not active Not active No
Guarantee
12 Olorunsogo 2 NIPP 750 Not active Not active No
(nipp) Guarantee
13 Alaoji nipp NIPP 504 Not active Not active No
Guarantee
14 Sapele 2 NIPP 500 Not active Not active No
(nipp) Guarantee
15 Geregu nipp NIPP 435 Not active Not active No
Guarantee
16 Ihovbor nipp NIPP 450 Not active Not active No
Guarantee
17 Calabar NIPP 625 Not active Not active No
(odukpani) Guarantee
18 Gbarain NIPP 225 Not active Not active No
Guarantee
19 Afam vi IPP 650 Full active Full active Self-Supplied
(shell) PPA GSA
20 Okpai IPP 480 Full active Full active Self-Supplied
PPA GSA
21 Trans-amadi IPP 136 Not active Not active No
ipp Guarantee
22 Rivers ipp IPP 180 Not active Not active No
Guarantee
23 Ibom power IPP 198 Not active Not active No
Guarantee
24 Omoku IPP 150 Not active Not active No
Guarantee
25 Paras IPP 85 Active- Full active N/A
Bilateral GSA
Page 15 of 24
Babatunde et al., Cogent Engineering (2023), 10: 2157536
https://doi.org/10.1080/23311916.2022.2157536
Page 16 of 24
Table 2. Privatised sectors’ sample financial statement
2012 N’000 2013 N’000 2014 N’000 2015 N’000 2016 N’000 2017 N’000 2018 N’000
https://doi.org/10.1080/23311916.2022.2157536
Page 17 of 24
Babatunde et al., Cogent Engineering (2023), 10: 2157536
https://doi.org/10.1080/23311916.2022.2157536
20
15
10
0
15-Jan 15-Feb 15-Mar 15-Apr 15-May 15-Jun 15-Jul 15-Aug 15-Sep 15-Oct 15-Nov 15-Dec
make the electricity sector stagnant and unsustainable with limited investment and the system’s
eventual collapse.
The Nigeria Electricity Regulation Commission ensures that the investor’s tariff is fair and
adequate to finance their operations while still making sensible profits from efficient opera
tions. NERC developed a system known as the Multi-year Tariff Order. It is a tool meant for
setting cost-reflective tariffs to enable funding and functioning of the power sector. The
minor review is twice a year, considering ± 5% changes in a defined parameter such as
generation capacity, gas prices, inflation, and exchange rates corresponding to tariff imple
mentation adjustment. Similarly, a series of significant reviews in 5 years is expected to cover
the costs of generating electricity, transmission system usage, regulation, market operation,
and distribution charges. However, MYTO 2015 is based on specific parameters and assump
tions that have seriously affected other factors and have become unrealistic. Moreover, the
economic parameters used have also changed rapidly and in no correlation to the 5 years
duration of the review. As a result, there has been a tariff shortfall, meaning Discos’ allowable
revenue has fallen short of what the real revenue is supposed to be. Table 3 shows the
difference in the MYTO Tariff assumption.
(Cost-reflective tariff in the Nigerian electricity supply industry (NESI)—Businessday NG, 2020)
The table clearly shows a huge difference between the forecast and the reality of
December 2019. The overall effect of this is the tariff shortfall that the private investors are
experiencing. It is non-cost reflective of their operations and a dangerous omen for the power
sector’s future.
Page 18 of 24
Babatunde et al., Cogent Engineering (2023), 10: 2157536
https://doi.org/10.1080/23311916.2022.2157536
5.7. Vandalisation
The vandalisation of gas pipelines, transmission, and distribution lines is rampant and poses
a serious threat to private investors. There is also colossal revenue loss associated with this due
to the plant’s risk and cost of non-operation. The vandalisation of gas pipelines and power
infrastructure has limited the development of the power sector. Table 4 captures some of the
vandalisation recorded
6. Way forward
Like other sectors of Nigeria’s economy, the policies directed at improving Nigeria’s electricity
sector have been largely imported, with few homegrown policies addressing Nigeria’s pecu
liarities. In this work, we put forward a proposed power sector structure that can solve the
sector’s many protracted problems; the structure will, in turn, substantially turn around the
national economy. This proposed structure is wholly deregulated, liberalised, and subject
strictly to demand and supply. Figure 12 shows that the subsector’s generation, transmission,
and distribution freely and flexibly, without regulatory restrictions, interact with one another
and the consumer. The key differences between this model and the existing structure are;
● Generation companies of different categories and sizes freely and directly trade with distribution
companies and consumers while trading with the transmission grid operators.
● The exchange of services/product for revenue is a two-way interaction among all sectors driven
solely by the free-market force of demand and supply.
● Multiple transmission grid operators with government-licensed trade associations enforce a framework
for an operation that makes these grids easy to integrate into a single, smart national grid.
6.1. Generation
The most discussed topic in Nigeria’s electricity sector is the sector’s generation capacity; as stated
earlier in this work, the national grid’s transmission capacity is less than the total operational
capacity of available grid power plants. This capacity shortage shows that generation capacity
Page 19 of 24
Babatunde et al., Cogent Engineering (2023), 10: 2157536
https://doi.org/10.1080/23311916.2022.2157536
shortage is not the sector’s most critical challenge, contrary to popular belief. Frequent grid
collapse and power rejection by distribution companies (Discos reject 17,657MW as power outage
persists—Punch Newspapers, 2020) show that even if more power is generated, these capacities
cannot be wheeled to the consumers. This notwithstanding, Nigeria is in dire shortage of genera
tion capacity. The solution to this shortage is not more budget to deliver more power plants (as
most socio-political analysts believe). However, the solution lies in the right economic policies that
can attract needed investment from private investors who can key into the model described above
for opportunities.
If supported with the right policies, this model will promote a wide range of investors. Most
importantly, medium-scale investors will come into the sector as off-grid generation, captive, and
embedded generation operators; these solutions can be delivered without the hindrance of the
national grid capacity shortage. Many value chains in the electricity sector and sectors in primary
energy sources will also take a new life of their own from these activities. Typically the proliferation
of these embedded, captive, and off-grid plants will spur investment opportunities in sectors like
natural gas distribution; these are definite progressions driven by free-market forces and
opportunities.
6.2. Transmission
In the model proposed, less emphasis is on the national grid as it is currently operated. Total
deregulation and liberalisation of Nigeria’s electricity market will attract investors into the national
grid sector. The current grid capacity cannot handle the capacities this model can deliver hence
the investors’ involvement in driving toward a smarter grid. The smart grid comprises as many
mini-grids of various sizes and capacities as there can be across the nation, developing as
described under generation in the last paragraph; a privatised TCN only becomes a major player
in this free market scheme through it is existing vast infrastructure.
The main policy objective that the national grid regulations would seek to achieve would be
a framework for integration/interlinking of these mini-grids with sizeable capacities into a new
smart national grid. Today, there are technologies to achieve these interlinks. However, only
investors in a deregulated and liberalised market can bring them to bear. The government’s core
objective and responsibilities in this model are national security, not pricing or other economic
decisions. They only set the framework for regulating a deregulated electricity sector to preserve
national security, public safety, and consumer rights.
Page 20 of 24
Babatunde et al., Cogent Engineering (2023), 10: 2157536
https://doi.org/10.1080/23311916.2022.2157536
6.3. Distribution
Contrary to the most popular public opinion in Nigeria, the weakest link in the Nigeria electricity
sector is the distribution sub-sector because infrastructure is most deficient in this subsector. The
deficiency impacts the sectors’ entire value chains. Most studies and public discourse have been
about generation capacity deficiency. The alarming and worse deficit in the distribution system is
rarely discussed; hence the public’s public perception sadly influences political and economic
decisions, especially by the government. In the model proposed in this work, the government is
expected to go further than its recent efforts, including privatising the distribution companies and,
most recently, the service-reflective tariff by NERC. Policies that totally deregulate and liberalise
the sector are needed to attract the right investment to bridge the distribution system’s infra
structure gap.
7. Conclusion
In the Nigerian Government, 1999 proposed implementing diverse reforms that would transform
the state-owned vertically operated electricity industry to a more efficient unbundled market
consisting of various agencies and companies coordinated by an independent regulator. The
restructuring has improved the infrastructure capacity and service deliveries across the market’s
value chain. Based on the discussions from the previous sections, the actors in the NESI pay
attention must propose effective ways of addressing the various challenges highlighted in this
study. Although the NESI is now deregulated and the private sector is driven, its significance to
industrial development and economic growth will entail strategic intervention from the govern
ment. The following are the findings of this study:
● Various reforms have been aimed at raising the Nigerian electricity sector’s generation capacity to
40 GW by 2020, and it is clear that this is not achievable, with the current total installed capacity still
below 13 GW. Operational 3,879.MW generation capacity is smaller than the 5,300 MW transmission
wheeling capacity; nevertheless, a system failure is likely to occur if the total installed 12,522 MW
capacity were transferred into the transmission network. The transmission network is radial and, as
such, vulnerable to low reliability and frequent failure. Nevertheless, about 80% of Nigerians have
decentralized off-grid 8–14 GW backup power sources such as fossil-powered generators and
inverter solar PVs and use them. Still, there is electricity trade between Nigeria and some West
African Power Pool members amidst Nigeria’s lack of electricity supply to the extent that member
countries owed Nigeria a total amount of N29.97 billion.
● The framework for electricity tariffs has grown over the years in Nigeria, with a non-cost-reflective
tariff. Cost-reflective tariffs are proposed to replace non-cost-reflective tariffs with potential service-
reflective tariffs. MYTO comprehensively optimises and analyses the necessary operating expenses,
overhead, and a real return on investment to build straightforward tariffs with integrity and wide
spread adoption. Non-cost-reflective MYTO 2015 is focused on essential criteria and projections,
which have become impractical and have seriously affected other variables. Future changes to
tariffs will now be focused on deals and agreements between DisCos and groups of customers. If
DisCos fails to achieve performance targets, bonuses may be used to repay customers. The IPPs are
only charged for their running expenses and not for investments. This module is significant as it
establishes the viability of the generation for private investment. It is also considered critical by the
Page 21 of 24
Babatunde et al., Cogent Engineering (2023), 10: 2157536
https://doi.org/10.1080/23311916.2022.2157536
Page 22 of 24
Babatunde et al., Cogent Engineering (2023), 10: 2157536
https://doi.org/10.1080/23311916.2022.2157536
Page 23 of 24
Babatunde et al., Cogent Engineering (2023), 10: 2157536
https://doi.org/10.1080/23311916.2022.2157536
© 2023 The Author(s). This open access article is distributed under a Creative Commons Attribution (CC-BY) 4.0 license.
You are free to:
Share — copy and redistribute the material in any medium or format.
Adapt — remix, transform, and build upon the material for any purpose, even commercially.
The licensor cannot revoke these freedoms as long as you follow the license terms.
Under the following terms:
Attribution — You must give appropriate credit, provide a link to the license, and indicate if changes were made.
You may do so in any reasonable manner, but not in any way that suggests the licensor endorses you or your use.
No additional restrictions
You may not apply legal terms or technological measures that legally restrict others from doing anything the license permits.
Cogent Engineering (ISSN: 2331-1916) is published by Cogent OA, part of Taylor & Francis Group.
Publishing with Cogent OA ensures:
• Immediate, universal access to your article on publication
• High visibility and discoverability via the Cogent OA website as well as Taylor & Francis Online
• Download and citation statistics for your article
• Rapid online publication
• Input from, and dialog with, expert editors and editorial boards
• Retention of full copyright of your article
• Guaranteed legacy preservation of your article
• Discounts and waivers for authors in developing regions
Submit your manuscript to a Cogent OA journal at www.CogentOA.com
Page 24 of 24