(iii)Doubling Projects
To exploit the full potential of coal loading, doubling of the 195 km Talcher-Paradeep section
has been completed. Doubling of 264 Km long Titilagarh – Vizianagaram line has also been
completed for traffic flow to VSKP Port. The doubling work between Khurda Road to Puri (43
kms) is in progress, out of which, the work upto Delang (15 kms) has been completed. The
doubling between Sambalpur-Rengali (22.7 Km) has been completed during the year 2011.
3 New Talcher-Bimlagarh 810.78 2003- 106.09 30.00 Land acquistion & Major
Line new line (154 km) 04 Bridge works are in
progress. 136.86 Ac. of
land out of 258.93
Ac.taken over between
Km.0-25.Tender for Earth
work and minor bridge
between Km.10.5 to 18.5
awarded. Handing over of
Govt. & Forest land is still
awaited.
Likely date of completion
(Talcher to Sunakhani 20
Km) :31.12.2013 subject to
early availability of land.
GAUGE CONVERSIONS
4.00 G.C. Naupada- 168.88 1997- 182.30 2.00 The entire section from
Gunupur(90km) 98 Naupada to Gunpur
completed and opened for
passenger traffic on
21.08.2011.
DOUBLING PROJECTS
5 Doubli Jharsuguda - 201.17 2005- 153.69 40.00 Brundamal Yard (3 New
ng Rengali (25.6 Km) 06 lines) commissioned
doubling. .Temporary Diversion
between Lapanga-
Brundamal Block Section
opened for traffic on
11.4.2012. E/W, Bridges
and track linking woks are
in progress.
Likely date of completion:
30.06.2013.
6 Doubli Vizianagaram- 194.89 2006- 153.45 40.00 Kantakapalli - Kottavalasa
ng Kottavalasa-3rd line 07 (7.75 kms) & Vizianagaram
(34.70 km) - Korukonda (10.65 kms) :
Track linking completed
and Engine rolled on
28.3.2012 & 30.3.2012
respectively.
Temporary diversion line
between ALM-KPL
commissioned;Heavy
regrading in existing
Down line near
Kantakapalli Yard
completed.Remaining
bridge and track linking
works are in progress.
Likely date of completion :
31.05.2013.
18 ROB/ Dhenkanal - 15.170 2009- 0.1144 1.0000 Road diversion and all the
RUB Sadasibpur ROB in 0 10 12 Piles in foundation
lieu of LC No. CT-41 completed; Pile cap work
in progress.
Likely date of completion :
30.06.2013.
19 ROB/ Budhapank-Talcher 19.240 2009- 0.1057 1.2052 Earthwork for road
RUB ROB in lieu of LC 0 10 diversion completed.
No.CT-81 Likely date of completion :
30.09.2013
20 ROB/ At Sukinda Road 11.322 2009- 1.1404 2.1521 All piles including pile cap
RUB Yard /Man 5 10 in foundation completed;
Gobindapur - ROB All four piers and one bed
in lieu of LC No.16 block completed.
Likely date of completion
:28.02.2013