Professional Documents
Culture Documents
Rural Energy Master Plan - REMP
Rural Energy Master Plan - REMP
Biomass as primary Dependence on biomass-based fuels for cooking reduced to 65 percent of the rural
cooking fuel population. Corresponding development to 20 percent in urban areas shall ensure an
overall national biomass dependence reduced to below 50 percent.
Adoption of ICS Improved Cooking Stoves (ICS) used by 40 percent of the 65 percent biomass
dependent rural population. 3.7 million households must obtain ICS by 2030; 2.5
million of these in rural areas (assuming 60 percent ICS users among the 20 percent
biomass dependent urban population).
Adoption of LPG increased to 21 percent market share in rural areas. The main LPG development is
Liquified Petroleum expected to be ensured in cities, towns, and district centres, to reach 30 percent of
Gas (LPG) as cooking the national population combined. Capacity for LPG import and storage will have to
fuel reach approximately 370,000 MT per year, and two million rural households will need
to obtain stove and cylinder.
Wood fuel demand Significant reduction of biomass energy consumption compared to 2016 (more than
60 percent reduction from the assumed Business-as-Usual scenario in 2030.
It is proposed that REA take a lead role in coordinating and catalysing the required response, which has
been organized into three separate programmes implementation:
• REA Cooking Energy Capacity Building Programme (REACE). Builds capacity within REA for
executing and coordinating interventions related to cooking energy.
• Transitioning to Improved Cooking Services Programme (TrICS). A is mechanisms directed
IC RE ’ k -based expansion of rural energy services.
• Achieving Clean Cooking Energy Solutions Programme (ACCeS). Aims at expanding clean
cooking solutions such as LPG and cooking with electricity to rural Tanzania through provision of
support to commercial actors/NGOs.
TrICS and ACCeS both include financial support to projects as well as development of technical expertise
and aim at enhancing affordability of cooking fuels and technologies; promoting scale-up of supply chains
through entrepreneurship and micro-credit services; social marketing of energy technologies; and
engaging pilot end users of energy solutions across households, institutions, and macro levels.
The figure below presents the three programmes, along with recommendations for improvements in the
enabling framework.
1 In addition to the above, approximately USD 300 million for FY 2022/23 and USD 243 million for FY 2023/24 are budgeted for costs related to on-going electrification
projects. These costs are not included in the analysis, as it is assumed that they largely are covered by existing donor commitments.
2.1 Objective
The ov j RE P “ R E RE -to-date
tool for planning and implementation of rural energy provision meeting target set in the National
Energy Policy, National Strategy for Growth and Poverty Alleviation (MKUKUTA), and Sustainable
Energy for All (SE4All) goals. The plan is also aimed at exploitation and utilisation of renewable energy
”
The high-level objectives pertaining to electricity and clean cooking are found in the figure below.
The analysis and recommendations contained in this REMP builds on extensive data collection efforts
and stakeholder consultations. Based on detailed situational analyses, the RESP (Annex A) and CEAP
(Annex B) provide extensive analyses and recommendations as to how the overall objectives of the
REMP can be reached. The specific analytical approach applied for each of the sub-reports are outlined
in the respective Volumes and summarized in Chapter 2 (Electricity) and Chapter 3 (Improved and
Clean Cooking) of this Main Report. Here they are further packaged into six programs with
accompanying projects and activities for implementation.
Chapters 2 and 3 also provide a policy, regulatory, and institutional analysis for electricity and cooking
respectively to identify barriers to implementation and provide recommendations as to how these can
be addressed.
In order to ensure timely implementation and effective monitoring of progress, chapter 4 lays out a
REMP implementation strategy including detailed timelines, while chapter 5 provides a high-level
financing plan as a point of departure for the forthcoming REA resource mobilization plan. Finally,
chapter 6 contains the REMP Monitoring and Evaluation Framework.
2.3 Definitions
The adaptation and successful implementation of this REMP relies on the joint and collaborative efforts
of a broad set of institutions, organizations, private sector companies, and individuals. For these
diverse groups to coordinate their efforts and allocate resources correctly, it is important that the
applicable targets and strategies are clearly defined.
Within the international and Tanzanian energy access space, there are, unfortunately many examples
of terms that overlap, are used interchangeably, have changing definitions, and even contradict one
another. There is, for example, a tendency to rely on binary measurements of access or connectivity
to modern energy services (have/don´t have). These fail to capture several key issues, such as how
poor electricity supply from the grid may limit its usefulness. Therefore, this REMP applies the SE4All
Electricity
Access to electricity Population living in localities served by electricity and thus reaping benefits from
services these services with an opportunity to gain connectivity.
Access to electricity services = Total number of people living within a radius of 600
meters from the secondary side of distribution transformer/Total Population
Connectivity Population being directly served by either grid-based electricity services or stand-
alone systems, providing at least Tier 2 access.
Connectivity to electricity services = Total Number of Connected Households/Total
Population
Low-cost Distribution technologies for electricity supply that deviate from international
Technologies design standards but can be sufficient in rural areas with low load profiles
typically found in rural areas in Sub-Saharan African. Their purpose is to reduce
costs while ensuring appropriate quality for the consumers.
Micro-grid A micro grid consists of one or several very small power production units (up to
100 kW) such as solar PV + storage. Power is distributed via LV lines to a group of
consumers, such as a small village or a group of households.
Provides “Connectivity”.
Mini-grid A mini grid consists of one or several power production units (for example hybrid
PV + diesel or wind + diesel) of a capacity ranging from a 100 kW to a 10 MWs.
Power is distributed to a limited geographical area, such as one or more villages
via MV and LV distribution lines. Could be connected to the national grid from
establishment or at a later time.
Provides “Connectivity”.
Pico-PV products Pico systems consist of a single item (e.g. lamp or mobile charger) powered by
any source of energy ranging from a few watts up to ca 200 W that is not
connected to any appliance in the household and is used for one specific energy
purpose.
Does NOT provide “Connectivity”.
Private mini-grids A mini-grid owned and operated by any legal entity other than TANESCO.
Stand-alone systems Technologies and products that provide a minimum electricity service level
(typically Tier 2) to specific households, businesses or institutions that are not
connected to the main grid or a mini- or micro grid with typically less than 20 Wp
installed. Both produces and supplies electricity in one location and serves one
beneficiary – e.g. a household. This definition encompasses solar home systems
(SHS), but not Pico-PV products.
Provides “Connectivity”.
TANESCO isolated An electricity grid that is operated by TANESCO but is not inter-connected to the
grid national grid.
Provides “Connectivity”.
Clean Cooking
Biomass energy Charcoal and firewood, but also briquettes, pellets and similar solid biomass
Cooking solutions Cooking solutions are referred to as the combination of a cookstove and a type of
cooking fuel taken together
Cooking system A cooking system includes all cooking solutions being used, as well as the cooking
location and ventilation
Improved cooking Refers to a household context that has met at least Tier 2 standards of the Multi-
services Tier Framework (MTF) across all six measurement attributes but not all for Tier 4
or higher. Household contexts with a status of MTF Tier 2 or Tier 3 are considered
in Transition.
Improved cookstoves Fuel-stove combinations based on biomass energy that achieve emissions
(ICS) performance measurements of Tier 2 or Tier 3, following ISO/TR 19867-3:2018
In line with the stated policy preferences of the GoT and building on the extensive grid expansion that
has taken place over the past years, it is proposed to extend the grid to 2,550 rural settlements in the
REMP database that are not part of existing electrification efforts, but that meet the following
requirements (see section 4 of RESP for further details):
• Not located inside the limits of National Park, Game and Forest, or other protected areas;
• Not located on isolated islands without existing MV lines;
• Less than 30 kilometres from existing MV lines;
3 Tanzania's Sustainable Energy for All Action Agenda. Ministry of Energy and Minerals: Dar es Salaam.
The following sections outline the key features of each programme, list their associated projects and
activities, and involvement of relevant stakeholders as a basis for detailed scoping and planning for
execution. Details related to implementation strategies and financing are found in chapters 5 and 6 of
this REMP Main Report.
Nearly all the identified grid strengthening projects are already included in the PSMP 2020 update but
need to be prioritized for immediate planning and implementation to avoid severe supply problems
resulting from the planned rural access expansion.
The table below outlines main activities under each project with tentative timing and implementing
partners. Implementation strategies, financing, and monitoring and evaluation is discussed in chapters
4, 5, and 6 respectively.
Table 2. NGAP – Projects and Activities.
1.3 Construction work and commissioning Target areas Year 2-5 TANESCO,
contractors
The RESP identifies a 400 kV transmission line from Kinyerezi to Arusha as critical to meeting the
existing and future demand in Northern Tanzania. The project is included in the PSMP 2020.
2.3. Construction work and commissioning Target areas Year 2-5 TANESCO,
contractors
3.3. Construction work and commissioning Target areas Year 2-5 TANESCO,
contractors
4.3. Construction work and commissioning Target areas Year 2-5 TANESCO,
contractors
5.4. Construction work and commissioning Target areas Year 2-5 TANESCO,
contractors
6.3. Construction work and commissioning Target areas Year 2-5 TANESCO,
contractors
7.3. Construction work and commissioning Target areas Year 2-5 TANESCO,
contractors
Costs
The table below contains high-level budget estimates for the seven projects under NGAP. 10 percent
have been added to the capital expenditure to cover feasibility studies, project management,
construction supervision, contingencies and other related costs. Please refer to the PSMP 2020 for
further details on capital costs. Project financing is discussed in chapter 6 of this report.
Table 3. NGAP - High-level budget estimates.
Cost
Project
(USD million)
8: Feasibility studies and administration (10 percent of total capital expenditures) 140
MoE Overall programme overseer Coordinate interventions under NGAP with other
policy priorities.
REA Partner to TANESCO in program Ensure coordination between NGAP and other
planning programmes under this REMP.
Funds from GoT allocated to Less funds received Seek funds from alternative
TANESCO than requested sources or scale down
activities
Funding from development partners Less or no funds Seek funds from alternative
to match provisions by GoT allocated from sources or scale down
development partners activities
Programme To expand the national grid to all rural areas where this can be done in a cost-
Objective efficient manner.
2: RGAP Wave 1
3: RGAP Wave 2
In order to properly organize this electrification project, the RESP divides the scope into five zones as
detailed in the figure below. The boundaries of each zone, along with details on which locations are
included in the first and second wave respectively are found in the RESP.
The table below outline main activities proposed to achieve planned objectives, with tentative timing
and implementing partners. It must be noted that the load-flow studies found in the REDP should be
updated once the scope of HEP (electrification of all 37,610 unelectrified hamlets) has been
georeferenced. The hamlets that can be electrified without investments in the grid over and above
what is outlined in NGAP should be given priority in implementation.
Table 7. RGAP – Projects and Activities.
1.1 Scope verification, further load-flow studies All regions Year 1 REA, Consultant
based on georeferenced scope for HEP, detailed
electrical studies 4 and staging of projects
1.2 Preparation of relevant tender documents for All regions Year 1 REA, Consultant
contractors
2.1 Construction and commissioning, Lot 1 Relevant Year 2-4 REA, consultant,
(Central) regions contractors
2.2 Construction and commissioning, Lot 2 Relevant Year 2-4 REA, consultant,
(East) regions contractors
2.4 Construction and commissioning, Lot 4 Relevant Year 2-4 REA, consultant,
(South) regions contractors
2.5 Construction and commissioning, Lot 5 Relevant Year 2-4 REA, consultant,
(West) regions contractors
3.1 Construction and commissioning, Lot 1 Relevant Year 3-8 REA, consultant,
(Central) regions contractors
3.2 Construction and commissioning, Lot 2 Relevant Year 3-8 REA, consultant,
(East) regions contractors
3.3 Construction and commissioning, Lot 3 Relevant Year 3-8 REA, consultant,
(North) regions contractors
3.4 Construction and commissioning, Lot 4 Relevant Year 3-8 REA, consultant,
(South) regions contractors
3.5 Construction and commissioning, Lot 5 Relevant Year 3-8 REA, consultant,
(West) regions contractors
4.1 Include activities to promote productive use All regions Year 2-8 REA, microcredit
of electricity (PUE) in all RGAP projects providers
4.2 Implement connection subsidy for all rural All regions Year 2-8 MoE, REA,
consumers TANESCO
Costs
The table below contains high-level budget estimates for the five projects under RGAP. 10 percent
have been added to the capital expenditure to cover feasibility studies, project management,
construction supervision, contingencies, and other related costs. Cost-breakdowns for the projects
originating in the REMP database can be found in the Annex C.
Table 8. RGAP - High-level budget estimates.
Cost
Project
(USD million)
1: Scope verification 55
Total 4,025
Funds from GoT allocated to REA Less funds received than Scale down activities
for implementing RGAP requested
6 Cost of electrifying 37,610 unelectrified ha “F R RE P III 0 ” (now re-named HEPP), applying the Bank of Tanzania USD/Tsh
average exchange rate of 2298.5843 applicable on April 4th, 2022
7 Based on experience from PUE programmes under REDP phase 1
Funding from development Less or no funds allocated from Scale down activities
partners to match provisions by development partners
GoT
There is sufficient grid capacity If the main grid is not Implement required NGAP
for connection of new projects strengthened in parallel with grid strengthening
grid electrification of rural areas, measures in parallel with
provision of reliable access to grid electrification
electricity might not be possible.
TANESCO has financial capability TANESCO has not enough funds Ensure cost-reflective
to maintain grid to ensure maintenance of new tariffs
lines
Power losses and voltage drops Energy losses increase Validate network
dramatically due to voltage extensions with detailed
drop. Actual network collapse electrical studies
due to a poor network analysis
Overall Objective To provide reliable electricity supply to scattered households and remote
locations where grid extension is not a viable option
Given the vibrant developer community still present in Tanzania, and that Tanzania has one of the best
regulatory frameworks for private mini-grids in Africa it is deemed appropriate that the private sector
is tasked with serving the locations which are recommended for electrification through mini-grids. This
reduces the need for scares public investment resources, and, given proper regulatory oversight,
ensures that international best practices are leveraged. Pending further analysis, 20-year concessions
for all mini-grid within each of the five zones are envisioned, complete with PUE-components to induce
demand.
In order to properly organize the programme, the 313 mini-grids are divided according to five
geographical zones, as indicated in the figure below.
The figure below presents the number of mini-grids and aggregated investment costs per zone.
The table below outline main activities proposed to achieve planned objectives, with tentative timing
and implementing partners.
Table 12. BGAP – Main Activities.
1.2 Tender for private sector developers REA HQ Year 1 REA, EWURA,
consultant
3.1 Streamline best practice into Dodoma Year 1 MoE, REA, EWURA,
Tanzanian rules and regulations Consultant
Costs
The table below contains high-level budget estimates for the two projects under BGAP. 10 percent
have been added to the capital expenditure of mini-grids to cover tendering, project management,
construction supervision, contingencies, and other related costs. Detailed cost-data for mini-grids can
be found in Annex D.
Table 13. BGAP - High-level budget estimates.
Cost
Project
(USD million)
Project 1: Tendering of mini-grid concessions from the private sector (including total 205
investment costs for mini-grids)
Total 236
EWURA Regulator of the energy sector Provide required approvals, and regulatory
in Tanzania oversight.
Private Develops, owns, and operates Successful tenderer will develop, own, and
developers private mini-grids operate the relevant mini-grids.
Ports Manages and operates the Supports compliance with existing rules and
Authorities ocean ports and lake ports of regulations for import of goods required for
Tanzania electrification
Funds from GoT allocated to REA for Less funds received Scale down activities
implementing NGAP than requested
1999 Tanzania Development The Tanzania Development Vision 2025 aims to transform Tanzania into
Vision 2025 a middle-income and semi-industrialized nation by 2025, a milestone
that was achieved in 2020.
2009 National Public-Private The main objective of the PPP Policy is to promote private sector
Partnership (PPP) participation in the provision of resources for PPPs. Main resources
Policy earmarked for PPPs include investment capital, managerial skills, and
technology. Participation in PPPs may take place in both productive and
socio-economic services sectors, in which energy is one of them. The
private sector has the leading role in identifying and implementing
PPPs.
2013 National Electrification The National Electrification Investment Prospectus (2013 -2022)
Investment Prospectus stipulates the investments required to advance electrification in a cost-
efficient way. It indicates how the investments should be financed and
determines the institutional, regulatory, and capacity strengthening
measures for the implementation.
2014 Electricity Supply The ESI Reform Strategy and Roadmap (2014-2025) calls for
Industry Reform liberalization of electricity sectors by functional unbundling TANESCO
Strategy and Roadmap into a generation company, a Transmission System Operator, and one
or more distribution companies. The ultimate objective of unbundling is
to facilitate increased private sector participation in electricity markets,
while improving efficiency and reducing costs.
2015 National Energy Policy NEP 2015 aims to attract more private investment and local
participation in the energy sector, improve efficiency and energy
conservation as well as access to modern energy services and increase
the share of renewables in the electricity generation mix.
2015 T z ’ The Action Agenda seeks to integrate the multi-tier efforts that the
Energy for All Action country is implementing towards increasing universal access to energy,
Agenda 2015 energy efficiency and use of renewable energy. With the Agenda, the
Government of Tanzania continues its commitment for the transformation
of its energy sector, and deepen the reforms needed to scale up public
and private investments in the sector to meet its SE4All goal.
2020 Power System Master The Tanzania Power System Master Plan was first developed in 2008,
update Plan and last updated in 2020. It provides an expansion plan for the national
grid in the short- (2024), medium- (2034) and long-term (2044).
2021 The Third Five Year The FYDP III 2021/22 – 2025/26 “ k
National Development infrastructures including roads, railways, water and air transport as well
Plan (FYDP) as reliable access to energy; continue to strengthen the business and
2021 Environmental Policy The Environmental Policy points to sound management of the impacts
of energy development and use to minimise environmental
degradation. This includes promotion of sustainable renewable energy
resources and energy efficiency, as well as sound environmental impact
assessment for energy projects.
Based on the findings and recommendations of the RESP, the table below outlines several
recommendations for strengthening the existing policy framework to meet the objectives of this
REMP.
Table 17. Recommendations for changes in the policy framework for rural electrification.
Recommendation Context
1: Review and T E P C 8 “
update the arises taking into considerations emerging activities, major changes, and developments
National Energy ” I EP
Policy. has changed significantly since 2015, both in Tanzania and globally. Because of the
significant achievements in the energy sector and the changing national and global
environment the current NEP does not fully reflect the future development needs of
Tanzania.
A review is thus recommended to ensure that the policy is updated and relevant to
national development objectives and energy sector challenges, particularly in terms of
technological solutions, sector structuring, and reform.
2. Undertake The NEP states that baseline data and information will be collected as a benchmark for
regular tracking the implementation of the policy, and that progress reporting will be done
monitoring of semi-annually. The 2020 Joint Energy Sector Review noted that capacity required to
NEP undertake these monitoring and evaluation activities are under development at the
implementation Ministry of Energy (Norconsult, 2020). It is recommended that progress monitoring and
evaluation is done on a regular basis to track and strengthen accountability for sector
development.
3: Ensure TANESCO plays the key role in efforts to increase connectivity and improve quality of
acceptance of supply for Tanzanian electricity consumers. It is clear that meeting the increased
cost-reflective on- demand from planned access expansions, while maintaining its current asset base will
grid tariffs to pose a significant financial and operational challenge for TANESCO in the years to
achieve sector come. However, Tanzanian on-grid retail tariffs are not cost-reflective, a fact that
sustainability requires urgent action to put the sector on a path to sustainability and enable
TANESCO to make timely investment in system expansion, maintenance, and
rehabilitation.
5: Consider The cost of connection and house wiring constitutes a significant barrier to connection
subsidies to for many rural households which live within reach of the grid. In order to bridge the
reduce cost of gap between access and connectivity it is recommended that subsidies to reduce the
cost of connection are continued. However, these need to be funded either through
connection and direct subsidies from government/development partners or cross-subsidies from other
house wiring electricity consumers to ensure the financial sustainability of TANESCO.
6: Strengthen Tanzania Bureau of Standards (TBS) is charged with controlling that imported and
control of off-grid locally produced off-grid equipment such as solar homes systems comply with
equipment governing standards and regulations. In order to safeguard the interests of consumers
that are may not have the opportunity to get a metered connection in their homes for
many years to come is recommended that the bureau is provide with sufficient
resources for increased control activity.
2001 EWURA Act Established EWURA to regulate tariffs for electricity trade in the country, and
promote the availability of regulated services to all, including low-income, rural,
and disadvantaged consumers.
2004 Environmental Act to provide for legal and institutional framework for sustainable management
Management Act of environment; to outline principles for management, impact and risk
assessments, prevention and control of pollution, waste management,
environmental quality standards, public participation, compliance, and
enforcement.
2005 Rural Energy Act Established the Rural Energy Agency to enhance energy access in rural areas.
2008 Electricity Act Provides facilitation and regulation of generation, transmission, transformation,
distribution, supply, and use of electric energy, including rural electrification.
2009 Public-Private Regulates private and public sector participation in the provision of resources
Partnership act for PPP enterprises.
2011 Public Provides the legal framework for public procurement in Tanzania, including anti-
Procurement Act corruption practices.
In addition, several regulatory instruments have been put in place. These are listed in Annex E to this
report.
The table below outlines several recommendations for strengthening the regulatory framework to
meet the objectives set out in this REMP.
Table 19. Recommendations for changes in the regulatory framework for rural electrification.
Recommendation Context
1: Clarify roles There is a need for the Government to clarify how and where there is room for the
and private sector to contribute towards the electrification of Tanzania. This is particularly
responsibilities of important in the mini-grid space, where experienced and reputable developers are
the private sector ready to invest when and if they get predictability related to tariffs and certainty about
where the grid will be expanded and when.
2: Ensure Investments in renewable energy generation and mini-grids require significant upfront
reasonable capital investments. In order to increase private-sector investments, the GoT therefore
incentives for looks to ensure fair, balanced, and predictable framework conditions as reflected in
private sector the 2020 SPP rules.
investments
3: Strengthen the As the role of the private sector increases, so does the importance of regulatory
capacity for oversight and ability to enforce existing rules and regulations. The 2020 Joint Energy
regulatory Sector Review finds that there is “limited capacity for rolling out and enforcing legal
oversight and and regulatory provisions, for example establishing a clear mechanism for
enforcement enforcement of the legal framework (including penalties); building capacity for the
enforcement of the legal and regulatory provisions; and ensuring local standards of
4: Technical While key institutions such as REA and TANESCO have considerable capacity to
assistance and implement rural electrification projects, as demonstrated by their success over the
capacity building past years, there is still room to improve with regards to regulatory oversight. This
for improved includes the institutionalisation of competence in Geographic Information Systems
oversight (GIS). Other examples include the private sector´s use of the Tanzanian National e-
Procurement Systems. Improved use of such systems will enhance the regulatory
oversight capacity of the Government and augment service delivery.
5: Consider According to the Environmental Impact Assessment (EIA) and Audit Regulations, all
targeted energy projects are classified as Type A, therefore requiring a mandatory EIA to be
simplification to carried out prior to the commencement of the project. Several SPPs, especially solar
the energy developers, have raised concerns on why smaller renewable projects which are
environmental
considered to be clean with little environmental risks be subject to the same EIA
and social
procedures as the large energy projects (e.g. thermal power and hydro-electric dam).
framework for
small power The mandatory EIA requirements are considered by some to have a negative impact on
plants the rate of investment in renewable energy, thus limiting the access to energy services
in rural areas.
It is recommended that the National Environmental Management Council (NEMC)
consider review and amendment of the respective regulations and laws which were
developed while the renewable energy (solar and others) in Tanzania was at infancy
stages among other issues to:
• Provide indicative number of days and charging rates for EIA consultants in
undertaking the assessment based on size and nature of the project; and
• Allow bundling of projects to have one environmental clearance certificate.
Recommendation Context
1: Clarify roles and Whereas REA is the key institution promoting and implementing rural
responsibilities electrification projects, TANESCO remains the most critically important stakeholder
between REA and for quality, reliability, and long-term sustainability of rural electricity supply. REA is
TANESCO in rural responsible for development and construction of rural electrification projects
electrification which are formally handed over to TANESCO on commissioning. However, as
planning and owner of existing and ultimately new infrastructure, TANESCO must have a formal
implementation and key role in planning, setting priorities and overseeing implementation.
A disconnect between the planning/implementation institution (REA) and the
owner/operational institution (TANESCO) could pose a risk to the long-term
sustainability of rural electricity access expansion.
2: Strengthen capacity TANESCO takes over a large amount of new rural electrification infrastructure from
for operation and REA each year. Sound operation and maintenance of these assets by TANESCO
maintenance of rural requires (i) sufficient financing and budgets, and (ii) operation and maintenance
electricity networks plans and competence at district level offices responsible for rural infrastructure.
In addition to establishing cost-reflective tariffs, it is therefore recommended that
TANESCO strengthen their internal capacity related to maintenance of rural
distribution infrastructure.
3: Strengthen M&E The MoE is responsible for regular progress monitoring and reporting on policy
capacity in the implementation. However, the 2020 Joint Energy Sector Review noted that
Ministry of Energy capacity required to follow up is under development at the Ministry, and
monitoring and evaluation of policy implementation is not undertaken as
stipulated in the 2015 NEP. The MoE is recommended to establish dedicated
capacity for policy implementation and progress monitoring and evaluation (M&E).
12 Sustainable Energy for All Gender Action Plan, Tanzania Ministry of Energy, 2018
13 Ibid
14 Global Assessment Report on Biodiversity and Ecosystem Services, Intergovernmental Science-Policy Platform on Biodiversity and Ecosystem Services, 2019
4.1 Targets
The overall objective of the CEAP is to foster a vibrant rural energy sector through a concerted effort
between public and private sector to achieve the 2030 targets, with REA taking a lead role in
coordinating and catalysing projects.
Targets have been set in line with national policies and development strategies including the SE4All
Action Plan15 , and international development goals. Specifically, the CEAP aims to contribute to the
goal that 75 percent of the population in Tanzania should have access to modern cooking solutions by
2030. As evident from the figure below, achieving this target will require a significant step-up from
business-as-usual. In fact, 42 million people will have to gain access to modern cooking solutions over
the 8-year period covered by this REMP – 62 percent more than what is assumed under a business-as-
usual scenario.
In the CEAP, implications of the SE4All goals in terms of uptake of improved and clean cooking has
been simulated to map the required progress in different population segments. Based on projections
and analyses regarding the relative potential of various solutions to contribute to large-scale transition
15 Tanzania's Sustainable Energy for All Action Agenda. Ministry of Energy and Minerals, 2015.
Biomass as primary Dependence on biomass-based fuels for cooking reduced to 65 percent of the
cooking fuel rural population. Corresponding development to 20 percent in urban areas shall
ensure an overall national biomass dependence reduced to below 50 percent.
Adoption of ICS Improved Cooking Stoves (ICS) used by 40 percent of the 65 percent biomass
dependent rural population. 3.7 million households must obtain ICS by 2030; 2.5
million of these in rural areas (assuming 60 percent ICS users among the 20
percent biomass dependent urban population).
Adoption of Liquified LPG increased to 21 percent market share in rural areas. The main LPG
Petroleum Gas (LPG) development is expected to be ensured in cities, towns, and district centres, to
as cooking fuel reach 30 percent of the national population combined. Capacity for LPG import
and storage will have to reach approximately 370,000 MT per year, and two
million rural households will need to obtain stove and cylinder.
Share of rural 60 percent of the population in rural areas achieves access to improved or clean
population with access forms of cooking energy. This corresponds to 12.3 million households nationally,
an increase of almost 11 million from the 2016 baseline (assuming 92 percent of
urban populations, implying 75 percent on national level).
Wood fuel demand Significant reduction of biomass energy consumption compared to 2016 (more
than 60 percent reduction from the assumed Business-as-Usual scenario in 2030.
Achieving these developments by 2030 will require massive, coordinated public efforts, combined with
a focus on facilitating market development through an enabling framework and creation favourable
conditions for commercial actors, building awareness and promoting behavioural change.
Implementation of the CEAP will therefore mark a significant step-up of national efforts to improve
health and livelihoods and reduce pressure on forest reserves and the environment, as outlined in the
subsequent section.
TrICS and ACCeS build on market-based approaches for scaling up access to improved and clean
cooking in rural Tanzania:
• TrICS promotes fuel and stove solutions ranked as VPT 16 Tier 2-3 (e.g. ICS for biomass energy).
• ACCeS promotes fuel and stove solutions ranked as VPT Tier 4 and 5, regarded as clean cooking
services (e.g. eCooking, biogas, natural gas and LPG).
Both programmes include financial support to projects as well as development of technical expertise
and aim at enhancing affordability of cooking fuels and technologies; promoting scale-up of supply
chains through entrepreneurship and micro-credit services; social marketing of energy technologies;
and engaging pilot end users of energy solutions across micro, meso, and macro levels.
The following sections outline the key features of each programme, list their associated projects or
activities, proposed implementation strategy and involvement of relevant stakeholders as a basis for
detailed scoping and planning for execution.
RE CE’ is to put in place the required internal organization to implement the CEAP,
including routines, knowl RE ’ headquarters and as well as increasing
RE ’ through coordination and collaboration with PO-RALG. Training
staff in cooking energy and related funding modalities will enable coordination and monitoring of
interventions funded by the agency.
Training of REA staff in modern cooking solutions, and in national and international cooking and stove
standards will ensure that the agency has the technical expertise to take a lead for securing improved
and clean cooking services in rural Tanzania. REACE also foresees development of a system for regional
planning of interventions by using GIS. REA will take a role in monitoring and evaluating interventions
across the whole cooking energy sector by supporting surveys in 2026 and 2030. In so doing the REACE
builds on the SE4All Action Agenda for Tanzania.
2: Increased capacity for reaching remote rural areas with cooking energy
interventions
The table below outlines main activities proposed to achieve planned objectives, with tentative timing
and implementing partners. It is worth noting that implementation of the global Impact of Access to
Sustainable Energy Survey (IASES) is proposed for Tanzania in order to support the monitoring and
evaluation efforts. Please refer to the CEAP for further details on IASES.
Table 23. REACE – Projects and activities.
RE ’
REA HQ, MoE, VPO, REA,
capacity for implementing and supporting Year 1
Dodoma consultant
projects on cooking energy
REA HQ,
1.4 Train staff with relevant expertise for Dodoma
Year 2 - 5 REA
supporting cooking energy interventions
Project 2: Increased capacity for reaching remote rural areas with cooking energy interventions
REA HQ,
Dodoma
R RE ’
Year 1 - 2, 5 MoE, REA, PO RALG
reorganize if necessary Regions and
districts
2.4 Coordinate activities with PO RALG and Target regions REA, PO RALG, private
Year 2 - 8
private sector and districts sector
3.1 Develop a plan for integration of TBS- REA HQ, MoE, MoH, TBS, REA, and
Year 1 and 2
standards and MTF in Tanzania Dodoma other stakeholders
3.2 Train REA staff in the plan for REA HQ, REA, VPO, TBS, and other
implementation of national and Dodoma Year 2
stakeholders
international standards
Project 4: Deployment of geospatial planning tool for planning and monitoring cooking energy
interventions
4.2 Develop software for planning and REA HQ, MoE, REA, software
Year 2 - 3
monitoring Dodoma provider
REA HQ,
4.3 Train REA staff in use of GIS software Year 2 - 3 REA, software provider
Dodoma
REA HQ,
4.5 Apply GIS software RE ’ Dodoma
and other k ’ programmes on Year 2 - 8 REA, PO RALG
cooking energy Target regions
and districts
5.1 Analyse results from IASES REA HQ, Year 1 and 2 NBS, REA, MoE, EWURA,
Dodoma TANESCO and PO RALG
5.3 Apply results from the IASES surveys for REA HQ, Year 2 - 8
monitoring progress towards the REMP and Dodoma REA
SE4All targets
Costs
The table below contains high-level budget estimates for the five projects under REACE. Further details
can be found in the CEAP.
Project Cost
(USD million)
Project 2: Increased capacity for reaching remote rural areas with cooking energy 11
interventions
Total 34
MoE Overall programme overseer Coordinate interventions in REACE with initiatives and
programmes under other energy agencies and
ministries
PO-RALG Oversees policy and interventions Ensure anchoring, relevance and implementation of
regionally, at district level and cooking energy interventions from district level and
locally locally. CEAP nation-wide coordination and monitoring
MIT Oversees industrial development Provide advice and policy coordination for capacity
building under REACE related to industrial
development in the cooking energy sector
MoH Oversees public health protection Provide advice and policy coordination for capacity
from all causes including health building under REACE related to indoor air pollution
impacts caused by cooking
MNRT Oversees policy and regulation for Provide advice and policy coordination for capacity
management of natural resources building under REACE related to supply of biomass
energy
MoCDGWS Oversees policy on community Provide advice and policy coordination for capacity
development and gender equality building under REACE related to gender
TPDC National supplier of petroleum Provide advice and policy coordination for capacity
energy building under REACE related to natural gas and LPG
NEMC National partner to ensure Provide advice on how to meet health and
compliance with environmental environment targets, and ensure that interventions
and health impacts of interventions supported by REA are in compliance with national
regulations
TFS Develops and manages national Collaboration for capacity building under REACE
forest resources related to supply of biomass energy
TANESCO National electricity utility Partner in revision of regional capacity and routines of
REA
TBS Formulates and delivers standards, Provide advice and training for implementation of
safety measures, and conformity TZS473:2019 in Tanzanian cookstove markets
assessment
NBS Provides official statistics to the Implementation of surveys for monitoring impact of
Government, business community interventions in CEAP and by other stakeholders, as
and the public at large per the SE4All targets for the country
Research Conducts research and education Provide training on improved cooking solutions to REA
and on energy staff Provide training on prevention of indoor air
educational pollution to REA staff
institutions
NGOs and NGOs and SMEs working Provide training for REA in Tanzanian cookstove
commercial renewable energy in Tanzania technologies and markets
actors
Funds from GoT allocated to REA for Less funds received than Sensitization/awareness to decision-
implementing REACE requested, or delay of makers on clean cooking; Scale down
funds to implementing activities, or postpone activities
agencies
Funding from development partners to Less or no funds REA prioritises parts of CEAP that can
match provisions by GoT allocated from be conducted without large
development partners investments
Staff competence and capacity for Limited capacity and Hire staff based on competency
implementing CEAP competence for required
implementation
Private sector and government Partners do not commit REA prioritises parts of CEAP that can
institutions engaged in implementation to REACE be conducted without strong
of REACE partnerships
Financial support for IASES II and III No financing received Collaborate with NBS to conduct
lighter version of IASES II and III
Overall Objective To promote access to improved cooking services and stimulate rural energy
markets
17 The term Improved Cooking Services refers to a household context that has met at least Tier 2 standards of the MTF across all six measurement attributes but not all
for Tier 4 or higher.
The table below outlines main activities proposed to achieve planned objectives, with tentative timing
and implementing partners.
Table 28. TrICS – Projects and activities.
1.2 Coordinate/establish regional Target areas Year 2 - 8 MoE, REA, MoH, VPO, PO
partnerships with local stakeholders RALG, TBS, VETA, SIDO, and
private sector
1.3 Develop training material for ICS REA HQ, Dodoma Year 2 - 3 Academic institutions, REA,
TBS, private sector, NGOs,
SIDO, VETA
1.4 Conduct ICS training for entrepreneurs Target areas Year 2 - 4 VETA, SIDO, REA, NGOs,
in ICS private sector
1.5 Support entrepreneurs for testing and Target areas Year 2 - 8 REA, TBS, SIDO
certifying ICS
2.1 Establish a funding line through REF REA HQ, Dodoma Year 2 MoE, REA, MIT
for RBF for large-scale ICS production
2.3 Annual calls for tenders REA HQ, Dodoma Year 2 – 7 REA
2.4 Provide training in ICS design, Dodoma Year 2 - 4 REA, MIT, development
standards and production partners, NGOs, TBS,
private sector
3.2 Use regional stakeholder group to Target regions Year 2 – 7 REA, LGA, consultant,
identify pilot end users in regions, schools private sector
and other institutions
3.8 Awareness campaign on health and Target regions Year 2 - 8 VPO, MoH, NGOs, REA,
environmental impacts from cooking Private sector
3.9 Monitor and evaluate based on IASES Country-wide Year 5 and NBS, REA, MoH, PO RALG
II, III (REACE programme) 8
4.2 Coordinate/establish regional Target areas Year 1 - 8 REA, VPO, MNRT, PO RALG,
partnerships with local stakeholders NGOs, development
partners
4.3 Develop call for projects on REA HQ, Dodoma Year 3 REA, VPO, MNRT, PO RALG,
sustainable biomass energy production NGOs, development
partners
REA Implementing agency of the Identify target regions; Facilitate capacity building of
programme SMEs, commercial enterprises; Provide funding to SMEs,
entrepreneurs and NGOs
MoH Oversees health policy Advice on health effects caused by indoor air pollution
implementation and advise better types of ventilation and cooking
technologies
PO RALG Oversees regional planning and Participate in identification of target regions and regional
interventions stakeholders and collaborate with REA in coordination of
efforts under TrICS.
TRA Collects taxes and levies Collaborate with REA and MoE to lower costs of ICS
NGOs Collaborative partner for Coordinate and implement private sector initiatives in the
intervention of projects ICS sector and biomass energy supply projects
SMEs Small- and Medium sized Produce and sell stoves in targeted locations. Develop a
Enterprises market network of dealers and agents. Produce and sell
stoves, fuels and energy
MIT Oversees industrial Provide advice and policy coordination for capacity
development building under TrICS related to industrial development in
the cooking energy sector
Project Cost
(USD million)
Total 85
Successful implementation of Elements of TrICS may not be TrICS may continue with less
REACE programme implemented institutional knowledge in REA of
cooking energy and new standards.
Enabling policy and regulatory Policy and regulatory Sensitize policy and decision-makers to
framework in place requirements identified in declare clean cooking at national agenda
CEAP not in place
MoE to be capacitated to develop and
effectively monitor policy and
regulations on cooking
TrICS may continue with less
institutional support by other GoT
bodies
Overall Objective To promote access to clean cooking solutions through market-based approaches
The table below outline main activities proposed to achieve planned objectives, with tentative timing
and implementing partners:
Table 33. ACCES – Projects and activities.
Project 1: Demand and market established for LPG across Tanzania Mainland
1.1 Establish a modality for RBF in REA REA HQ Year 1 – 2 MoE, REA, consultant
1.2 Determine indicators for identifying REA HQ Year 1 – 2 REA, PO RALG, LPG
eligible target populations distributors
1.4 Call for tenders for first wave RBF REA HQ Year 2 REA
1.6 Conduct marketing and education Semi-rural target Year 2 – 4 REA, LPG distributors
areas
1.8 Provide RBF based on targeted sales REA HQ Year 3 – 4 REA, LPG distributors
1.9 Call for tenders for second wave RBF REA HQ Year 4 REA
1.11 Conduct marketing and education Rural target areas Year 4 – 7 REA, LPG distributors
1.12 Monitor performance Rural target areas Year 5 – 8 REA, LPG distributors,
consultant
1.13 Provide RBF based on targeted sales REA HQ Year 5 – 8 REA, LPG distributors
2.2 Identify target areas in regions Rural areas Year 2 - 7 REA, PO-RALG, LPG
distributors, regional
branches of financial
institution, public
institutions
2.3 Call for applications for subsidized loan Rural target areas Year 3 - 7 REA, financial institution
from micro-finance groups and public
institutions in target areas
2.4 Provide subsidized loan for acquisition Selected locations Year 3 - 7 Financial institutions
of LPG
2.6 Capacity building of LPG retailers Selected locations Year 3 - 7 LPG distributor
3.1 Dialogue with biogas stakeholders Dodoma Year 2 - 3 REA, CAMARTEC, NGOs,
Project developers
4.1 Dialogue with eCooking stakeholders Dodoma Year 2 - 3 REA, electricity service
providers, NGOs, Project
developers
4.4 Call for proposals and select three for REA HQ Year 3 REA
funding
4.7 Evaluate and compare modes of Three target areas Year 7 Consultants, REA
electricity supply for eCooking
4.8 Assess viability. Decide if, how and what Dodoma Year 7 REA, MoE
mode to support in new target areas
5.1 Implement pilot project in Lindi and Lindi and Year 1 - 3 MoE, TPDC and other
Mkuranga Mkuranga stakeholders
5.2 Dialogue with natural gas stakeholders Dodoma Year 2 - 3 MoE, TPDC and other
stakeholders
5.3 Feasibility study to identify target areas Target areas along Year 3 TPDC, REA
main pipeline
5.4 Develop specifications for natural gas Dodoma Year 3 MoE, TPDC, REA
project
5.5 Contract for financing natural gas REA HQ Year 3 GoT, REA and other
project stakeholders
5.6 Fund natural gas project Target areas along Year 3 - 6 GoT, REA and other
main pipeline stakeholders
5.7 Monitor natural gas project Target areas along Year 3 - 6 TPDC, REA
main pipeline
5.8 Evaluate natural gas project Target areas along Year 6 TPDC, REA, consultants
main pipeline
5.9 Assess viability of provision in new Dodoma and Year 6 MoE, TPCD, REA
areas where natural gas pipeline is target areas
extended. Decide if, how and what mode to
support in new target areas (repeat steps
5.2-5.8)
6.2 Develop educational material for safe REQ HQ Year 2 - 3 REA, consultants, LPG
use of LPG and natural gas distributors
6.4 Conduct public campaigns in media and National, targeted Year 3 - 6 MoH, REA,
live demonstrations to create awareness of semi-urban and Development partners,
health impact with clean cooking solutions rural population NGOs, Private sector
(ACCeS programme) and media
6.5 Conduct public campaigns in media to National, targeted Year 3 - 6 MoH, REA,
create awareness of health benefits of rural population Development partners,
improved cooking services (TrICS NGOs, Private sector
programme) and media
6.6 Monitor and evaluate ACCeS- Country-wide Year 5 and 8 NBS, REA
programme based on IASES II, III (REACE
programme)
Costs
The table below contains high-level budget estimates for the five projects under ACCeS. Further cost
details can be found in the CEAP.
Table 34. ACCeS - High-level budget estimates.
Project Cost
(USD
million)
Project 1: Demand and market established for LPG across Tanzania Mainland 51
Total 111
MoCDGWS Oversees community Provide advice and policy coordination of initiatives directed
development policy and towards gender equality and social inclusion
gender
TPDC Regulate and facilitate Implementation of national policy for promotion of liquid
supply of petroleum and gaseous petroleum fuels. Implementation of projects
products on natural gas.
LPG Supply LPG in Tanzania Memorandum of Understanding with REA to supply LPG in
distributors rural areas based on RBF.
Provide capacity building of retailers.
Marketing and awareness creation.
NGO, CBO Implement eCooking Develop project proposals, implement project and monitor
projects development
Education and
Education and training on
research Participate in awareness and educational campaigns
health
institutions
Banks, Manage funds to public Collaborate with REA to establish revolving fund for
financial subsidized loans to institutions and micro-finance groups
institutions
Provide loans to selected beneficiaries
Successful implementation of Few or no additional staff hired. ACCeS may continue with less
REACE programme Limited resources for operational institutional knowledge in REA of
costs cooking energy and new standards.
Funds from GoT allocated to Less funds received than Scale down activities
REA for implementing REACE requested
Government institutions Partners do not commit to ACCeS REA prioritises parts of ACCeS that
engaged in implementation of can be conducted without strong
ACCeS partnerships
Funding from development Less or no funds allocated from REA prioritises parts of CEAP that can
partners to match provisions by development partners be conducted without large
GoT investments
Contracts with LPG distributors No interest or capacity among Focus on demand-side interventions
LPG distributors
Implementation of MoH Limited priority to achieve a ACCeS may continue with less strong
Strategic Plan HSSP V (2021) reduction of indoor air pollution enabling framework
includes focus on IAP H’
Enabling policy and regulatory Policy and regulatory Sensitize policy and decision-makers
framework in place requirements identified in CEAP to declare clean cooking a national
not in place agenda
ACCeS may continue with less
institutional support by other GoT
bodies
2001 EWURA Act Established EWURA to regulate tariffs for electricity trade in the
country, and promote the availability of regulated services to
all, including low-income, rural, and disadvantaged consumers.
2003 National Energy Policy The 2003 policy laid the foundation for promoting renewable
energy sources and encouraging private sector participation in
Tanzania.
2005 Rural Energy Act Established the Rural Energy Agency in order to enhance energy
access in rural areas.
2015 National Energy Policy Aimed to attract more private investment and local
participation in the energy sector, improve efficiency and
energy conservation as well as access to modern energy
services and increase the share of renewables in the electricity
generation mix.
2015 Executive Agencies Act Established PBPA to coordinate and manage efficient
procurement of petroleum products through Bulk Procurement
System.
In addition to the documents listed above it is worth highlighting that the United Nations Framework
Convention on Climate Change Paris Agreement was ratified by Tanzania in May 2018. The first
Nationally Determined Contributions (NDCs) promote energy efficiency technologies, enhancing
efficiency in wood fuel extraction and utilisation, and enhancing use of renewable biomass.
Recommendation Context
1: Address SDG 7 and Low ability to pay in rural areas is an important barrier to improving energy
associated goals services for a large part of T z ’ T IC
through cross- cylinder and stove for LPG may represent an unsurmountable upfront investment
sectoral national for many rural households.
effort
Ensuring availability and affordability of improved and clean alternatives for
cooking in rural Tanzania will require substantial investment in infrastructure, such
as industrial-scale production capacity of ICS, storage and filling facilities for LPG,
development of distribution capacity, and support to market activities to make
provision commercially viable and enable expansion into new areas.
A national and cross-sectoral effort must be made to address SDG 7, 3, 5, 13 and
15, supported by appropriate allocation of public funding over the national
budget.
2: Acknowledge One of the objectives in NEP 2015 is to enhance utilisation of renewable energy
biomass energy as a resources, including biomass, so as to increase its contribution in diversifying
mainstay in the I “ Government shall
energy supply facilitate efficient biomass conversion and end- ” However,
sustainable production and use of biomass resources fall under the mandate of
several Government ministries.
To create an enabling framework for reaching the SE4All, policies across sectors
k ’
and policies and regulations in the forestry and energy sectors should be aligned.
3: Coordinate GoT Since the 1970s Tanzania has seen numerous government and development
and development partner-led efforts to promote improved and clean cookstoves and fuels, but with
partner interventions limited effect in terms of scale and lasting results.
to promote clean
The Country Action Plan for Clean Cookstoves and Fuels 18 , reported that the
cooking
enabling environment has been stifled by policy and market failures, a lack of
awareness on the benefits of clean cookstoves, weak government policies and
insufficient access to finance.
To create an enabling framework for reaching the SE4All, increased effort should
be made to coordinate government and development-led interventions to
promote clean and improved cooking alternatives, such as LPG, eCooking and ICS.
Current and planned development projects and programmes are described in the
CEAP.
4: Implement an According to the 2020 Joint Energy Sector Review, statistical data and reports that
information and exist on national energy consumption patterns lack the necessary depth and detail
knowledge to inform policy and regulatory decision-making, and MoE lacks a comprehensive
management system system for national monitoring and evaluation of the energy sector 19 . An area that
for the energy sector is poorly addressed is the extent and consequences of fuel stacking, which is an
important factor for interventions on cooking energy.
Increased capacity for M&E should established by the MoE. This could include an
energy information and knowledge management system to be implemented by
MoE in coordination with stakeholders including the National Bureau of Statistics.
5: Increase attention There is in inadequate awareness of indoor pollution and its health impacts among
towards causes and the public health services and extension as well as in the general population.
effects of indoor air
Impact of Indoor Air Pollution is not addressed in depth in current policy and
pollution in health
regulation related to public health. This in turn limits the attention to adoption of
policy
improved and clean cooking stoves, especially by the rural population.
Health policy and regulations should increase attention towards causes and
effects of indoor air pollution, and public awareness raising. The Health and
Pollution Action Plan has proposed actions for addressing indoor air pollution,
including awareness creation and promotion of clean cooking solutions. Efforts to
address indoor air pollution should be coordinated between the energy and health
authorities.
6: Increase attention Gender is a crosscutting issue, and women and children carry the largest burden
towards burden on from exposure to pollutants coming from cooking with firewood and charcoal. The
women and children head of household are often men, delimiting the range of decision of the source of
from indoor air energy used for cooking.
pollution
The MoCDGWS is responsible for gender-related policy in Tanzania. In
development of new policy increased attention should be given to impacts from
cooking energy use and measures to address impacts of these, and awareness to
both men and women on the effects of pollution.
7: Support capacity Research institutions lack the necessary resources to conduct research on climate
building and change mitigation and Global Warming Potential of development interventions.
structural changes in
It will be critical to support research institutions in Tanzania to study Global
energy sector public
Warming Potential of different energy sector trajectories, including the SE4All
institutions
scenario. Research can be strengthened through collaboration with international
research institutions.
8: Support research Energy for cooking receives considerably less funding than other decentralised
institutions in energy sources in Tanzania. The budget set aside for cooking energy in REA is TZS
Tanzania to study two billion, or 0.5 percent of the total budget.
climate change
The sources of finance earmarked for REA include Government Budgetary
allocation as a cross-subsidy through the Petroleum Levy and the Electricity Levy.
impact of energy With increasing energy consumption in urban areas, allocation to REA increases.
interventions Allocation of sufficient funding to cooking energy should also be provided from
other sources. These issues are further discussed in chapter 6.
Recommendation Context
1: Effective market The rural energy economy largely is informal, not perfectly integrated in financial
regulation of all fuels markets, and therefore difficult to regulate through fiscal policy.
Effective market regulation should be communicated and framed through
information, awareness creation and education. Policy for increasing use of
improved and clean cookstoves and fuels should be an integral part of formalization
of the rural economy at large.
2: Enforcement of Lack of coordination in importation of LPG (e.g., bulk importation and regulation)
stove and fuel continues to be a challenge. Implementation of a national LPG promotion plan is
standards by TBS proposed to address the barriers to use of LPG in rural Mainland Tanzania.
5: Price LPG Price volatility and lack of control over large regional price differentials and local fees
strategically and levies adversely affect adoption and sustained use of clean cooking fuels such as
LPG. The regulation of energy distribution has significant impact on the ability to scale
up investments and increase availability into gradually more rural areas.
EWUR ’ LP z
for urban and rural markets. Consider implementation of an instrument like the
electricity life-line tariff, for LPG.
6: Incentivise ICS Even when the long-term running costs of an alternative solution is competitive,
production the purchase of an ICS or a cylinder and stove for LPG or eCooking equipment may
represent an unsurmountable upfront investment for many rural households.
Through the NEPs, the GoT has been promoting substitution of charcoal and
firewood by providing tax relief to stimulate the use of LPG in the country. In 2008-
2009 import duties and VAT were removed from LPG. All other cooking fuels have
taxes, royalties, duties, and levies.
Costs are largely driven by material expenditures and capital investments required
for installing production lines, and exemption from VAT and other fees for input
materials, licenses, and capital expenditures would therefore enhance affordability.
7: Reduce import ICS produced in other countries may be imported. Uptake of important stoves can
duties for ICS be incentivised by lowering import duties on ICS that meet Tanzanian standards. A
risk associated with this is that domestically produced stoves are less competitive
on price.
8: Reduce import LPG requires upfront investment for households for purchasing the cylinder, cooker,
duties for LPG and gas, making the solution unaffordable for lower-income users. The inability to
appliances afford to purchase large refills of gas (usually six kilo refills of gas). Lower-income
customers will typically be buying sufficient charcoal for just a few meals whereas a
’
Tax advantages and reforms can increase affordability, for example: Exemption of
import duties on LPG tanks and regulators, and reducing import duties and VAT for
LPG stoves, to reduce start-up costs for purchase of cylinder and stove.
9: Regulate charcoal The charcoal sector and supply chain from rural producers to urban consumers is in
value chains the process of being formalized through regulation by TFS. This contributes to
increase the cost of charcoal in cities, thereby increasing urban demand for
alternatives such as LPG, eCooking and use of natural gas. Charcoal costs less and is
used less in rural Tanzania due to locally available firewood. The effect of
formalization of the charcoal sector is likely to have marginal direct effect on rural
energy consumption, but it may contribute to the general formalization of the rural
economy.
Formalisation through regulation of biomass energy value chains sector must
acknowledge that charcoal production and sales is a livelihood strategy for
hundred-thousands of people in rural Tanzania.
Regulation of the charcoal value chains should provide financial incentives to rural
producers based on efficiency of production. This should be bolstered by increased
cross-sectoral capacity for regulation of upstream and mid-stream charcoal supply
through dialogue between VPO, TRA, PO RALG, LGAs and producers and
establishment of producer organizations.
Recommendation Context
1: Strengthen Advisories such as the Biomass Energy Strategy Tanzania and the 2020 Joint Energy
coordination between Sector Review point to the lack of coordination between energy and forestry sectors
energy and forestry as an important barrier for successful interventions to reduce rate of deforestation.
sectors T z ’ RT F
Beekeeping Division. TFS has been mandated with policy development,
management of the charcoal trade and revenue collection. TFS manages the
Tanzania Forest Fund which is used to promote, facilitate, and finance projects to
enhance sustainability of use of forest resources. A possible enabler is that VPO is
responsible for environment, and as such an entity which bridges the policy
domains. VPO is situated for overseeing demand and supply-side interventions to
regulate biomass energy use policies and interventions.
2: Build the capacity The health dimension of cooking energy should be anchored in MoH. However, a
of MoH oversee health barrier for cross-sectoral effort for promoting clean cooking is that indoor air
aspects of clean pollution has received limited attention in the health sector. National Institute for
cooking Medical Research and Muhimbili University of Health and Allied Sciences are
relevant research and education institutions that work on indoor air pollution in
Tanzania. In implementing the NEPs, the MoE and REA are engaged in work to
reduce the health burden from indoor air pollution. MoH has the mandate to
promote initiatives to improve public health. The ministry is a natural nodal point
for coordinating awareness raising campaigns and education related to improving
the household context of cooking energy use towards the SE4All goal.
3: Revitalise the Rural An effective entity for coordination of energy sector activities with other cross-
Energy Working Group cutting sectors is necessary. A barrier to implementation of cooking interventions
as enabling body for under REA is the lack of a coordinating body for cross-sectoral interventions. The
joint institutional Rural Energy Working Group is positioned to be an enabling body for overseeing
efforts
joint institutional efforts to implement CEAP: It is constituted by the most strategic
k ’ E I
MoE, REA, EWURA, TBS, TANESCO, NEMC, TPDC, MoFP, MNRT, MIT, COSTECH,
private sector representative, PO RALG and a development partner representative
as an observer. The working group has been inactive but was supposed to meet
several times a year to deliberate on issues cross cutting sector boundaries. Its
decisions previously were not binding to any of the participating institutions. To
coordinate the cross-sectoral effort to establish an enabling framework of policies,
regulations and institutions for reaching SE4All, it is recommended that the Rural
Energy Working Group is re-vitalized with a workplan and commitment that agreed
decisions must be legally binding. Composition should be considered in light of
needs arising.
4.4.1 Environment
The environmental sectors track the consumption of natural resources – both renewable and non-
renewable – and estimate the impact of the use and depletion of such resources on production, health
and other sectors. The usage of firewood and charcoal as a primary source for cooking energy leads to
a considerable increase greenhouse gas emission, loss of biodiversity, and in extreme cases, soil
erosion because of deforestation. The tension between the satisfaction of human needs and the
degradation of the environment is high and requires rethinking and changing the usage of energy from
REMP Main Report August 25th, 2022 Page 63
firewood and charcoal, to more sustainable ones. Population and production levels determine the
demand of those natural resources and the generation of waste and air pollution. Nevertheless,
investment decisions can influence the level of waste treatment, alternatives, and capacities for
renewable energy, resulting in more responsible use of national natural resources. To reduce the
impacts and vulnerability of climate change Tanzania has committed to NDCs, intending to enhance
inefficiency in wood fuel utilization, to enhance the use of renewable energy across the country, to
promote the use of energy efficiency technology and behaviour and to promote rural electrification.
These actions are aimed at reducing the rate of forest degradation and adapt to climate change.
4.4.2 Gender
In terms of gender equality, SDG5 aims to empower all women and girls. Giving women opportunities
to generate income is a start in the social process required to reach that goal. In the current social
context of Tanzanian society, there is an unbalance share of domestic unpaid work, divided in many
activities that take most of the time of women in many households. Additionally, cooking and gathering
wood, represent one of the most time-consuming of daily responsibilities carried by women. In many
cases women have to walk long distances to get firewood and then engage many hours making food,
often being exposed to polluted air. The implementation of clean cooking energy shortens the time
involved on food preparations, providing space and opportunities to get employed and/or engaged in
educational alternatives. The empowerment of all women and girls is a vision that not only benefits
women, also impacts further in other family members, and in a wider extent many aspects of society,
creating fluency and symmetry within household members. Finally, granting women the alternative of
choosing how to administrate their time, becomes potentially the first step towards a more balanced
and equal society in which the vital role of women is guaranteed with their full and equal participation
and leadership in all areas of sustainable development.
4.4.3 Health
Indoor air pollution is one of the main reasons for lung diseases. The exposure to airborne pollutants
is harmful for those breathing it, but also one of the reasons of malformations, damage to the brain
and low birth weight in babies in the womb, in addition to other complications during the gestation
period. The long hours expended in cooking activities, represent a constant exposure to polluted air.
The particles arising from solid fuels such as wood, charcoal, and animal dung for cooking create
unhealthy living environment. Cooking over open fires or inefficient stoves typically entails burning
fuels like wood, charcoal, coal, and kerosene, which releases harmful, climate-warming emissions.
Short-lived climate pollutants—such black carbon and methane (CH4), as well as other greenhouse
gases, such as carbon monoxide (CO) and carbon dioxide (CO2), which are emitted due to the
incomplete combustion of kerosene and solid fuels that occurs while cooking using these unhealthy
methods. Furthermore, the implementation of cleaner cooking energies will provide efficient solution
to eradicate diseases related to indoors bad air quality. As health being one of the key components of
a fulfilling life, it must be then taken into consideration as a top priority of any development project.
In addition to the above, approximately USD 300 million for FY 2022/23 and USD 243 million for FY
2023/24 (see Annex G for details) are budgeted for costs related to on-going electrification projects.
These costs are not included in the analysis, as it is assumed that they largely are covered by existing
donor commitments.
20 Applying the Bank of Tanzania exchange rate on February 11th, 2022 of 2298.1564
Development partners In the last nine years, it is estimated It is assumed that the development
that development partners have partner contribution to REF will
provided around USD 1,657 million continue on existing levels.
to the energy sector Tanzania 23 ,
It is further assumed that
equal to an average of USD 188 development partners will continue
million per year. to support investments in
I RE ’ W kP transmission and generation at the
Budget for 2020/21, the total levels seen over the past nine years.
revenue expected to be received
from development partners is TZS
32.32 Billion, equal to USD
approximately 13.5 million 24 .
The figure below presents an extrapolation of resources that would be available over the coming 8-
year period for rural electrification and clean cooking based on the above assumptions. Funds from
the prioritized grid strengthening projects under NGAP are not included, but it is assumed that donor
funds will continue to be available to support priority investments in the Tanzanian power system.
21 Applying the Bank of Tanzania exchange rate on February 11th, 2022 of 2298.1564
22 REA Five Year Strategic Plan July 2021 – June 2026, 2021
23 Action Document for Integrated Approach to Sustainable Cooking Sol E F E F : ΤΖ/FE /0 0-142
24 Applying the Bank of Tanzania exchange rate on February 11 th, 2022 of 2298.1564
6.3 Conclusion
It is notable and encouraging for the overall sustainability of the Tanzanian power sector that the
forecasted revenues from government sources are expected to be sufficient to cover a significant share
of the required investments. Even so, it seems clear, based on the estimates provided above, that a
funding gap remains for completion of all REMP activities. This will be further addressed in the
forthcoming REA Resource Mobilization Plan.
A gradual shift of resources from electrification towards clean cooking is expected, as the decades long
effort to expand access in rural Tanzania is coming to an end after the end of this REMP period. Nearly
99 percent of REF funding has financed the prioritized grid extension projects over its 10 years of
existence, but the ramping up of resources for clean cooking over the 8-year REMP period is a clear
signal of the Government and REA´s commitment to this important policy area.
Universal access to 100% of the population Nation-wide Access and connectivity to electricity
electricity and non- with access to electricity by survey in 2030 include national grid, mini-grids, and
electrical energy for 2030 off-grid solutions.
cooking
75% of the population with Modern Cooking is defined in
connection to electricity by accordance VPT Tier 4 or above.
2030
To achieve 75% of the total population
75% of the population with with access to modern cooking, 60% of
access to modern cooking the population in rural areas must have
solutions by 2030 access
The following tables present a monitoring framework covering the six REMP programmes and their
respective activities. In addition to Key Performance Indicators (KPIs) for each activity, the framework also
details targets for each indicator, in line with the project descriptions set out in the RESP and CEAP
respectively.
It is proposed that several KPIs be monitored through the three IASES surveys that are proposed for 2022,
2026, 2030 respectively. The 2022 survey will constitute a baseline for these indicators, and these are
consequently left blank in the framework – to be filled in once the survey is complete.
Large scale industrial % RE ’ 0 50,000 100,000 12,000 150,000 200,000 500,000 Project
production of ICS for cooking energy purposes reports
firewood and charcoal to
provide sufficient amounts
of affordable stoves
supported
Increased adoption of ICS # trainings conducted 0 0 100 500 1,000 2,000 5,000 Project
at meso-user level. reports
Increased adoption of ICS # Planning and monitoring To be 200,000 250,000 300,000 500,000 800,000 2,500,000 IASES
at micro-user level. report per year established surveys
based on IASES
study 2021/2022
Increased sustainable # IASES surveys conducted 0 0 1,000 20,000 40,000 50,000 100,000 Project
biomass energy supply reports
This Rural Electricity Supply Plan (RESP) is the second of three volumes constituting the REMP 2022 –
2030. It describes how the targets set out for electrification of Tanzania over the next 8 years can be
reached, including analyses and recommendations for three programs with corresponding projects and
activities.
Ensuring 100 percent access and 75 percent connectivity to metered connections by 2030 will require
deployment of a continuum of on-, mini-, micro-, and off-grid solutions across rural Tanzania. In addition,
it is assumed that the population with no metered connection in 2030 will be served by stand-alone
systems to ensure universal access to electricity as defined by SE4All.
The geospatial electrification planning approach taken in this RESP is based on a national GIS database
from the National Bureau of Statistics (REMP database), which includes 15,211 georeferenced settlements
in mainland Tanzania. Other databases (e.g. PO RALG, postcodes) only list villages and sub-villages in
tables without any information on population or coordinates (longitude and latitude) and can therefore
not be utilized for geospatial planning purposes. The REMP database identifies 2,865 rural settlements
that do not have access to electricity, and which are not part of existing electrification programmes.
Because georeferenced locations of all hamlets are not available, the REMP database does not constitute
all settlements in Tanzania. Although not included in the REMP database, the electrification program REDP
III which aims to electrify all 37,610 hamlets in Tanzania that currently have no electricity access is included
in the scope of this RESP.
Applying the software GEOSIM, a geospatial analysis was conducted in order to identify, select and rank
the areas with the highest social and economic impact of electrification. An electricity load forecast was
also conducted for the georeferenced unelectrified rural settlements in the REMP database in order to
establish their future demand for electricity. The Renewable Energy Assessment identifies resources and
the technology options available for rural electrification through mini-grids based on renewable energy
resources. The purpose of this methodological approach is to provide techno/economic
recommendations as to how the unelectrified rural settlements best can be electrified. The analysis was
further supported by a load-flow analysis of the Tanzanian national grid, to examine the impacts of
increased rural loads. The overall approach is presented in the figure below.
1.2 Definitions
The adaptation and successful implementation of this RESP relies on the joint and collaborative
efforts of a broad set of institutions, organizations, private sector companies, and individuals. For
these diverse groups to coordinate their efforts and allocate resources correctly, it is important that
the applicable targets and strategies are clearly defined.
Within the international and Tanzanian energy access space, there are unfortunately many
examples of terms that overlap, are used interchangeably, have changing definitions, and even
contradict one another. There is, for example, a tendency to rely on binary measurements of access
Source: https://www.worldbank.org/content/dam/Worldbank/Topics/Energy
More generally, definitions have important implications in terms of target setting, monitoring, and
communication. Therefore, a set of clearly defined definitions have been developed for this RESP.
To the degree possible and reasonable, this terminology is consistent with existing use in Tanzania.
Access to electricity Population living in localities served by electricity and thus reaping benefits
services from these services with an opportunity to gain connectivity.
Access to electricity services = Total number of people living within a radius
of 600 meters from the secondary side of distribution transformer/Total
Population
Low-cost Technologies Distribution technologies for electricity supply that deviate from
international design standards but can be sufficient in rural areas with low
load profiles typically found in rural areas in Sub-Saharan African. Their
purpose is to reduce costs while ensuring appropriate quality for the
consumers.
Micro-grid A micro grid consists of one or several very small power production units
(up to 100 kW) such as solar PV + storage. Power is distributed via LV lines
to a group of consumers, such as a small village or a group of households.
Provides “Connectivity”.
Mini-grid A mini grid consists of one or several power production units (for example
hybrid PV + diesel or wind + diesel) of a capacity ranging from a 100 kW to a
10 MWs. Power is distributed to a limited geographical area, such as one or
more villages via MV and LV distribution lines. Could be connected to the
national grid from establishment or at a later time.
Provides “Connectivity”.
Pico-PV products Pico systems consist of a single item (e.g. lamp or mobile charger) powered
by any source of energy ranging from a few watts up to ca. 200 W that is
not connected to any appliance in the household and is used for one
specific energy purpose.
Does NOT provide “Connectivity”.
Private mini-grids A mini-grid owned and operated by any legal entity other than TANESCO.
Stand-alone systems Technologies and products that provide a minimum electricity service level
(typically Tier 2) to specific households, businesses or institutions that are
not connected to the main grid or a mini- or micro grid with typically less
than 20 Wp installed. Both produces and supplies electricity in one location
and serves one beneficiary - e.g. a household. This definition encompasses
solar home systems (SHS), but not Pico-PV products.
Provides “Connectivity”.
TANESCO isolated grid An electricity grid that is operated by TANESCO but is not inter-connected
to the national grid.
Provides “Connectivity”.
1.3 Objectives
T j RE P “ RE -to-date tool for planning and
implementation of rural energy provision meeting target set in the National Energy Policy 2015,
National Strategy for Growth and Poverty Alleviation (MKUKUTA) and Sustainable Energy for All
(SE4ALL) goals. The plan is also aimed at exploitation and utilisation of renewable energy sources
for improved energy supplies in the country”.
The high-level objectives pertaining to electricity and clean cooking energy are found in the figure
below.
Figure 2. Specific REMP objectives pertaining to electricity and clean cooking energy.
In order to guide the preparation of this RESP, the high-level targets related to electricity access
and connectivity in rural Mainland Tanzania have been further broken down as outlined in the
figure below. The baseline numbers are from a 2019/20 survey conducted by the National Bureau
of Statistics (NBS) for REA 1 . 0F0F
It is assumed that the population with no metered connection in 2030 will be served by stand-alone
systems to ensure universal access to electricity as defined by SE4All.
1.4 Methodology
This section presents an overview of the methodological approach for identification of projects for
provision of electricity to the rural communities in Tanzania, which is further substantiated in
subsequent sections.
Figure 4. Methodology for identification of electricity supply options for the rural communities in Tanzania.
electrification. Data on health, education and economic facilities have been gathered for each
georeferenced rural settlement and added to a Geographic Information Systems (GIS) database
established for the Project. These data have then been processed through an analytical matrix,
similar to the approach taken for the Human Development Index, and an Indicator for Potential
Development (IPD) for each of the unelectrified villages has been calculated. The villages with the
highest score are considered as Development Poles (DP). These DPs will be given a higher priority
in the rural electrification planning and will be ranked according to this rated potential.
The overall Spatial Analysis process is illustrated in the figure below.
REMP database
The geospatial electrification planning approach under REMP is based on a national GIS
database from National Bureau of Statistics (NBS) from 2016, which in this RESP is referred to
as the REMP database.
This database is the only source providing all information required for geospatial electrification
planning. Other databases only list villages and sub-villages in tables without any information
on population or coordinates and can therefore not be utilized for geospatial planning
purposes. The database includes 15,211 settlements in mainland Tanzania.
The REMP database divides mainland Tanzania into 26 regions which are further divided into 139
districts (Wilaya) 3 , also known as local government authorities. Of the 139 districts, 34 are urban
2F2F
units (Municipal Councils, City Councils and Town Councils). The urban districts are marked green
in the map below.
REMP database is different from the total number of settlements supplied by existing mini-grid
projects. The reasons for this are twofold: i) Some power plants provide energy to several
settlements; and ii) other mini-grids provide electricity to settlements that are not defined in the
REMP database.
Table 2. Existing mini-grids projects.
4 Technical data and location of these projects were gathered from https://www.energyaccessexplorer.org/
Densification is the connection of new customers to the distribution network in already electrified
settlements. The densification potential is huge as only a portion of the potential customers in
electrified settlements is connected. The first phase of REDP has been completed with 33,102
customers out of out of 34,600 connected to the grid equivalent to 95.7% in total in the 295
targeted villages and 99 targeted hamlets 6 .
2) Rural Electrification Densification Program (REDP) – Second Phase (rounds A, B, C)
The second phase of the REDP program is targeting 3,924 hamlets to be connected to electricity
through the national grid. It is divided in three rounds with round A and B targeting 1,103 and
2,821 hamlets respectively. Round B will comprise 10 regions (1,346 hamlets), while six additional
regions (1,475 hamlets) will be implemented under the REDP IIC program.
REDP IIA is currently ongoing and will be completed in March 2022. The program has consequently
“ ” RE P For REDP IIB, procurement of EPC
contractors is ongoing, and the program is expected to be completed by December 2023. Because
the lots for village electrification have already been awarded, the villages targeted by this program
are not included in the economic assessment of this study. On the other hand, the network
extensions to connect the targeted villages to the existing grid have been simulated. Regarding
REDP IIC, the deadline for submission of bids from EPC contractors was January 24, 2022. The
project is expected to be completed in March 2024, and the localities have therefore been
considered in both the simulation of grid extensions and the economic assessment.
3) Rural Electrification Densification Program (REDP) – Third Phase
This program will target all unelectrified hamlets in all regions.
This project was implemented through government initiatives to electrify rural areas in Tanzania,
especially in Ruvuma and Njombe Regions. The major objective of this project is to extent
T E CO’ k activities,
freshwater pumping, secondary schools. A total of 119 villages and sub-villages have been
electrified through this project and the REMP database have been updated accordingly.
9) Backbone Transmission Investment Project
The rural electrification component of this project was financed by Sweden and Norway and
targeted about 122 villages. By July 2020 a total of 16,790 out of 30,350 initial customers have
been connected 8 . 104 of these villages have been updated as electrified in the REMP database.
7F7F
7 Source: «Makambako – Songea 132 kV Transmission Line and Electrification of Songea and districts in Ruvuma and Iringa, Tanzania » Project
report, 2012
8 Source : REA, Development partners support to REF – Annual Progress Rapport July 2019 – August 2020
These projects were demonstrating low-cost rural electrification design standards. Located in
eastern Tanzania, the Kilombero project provides electricity to 16 villages along a 105-kilometre
corridor that lacks an electricity distribution network. The Mbozi project, in southwestern
Tanzania, provides electricity to 10 villages by extending existing power lines more than 50
kilometres. Of the 26 villages listed, 20 villages were identified in the REMP database and their
electrification status have been updated accordingly.
12) Ifakara substation project 10 9F9F
The project comprises construction of the 220/33 kV Ifakara substation and 70 kilometres of
distribution lines in Kilombero district as well as low voltage reticulation and grid connections of
1,050 customers in the villages of Mofu, Idandu, Msumbiji A, Idete west, Kisawasawa, Kiogosi,
Michenga, Ihenge and Ihanga. Status of the villages identified in the REMP database is defined as
electrified.
13) DFID/SIDA mini grids facility 11 - Stage II 10F10F
The first call for proposal for the Tanzania Mini-Grids Results-Based Financing (RBF) Facility was
launched by REA in September 2016. This first call for proposal implemented in 2017, selected 24
applications from mini-grid developers to receive results-based incentives per mini-grid
connection delivered and sustained. These incentives are offered based on the quality of service
delivered, based on SEforALL Tiers of Energy Access, and effectively extends the rural
electrification subsidy support offered to new grid extensions to the mini-grid sector for the first
time. In November 2019 a second call for proposal was done known as Stage II. This Stage II
program was targeting 260 villages and is now completed.
14) Lighting Rural Tanzania Competition 12 1F1F
The first project under this competitive grant program was the LRTC2010 which was followed by
LRTC2012 and LTRC2014. All competitions under this program aim at increasing access to modern
energy services, improving lighting technologies and substituting the use of kerosene and candles
for lighting in rural areas. This program is contributing to the overall national targets for energy.
LTRC 2014 intended to provide electricity to about 26 villages through this program. 18 of these
RE P I “ ”
15) Other independent projects
This category includes among other independent projects, the Njombe hydro project, the
Mwenga small hydro project and the Kilolo-Maguta project.
9
Source: NRECA International implements low-cost rural electrification pilot project in Tanzania
10 Source : EoI - Supervision services for construction of 220/33 KV substation at IFAKARA
11 Source: Green Mini-Grids Africa – Update on the DFID-Supported Programme
The table below lists the number of DPs in each region and highlight that these are unevenly
distributed across the country. This can be explained by the following factors:
Number of
Number of Share of
Name settlements
Development Poles Development Poles
not electrified
Arusha 34 7 21%
Dar Es Salaam 26 11 42%
Dodoma 81 11 14%
Geita 145 29 20%
Iringa 70 1 1%
Kagera 76 11 14%
Katavi 42 10 24%
Kigoma 51 45 88%
Kilimanjaro 88 3 3%
Lindi 70 2 3%
Manyara 51 9 18%
Mara 64 9 14%
Mbeya 237 7 3%
Morogoro 114 13 11%
Mtwara 280 2 1%
Mwanza 131 17 13%
Njombe 68 0 0%
Pwani 171 6 4%
Rukwa 209 20 10%
Ruvuma 127 6 5%
Shinyanga 129 11 9%
Simiyu 52 10 19%
Singida 63 6 10%
Songwe 56 5 9%
Tabora 88 19 22%
Tanga 340 16 5%
Total 2,863 286 10%
2) National energy surveys for 12 additional regions conducted by the NBS in 2013 14 . 13F13F
The objective of this approach is to reflect the actual demand and expected consumption patterns
observed in unelectrified rural settlements after electrification.
In order to calculate levelized costs for the electrification projects and by that compare the various
renewable technologies relevant for mini-grids, the load forecast has been studied for a 20-year
period. The results are however also be presented for the two respective REMP phases, i.e. year
2022-2025 and 2025-2030.
Based on the consumption profiles per category of beneficiaries (households, social infrastructures,
productive activities etc.), the load forecast software provides the following indicators:
• Number of customers (LV/MV);
• Peak demand (kW);
• Annual consumption (kWh); and
• Classified load curves (monotonic).
13 Source: Load forecast report - Integrated Rural Electrification Planning in Tanzania (IED, 2012)
14 Source: National energy surveys for 12 regions. Unpublished database (NBS, REA, 2013)
3) Connected households
As for non-connected households, the connected households have been divided in three categories
based on average number of kWh consumed per month.
Table 8. Electricity distribution connected households.
Based on the parameters listed in in the tables above, the average consumption for each household
category was modelled.
3.1.4 Key Parameters and Assumptions Applied in the Load Forecasting Model
The load forecast builds on a series of assumptions which are laid out below.
1) Consumption and connection parameters for three demand scenarios
Three scenarios have been developed for rural demand, which depend on factors like industrial
activities in the settlement, government directive on electricity tariffs, attractiveness of the village
on the neighbouring unelectrified villages and so forth. These factors can have a direct impact on
the connection rate as well as consumption growth for households, infrastructure, and services. On
that basis, the baseline scenario has been developed as a reference and the optimistic scenario as
a situation where connection rate and consumption growth rate are higher than expected. The
pessimistic scenario is much more conservative in terms of connection and consumption rate
Table 13. Connection and consumption growth rate parameters for the baseline scenario
Table 14. Connection and consumption growth rate parameters for the optimistic scenario
15 percent, and probably higher for older networks. Because specific losses of specific lines are not
known, average technical distribution losses of 15 percent have been assumed.
16 PSMP 2020
The figures below show households and infrastructures and services consumption growth from
2021 to 2040. With regard to the households, it should be noted that the consumption increases
by a factor 13 during the course of the analysis period. In the same period, the infrastructure and
service load are characterized by a lower growth rate. This trend is mainly due to 70 percent of the
infrastructures and services being connected in the first year whereas only 30 percent of
households are connected the same year.
The share of domestic demand (household electricity demand as a share of total demand) and
number of LV customers for a village with 3,000 inhabitants respectively are shown in the two
figures below, while the daily and yearly load curves for the same example village are presented in
the subsequent tables. It can be seen that the number of low voltage customers are increasing from
166 in year 2021 to 718 in year 2040 mainly due to household consumption growth during that
period. Further, the domestic share of total demand increases from 26 percent in 2021 to 55
percent in 2040.
Figure 12. Number of customers (example for a settlement with 3,000 inhabitants).
Table 18. Yearly load curve (baseline scenario – example for a 3,000-inhabitant settlement).
Demand
Peak 2022 Demand 2025 Peak 2025 Demand 2030 Peak 2030
Region 2022
(kW) (MWh) (kW) (MWh) (kW)
(MWh)
Arusha 73,231 12,879 126,074 22,571 196,339 34,928
Dar Es
53,841 9,922 94,974 17,833 158,655 29,179
Salaam
Dodoma 211,006 36,831 352,212 62,769 544,049 96,427
Geita 362,724 64,372 618,016 111,904 982,798 176,170
Iringa 83,263 14,274 138,067 24,133 210,762 36,722
Kagera 229,030 40,560 389,562 70,398 624,599 111,629
Katavi 70,055 12,349 119,709 21,504 191,572 34,070
Kigoma 237,589 43,182 414,356 76,733 673,643 122,884
Kilimanjaro 93,896 16,215 154,205 27,193 239,718 42,050
Lindi 182,519 31,442 300,755 52,891 465,348 81,462
Manyara 195,878 34,388 330,828 59,267 524,311 93,114
Mara 123,949 21,725 207,783 37,199 321,210 57,165
Mbeya 285,662 48,639 465,379 80,878 713,117 123,568
Morogoro 304,770 52,960 515,379 91,279 801,554 141,121
Mtwara 378,641 64,289 619,937 107,319 945,768 163,239
Mwanza 300,606 52,864 502,453 90,300 792,287 141,181
Njombe 90,715 15,385 148,123 25,612 227,735 39,273
Pwani 185,507 31,639 304,064 52,885 461,986 80,159
Rukwa 262,275 45,484 442,651 78,246 683,001 120,183
Ruvuma 317,086 54,770 524,130 92,401 809,540 141,948
Shinyanga 294,283 51,176 490,137 87,026 766,233 135,140
Simiyu 237,631 41,823 397,353 71,490 626,186 111,714
Singida 249,407 43,807 415,853 74,645 656,603 116,872
Songwe 207,856 36,287 347,276 61,883 546,792 96,698
Tabora 407,874 72,165 695,316 125,508 1,114,067 198,882
Tanga 545,304 93,911 903,057 158,689 1,391,205 243,378
Figure 13. Tanzania mainland demand map for unelectrified areas (baseline scenario – year 2025).
in the REMP database will be electrified by this point in time. The HV/MV substations load is a rough
estimate which does not take into account any electrification agenda, but rather provides an
overview of the energy and peak load required. The estimate is summarized in Table 20 and is used
as input data for the grid analysis presented in chapter 5.
Figure 15. Substation coverage areas for year 2025 (baseline scenario).
4.1.1 Principles
Grid extensions are simulated on the basis of an automated cost-benefit algorithm in GEOSIM. The
GEOSIM simulations consider favourable geographical conditions (roads) and other obstacles as
well as environmental constraints (lakes or protected areas) when identifying the preferred MV and
LV line routes. The main outputs of the simulation are:
• Number of settlements to electrify;
• Investments at village level, including costs for MV lines, LV lines, transformers, and meters;
• Length of MV lines; and
• Population impacted.
Simulations have been performed of grid extensions and associated investments for non-electrified
settlements in the REMP database for which no electrification program has been identified. Grid
extension simulations are also performed for the non-electrified locations targeted by the Turnkey
III Phase 2, and REDP 2A and 2B programs. However, because these programmes are under
implementation and have already been budgeted, their investment costs are not included in the
results of the analysis.
Unelectrified rural settlements in the REMP database are considered for mini-grid electrification if
they:
1. Are located deep inside National Park, Game and Forest reserve limits;
2. Are located on isolated islands without existing MV lines;
3. Are located beyond 30 kilometres from existing MV lines;
4. Have a population (in 2022) of less than 500 inhabitants AND a distance from existing network
greater than one kilometre;
5. Have an average cost per connection greater than USD 2,000.
The first criterion avoids the construction of overhead lines in sensitive areas where their
installation could harm the aesthetics of environments and landscapes. However, exceptions are
made for towns and villages directly located on the boundaries of these protected areas. The
subsequent four criteria aim to exclude settlements for which the cost of connection per household
would become too high either because they are located are too far from the existing network or
because the number of customers is too low. The limit of 30 kilometres from existing lines is based
Figure 16. Example of a settlements with a high connection cost that can be maintained as candidate for grid
connection.
A number of low-cost solutions for grid electrification have also been considered. This analysis can
be found in Annex H.
2025 (MWh)
Investment
settlements
Population
Peak 2025
customers
Demand
MV line
# of DPs
Region
No. of
(2025)
(USD)
2022
(kW)
# of
2025 (MWh)
Investment
settlements
Population
Peak 2025
customers
Demand
MV line
# of DPs
Region
No. of
(2025)
(USD)
2022
(kW)
# of
Dodoma 45 6 171,780 216 11,795,973 81,307 14,564 10,972
Geita 240 42 950,402 534 51,156,567 440,380 79,131 60,725
Iringa 124 4 231,516 221 16,246,322 136,571 23,690 16,024
Kagera 75 15 324,734 173 16,987,896 145,127 26,207 20,604
Katavi 51 21 311,711 336 19,440,652 134,235 24,410 19,942
Kigoma 34 30 400,859 181 18,679,683 156,027 28,877 25,387
Kilimanjaro 75 3 209,145 95 11,517,033 110,950 19,555 13,853
Lindi 54 1 205,154 97 10,504,356 87,680 15,948 12,814
Manyara 94 13 325,442 361 21,745,354 160,053 28,514 21,257
Mara 61 8 209,174 101 11,198,804 101,346 18,094 13,487
Mbeya 65 1 106,228 91 7,536,501 66,154 11,408 7,518
Morogoro 92 12 247,764 221 15,991,261 130,707 23,050 16,478
Mtwara 247 2 451,112 460 33,157,238 284,417 49,067 31,829
Mwanza 14 2 64,895 42 3,534,568 29,239 5,277 4,129
Njombe 30 0 67,983 121 5,864,242 39,346 6,855 4,659
Pwani 141 11 471,139 408 29,062,160 226,564 40,502 30,580
Rukwa 176 23 549,596 559 35,882,239 269,965 48,039 35,532
Ruvuma 118 5 345,726 399 23,995,360 181,175 31,995 22,798
Shinyanga 153 14 511,817 489 32,855,861 257,828 45,762 33,536
Simiyu 41 10 184,256 122 10,133,700 81,820 14,791 11,664
Singida 61 6 239,909 229 14,912,855 114,651 20,501 15,386
Songwe 30 0 55,259 33 3,471,213 33,218 5,760 3,822
Tabora 169 24 558,413 425 33,455,633 277,481 49,339 36,700
Tanga 331 15 800,712 532 49,034,454 439,518 77,062 53,870
Total 2,550 280 8,153,237 6,624 498,331,855 4,058,635 721,528 533,993
The figure below shows the expected status of MV grid infrastructure when completed in 2025.
4.2.1 Principles
Hydro and biomass power plants, solar PV-battery systems (with diesel as backup) and wind power
are considered as potential mini-grid supply options for the RESP. In principle, the choice of
to the 2020 update of the Tanzania Power System Master Plan (PSMP), two main sources of
information were used in the REMP study to assess the most promising sites in terms of hydropower
mini-grids implementation. The first comes from the Integrated Rural Electrification Planning Study
which was undertaken by REA in 2013 with financing from the European Commission. After a high-
level field study in Mororogo and Lindi regions, 45 sites were identified and georeferenced by the
program. The third source is the Renewable Energy Mapping: Small Hydro Tanzania study from
2015. It was warried out by the Energy Sector Management Assistance Program (ESMAP), a global
knowledge and technical assistance program managed by the World Bank, in close coordination
with REA. From a consolidated database recording 455 sites, 78 locations were visited for more
accurate analyses. To date, the above-mentioned studies give the most complete and accurate level
of information. In all 123 verified sites ranging from 20 kW to 26,000 kW installed capacity were
georeferenced for the REMP studies although only a part of them were used for the simulation of
the mini-grid implementation.
solar mini-grid. Recorded investment costs are in a range of 5.5 to 6 USD/Wp, with LCOEs around
20 https://www.seforall.org/publications/state-of-the-global-mini-grids-market-report-2020
The Global Solar Atlas created by the World Bank, ESMAP and Solargis, was used to define the
overall solar resources assessment as well as the irradiation seasonality (17%).
Tanzania has high levels of solar energy, ranging between 2,800-3,500 hours of sunshine per year,
and a global horizontal radiation of 4–7 kWh per square meter per day. Solar resources are
21 Source: https://www.researchgate.net/publication/351451010_Are_Mini-grid_Projects_in_Tanzania_Financially_Sustainable
3) Agro-industrial Biomass
Medium and small-scale uses of biomass for electricity generation in rural areas are taking off.
Biomass is presently used for electricity generation, especially in the Central (Tanga, Morogoro,
Iringa) and the Northern (Shinyanga, Kagera, Geita) regions of the country. To date, 25 biomass
power plants have a cumulative installed capacity of 58 MW 23 . Almost all are privately owned by
2F2F
sugar, sisal, paper, tea, coffee or saw producers. Among them, seven biomass power plants are
supplying power to the national grid. TPC-Moshi and Kilombero, two major sugar factories are the
most important with 17,5 and 10,5 MW installed capacities. The 18 others are operating for isolated
mini-grids with installed power capacities lower than one MW installed.
The potential for modern biomass uses is high, considering that the raw material available is
abundant and includes:
• Sugar bagasse - 1.5 Mega Ton per Year (MTPY)
• Sisal - 0.2 MTPY
• Rice husk - 0.2 MTPY
• Coffee husk - 0.1 MTPY
• Municipal solid waste - 4.7 MTPY
Further supplies can be obtained through sustainably harvested fuelwood from fast-growing tree
plantations.
The location of potential resources for the development of biomass pants (rice, sugarcane and sisals
fields) comes from the 2013 IREP study (see map below). However, with limited site information,
these estimates remain preliminary and should be considered as purely indicative.
22 Source: Tanzania solar power (TANZANIA INVEST, 2020). Available online: https://www.tanzaniainvest.com/pv.
23 Source: https://www.seforall.org/publications/state-of-the-global-mini-grids-market-report-2020
4) Wind Power
Although many wind power projects have been announced, such as that of the Chinese group Sany
Heavy Industries (600 MW) or the one near Siginda (100 MW) and in Makambako (100 MW) The
Mwenga wind farm (Iringa region) is the first utility scale project that has reached completion, with
a capacity of 2.4 MW. The existence of smaller wind turbines in the country is not known.
According to its developer (Camco Clean Energy), the Mwenga project provides the demonstration
’ j I ,
power projects, by an online review for genset production and wind turbines and by capitalizing on
regional experiences in the PV and biomass sector. The related costs do not include only the
generating plant but also the associated transmission facilities to connect to the grid if that is the
case.
24 Source: ESMAP, Small hydro resource mapping in Tanzania, April 2015, 181 p.
Solar efficiency % 88
Genset efficiency % 90
2) Biomass Projects
As shown in the map below, none of the large, isolated localities that are candidates for off-grid
electrification fall within an area suitable for processing one of the identified agricultural residues
(rice husks, sisals, and sugar cane). For this reason, no simulation of biomass power plants was
Peak PV 2025
Peak PV 2031
2025 (MWh)
Investment
PV projects
population
customers
Demand
Covered
Average
Region
# of LV
(2025)
(2025)
Initial
(USD)
LCOE
(kW)
(kW)
Arusha 4 3,512 289 2,375,023 2,231,814 393 828 0.45
Dar Es
1 430 40 347,669 327,431 55 105 0.44
Salaam
Dodoma 7 14,768 1,103 6,954,718 6,690,122 1,185 2,535 0.45
Geita 3 6,427 475 3,015,174 2,840,981 513 1,023 0.45
Iringa 17 18,050 1,437 10,464,375 9,771,470 1,739 3,679 0.45
Kagera 4 10,341 753 4,628,845 4,519,428 795 1,645 0.44
Katavi 5 12,070 889 5,480,390 5,298,523 938 2,037 0.45
Kigoma 0 - - - - - -
Kilimanjaro 7 9,679 754 5,182,785 5,297,643 865 1,831 0.44
Lindi 12 12,858 1,031 7,764,764 7,378,475 1,290 2,651 0.45
Manyara 5 12,323 892 5,449,470 5,182,955 936 2,070 0.44
Mara 0 - - - - - -
Mbeya 35 22,097 1,945 16,162,546 14,500,719 2,616 5,207 0.45
Morogoro 18 11,239 971 7,763,739 7,834,512 1,255 2,561 0.45
Mtwara 29 28,968 2,333 17,884,868 17,144,959 2,968 6,259 0.45
Mwanza 6 5,122 424 3,209,211 2,949,592 527 1,162 0.45
Njombe 21 27,705 2,166 15,508,544 15,107,843 2,597 5,357 0.44
Pwani 50 58,903 4,685 34,306,721 33,414,884 5,720 11,761 0.45
Rukwa 43 34,076 2,831 21,714,428 19,849,182 3,552 7,358 0.45
Ruvuma 13 26,413 1,947 12,039,487 11,723,921 2,058 4,240 0.45
Shinyanga 5 7,119 564 4,204,435 3,674,868 702 1,443 0.45
Simiyu 0 - - - - - -
Singida 4 8,617 648 4,174,335 3,710,085 710 1,465 0.45
Songwe 8 3,578 331 2,802,360 2,597,737 444 918 0.45
Tabora 5 11,126 835 5,337,244 4,771,990 907 1,929 0.45
Tanga 10 9,848 792 5,793,217 5,717,254 958 1,873 0.45
Total 312 355,269 28,135 202,564,348 192,536,388 33,723 69,937 0.45
Arusha 1,032
Kilimanjaro 566
Tanga 2,955
Manyara 1,498
Pwani 1,084
Dodoma 1,996
Morogoro 1,808
Singida 1,476
Iringa 726
Njombe 690
Mbeya 1,536
Songwe 1,039
Rukwa 770
Tabora 2,859
Shinyanga 1,837
Katavi 501
Kigoma 1,063
Lindi 1,117
Mtwara 1,663
Ruvuma 2,458
Mwanza 1,887
Geita 1,022
Kagera 2,455
Simiyu 2,187
Mara 1,385
Total 37,610
This work is expected to take six years to complete, at an estimated cost of Tsh 7,498,787.77 million,
equal to around USD 3.2 billion 25 . Because no georeferenced database exists of all hamlets in
24F24F
Tanzania, this scope has not been included in the techno/economic optimizations in this RESP. A
verification exercise will therefore be required (see REMP Main Report for further details).
used for distribution. In February 2020, the peak demand (coincidental) in the main grid was 1,152
MW 27 .
26F26F
The installed capacity in the main grid is currently some 1,566 MW according to the 2020 update of
the PSMP. The generation mix is dominated by hydro and thermal power plants. Gas findings off
the coast and the completion of a gas pipeline from the gas fields to Dar es Salaam has boosted the
investments in gas fuelled power plants. The distribution of installed capacity and load across
Tanzania in 2020 is shown in the figures below.
Figure 26. Installed capacity and measured coincidental load in Tanzania 2020.
26 Kigoma, Kagera, Katavi, Rukwa, Lindi, Mtwara and Ruvuma are not connected to the main national grid.
27 Source: 2020 update of the Tanzania Power System Master Plan
Figure 27. Distribution of transmission lines over the short-term, medium-term, and long-term planning
periods according to PSMP 2020.
Figure 28. Planned new generation capacity from 2020-2026 according to the PSMP 2020.
The PSMP 2020 also includes a load forecast for the period towards 2030 which in the figure below
is plotted together with the measured coincidental peak demand in the system as well as the
forecast from the previous PSMP 2016. The estimated system peak for the period up to 2025 is also
included and ‘RE P ’. The estimated peak is based on the assumptions given
in section 5.2.1.. As can be seen from the figure, the actual measured peak demand for 2016-2020
has been consistently lower than the expected forecast from PSMP 2016.
6.5 percent for existing load was applied. The measured system peak load from 2017 and the
estimated system peak load in year 2025 based on a growth rate of 6.5 percent is shown in the
table below. The load for existing factories supplied from Bulyanhulu and Kange is assumed
constant.
Table 32. Measured system peak load in 2017 and estimated system peak load in 2025 30 . 29F29F
Sensitivities
For the purpose of this study, three main sensitivities are considered:
1) Implementation of the North-East transmission project
According to PSMP 2020, the North-East project is planned to be implemented by 2025. The main
components of the North-East project are as follows:
• One double circuit 400 kV line Kinyerezi-Chalinze (93 km)
• Two single circuit 400 kV lines Chalinze-Segera (175 km)
• Two single circuit 400 kV line Segera-Arusha (366 km)
• One double circuit 220 kV line Segera-Tanga (64 km)
• New 400 kV substations at Chalinze and Segera with transformation to 132 and 220 kV and
reactive power equipment
By February 2022 TANESCO reported that project financing for the 400kV lines is in progress and
that the implementation period will be 28 months after completion of the financing arrangement.
Regarding the new substation at Chalinze, work commenced in October 2021 and planned
figures are five years old, it is assumed that the distribution is still representative for the current
situation during dry season. Based on these data, it is assumed that 50 percent of the generation
capacity in the hydro power plants is available at peak load during dry season and this is included
as a sensitivity in the analysis.
600
500
400
[MW]
300
200
100
28.07.2016 01.09.2016
01.10.2016 01.09.2017
Installed hydro power capacity
Figure 30. Hydro power generation for four 24-hour periods during dry season.
JNHPP &
Without JNHPP Including JNHPP
Project Season
North-East Dry Wet Dry Wet
Excluded 90 MW 150 MW 150 MW 150 MW
Included 120 MW 200 MW > 500 MW > 500 MW
In addition, increased transformer capacity and regional transmission reinforcements are required
to facilitate additional load in some substations, highlighting limitations in the main transmission
system. Reinforcements required regionally or at substation level are described in the following
sections.
Mara Region
In the Mara region, the following HV/MV substations are supplied via a 132kV radial from Mwanza:
• Bunda
• Kibara (supplied via a 66 kV radial from Bunda)
• Musoma
• Nyamongo
Without the REMP loads, estimated peak load in the four substations in year 2025 is about 44.6 MW
in total. The existing 132kV line from Mwanza has thermal capacity of about 112 MVA, and the total
distance from Mwanza to Nyamongo is about 300 kilometres.
Table 36. Estimated system peak load and REMP load in Mara region in 2025.
Substation Existing load forecast 2025 REMP load forecast 2025 Total
(MW) (MW) (MW)
Bunda 7.9 53.2 61.1
Kibara 3.1 3.3 6.4
Musoma 11.0 21.5 32.5
Nyamongo 22.6 18.2 40.8
Total 44.6 96.2 140.8
TANESCO has informed that a 7.3 MVAr capacitor bank is installed at Nyamongo substation but has
never been in service. The reason for this is unknown, but severe voltage steps following switching
of the capacitor bank (in the range of 30 percent at the 33 kV busbar) might be a reason.
Figure 32. Voltages in Mara region without the Capacitor bank at Nyamongo in service.
Figure 33. Voltages in Mara region with the Capacitor bank at Nyamongo in service.
Tabora region
In Tabora region, the following HV/MV substations are supplied via a 132 kV radial from Shinyanga:
• Tabora
• Lusu (Nzega)
Without REMP loads, estimated total peak load in the two substations are about 19.6 MW in year
2025. The 132 kV line from Shinyanga has thermal capacity of about 112 MVA, and the total
distance from Shinyanga to Tabora is about 203 kilometres.
Table 37. Estimated system peak load and REMP load in Tabora region in 2025.
The figure shows voltages in the 132kV system in Tabora region for increased rural electrification
at Lusu and Tabora, assuming sufficient transformer capacity to 132kV in Shinyanga substation. The
starting point in the figure (0 MW) is peak load without rural electrification in 2025. When REMP
load is gradually added to Tabora, voltage drops below 0.9 pu for load increase above 20 MW.
Furthermore, it should be noted that the transformer capacity between 220kV and 132kV at
Shinyanga is 2x60 MVA. The transformer capacity is fully utilized for about 82 MW load increase
(REMP load) in Tabora. Considering uncertainties regarding tap changer operation of the two
220/132/33 kV transformers at Shinyanga, the voltage at the 132 kV bus at Shinyanga might very
well be further below 1.05 pu than the model simulation calculated (see figure below). Lower
starting voltage in Shinyanga will further reduce the capacity for increased load (electrification) at
Tabora.
Potential Mitigating Measures in Tabora Region
It might be possible to install reactive power compensation equipment in the 132kV system in order
to increase the voltage towards Tabora substation. This would however require additional 220/132
kV transformer capacity at Shinyanga. Several smaller capacitor banks switched sequentially would
be needed in order to avoid excessive voltage steps. Dynamic reactive power equipment (STATCOM
or SVC) could be an option, but such equipment is expensive.
In PSMP 2020, two 132kV lines from Tabora are proposed. One line is from Tabora to Kigoma via
Urambo and Nguruka, while another line is from Tabora to Katavi via Ipole and Inyonga. The
implementation of these lines includes new substations and transformers at Urambo, Ipole and
Inyonga. The actual implementation plan is uncertain, but it seems reasonable to expedite this
Project rather than invest in reactive power equipment in order to facilitate full rural electrification
in Tabora region.
Table 40. Substations with sufficient capacity for both increased existing load and all REMP load (2025)
1 Yes 33
32F32F Yes Yes
2 No Yes Yes/No
3 No No Yes
4 No No No
All new REMP load can be added without the voltage dropping below
Yes
Sufficient voltage the threshold.
stability Forecasted REMP load cannot be added without the voltage dropping
No
below the threshold.
Prior to implementation of the North-East project, i.e., the 400kV corridor between Arusha and
Kinyerezi, the existing transmission system limits the amount of power that can be transferred from
the generation plants in the Dar es Salaam area to other parts of the country. This is in particular a
challenge during dry season with reduced generation from the hydropower plants. During dry
season at peak load in year 2025, the transmission lines Ubungo-Mlandizi (132kV) and Kidatu-Iringa
(220kV) are overloaded without any new load from the REMP load forecast.
Prio-rity [1-4]
capacity incl.
ulated REMP
system peak
Loading incl.
Voltage [kV]
REMP load
REMP load
REMP load
load [MW]
load [MW]
Substation
Estimated
Total load
Available
capacity
forecast
forecast
Current
HV/MV
HV/MV
Accum-
Region
[MVA]
[MW]
[MW]
[MW]
[%]
Dar es
Ubungo 132 510.0 94.3 44.4 138.7 356.0 27 % 44.4 1
Salaam
Makum- Dar es
132 120.0 88.5 2.2 90.7 25.7 76 % 173.0 2
busho Salaam
Nyumba ya
Kilimanjaro 66 15.0 0.0 0.2 0.2 14.4 1% 173.2 2
Mungu
Iringa Iringa 220 45.0 14.3 22.5 36.8 6.9 82% 263.8 2
Kia Arusha 132 40.0 23.8 8.8 32.6 6.2 82% 272.6 2
Mlandizi Pwani 132 40.0 28.2 14.0 42.2 -3.4 105% 331.7 2
Same Kilimanjaro 132 6.0 4.3 5.9 10.2 -4.4 170 % 337.6 2
Kasiga Tanga 132 25.0 5.4 40.7 46.1 -21.8 184% 378.3 2
Benaco Kagera 220 0.0 0.0 23.0 23.0 -23.0 999 % 401.3 2
Tanga Tanga 132 40.0 37.2 27.2 64.4 -25.6 161% 428.5 2
ulated REMP
system peak
Loading incl.
Voltage [kV]
REMP load
REMP load
REMP load
load [MW]
load [MW]
Substation
Estimated
Total load
Available
capacity
forecast
forecast
Current
HV/MV
HV/MV
Accum-
Region
[MVA]
[MW]
[MW]
[MW]
[%]
Njiro Arusha 220 60.0 77.7 6.5 84.2 -26.0 140 % 435.0 2
Buzwagi Shinyanga 220 45.0 35.3 47.7 83.0 -39.3 184 % 482.7 2
Singida Singida 220 50.0 10.7 79.3 90.0 -41.5 180 % 562.0 2
Nyakanazi Kagera 220 0.0 0.0 0.0 80.4 -80.4 999% 642.4 2
Musoma Mara 132 30.0 11.0 21.5 32.5 -3.4 108 % 715.9 4
Mabuki Mwanza 220 45.0 6.4 40.7 47.1 -3.5 105 % 756.6 4
Tabora Tabora 132 30.0 11.6 46.3 57.9 -28.8 193 % 858.1 4
Dar es
Mbagala 132 30.0 41.7 22.3 64.0 -34.9 213 % 880.4 4
Salaam
Bunda Mara 132 18.0 7.9 53.2 61.1 -43.6 339 % 933.6 4
Mwanza Mwanza 220 60.0 74.8 47.9 122.7 -64.5 204 % 981.5 4
Songea Ruvuma 220 20.0 12.7 89.6 102.3 -82.9 511 % 1071.1 4
Kange Tanga 132 25.0 27.4 86.7 114.1 -89.9 456 % 1157.8 4
Lusu Tabora 132 15.0 8.0 100.7 108.7 -94.2 725 % 1258.5 4
Makam-
Njombe 220 30.0 8.6 140.5 149.1 -120.0 497 % 1399.0 4
bako
Bulyanhulu Geita 220 20.0 44.5 131.6 176.1 -156.7 881 % 1530.6 4
Table 44 presents mitigation measures for HV/MV substations in order to facilitate connection of
the forecasted REMP load.
Table 44. Proposed mitigation measures for HV/MV substations to facilitate connection of the forecasted
REMP load.
Voltage Priority
Substation Region Mitigation measures
[kV] [1-4]
Ubungo Dar es Salaam 132 1 N/A
Kidatu Morogoro 220 1 N/A
Kihansi Morogoro 220 1 N/A
North-East Project
Resolves transmission bottlenecks out
400 kV lines Kinyerezi-Chalinze-Segera- 320,000
from Dar es Salaam
Arusha
Resolves voltage stability constraints for
400 kV lines Kinyerezi-Lindi-Tunduru- Lindi and Songea, as well as
401,000
Songea facilitateFREDP II connection of new REMP
load in Ruvuma region.
New REMP load in Iringa, Njombe and
Mbeya will introduce voltage stability
400 kV lines Iringa-Kisida-Tunduma 213,000 constraints. The lines will resolve this by
connecting the REMP load to the new
substations connected to 400kV.
Facilitates electrification in Mara region
400 kV line Mwanza-Musoma 100,000 and
improves voltage stability
Facilitates electrification in Tabora region
132 kV line Tabora-Kigoma 72,000
and improves voltage stability
Facilitates electrification in Tabora and
132 kV line Tabora-Mpanda (Katavi) 74,000
Katavi regions
Upgrade of transmission lines from 66 kV
220 kV lines upgrade Babati-Mbulu-Karatu to 220 kV to improve voltage stability at
64,000
and Babati-Kondoa Babati, Mbulu, Karatu, and Kondoa
substations
Indicative cost estimates for upgrading of HV/MV substation transformers are presented in
the table below. The estimates are taken from PSMP 2020 and include both the cost of transformer
and the switchgear bay. The cost of a 132kV switchgear bay has also been used for a 66kV
switchgear bay. The transformer upgrades presented in the table are required regardless of the
load increase caused by rural electrification.
A detailed assessment regarding future transformer layout will be required for each HV/MV
substation.
Table 46. Cost Estimates for Transformer Upgrades.
Proposed new
Cost
Substation Region Voltage [kV] transformer
[kUSD]
capacity [MVA]
Substations with insufficient capacity for both increased existing load and new REMP load 2025
Njiro Arusha 220 40 6,800
Mbagala Dar,es,Salaam 132 50 5,600
Nyakanazi Kagera 220 100 7,600
Nearly all the identified grid strengthening projects are already included in the PSMP 2020 update
but need to be prioritized for immediate planning and implementation to avoid severe supply
problems resulting from the planned rural access expansion.
The table below outlines main activities under each project with tentative timing and implementing
partners. A full Monitoring and Evaluation framework is found in the main volume of the REMP,
along with the aforementioned implementation strategies and financing plan.
Table 48. NGAP – Projects and Activities.
1.3 Construction work and commissioning Target areas Year 2-5 TANESCO,
contractors
2.3. Construction work and commissioning Target areas Year 2-5 TANESCO,
contractors
3.3. Construction work and commissioning Target areas Year 2-5 TANESCO,
contractors
4.3. Construction work and commissioning Target areas Year 2-5 TANESCO,
contractors
5.4. Construction work and commissioning Target areas Year 2-5 TANESCO,
contractors
6.3. Construction work and commissioning Target areas Year 2-5 TANESCO,
contractors
7.3. Construction work and commissioning Target areas Year 2-5 TANESCO,
contractors
Costs
The table below contains high-level budget estimates for the seven projects under NGAP. 10
percent have been added to the capital expenditure to cover feasibility studies, project
management, construction supervision, contingencies, and other related costs. Please refer to the
PSMP 2020 for further details on capital costs. Project financing is discussed in REMP Volume 1.
Table 49. NGAP - High-level budget estimates.
Project Cost
(USD million)
REA Partner to TANESCO in program Ensure coordination between NGAP and other
planning programmes under this REMP.
Funds from GoT allocated to Less funds received Seek funds from alternative
TANESCO than requested sources or scale down
activities
Funding from development partners Less or no funds Seek funds from alternative
to match provisions by GoT allocated from sources or scale down
development partners activities
Programme To expand the national grid to all rural areas where this can be done in a
Objective cost-efficient manner.
2: RGAP Wave 1
3: RGAP Wave 2
In order to properly organize this electrification project, the scope is split into five regions as
detailed in the figure below.
The table below outlines main activities proposed to achieve planned objectives, with tentative
timing and implementing partners. It should be noted that the load-flow studies found in the RESP
should be updated once the scope of REDP III (electrification of all 37,610 unelectrified hamlets)
has been georeferenced. The hamlets that can be electrified without investments in the grid over
and above what is outlined in NGAP should be given priority in implementation.
Table 53. RGAP – Projects and Activities.
1.1 Scope verification, detailed electrical All regions Year 1 REA, Consultant
studies and staging of projects
1.2 Preparation of relevant tender documents All regions Year 1 REA, Consultant
for contractors
2.1 Construction and commissioning, Lot 1 Relevant Year 2-4 REA, consultant,
(Central) regions contractors
2.3 Construction and commissioning, Lot 3 Relevant Year 2-4 REA, consultant,
(North) regions contractors
2.4 Construction and commissioning, Lot 4 Relevant Year 2-4 REA, consultant,
(South) regions contractors
2.5 Construction and commissioning, Lot 5 Relevant Year 2-4 REA, consultant,
(West) regions contractors
3.1 Construction and commissioning, Lot 1 Relevant Year 3-8 REA, consultant,
(Central) regions contractors
3.2 Construction and commissioning, Lot 2 Relevant Year 3-8 REA, consultant,
(East) regions contractors
3.3 Construction and commissioning, Lot 3 Relevant Year 3-8 REA, consultant,
(North) regions contractors
3.4 Construction and commissioning, Lot 4 Relevant Year 3-8 REA, consultant,
(South) regions contractors
3.5 Construction and commissioning, Lot 5 Relevant Year 3-8 REA, consultant,
(West) regions contractors
4.1 Include activities to promote PUE in all All regions Years 2-8 REA, microcredit
RGAP projects providers
4.2 Implement connection subsidy for all rural All regions Years 2-8 MoE, REA,
consumers TANESCO
Costs
The table below contains high-level budget estimates for the five projects under RGAP. 10 percent
have been added to the capital expenditure to cover feasibility studies, project management,
construction supervision, contingencies, and other related costs. Cost-breakdowns for the projects
originating in the REMP database can be found in Annex C.
Project Cost
(USD million)
1: Scope verification 5 35
34F34F
Total 4,025
Funds from GoT allocated to REA Less funds received than Scale down activities
for implementing RGAP requested
There is sufficient grid capacity If the main grid is not Implement required NGAP
for connection of new projects strengthened in parallel with grid strengthening
grid electrification of rural measures in parallel with
areas, provision of reliable grid electrification
access to electricity might not
be possible.
TANESCO has financial capability TANESCO has not enough Ensure cost-reflective
to maintain grid funds to ensure maintenance tariffs
of new lines
Power losses and voltage drops Energy losses increase Validate network
dramatically due to voltage extensions with detailed
drop. Actual network collapse electrical studies
due to a poor network
analysis
Overall Objective To provide reliable electricity supply to scattered households and remote
locations where grid extension is not a viable option
Given the vibrant developer community still present in Tanzania, and that Tanzania has one of the
best regulatory frameworks for private mini-grids in Africa it is deemed appropriate that the private
sector is tasked with serving the locations which are recommended for electrification through mini-
grids. This reduces the need for scares public investment resources, and, given proper regulatory
oversight, ensures that international best practices are leveraged. Pending further analysis, 20-year
concessions for all mini-grid within each of the five zones are envisioned, complete with PUE-
components to induce demand.
The figure below presents the number of mini-grids and aggregated investment costs per zone.
The table below outline main activities proposed to achieve planned objectives, with tentative
timing and implementing partners.
Table 57. BGAP – Main Activities.
1.2 Tender for private sector developers REA HQ Year 1 REA, EWURA,
consultant
3.1 Streamline best practice into Dodoma Year 1 MoE, REA, EWURA,
Tanzanian rules and regulations Consultant
Costs
The table below contains high-level budget estimates for the two projects under BGAP. 10 percent
have been added to the capital expenditure of mini-grids to cover tendering, project management,
construction supervision, contingencies, and other related costs. It is, as further discussed in the
financing plan of Detailed cost-data for mini-grids can be found in Annex D.
Project Cost
(USD
million)
Project 1: Tendering of mini-grid concessions from the private sector (including 205
total investment costs for mini-grids)
Total 236
EWURA Regulator of the energy sector Provide required approvals, and regulatory
in Tanzania oversight during approval, construction, and
operations.
Private Develops, owns, and operates Successful tenderer will develop, own, and
developers private mini-grids operate the relevant mini-grids.
Ports Manages and operates the Supports compliance with existing rules and
Authorities ocean ports and lake ports of regulations for import of goods required for
Tanzania electrification
Funds from GoT allocated to REA for Less funds received Scale down activities
implementing NGAP than requested
The Rural Energy Agency (REA) is established the under the Ministry of Energy (MoE) to promote and facilitate
availability and access to modern energy services in rural Mainland Tanzania. The CEAP is intended to be
operationalized as a guiding tool for MoE through REA. Aiming to stimulate a gradual transition towards
cleaner cooking, it presents a set of concrete actions along three main programmes and also provides policy
level recommendations aimed at creating a favourable framework to enable an energy transition in rural
parts of Tanzania mainland.
Since its establishment REA has successfully provided rural electrification across Tanzania and has a strong
institutional capacity for implementing programmes for grid extension and support for renewable energy
projects. The REACE programme aims at building REA’s capacity for support and implementing projects also
for improved and clean cooking. The programme aims at enhancing existing infrastructure and institutional
arrangements in REA for monitoring and coordination of cross-sectoral efforts involving different
stakeholders and development partners. It also seeks to leverage ongoing initiatives by other actors in the
energy, environment, forestry, and health sectors, to create a strong institutional framework for achieving
the SE4ALL targets.
The REACE programme is designed to achieve five specific objectives: 1) Strengthen REA’s institutional
capacity for implementing and coordinating interventions related to cooking energy services in rural
mainland Tanzania; 2) Strengthen REA’s capacity for outreach in remote parts of Tanzania mainland and areas
with low population density; 3) Strengthen REA’s capacity for application of the ESMAP MTF, VPT and
national standards in energy-sector interventions; 4) Develop and apply a geospatial planning tool for
planning, coordinating and monitoring cooking energy interventions; 5) Establish national monitoring of
cooking energy sector.
The two programmes TrICS and ACCeS build on market-based approaches for scaling up access to improved
cookstoves (ICS) for biomass energy, and clean cooking solutions in rural Tanzania. Both programmes include
financial support to projects as well as development of technical expertise, and aim at enhancing
affordability, availability and sustainability of cooking fuels and technologies; promoting scale-up of supply
chains through entrepreneurship and micro-credit services; social marketing of energy technologies;
alternative delivery models; and engaging pilot end users of energy solutions across micro and meso level.
The populations targeted for interventions in TriCS and ACCeS are to be differentiated based on socio-
economic indicators, distance to infrastructure, and population density in settlement area. The majority of
Tanzania’s rural population make their livelihoods in agriculture use, have low degree of access to modern
energy services, and rely on VPT Tier 0 or 1 cooking solutions.
TrICS will mainly be targeting the population with lower income, in areas with low population density. The
programme promotes transition to biomass energy and stove solutions ranked as VPT Tier 2 and 3, regarded
List of Figures
Figure 1 Urban districts and rural areas in mainland Tanzania. ......................................................................................... 1
Figure 2 Regional wood fuel dependency and primary fuel used for cooking. .................................................................. 3
Figure 3. Development process of the CEAP. ...................................................................................................................... 7
Figure 4 Consumption pattern by settlement type .......................................................................................................... 10
Figure 5 Drivers of change ................................................................................................................................................ 13
Figure 6 Barriers to transition to cleaner cooking in Tanzania ......................................................................................... 13
Figure 7 Baseline (NBS, 2016), Business as Usual scenario vs. SE4ALL target. ................................................................. 19
Figure 8 Possible end situation in 2030 achieving the overall SE4ALL goal. ..................................................................... 20
Figure 9 SE4ALL scenario, allocation on VPT Tiers. ........................................................................................................... 23
Figure 10 Programme descriptions for CEAP. ................................................................................................................... 24
Figure 11 Cooking solutions, ranked by VPT Tiers, and relevance in CEAP’s programmes. ............................................. 25
Figure 12 REA’s organisational structure .......................................................................................................................... 69
1 ESMAP (2020): The State of Access to Modern Energy Cooking Services. The World Bank: Washington D.C.
2 MEM (2015): SE4ALL Action Agenda. Ministry of Energy and Minerals: Dar es Salaam.
3 IEA (2020). Tanzania Country Profile. URL: https://www.iea.org/countries/tanzania, accessed 10 November 2020. International Energy Agency: Paris.
4 NBS (2020). Energy Access and use Situation Survey II in Tanzania Mainland 2019/20. Summary of Key Findings. National Bureau of Statistics: Dar es Salaam.
5 NBS (2019). Tanzania Mainland. Key Indicators Report. 2017-18 Household Budget Survey. National Bureau of Statistics: Dar es Salaam.
As evident from the map above, biomass energy provides an affordable and accessible energy option in most
areas in the country. In rural areas, firewood is readily available from local sources, and energy costs are
largely unaffected by volatile energy prices in international markets. Use of domestic biomass energy thus
contributes to securing domestic energy supply. Reliance on biomass as a domestic and renewable source of
energy also contributes to national supply security and balance of payments. Increasing demand for charcoal
in urban areas has created a large charcoal sector, which provides a significant source of employment and
revenue generation and contributes to redistribution of capital to rural areas.
However, the strong reliance on biomass also represents a range of challenges.
Inefficient combustion of biomass energy leads to an increased disease burden in the country and a high
number of pre-mature deaths. Indoor air pollution has been estimated to cause 33,024 premature deaths
annually in Tanzania. High levels of particulate matter and reactive chemical substances in smoke also
increases the disease burden. Disability Adjusted Life Year (DALY) is a measure of overall disease burden,
expressed as the cumulative number of years lost due to ill-health, disability or early death. The Global
Burden of Disease study estimated indoor air pollution to take 1,414,699 DALYs in Tanzania 6 .
Traditionally, women and men have different roles, responsibilities and voices within households and in
markets. Women are often the primary cooks in the households, and indoor air pollution and provision of
6 GBD (2016) Global Burden of Disease Study 2016. Institute for Health Metrics and Evaluation: Washington DC.
7 UNFCCC (2012). Information note. Default values of fraction of non-renewable biomass for least developed countries and small island developing States. Clean
Development Mechanism. EB 67, Report, Annex 22.
8 TFS (2015). NAFORMA. National Forest Resources Monitoring and Assessment of Tanzania. Main results. Tanzania Forest Services Agency and Doggart, N., Morgan-
Brown, T., Lyimo, E., Mbilinyi, B., Meshack, C. K., Sallu, S. M., & Spracklen, D. V. (2020). Agriculture is the main driver of deforestation in Tanzania. Environmental
Research Letters, 15(3), 034028.
9 Choumert-Nkolo, J., Motel, P. C., & Le Roux, L. (2019). Stacking up the ladder: A panel data analysis of Tanzanian household energy choices. World Development, 115,
222-235.
10 EWURA (2019). Energy and Water Utilities Regulatory Authority Annual Report 2018/19. Tanzania: Dar es Salaam.
11 NBS (2019). Tanzania Mainland. Key Indicators Report. 2017-18 Household Budget Survey. National Bureau of Statistics: Dar es Salaam.
12 NBS (2020). Energy Access and use Situation Survey II in Tanzania Mainland 2019/20. Summary of Key Findings. National Bureau of Statistics: Dar es Salaam.
13 ESMAP (2020). Cooking With Electricity. A Cost Perspective. The World Bank: Washington DC.
2.1.3 Options and Approaches for Improved Cooking in Rural Mainland Tanzania. Socio-
Economic Analyses
Findings from the Inception phase and the demand analysis, projections and targets were analysed further
through economical and financial assessments of each of the prioritized options to show the economic
attractiveness of the various options as well as the attractiveness from the users’ financial perspective.
The analysis identified important barriers for market development existing for various energy options. These
were related to energy security as well as the environmental, social and cultural values or costs that each
option represented. The analytical approach to account for such factors included a qualitative assessment of
each option along five dimensions:
i. Availability
ii. Affordability
iii. Technology development
iv. Environmental and social sustainability
v. Regulation and governance
The analysis also provided an overview of indicative associated costs and required market developments as
well as indicative public action that will be required to achieve targets.
The baseline consumption pattern of cooking energy is shown in the figure above. It illustrates the strong
dependence on biomass in different types of settlement areas and highlights the difference in consumption
patterns across the rural/urban divide. Biomass energy is prevalent in both urban and rural areas. Firewood
is commonly used in rural areas whereas proportion of charcoal use increases with degree of urbanization.
Diversity of the energy mix both at aggregate level and at household level increases with population and
degree of urbanization. A household context with reliance on multiple fuels for cooking is common in urban
and peri-urban areas of Tanzania. This is in part driven by the increasing availability of fuel and stove
14 The analyses were undertaken in 2017; however the situation has remained largely unchanged (NBS, 2019; NBS, 2020).
Consumption forecasts for energy use and impact on demand for biomass energy has been modelled based
on the baseline data, as detailed in chapter 4.4. The projections show that in a ‘Business as Usual’ scenario,
which assumes organic and market driven growth continuing without a significant step-up of efforts to
accelerate the transition, the large majority of the population, in particular the rural population, would
continue to rely on biomass and inefficient cooking methods. While the relative portion of the population
relying on biomass would somewhat decrease, the demand for biomass would continue to increase due to
the increased population.
The rate of consumption of forest biomass will increase. Forest degradation has substantial negative impact
on local and regional ecosystem services and biodiversity, as well as on net greenhouse gas emissions for
Tanzania.
The annual consumption of biomass energy in Tanzania is estimated at 62.3 million m3, while the sustainable
yield is estimated at 42.8 million m3, leaving a 19.5 million m3 deficit. This “gap”, defined as the negative
difference between allowable cut and actual cut, is deforestation caused by clearing of new agricultural land
and unsustainable use of wood fuels. In Tanzania about 373,000 Ha/year of forest was lost from 1995 to
2010 16 .
The population size in mainland Tanzania was estimated to 52,691,314 for 2018 17 . The population grows at
2.9 percent per year. Rural use of firewood is less harmful to forests than charcoal burning and use of charcoal
in urban areas is widespread in urban Tanzania. Charcoal consumption mainly in urban areas has nearly
doubled over the past ten years due to urbanisation and high prices or scarcity of the alternatives such as
kerosene, electricity and LPG. It is projected that demand for charcoal, without supply and demand side
interventions will double by 2030, from approximately 2.3 million tonnes of charcoal in 2012.
Meanwhile, little to no correlation with level of forest coverage and per capita consumption of biomass
energy has been found across Tanzania’s regions (Phase 2). This suggests that in rural areas, there is either
no scarcity of firewood, or that there is high degree of elasticity in the demand for energy for cooking. The
cost incurred by increasing deforestation may be the time it takes to collect firewood, a burden often carried
by women, or a reduction in the quality of the biomass fuels used for cooking. Local deforestation therefore
potentially has a double negative impact on women caused by the additional burden of firewood collection
with increasing distances, and the increased indoor air pollution from low-grade fuels.
15 Choumert-Nkolo, J., Motel, P. C., & Le Roux, L. (2019). Stacking up the ladder: A panel data analysis of Tanzanian household energy choices. World Development, 115,
222-235.
16 TFS (2015). NAFORMA. National Forest Resources Monitoring and Assessment of Tanzania. Main results. Tanzania Forest Services Agency.
17 NBS (2012). Population and Housing Census 2012, National Bureau of Statistics: Dar es Salaam.
Sex
Age
As seen in the table above, health impacts caused by indoor air pollution are high among elderly people and
children below 5 years of age. This is mainly because of long term effects of smoke exposure that exacerbates
chronic disease outcomes during the older age and the fact that children at those ages spend more time
indoors and remain vulnerable to shorter term health effects than the rest of the age groups.
18 MoHCDGEC (2019). Health and Pollution Action Plan. United Republic of Tanzania. UNIDO: Dar es Salaam.
19 GBD (2016) Global Burden of Disease Study 2016. Institute for Health Metrics and Evaluation: Washington DC.
3.4.1 Affordability
Affordability is determined by the cost of a given
cooking solution and people’s ability and
willingness to pay. Rural areas are characterized by
low-income levels from partial subsistence
livelihoods in agriculture, and often imperfect Figure 6 Barriers to transition to cleaner cooking in Tanzania
markets. In Tanzania the poorer segments spend
about 35 percent of their household income on
energy while the better-off spend only 14 percent
for the same 20 . Low ability to pay in rural areas is an
important barrier to improving energy services for
a large part of Tanzania’s population.
In urban areas LPG is currently more affordable
than charcoal. In 2008-2009 import duties and VAT Figure 5 Drivers of change
were removed from LPG products and the
consumption of LPG is growing rapidly. This growth stems from increasing usage LPG by wealthier households
and commercial establishments, and by a continuous increase in the price of charcoal, particularly in urban
centers. The increasing cost of charcoal is a result of levies on charcoal and other policies to reduce charcoal
consumption. In contrast to urban areas, rural Tanzania presents an energy context where locally bought or
collected firewood is the primary cooking fuel. Modern fuels and stove alternatives are scarcely available and
cannot compete cost-wise, in particular against the alternative of freely gathered firewood. Further, even
when the long-term running costs of an alternative solution is competitive, the purchase of an improved
stove or a cylinder and stove for LPG may represent an unsurmountable upfront investment for many rural
households.
Tanzania depends on importing all LPG and kerosene, which burdens the country’s economy and rural
communities. Prices of imported fuels are volatile and have been hindering the efforts to increase the rural
energy access. The price of LPG also reflects several layers of fees and levies applied by central and local
authorities throughout the supply chain. Low-income households are particularly vulnerable to the volatile
energy costs because they have few assets to fall back on and limited ability to afford to energy related costs
and effects.
3.4.2 Availability
In rural Tanzania, lack of infrastructure to ensure availability of modern fuels in the markets is a key challenge.
Policies centered on price changes may not be effective in changing consumer behavior unless alternatives
are readily accessible. Rural markets are unattractive for commercial market actors such as LPG distributors
due to low population density, high logistical costs and low demand. Ensuring availability of improved and
clean alternatives for cooking in rural Tanzania will require substantial investment in infrastructure, such as
20 MEM (2017). Project Document: SE4ALL Implementation in Tanzania Programme (SITAP). Ministry of Energy and Minerals: Dar es Salaam.
21 NBS (2020). Energy Access and use Situation Survey II in Tanzania Mainland 2019/20. Summary of Key Findings. National Bureau of Statistics: Dar es Salaam.
The Tanzanian SE4ALL Action Agenda towards 2030 states a commitment embracing as a fact that the access
to modern energy services is a precondition for development goals, beyond the energy sector, such as
poverty eradication, access to clean water and clean energy sources in order to increase health conditions,
improved public health, education and women empowerment, and even increase food production. The
SE4ALL Action Agenda provides the most concrete quantified target, shown in the table below. The ambition
is access to modern cooking solutions for 75 percent of the population by 2030. It targets an increased
percentage of Tanzanian population with access to modern cooking solutions from 16 percent in the baseline
year 2012 to 34 percent by 2025, and 75 percent by 2030.
22 MEM (2015). The National Energy Policy. 2015. Ministry of Energy and Minerals: Dar es Salaam.
Doubling global
Universal access to modern energy rate of Doubling share of renewable energy
services improvement of in the global energy mix
energy efficiency
23 MEM (2017). Project Document: SE4ALL Implementation in Tanzania Programme (SITAP). Ministry of Energy and Minerals: Dar es Salaam.
24 VPO (2021). Nationally Determined Contribution. Vice President’s Office: Dodoma.
Table 3 SDG7, Ensure access to affordable, reliable, sustainable and modern energy for all.
SDG7.1 By 2030, ensure universal access to affordable, reliable and modern energy services
SDG7.2 By 2030, increase substantially the share of renewable energy in the global energy mix
By 2030, enhance international cooperation to facilitate access to clean energy research and
SDG7.a technology, including renewable energy, energy efficiency and advanced and cleaner fossil-fuel
technology, and promote investment in energy infrastructure and clean energy technology
By 2030, expand infrastructure and upgrade technology for supplying modern and sustainable energy
services for all in developing countries, in particular least developed countries, small island developing
SDG7.b
States, and land-locked developing countries, in accordance with their respective programmes of
support
Figure 7 Baseline (NBS, 2016), Business as Usual scenario vs. SE4ALL target.
To map out the required progress in different segments of the population with regard to uptake of different
cooking systems, an SE4ALL Scenario for Transition to Improved and Clean Cooking has been simulated.
Aiming to contribute to the SE4ALL ambition while taking a special focus on energy use in rural areas, the
25In the SE4ALL terminology ‘modern cooking’ is understood to include both Improved Cooking Services such as ICS and Clean Cooking
Solutions. In contrast, the ESMAP Multi-Tier Framework defines Modern Energy Cooking Services (MECS) as achieving Tier 4 or above.
Tanzania Mainland 2030 Assumptions for Rural Areas 2030 Assumptions for Urban Areas by 2030
Figure 8 Possible end situation in 2030 achieving the overall SE4ALL goal.
The resulting end situation in 2030 for national, rural and urban areas is shown in the figure above.
Implications with regard to transition within specific population groups toward improved or clean cooking
energy is outlined in the table below.
The scenarios show that achieving the SE4ALL target implies that the part of the population that continues
to remain on biomass as primary cooking fuel will have to fall to short of 50 percent of the population, and
of this almost half will use ICS. LPG needs to be ramped up to reaching 30 percent of the population. While a
large share of this will happen in urban areas, CEAP also takes the ambition of two million rural and semi-
rural households transitioning to LPG.
The implied ambition for rural areas of the SE4ALL scenario is an ambitious one and the extent to which it is
realistic will rely on not only successful implementation of CEAP: It is important to recognize that achieving
this situation assumes a particularly fast change in urban areas, including reducing the reliance on biomass
to a mere 20%, supplying more than forty percent of the urban population with LPG, and more than one third
accessing other clean solutions, such as eCooking, natural gas, and ethanol.
In rural areas, which is the primary focus of this Action Plan, the population relying on biomass will have to
decline to around 65 percent, and of these, 40 percent must gain access to improved cooking services. LPG
distribution, primarily targeting relatively densely populated, rural towns and other rural areas within reach
of access roads, will have to be used by more than a fifth of the rural population.
Reaching this scenario will require significant scaled-up supply capacity for the various solutions. Some
numbers are presented to illustrate the table below. Achieving these developments by 2030 will require
massive, coordinated public efforts, combined with a focus on facilitating market development through an
enabling framework and creation favourable conditions for commercial actors; building awareness and
promoting behavioural change.
➔ % of rural 60% of the population in rural areas achieves access to improved or clean forms of
population cooking (75 percent on national level and 92 percent in urban areas).
with access
➔ Woodfuel Significant reduction of wood fuel consumption compared to 2016 (more than 60
demand percent reduction (20 percent less) than the assumed Business as Usual levels in 2030)
With regard to woodfuel demand, the strong reduction assumes great advances in biomass management as
a prerequisite for achieving targets for total biomass consumption that is close to that of SE4ALL. The
development in the urban area requires strong regulation on charcoal and massive rollout of LPG, as well as
implementation of plans for other clean fuels such as gas and ethanol. LPG consumption will increase 5-fold
and storage capacity for LPG to allow for this.
It becomes clear that in order to reach the ambitious SE4ALL goals, the scale of the transition and thus the
efforts required to achieve it, are colossal. Implementing CEAP will contribute but not alone ensure these
results. Efforts will be needed on several levels and involve stakeholders across the Tanzanian society and
embrace broad-based action, from national energy policies, improved regulatory framework, and improved
coordination, to infrastructure investments, market development, and creating cultural and economic
incentives to change energy consumption patterns.
The SE4ALL scenario from section 4.4 has been categorised according to VPT Tiers for cooking solutions, as
outlined in the figure below. The illustration emphasises performance of cooking solutions over specific
designs.
26 http://catalog.cleancookstoves.org/
The National Bureau of Statistics (NBS) implements the project Impact of Access to Sustainable Energy Survey
(IASES) which is a country-wide survey to assess the impact of SE4ALL interventions from 2015 until 2020.
IASES builds on the MTF, with elements from the MTF-based impact assessment recently done in Rwanda 27 .
As a continuation of IASES the MTF can be applied for monitoring progress in implementation of CEAP. This
is planned in the REACE-programme, outlined in chapter 5.
27 ESMAP (2018). Rwanda Beyond Connections. Energy Access Diagnostic Report Based on the Multi-Tier Framework. The World Bank: Washington DC.
The CEAP objective to foster a transition of cooking energy consumption in rural Tanzania, is aligned with
objectives in the NEP 2015, the SE4ALL and the SDGs. Achieving the targets constitutes significant structural
and economic changes in Tanzania’s energy sector as well as a societal transformation of domestic energy
use. Expansion of improved and clean energy services for cooking in rural and peri-urban areas requires
strong public sector support to overcome barriers of availability and affordability. Executing the three
programmes implies cooperation with and support to private sector actors and market-based approaches to
stimulate to the development of a viable and demand-driven energy sector. The programmes activities fall
within REA’s mandate, as stipulated in the Rural Energy Act of 2005.
The CEAP provides a framework for implementation where REACE builds capacity within REA for executing
and coordinating interventions related to cooking energy, in order to create a strong basis and institutional
framework to support the implementation of TrICS and ACCeS
The REACE-programme addresses the need for increased capacity and competence within REA required to
support the advancement of improved and clean cooking. Capacity building is achieved through establishing
a structure within REA with a mandate to implement CEAP; enhancing technical expertise in REA on cooking
energy technologies; increasing regional capacity in REA for implementation of cooking energy interventions;
develop and implement a geospatial planning tool for planning of interventions; and conduct country-wide
surveys to assess the impact of interventions under REMP.
The two programmes TrICS and ACCeS build on market-based approaches for scaling up access to improved
and clean cooking in rural Tanzania. TrICS promotes fuel and stove solutions ranked as VPT Tier 2-3 (see figure
11). ACCeS promotes fuel and stove solutions ranked as VPT Tier 4 and 5, regarded as clean cooking services.
Both programmes include financial support to projects as well as development of technical expertise, and
aim at enhancing affordability of cooking fuels and technologies; promoting scale-up of supply chains through
entrepreneurship and micro-credit services; social marketing of energy technologies; and engaging pilot end
users of energy solutions in the domestic sector, commercial enterprises and public institutions.
The populations targeted for interventions in TriCS and ACCeS are to be differentiated based on socio-
economic indicators and settlement area. The majority of Tanzania’s rural population make their livelihoods
in agriculture use, have low degree of access to modern energy services, and rely on VPT Tier 0 or 1 cooking
solutions. TrICS will mainly be targeting the population with lower income, in areas with low population
density. ACCeS will mainly be targeting the rural population living in proximity to roads and other
infrastructure, typical semi-rural areas around district and urban centres.
The following sections outline the key features of each programme, including their respective associated
projects or actions, proposed implementation strategy and involvement of relevant stakeholders, and lay out
the assumptions that provide the basis for detailed scoping and implementation planning of the respective
projects.
An aggregated plan for cost and financing of the CEAP is presented in section 5.4, and a framework for
monitoring progress is included in the REMP Main Report (Volume 1).
5.1.2 Objectives
The Overall Objective of REACE is:
To increase REA’s capacity for fulfilling its mission “To promote and facilitate availability and access to
quality modern energy services in rural Mainland Tanzania” in the area of cooking energy.
REACE has five Specific Objectives:
1. Strengthen REA’s institutional capacity for implementing and coordinating interventions related to
cooking energy services in rural Tanzania.
2. Strengthen REA’s capacity for outreach in remote parts of Tanzania mainland and areas with low
population density.
3. Strengthen REA’s capacity application of the ESMAP MTF, VPT and national standards in energy-
sector interventions.
4. Develop and apply a geospatial planning tool for planning, coordinating, and monitoring cooking
energy interventions nationally.
5.1.3 Rationale
REA is to provide capacity building services, awareness creation and financial support for projects, and shall
“finance eligible rural energy projects that result in improvement in the livelihood of rural community” (see
section 7.3 for further details). REA has since its inception expanded access to electricity in rural Tanzania,
but efforts related to provision of cooking energy services have been marginal in comparison. Institutional
level development within REA combined with improvements across multiple sectors and institutions to
create an enabling framework of policies, regulation and institutions is necessary to ensure strong progress
in this area. To coordinate implementation of CEAP, REA requires strengthened institutional capacity.
Implementation of CEAP is an opportunity to establish REA as a lead actor to coordinate efforts from
development partners, private sector and public institutions. REA’s mandate to promote, support, facilitate,
stimulate, and improve access to modern energy services in rural areas positions the agency to take a lead
role in contributing to the SE4ALL goal.
The SE4ALL goal requires a country-wide effort reaching energy users in remote parts of rural Tanzania as
well as villages and towns with limited infrastructure. The population suffering most from household air
pollution and other burdens of cooking with traditional fuels and stoves live in areas with limited accessibility
and affordability of modern energy services. CEAP outlines market-based approaches to scale up access to
improved energy services, but substantial public sector support is required in remote areas with low demand.
The MoH is addressing indoor air pollution through public policy and the Health and Pollution Action Plan
from 2019. The MNRT and TFS oversee interventions regulating the supply side of biomass energy use. The
initiative Integrated Approach to Sustainable Cooking Solutions supported by the EU aims at promoting
sustainable management of forest resources while improving access to clean and improved cooking
solutions 28 . In parallel EU intends to support the Tanzania Energy Sector Reform Programme, foreseen to
provide technical support to the MoE updating the BEST and implementation of a regulatory framework for
clean cooking energy. The REACE programme will build on, contribute to, and align with other public sector
initiatives in the area of cooking energy.
REA has limited presence regionally in Tanzania. Seven electrical engineers represent REA through each of
TANESCO’s seven zonal offices on Tanzania Mainland. Their mandate is to facilitate coordination and
supervision of REA projects. This includes liaising between REA and stakeholders such as
contractors, TANESCO and President's Office Regional Administration and Local Government (PO-RALG). The
Zonal Engineers have mainly been involved in rural electrification projects and have limited experience with
projects related to cooking energy. Strengthened capacity of REA’s regional outreach is necessary for
implementation of CEAP and contributes wide-reaching efforts in remote rural areas also beyond 2030. Close
collaboration with PO-RALG is an important premise for implementation of CEAP programmes.
To achieve the SE4ALL goal, production and use of ICS must increase substantially towards 2030. An
increasing body of research shows that not all stoves labelled as ICS constitute significant improvements of
thermal efficiency and impact on indoor air pollution. Recently developed national and international
standards for stoves, fuels and access provide a basis for ensuring that ICS meet achieving the REMP targets.
Implementation of standard TZS473:2019 for biomass cookstoves can contribute to improve energy services.
Tanzania Renewable Energy Association (TAREA) and SNV Netherlands Development Organisation (SNV) are
currently working with Tanzania Bureau of Standards (TBS) through the EnDev III programme (2017-2021) to
promote the biomass cookstove standards. Enforcement of cookstove standards is also supported through
28 EU (2020). Action Document for Integrated Approach to Sustainable Cooking Solutions. European Development Fund (EDF): ΤΖ/FED/040-142
29 MEM (2015). Tanzania's Sustainable Energy for All Action Agenda. Ministry of Energy and Minerals: Dar es Salaam.
MoE Overall programme overseer Coordinate interventions in REACE with initiatives and
programmes under other energy agencies and
ministries
PO-RALG Oversees policy and interventions Ensure anchoring, relevance and implementation of
regionally, at district level and cooking energy interventions from district level and
locally locally. CEAP nation-wide coordination and monitoring
MIT Oversees industrial development Provide advice and policy coordination for capacity
building under REACE related to industrial
development in the cooking energy sector
MoH Oversees public health protection Provide advice and policy coordination for capacity
from all causes including health building under REACE related to indoor air pollution
impacts caused by cooking
MNRT Oversees policy and regulation for Provide advice and policy coordination for capacity
management of natural resources building under REACE related to supply of biomass
energy
MoCDGWS Oversees policy on community Provide advice and policy coordination for capacity
development and gender equality building under REACE related to gender
REA Implementing agency Coordinate overall effort in REACE; Revise routines and
organisational structure; Organize trainings; Strengthen
human resources in REA HQ and REA’s collaboration
regionally and at district level; Use the GIS software for
planning interventions in rural Tanzania; Procure and
oversee Technical Assistance contracts
TPDC National supplier of petroleum Provide advice and policy coordination for capacity
energy building under REACE related to natural gas and LPG
LGA Local partner for REA’s regional Collaborative partner for coordination and
offices strengthening of capacity in REA’s regional zones
NEMC National partner to ensure Provide advice on how to meet health and
compliance with environmental environment targets, and ensure that interventions
and health impacts of interventions supported by REA are in compliance with national
regulations
TFS Develops and manages national Collaboration for capacity building under REACE related
forest resources to supply of biomass energy
TANESCO National electricity utility Partner in revision of regional capacity and routines of
REA
TBS Formulates and delivers standards, Provide advice and training for implementation of
safety measures, and conformity TZS473:2019 in Tanzanian cookstove markets
assessment
NBS Provides official statistics to the Implementation of surveys for monitoring impact of
Government, business community interventions in CEAP and by other stakeholders, as per
and the public at large the SE4All targets for the country
Research and Conducts research and education Provide training on improved cooking solutions to REA
educational on energy staff Provide training on prevention of indoor air
institutions pollution to REA staff
NGOs and NGOs and SMEs working Provide training for REA in Tanzanian cookstove
commercial actors renewable energy in Tanzania technologies and markets
REA HQ,
1.4 Train staff with relevant expertise for Dodoma
Year 2 - 5 REA
supporting cooking energy interventions
Project 2: Increased capacity for reaching remote rural areas with cooking energy interventions
REA HQ,
Dodoma
2.1 Revisit REA’s regional outreach and reorganize
Year 1 - 2, 5 MoE, REA, PO RALG
if necessary Regions and
districts
2.2 Train and recruit staff with relevant expertise REA Year 2 - 4 REA
2.4 Coordinate activities with PO RALG and private Target regions REA, PO RALG, private
Year 2 - 8
sector and districts sector
3.1 Develop a plan for integration of TBS-standards REA HQ, MoE, MoH, TBS, REA, and
Year 1 and 2
and MTF in Tanzania Dodoma other stakeholders
3.2 Train REA staff in the plan for implementation REA HQ, REA, VPO, TBS, and other
of national and international standards Dodoma Year 2
stakeholders
Project 4: Deployment of geospatial planning tool for planning and monitoring cooking energy interventions
REA HQ,
4.3 Train REA staff in use of GIS software Year 2 - 3 REA, software provider
Dodoma
REA HQ,
4.5 Apply GIS software to oversee REA’s and other Dodoma
Year 2 - 8 REA, PO RALG
stakeholders’ programmes on cooking energy Target regions
and districts
5.1 Analyse results from IASES REA HQ, Year 1 and 2 NBS, REA, MoE, EWURA,
Dodoma TANESCO and PO RALG
5.3 Apply results from the IASES surveys for REA HQ, Year 2 - 8
monitoring progress towards the REMP and SE4All Dodoma REA
targets
Funds from GoT allocated to REA for Less funds received than Sensitization/awareness to decision-
implementing REACE requested, or delay of makers on clean cooking; Scale down
funds to implementing activities, or postpone activities
agencies
Funding from development partners to match Less or no funds REA prioritises parts of CEAP that can
provisions by GoT allocated from be conducted without large
development partners investments
Staff competence and capacity for Limited capacity and Hire staff based on competency
implementing CEAP competence for required
implementation
Sufficient staff for REA’s regional extension Few or no additional Train existing REA staff and allocate
staff hired to implementation of CEAP
Private sector and government institutions Partners do not commit REA prioritises parts of CEAP that can
engaged in implementation of REACE to REACE be conducted without strong
partnerships
Financial support for IASES II and III No financing received Collaborate with NBS to conduct
lighter version of IASES II and III
TrICS builds on existing mechanisms for project support within REA’s mandate. An important assumption is
that REA’s technical expertise on cooking energy has been enhanced, with sufficient available capacity in
REA’s HQ and regionally developed through the REACE programme.
5.2.2 Objectives
The Overall Objective of TrICS is:
To promote access to improved cooking services and stimulate rural energy markets
5.2.3 Rationale
A market-driven energy transition towards improved cooking services is gaining momentum in Tanzania’s
cities and large towns. In rural areas however, a series of interlinked challenges hinder the necessary pace of
a transition to widespread use of ICS. Barriers include affordability, availability, culture and traditions, and
lack of awareness of health effects of indoor air pollution. Rural populations generally have lower income
levels and make their livelihoods from partial subsistence agriculture. Farm households are often only
partially integrated in markets, including energy markets. Firewood is sourced locally from farm, nearby
forests or marketplaces, and provides a stable and reliable supply of affordable biomass energy.
Biomass fuels are a natural part of people’s culture and livelihoods, and firewood is the primary fuel for nearly
all households in rural Tanzania. In urban contexts, charcoal is the primary fuel for most households. Even in
relatively well-off homes with access to LPG and electricity, biomass energy is used as a secondary fuel for
special types of food, and as a means to ensure security of supply and reduce the high costs in meeting energy
needs. The constant and ubiquitous availability of biomass fuels in rural and urban areas make firewood and
charcoal practical solutions for securing predictable and affordable supply of energy, often in combination
with cleaner cooking solutions.
With increasing rural-urban migration, an increasing proportion of Tanzanians live in semi-rural or peri-urban
areas. Energy consumption patterns in these areas are mixed, but biomass energy continues to be the
dominant energy option. Interventions for promoting improved cooking services should consider the local
resource and socio-economic context, but also population density and proximity to infrastructure.
Annual deaths from indoor air pollution are estimated to 33,024, and the number of years lost due to ill-
health, disability or early death 1,414,699 DALYs. The most widespread form of indoor air pollution is from
indoor cooking using unprocessed biomass energy sources (fuel wood, charcoal and agricultural residues).
The majority of families in rural Tanzania live in small and poorly ventilated houses, which exposes them to
high levels of indoor air pollutants. Lack of awareness of health effects of indoor air pollution is a barrier to
transition from Tier 0 to higher-tier stoves. Awareness creation is also an enabler for a shift towards improved
cooking services.
Much research and development interventions have been invested in design and dissemination of ICS over
the years. The acknowledgment that not all improved stoves were actual improvements resulted in
international and national standards for verifying the quality of ICS, such as ISO19867-3:2018 and
TZS473:2019. These are voluntary and have yet to be enforced in Tanzanian markets. The implementation of
such standards is challenging in a market dominated by artisanal entrepreneurs with limited awareness and
financial capacity for having their products tested. There is also a lack of technical knowledge of stove design
among SMEs.
To achieve the SE4ALL goal, production and use of ICS must increase substantially towards 2030. There exists
a large network of NGOs and SMEs that produce and disseminate ICS across Tanzania Mainland. Many of
30 EU (2020). Action Document for Integrated Approach to Sustainable Cooking Solutions. European Development Fund (EDF): ΤΖ/FED/040-142
REA Implementing agency of the Identify target regions; Facilitate capacity building of
programme SMEs, commercial enterprises; Provide funding to SMEs,
entrepreneurs and NGOs
MoH Oversees health policy Advice on health effects caused by indoor air pollution
implementation and advise better types of ventilation and cooking
technologies
PO RALG Oversees regional planning and Participate in identification of target regions and regional
interventions stakeholders and collaborate with REA in coordination of
efforts under TrICS.
TRA Collects taxes and levies Collaborate with REA and MoE to lower costs of ICS
NGOs Collaborative partner for Coordinate and implement private sector initiatives in the
intervention of projects ICS sector and biomass energy supply projects
SMEs Small- and Medium sized Produce and sell stoves in targeted locations. Develop a
Enterprises market network of dealers and agents. Produce and sell
stoves, fuels and energy
MIT Oversees industrial Provide advice and policy coordination for capacity
development building under TrICS related to industrial development in
the cooking energy sector
1.1 Identify target regions using REA’s GIS REA HQ, Dodoma Year 2 - 7 MoE, REA, VPO, PO RALG
planning tool
1.2 Coordinate/establish regional partnerships Target areas Year 2 - 8 MoE, REA, MoH, VPO, PO
with local stakeholders RALG, TBS, VETA, SIDO, and
private sector
1.3 Develop training material for ICS REA HQ, Dodoma Year 2 - 3 Academic institutions, REA,
TBS, private sector, NGOs,
SIDO, VETA
1.4 Conduct ICS training for entrepreneurs in ICS Target areas Year 2 - 4 VETA, SIDO, REA, NGOs,
private sector
1.5 Support entrepreneurs for testing and Target areas Year 2 - 8 REA, TBS, SIDO
certifying ICS
2.1 Establish a funding line through REF for RBF REA HQ, Dodoma Year 2 MoE, REA, MIT
for large-scale ICS production
2.3 Annual calls for tenders REA HQ, Dodoma Year 2 – 7 REA
2.4 Provide training in ICS design, standards and Dodoma Year 2 - 4 REA, MIT, development
production partners, NGOs, TBS,
private sector
2.6 Establish supply chains to retailers in target Target regions Year 3 - 7 Industry
areas
3.1 Develop mechanism for provision of small REA HQ, Dodoma Year 1 REA, PO RALG
grants to meso-users
3.6 Awareness creation campaign in public media REA HQ, Dodoma Year 2 - 4 REA
of certified ICS
3.7 Support promotion of ICS at public fairs Target regions Year 2 - 4 REA
3.8 Awareness campaign on health and Target regions Year 2 - 8 VPO, MoH, NGOs, REA,
environmental impacts from cooking Private sector
3.9 Monitor and evaluate based on IASES II, III Country-wide Year 5 and NBS, REA, MoH, PO RALG
(REACE programme) 8
4.1 Identify target regions using REA’s GIS REA HQ, Dodoma Year 2 - 8 REA, VPO, TFS, NCMC, PO
planning tool RALG
4.2 Coordinate/establish regional partnerships Target areas Year 1 - 8 REA, VPO, MNRT, PO RALG,
with local stakeholders NGOs, development
partners
4.3 Develop call for projects on sustainable REA HQ, Dodoma Year 3 REA, VPO, MNRT, PO RALG,
biomass energy production NGOs, development
partners
Successful implementation of REACE Elements of TrICS may not be TrICS may continue with less
programme implemented institutional knowledge in REA of
cooking energy and new standards.
Implementation of MoH Strategic Plan Limited priority to achieve Strengthen the capacity of MoH on
HSSP V (2021) includes focus on IAP reduction of indoor air monitoring indoor air pollution
pollution in MoH’s agenda
TrICS may continue with less strong
enabling framework and support from
MoH
Enabling policy and regulatory Policy and regulatory Sensitize policy and decision-makers to
framework in place requirements identified in declare clean cooking at national agenda
CEAP not in place
MoE to be capacitated to develop and
effectively monitor policy and
regulations on cooking
TrICS may continue with less
institutional support by other GoT
bodies
5.3.3 Rationale
A transition towards cleaner cooking fuels is taking place in Mainland Tanzania, albeit slowly. The transition
starts with an increasing demand for modern fuels among high-income groups in major cities and expands
to medium-income groups and to urban areas elsewhere in the country. As supply chains and infrastructure
develops, distribution will gradually reach semi-rural areas. Housing and energy preferences change when
livelihoods are increasingly made through formal employment with fixed salaries, and with it the demand for
clean cooking solutions increases. Semi-rural areas, with reasonable proximity to roads or urban centres,
constitute a frontier market for commercial enterprises with high potential demand. However, investment
requirements for establishment of distribution and infrastructure development are high and demand is
uncertain, making expansion into these areas risky. Initial public sector support is thus required to attract
investment in energy services provision, support expansion of supply chains to more rural areas, and lay the
foundation for a self-sustained market growth. Interventions should be strategically steered towards specific
geographical contexts and socio-economic groups to maximize impact of the effort.
The increasing access to LPG and electricity in Tanzania presents an opportunity for transitioning the energy
sector towards the SE4ALL goal. LPG is currently more affordable than charcoal in Dar es Salaam, and
31 NBS (2019). Tanzania Mainland. Key Indicators Report. 2017-18 Household Budget Survey. National Bureau of Statistics: Dar es Salaam.
32 Not taking into account the source of electricity production, which in Tanzania is both renewable and fossil.
33 Byrne, R., Onsongo, E., Onjala, B., Todd, J. F., Chengo, V., Ockwell, D., & Atela, J. (2020). Electric cooking in Tanzania: an actor-network map and analysis of a nascent
socio-technical innovation system. Modern Energy Cooking Services (MECS)
34 ESMAP (2020). Cooking With Electricity. A Cost Perspective. The World Bank: Washington DC.
35 Ibid
MoCDGWS Oversees community Provide advice and policy coordination of initiatives directed
development policy and towards gender equality and social inclusion
gender
TPDC Regulate and facilitate Implementation of national policy for promotion of liquid
supply of petroleum and gaseous petroleum fuels. Implementation of projects
products on natural gas.
LPG distributors Supply LPG in Tanzania Memorandum of Understanding with REA to supply LPG in
rural areas based on RBF.
Provide capacity building of retailers.
Marketing and awareness creation.
NGO, CBO Implement eCooking Develop project proposals, implement project and monitor
projects development
Banks, financial Manage funds to public Collaborate with REA to establish revolving fund for
institutions subsidized loans to institutions and micro-finance groups
Provide loans to selected beneficiaries
Project 1: Demand and market established for LPG across Tanzania Mainland
1.1 Establish a modality for RBF in REA REA HQ Year 1 – 2 MoE, REA, consultant
1.2 Determine indicators for identifying eligible REA HQ Year 1 – 2 REA, PO RALG, LPG
target populations distributors
1.3 Apply GIS planning and monitoring system REA HQ Year 1 – 8 REA
1.4 Call for tenders for first wave RBF REA HQ Year 2 REA
1.6 Conduct marketing and education Semi-rural target Year 2 – 4 REA, LPG distributors
areas
1.8 Provide RBF based on targeted sales REA HQ Year 3 – 4 REA, LPG distributors
1.9 Call for tenders for second wave RBF REA HQ Year 4 REA
1.11 Conduct marketing and education Rural target areas Year 4 – 7 REA, LPG distributors
1.12 Monitor performance Rural target areas Year 5 – 8 REA, LPG distributors,
consultant
1.13 Provide RBF based on targeted sales REA HQ Year 5 – 8 REA, LPG distributors
2.1 Establish a revolving funding mechanism from Dodoma Year 2 REA, financial institution
REF, managed by third party bank
2.2 Identify target areas in regions Rural areas Year 2 - 7 REA, PO-RALG, LPG
distributors, regional
branches of financial
institution, public
institutions
2.4 Provide subsidized loan for acquisition of LPG Selected locations Year 3 - 7 Financial institutions
2.6 Capacity building of LPG retailers Selected locations Year 3 - 7 LPG distributor
3.1 Dialogue with biogas stakeholders Dodoma Year 2 - 3 REA, CAMARTEC, NGOs,
Project developers
4.1 Dialogue with eCooking stakeholders Dodoma Year 2 - 3 REA, electricity service
providers, NGOs, Project
developers
4.2 Develop specifications for three projects: 1) REA HQ Year 3 REA, consultants
eCooking with SHS, 2) eCooking with mini-grid,
and 3) eCooking with grid electricity
4.3 Identify target areas with SHS, mini-grid and Target areas Year 3 REA, electricity service
grid service providers providers, consultants
4.4 Call for proposals and select three for funding REA HQ Year 3 REA
4.8 Assess viability. Decide if, how and what mode Dodoma Year 7 REA, MoE
to support in new target areas
5.1 Implement pilot project in Lindi and Mkuranga Lindi and Year 1 - 3 MoE, TPDC and other
Mkuranga stakeholders
5.2 Dialogue with natural gas stakeholders Dodoma Year 2 - 3 MoE, TPDC and other
stakeholders
5.3 Feasibility study to identify target areas Target areas along Year 3 TPDC, REA
main pipeline
5.4 Develop specifications for natural gas project Dodoma Year 3 MoE, TPDC, REA
5.5 Contract for financing natural gas project REA HQ Year 3 GoT, REA and other
stakeholders
5.6 Fund natural gas project Target areas along Year 3 - 6 GoT, REA and other
main pipeline stakeholders
5.7 Monitor natural gas project Target areas along Year 3 - 6 TPDC, REA
main pipeline
5.8 Evaluate natural gas project Target areas along Year 6 TPDC, REA, consultants
main pipeline
5.9 Assess viability of provision in new areas Dodoma and Year 6 MoE, TPCD, REA
where natural gas pipeline is extended. Decide if, target areas
how and what mode to support in new target
areas (repeat steps 5.2-5.8)
6.1 Develop and overall strategy for awareness REA HQ Year 2 REA, consultants
creation, education and capacity building
6.2 Develop educational material for safe use of REQ HQ Year 2 - 3 REA, consultants, LPG
LPG and natural gas distributors
6.3 Produce educational and training material on REA HQ Year 3 Development partners,
eCooking NGOs, electricity service
providers, REA
6.4 Conduct public campaigns in media and live National, targeted Year 3 - 6 MoH, REA, Development
demonstrations to create awareness of health semi-urban and partners, NGOs, Private
impact with clean cooking solutions (ACCeS rural population sector and media
programme)
6.6 Monitor and evaluate ACCeS-programme Country-wide Year 5 and 8 NBS, REA
based on IASES II, III (REACE programme)
Successful implementation of REACE Few or no additional staff hired. ACCeS may continue with less
programme Limited resources for operational institutional knowledge in REA of
costs cooking energy and new standards.
Funds from GoT allocated to REA for Less funds received than Scale down activities
implementing REACE requested
Government institutions engaged in Partners do not commit to ACCeS REA prioritises parts of ACCeS that
implementation of ACCeS can be conducted without strong
partnerships
Funding from development partners to Less or no funds allocated from REA prioritises parts of CEAP that can
match provisions by GoT development partners be conducted without large
investments
Contracts with LPG distributors No interest or capacity among Focus on demand-side interventions
LPG distributors
Implementation of MoH Strategic Plan Limited priority to achieve a ACCeS may continue with less strong
HSSP V (2021) includes focus on IAP reduction of indoor air pollution enabling framework
in MoH’s agenda
Enabling policy and regulatory Policy and regulatory Sensitize policy and decision-makers
framework in place requirements identified in CEAP to declare clean cooking a national
not in place agenda
ACCeS may continue with less
institutional support by other GoT
bodies
TZS, 1000s,
rounded CEAP
Expenses Total 2022/23 2023/24 2024/25 2025/26 2026/27 2027-2030
Oper. Costs 80,860,000 4,420,000 12,740,000 11,960,000 11,440,000 11,180,000 29,380,000
Tech. Ass. 40,300,000 3,380,000 9,100,000 13,520,000 6,500,000 3,120,000 4,680,000
REF grants 385,320,000 4,940,000 10,920,000 59,540,000 87,620,000 79,820,000 142,480,000
Sub-total 506,480,000 13,000,000 32,760,000 85,020,000 105,560,000 94,120,000 176,540,000
2001 Energy and Water Utilities Established the Energy and Water Utilities Regulatory Authority
Regulatory Authority (EWURA) to regulate tariffs for electricity trade in the country, and
(EWURA) Act promote the availability of regulated services to all, including low-
income, rural, and disadvantaged consumers.
2003 National Energy Policy The 2003 policy laid the foundation for promoting renewable
energy sources and encouraging private sector participation in
Tanzania.
2005 Rural Energy Act Established the Rural Energy Agency in order to enhance energy
access in rural areas.
2008 Petroleum Act This Act provides regulation of importation, transportation, storage,
distribution, sale and use of petroleum and petroleum products,
including LPG, kerosene and natural gas.
2015 National Energy Policy Aimed to attract more private investment and local participation in
the energy sector, improve efficiency and energy conservation as
well as access to modern energy services and increase the share of
renewables in the electricity generation mix.
2015 Executive Agencies Act Established PBPA to coordinate and manage efficient procurement
of petroleum products through Bulk Procurement System (BPS)
Specific environmental issues including deforestation and indoor air quality that are specifically addressed in
a number of acts and policies include:
The NEPs confirms the ambition to transition the residential sector away from dependence on firewood and
charcoal. Reducing deforestation is considered an energy sector issue that policies should seek to address
through demand-side interventions. Key sector policies, acts and strategies that promote sustainable
management forest biomass resources from the supply side mainly fall under the MNRT, and include the
National Forest Policy (1998), the National Woodfuels Action Plan (2009), Guideline on Sustainable
Harvesting and Trade in Forest Products (2017), the Forest Act (2002), Charcoal Regulations (2006), National
REDD Strategy and Action Plan (2013). Currently the National Forestry Policy is under review and will include
a revised regulatory framework for wood fuel production, sales, and taxation.
Due to its impact on forests, national energy consumption is addressed as an environmental issue in the NEP
2015. The National Environment Policy (1997) and the Environmental Management Act (2004) provide the
legal and institutional framework for sustainable management of the environment. The National Biodiversity
Strategy and Action Plan (NBSAP) 2015-2020, describe the challenge of biodiversity loss caused by the use of
biomass fuel for cooking especially charcoal and firewood, National Environmental Action Plan (NEAP)
explains the challenges facing the energy sector which include climate change, high initial costs of
environmentally and socially sound energy technologies; and inadequate human and institutional capacities
and the Country State of Environment Report 2020 shows the impacts of cutting trees for charcoal production
and firewood on forests and land due to the high demand of fuelwood (90 percent of the country’s
population), especially in urban areas. The Climate Change Strategy (2012) outlines the technical and
institutional capacity of the country to address the impacts of climate change. The United Nations Framework
Convention on Climate Change (UNFCCC) Paris Agreement was ratified by Tanzania in May 2018. The first
NDCs promotes energy efficiency technologies, enhancing efficiency in wood fuel extraction and utilisation,
and enhancing use of renewable biomass 36 .
The NEPs addresse the negative impact on public health from inefficient use of woodfuels, as well as the
disproportionate burden on women. The Ministry of Health is a central actor in a coordinated effort to scale
up access to improved and clean cooking solutions. The Public Health Act (2009) aims at increasing the well-
being of the population by providing essential public health services, including improving equitable access to
services by focusing on geographic areas and vulnerable groups in the population with higher risks. The Act
focuses on communicable diseases and does not mention air quality. The National Health Policy (2017)
addresses the need for improvement of general health, but only indirectly addresses the negative health
Legal framework
The Energy and Water Utilities Regulatory Authority Act (2001, 2006)
The Public Private Partnership Policy of 2009 and Act of 2014, and as amended in 2018
Notable here is the Standards Act of 2009 which gives TBS the mandate to oversee and set standards of
imported and local made commodities, including fuel standards and standards for cooking technologies.
37 MoHCDGEC (2019). Health and Pollution Action Plan. United Republic of Tanzania. UNIDO: Dar es Salaam.
Recommendation: Address SDG 7 and associated goals through a cross-sectoral national effort
Barrier Ensuring availability and affordability of improved and clean alternatives for
cooking in rural Tanzania will require substantial and sustained investment in
infrastructure, such as industrial-scale production capacity of ICS, storage and
filling facilities for LPG, development of distribution capacity, and support to
market activities to make provision commercially viable and enable expansion
into new areas.
In NEP 2015 an objective is to enhance utilisation of renewable energy resources, including biomass, so as to
increase its contribution in diversifying resources for electricity generation. It is also stated that “the
Government shall facilitate efficient biomass conversion and end-use technologies”.
Since the 1970s Tanzania has seen numerous government and development-led efforts to promote improved
and clean cookstoves and fuels, but with limited effect in terms of scale and lasting results.
Statistical data and reports that exist on national energy consumption patterns lack the necessary depth and
detail to inform policy and regulatory decision-making.
Recommendation: Implement an information and knowledge management system for the energy sector
Barrier MoE lacks a comprehensive system for national monitoring and evaluation of
the energy sector (JESR, 2020). An area poorly addressed is the extent and
consequences of fuel stacking, which is an important factor for interventions
on cooking energy.
Enabler Increased capacity for M&E should established by the MoE. This could include
an energy information and knowledge management system to be implemented
by MoE in coordination with stakeholders including NBS.
Recommendation: Increase attention towards causes and effects of indoor air pollution in health policy
Barrier Impact of Indoor Air Pollution (IAP) is not addressed in depth in current policy
and regulation related to public health, including the Tanzania Health Sector
Strategic Plan 2021-2026 38 . This in turn limits the attention to adoption of
improved and clean cooking stoves, especially by the rural population.
Enabler Health policy and regulations should increase attention towards causes and
effects of indoor air pollution, and public awareness raising. The Health and
Pollution Action Plan 39 has proposed actions for addressing indoor air
pollution, including awareness creation and promotion of clean cooking
solutions. Efforts to address indoor air pollution should be coordinated
between the energy and health authorities.
Gender is a crosscutting issue, and women and children carry the largest burden from exposure to pollutants
coming from cooking with firewood and charcoal.
Recommendation: Increase attention towards burden on women and children from indoor air pollution
Barrier Gender is a crosscutting issue, and women and children carry the largest
burden from exposure to pollutants coming from cooking with firewood and
charcoal. The head of household are often men, delimiting the range of
decision of the source of energy used for cooking.
Enabler The MoCDGWS is responsible for gender-related policy in Tanzania. In
development of new policy increased attention should be given to impacts
from cooking energy use and measures to address impacts of these, and
awareness to both men and women on the effects of pollution.
Training needs assessment and capacity development for the energy sector took place between 2014 and
2019 including at MoE, EWURA, TANESCO, TPDC and PURA. Implementation of such capacity building is
ongoing but slow in some cases and sometimes are already outside the planned deadlines, according to the
2020 Joint Energy Sector Review 40 .
Recommendation: Support capacity building and structural changes in energy sector public institutions
Barrier Relevant expertise and capacity in government institutions for implementation
of policies in the energy sector is crucial when considering interventions to
support transition to improved and clean cooking energy.
38 MoH (2021). Tanzania Health Sector Strategic Plan 2021-2026. Ministry of Health, Community Development, Gender, Elderly and Children: Dodoma
39 MoHCDGEC (2019). Health and Pollution Action Plan. United Republic of Tanzania. UNIDO: Dar es Salaam.
40 JESR (2020). Joint Energy Sector Review. MoE: United Republic of Tanzania.
Recommendation: Support research institutions in Tanzania to study climate change impact of energy
interventions
Barrier There is limited knowledge of the impact on GHG emissions from a transition
from renewable biomass energy to increased reliance on LPG and other non-
renewable fuels. Research institutions lack the necessary resources to conduct
research on climate change mitigation and Global Warming Potential of
development interventions.
Enabler Support research institutions in Tanzania including SUA, UDOM and NCMC to
study Global Warming Potential of different energy sector trajectories,
including the SE4ALL scenario. Research can be strengthened through
collaboration with international research institutions.
Energy for cooking receives considerably less funding than other decentralised energy sources in Tanzania.
The budget set aside for cooking energy in REA is TZS 2 Billion, or 0.5 percent of the total budget.
41 EU (2020). Action Document for Integrated Approach to Sustainable Cooking Solutions. European Development Fund (EDF): ΤΖ/FED/040-142
Low ability to pay in rural areas is an important barrier to improving energy services for a large part of
Tanzania’s population.
Even when the long-term running costs of an alternative solution is competitive, the purchase of an ICS or a
cylinder and stove for LPG or eCooking equipment may represent an unsurmountable upfront investment for
many rural households. Through the NEPs, the GoT has been promoting substitution of charcoal and firewood
by providing tax relief to stimulate the use of LPG in the country. In 2008-2009 import duties and VAT were
removed from LPG. All other cooking fuels have taxes, royalties, duties and levies.
42 NBS (2019). Tanzania Mainland. Key Indicators Report. 2017-18 Household Budget Survey. National Bureau of Statistics: Dar es Salaam.
The charcoal sector and supply chain from rural producers to urban consumers is in the process of being
formalized through regulation by TFS. This contributes to increase the cost of charcoal in cities, thereby
increasing urban demand for alternatives such as LPG, eCooking and use of natural gas. Charcoal costs less
and is used less in rural Tanzania due to locally available firewood. The effect of formalization of the charcoal
sector is likely to have marginal direct effect on rural energy consumption, but it may contribute to the
general formalization of the rural economy.
The current capacity of REA to coordinate and implement CEAP needs to be significantly increased. Primarily,
an approval by the MoE and the Government of the proposed structural changes and recruitment plan is
necessary. Significant contributions are required by other parties in training and capacity building. The
capacity and knowledge building in REA will likely be supported through several Technical Assistance
assignments.
REA has 86 staff located mainly at the Head Office in Dodoma. REA’s presence in the regions is limited to one
electrical engineer stationed in each of TANESCO’s seven zonal offices. These zones each constitute 3-5
administrative regions of Tanzania. The REACE-programme under CEAP aims at building REA’s capacity for
implementation of projects across Tanzania’s regions through increased attention to REA’s regional
coordination with PO-RALG. Increased capacity regionally is necessary for targeted interventions in the
cooking energy area.
43 EU (2020). Action Document for Integrated Approach to Sustainable Cooking Solutions. European Development Fund (EDF): ΤΖ/FED/040-142
44 MEM (2015). Tanzania's Sustainable Energy for All Action Agenda. Ministry of Energy and Minerals: Dar es Salaam.
45 Byrne, R., Onsongo, E., Onjala, B., Todd, J. F., Chengo, V., Ockwell, D., & Atela, J. (2020). Electric cooking in Tanzania: an actor-network map and analysis of a nascent
socio-technical innovation system. Modern Energy Cooking Services (MECS)
8.1 Environment
The environmental sectors track the consumption of natural resources – both renewable and non-renewable
– and estimate the impact of the use and depletion of such resources on production, health and other sectors.
The use of firewood and charcoal as a primary source for cooking energy leads to a large in increase CO2
emission, loss of biodiversity, and in extreme cases, soil erosion from deforestation. The tension between
satisfaction of human needs and degradation of the environment is high and requires rethinking and
changing the usage of energy from firewood and charcoal, to more sustainable ones. Population and
production levels determine the demand of natural resources and the generation of waste and air pollution.
Nevertheless, investment decisions can influence levels of waste treatment, alternatives, and capacities for
renewable energy, resulting in responsible use of national natural resources. To reduce impacts and
vulnerability of climate change, Tanzania committed to Nationally Determined Contributions, intended to
enhance inefficiency in wood fuel utilization, enhance the use of renewable energy across the country,
promote the use of energy efficiency technology and behaviour and promote rural electrification. These
actions aim to reduce the rate of forest degradation and adapt to climate change.
8.2 Gender
In terms of gender equality, SDG5 aims to empower all women and girl. Giving women opportunities to
generate income is a start in the social process required to reach that goal. In the current social context of
Tanzanian society, there is an unbalance share of domestic unpaid work, divided in many activities that take
most of the time of women in many households. Additionally, cooking and gathering wood, represent one of
the most time consuming of daily responsibilities carried by women. In many cases women have to walk long
distances to get firewood and then engage many hours making food, often being exposed to polluted air.
The implementation of clean cooking energy shortens the time involved on food preparations, providing
space and opportunities to get employed and/or engaged in educational alternatives. The empowerment of
all women and girl is a vision that not only benefits women, also impacts further in other family members,
and in a wider extent many aspects of society, creating fluency and symmetry within household members.
Finally, granting women the alternative of choosing how to administrate their time, becomes potentially the
first step towards a more balanced and equal society in which the vital role of women is guaranteed with
their full and equal participation and leadership in all areas of sustainable development.
8.3 Health
Indoor air pollution is one of the main reasons for lung diseases. The exposure to airborne pollutants is
harmful for those breathing it, but also one of the reasons of malformations, damage to the brain and low
birth weight in babies in the womb, in addition to other complications during the gestation period. The long
hours expended in cooking activities, represent a constant exposure to polluted air. The particles arising from
solid fuels such as wood, charcoal, and animal dung for cooking create unhealthy living environment. Cooking
over open fires or inefficient stoves typically entails burning fuels like wood, charcoal, coal, and kerosene,
which releases harmful, climate-warming emissions. Short-lived climate pollutants—such black carbon and
methane (CH4), as well as other greenhouse gases, such as carbon monoxide (CO) and carbon dioxide (CO2),
which are emitted due to the incomplete combustion of kerosene and solid fuels that occurs while cooking
using these unhealthy methods. Furthermore, the implementation of cleaner cooking energies will provide
Wave 1: No issues in upstream Wave 1: Minor issues in upstream Wave 2: Problems in upstream Wave 2: Severe issues in upstream Wave 1: TANESCO isolated
grid grid grid grid grid
BUBUTOLE 17 659 1 869 2 087 162 997 419 186 365 0.45
BUGENIKA 17 663 2 196 2 452 183 1 061 904 196 392 0.46
KISIMANI 17 111 2 123 2 371 179 1 005 733 194 386 0.46
NJIA PANDA 17 029 1 079 1 205 94 632 101 119 230 0.46
SERYA 16 918 2 483 2 773 202 1 125 435 207 469 0.45
Iringa
IDUMULUTWA 5 217 708 791 62 382 128 66 200 0.44
IHANZUTWA 4 955 1 572 1 756 142 934 940 175 341 0.46
ILAMBO 5 342 2 081 2 324 176 1 000 298 193 383 0.45
KITIRU 4 972 1 182 1 320 100 661 535 122 309 0.45
MAGUNGULI 4 884 2 152 2 403 181 1 142 008 195 388 0.44
MAKADUPA 4 848 1 276 1 425 107 666 108 125 316 0.45
KINYAMWENDA 7 014 2 637 2 945 213 1 102 383 212 481 0.45
LULANGA 7 160 2 307 2 576 191 1 053 119 200 402 0.45
CHIMBUKO 2 691 1 881 2 101 163 1 051 034 186 366 0.45
LITUPU 2 436 1 281 1 431 107 707 713 125 316 0.46
RUAHA 2 949 1 296 1 447 108 702 068 126 317 0.44
ZINGA KIBAONI 2 284 1 637 1 828 146 1 014 290 177 346 0.44
Morogoro
CCT FOREST 827 498 556 48 369 909 59 114 0.46
CHINGHOWE 1 009 1 174 1 311 100 660 248 122 308 0.44
MKONO WA MARA 233 2 247 2 509 187 1 142 452 198 397 0.44
GONGO 1 042 1 567 1 750 142 997 273 175 341 0.46
KIASI 1 545 2 097 2 342 177 1 049 971 193 384 0.44
KIECHURU 1 546 1 198 1 338 102 659 077 122 310 0.44
KILULA TAMBWE 1 524 899 1 004 82 628 193 112 216 0.45
KIONGORONI 1 538 1 260 1 407 106 671 512 125 315 0.45
KWAMSANJA 1 118 1 860 2 077 161 1 090 628 185 365 0.46
MAGURUMATALI 1 085 2 637 2 945 213 1 229 944 212 481 0.45
MALIVUNDO 1 131 1 406 1 570 131 981 652 169 327 0.45
MBEZI MULUNGWANA 1 409 807 901 76 627 848 109 208 0.44
MKENGE 1 121 2 032 2 269 173 1 098 166 191 379 0.46
MNG'ARU 1 563 1 358 1 517 112 967 457 128 323 0.46
MSALA 1 544 1 597 1 784 144 956 322 176 343 0.44
MSIGI 1 086 1 621 1 810 145 1 020 401 176 345 0.45
NGARAMBE MAGHARIBI 1 558 1 130 1 262 97 684 119 210 477 0.45
NYAMBUNDA 1 493 1 673 1 868 149 1 031 271 178 349 0.45
SAADANI 1 038 1 889 2 110 163 1 032 167 186 367 0.44
SHUNGUBWENI 1 341 2 428 2 712 199 1 132 946 205 464 0.45
SIASA 1 458 1 729 1 931 153 1 048 983 180 353 0.45
YOMBO LUKINGA 1 270 851 950 79 636 031 110 212 0.44
ZIMBWINI 1 482 1 539 1 719 140 1 004 861 174 338 0.45
Tanga
BUYUNI 19 857 272 304 33 308 220 51 95 0.44
LENGUSELO 20 024 2 267 2 532 188 1 168 769 199 398 0.46
MSOMERA 19 921 2 332 2 604 192 1 173 466 202 404 0.45
OLDONYO KUMUR 17 893 786 878 74 603 640 108 207 0.45
MAKOKANE 18 569 1 803 2 014 157 1 021 119 182 360 0.44
MASHUVA 18 287 1 346 1 503 111 1 006 227 127 322 0.44
MWANGARIA 18 650 1 918 2 142 165 1 038 295 187 369 0.45
PANGARO 18 426 2 612 2 917 211 1 242 709 211 479 0.44
LERUMO 13 121 1 194 1 333 101 704 625 122 309 0.44
LORBENE 13 077 1 206 1 347 102 677 743 123 310 0.45
NGABOLO 13 176 2 196 2 452 183 1 112 371 120 236 0.45
RIKIUSHIOIBOR 13 172 3 771 4 211 291 1 563 053 282 575 0.45
Shinyanga
BUZINZA 9 723 1 829 2 043 159 974 031 183 362 0.46
MWAJIGINYA B 9 658 1 180 1 318 100 631 253 122 308 0.45
WAME 10 106 1 466 1 637 135 902 376 171 332 0.46
South Mbeya
BARABARANI 6 541 414 462 42 318 484 56 107 0.46
ILEYA 5 664 1 785 1 993 156 959 032 182 359 0.46
IYALA 6 343 2 366 2 642 195 1 044 737 203 459 0.46
MAGWARISI 6 463 1 757 1 962 154 937 258 181 356 0.46
LICHEHE 3 469 1 400 1 564 131 936 350 169 327 0.44
LIPWIDI 3 050 2 271 2 536 188 1 123 808 199 399 0.46
LYOWA 3 116 1 337 1 493 111 716 492 127 322 0.45
MIGOMBANI 3 026 1 588 1 773 143 996 455 175 342 0.44
MKAHARA 3 139 1 177 1 314 100 686 343 122 308 0.44
MKOMO 3 091 1 256 1 403 105 699 963 124 314 0.46
NAMANGUDU 3 226 1 293 1 444 108 707 597 126 317 0.46
NGONGO 3 334 1 362 1 521 112 943 070 128 324 0.45
GUKWA 11 913 1 601 1 788 144 951 319 176 343 0.44
IDIHANI 13 354 1 910 2 133 165 1 068 103 187 368 0.44
IGOLA 13 345 1 799 2 009 157 1 074 221 182 360 0.45
IKWAVILA 13 390 1 174 1 311 100 621 297 122 308 0.45
IWELA 13 741 1 572 1 756 142 927 372 175 341 0.44
KITOLE 13 661 1 795 2 005 157 1 087 204 182 359 0.45
LIMA 13 635 1 567 1 750 142 1 029 940 175 341 0.38
LWANZALI 13 668 1 344 1 501 111 983 866 127 322 0.44
NGALANGA 13 341 2 578 2 879 209 1 245 860 196 392 0.46
IFINGA 4 194 2 475 2 764 202 1 197 170 207 469 0.46
LUTUKIRA 4 256 3 308 3 694 261 1 494 541 266 537 0.45
MAGAZINI 4 584 6 230 6 958 465 2 085 055 371 785 0.45
MAGWAMILA 4 213 1 275 1 424 107 696 767 125 316 0.44
MDWEMA 4 596 1 989 2 221 170 1 081 871 190 375 0.45
MTERAWAMWAHI 4 574 2 134 2 383 179 1 117 959 194 387 0.46
KATETE 15 132 2 117 2 364 178 1 074 659 194 386 0.44
MKOLANI 15 131 3 236 3 614 256 1 430 171 264 531 0.45
Kagera
KANOGO 10 190 4 584 5 119 345 1 774 688 310 643 0.44
MSALALA 10 443 1 421 1 587 132 935 690 170 328 0.45
OMUBWEYA 10 310 2 510 2 803 204 1 201 347 208 471 0.44
Katavi
BUGWE 13 877 2 687 3 001 216 1 309 933 214 486 0.44
IPWAGA 13 969 2 146 2 397 180 1 030 054 195 388 0.45
ISEGENEZYA 13 966 2 510 2 803 204 1 095 767 208 471 0.46
MNYAMASI 13 919 2 694 3 009 216 1 288 426 214 487 0.44
Rukwa
CHANG OMBE 8 666 602 672 41 314 968 63 123 0.45
KALEPULA B 8 495 2 456 2 743 201 1 090 926 206 467 0.45
KAPEWA 8 589 1 297 1 448 108 639 154 126 318 0.44
MAJENGO 8 649 1 197 1 337 142 918 473 122 310 0.46
MLOMBO 8 631 1 362 1 521 142 900 719 128 324 0.45
MNAZI MMOJA 8 546 558 623 203 1 063 556 61 119 0.45
MDALAIGWE 7 943 2 228 2 488 186 1 019 798 197 394 0.45
MKOLA 8 093 1 684 1 881 150 936 462 179 350 0.46
UMANDA 8 297 1 342 1 499 111 671 384 127 322 0.45
USEGA 8 123 2 061 2 302 175 1 017 542 192 381 0.45
Electricity (Procurement of Power Projects and Approval of Power Purchase Agreement) Rules 2019-GN 453
The Electricity (Standardized Small Power Project Tariff) order, 2019, GN. 464
On-going projects Total Cost Total paid Balance Year 2022 Year 2023
The proposed measures are ultimately subject to approval by REA and TANESCO. Ongoing electrification
program are being implemented without use of any low-cost technologies, and there are no indications that
these will be applied for the planned programs. On that background, low-cost alternatives have not been
considered in the following analysis.