Download as pdf or txt
Download as pdf or txt
You are on page 1of 91

PMP Overview

and
Exam Practice Questions

Project Management Institute, 2013, A Guide to the Project Management Body of Knowledge
(PMBOK), 5th Ed.
Ward, Leroy, J., 2013, PMP Exam – Practice Test and Study Guide, 9th Edition

M.L. Springer
Sections
 Scope Management
 Procurement Management
 Time Management
 Risk Management
 Cost Management
 Communications Management
 Quality Management
 Human Resource Management
 Project Management Professional Certification Exam

M.L. Springer
Scope Management
Ensures the project contains all the work required, and only
the work required, to complete the project successfully.
Scope Management consists of scope planning and definition,
creating a Work Breakdown Structure (WBS), scope
verification and control.

M.L. Springer
Question #1

M.L. Springer
Question #1 - Answer

M.L. Springer
Question #2

M.L. Springer
Question #2 - Answer

M.L. Springer
Question #3

M.L. Springer
Question #3 Answer

M.L. Springer
Question #4

10

M.L. Springer
Question #4 - Answer

11

M.L. Springer
Procurement Management
Describes the processes that purchase or acquire
products, services or results, as well as contract
management processes. Procurement Management
consists of planned purchases or acquisitions,
contracting, requesting seller responses and
subsequent selection, contract administration and
contract closure.

12

M.L. Springer
Question #1

13

M.L. Springer
Question #1 - Answer

14

M.L. Springer
Question #2

15

M.L. Springer
Question #2 - Answer

16

M.L. Springer
Question #3

17

M.L. Springer
Question #3 - Answer

18

M.L. Springer
Question #4

19

M.L. Springer
Question #4 - Answer

20

M.L. Springer
Time Management
Defines the processes involved in the timely
completion of the project. Time Management
consists of defining and sequencing the work,
activity duration and resource estimations,
schedule development and schedule control.

21

M.L. Springer
Question #1

22

M.L. Springer
Question #1 - Answer

23

M.L. Springer
Question #2

24

M.L. Springer
Question #2 - Answer

25

M.L. Springer
Question #3

26

M.L. Springer
Question #3 - Answer

27

M.L. Springer
Question #4

28

M.L. Springer
Question #4 - Answer

29

M.L. Springer
Risk Management
Concerned with the processes involved in
conducting effective risk management on a
project. Risk Management consists of risk
planning, identification, qualitative and
quantitative analysis, response planning,
monitoring and controlling.

30

M.L. Springer
Question #1

31

M.L. Springer
Question #1 - Answer

32

M.L. Springer
Question #2

33

M.L. Springer
Question #2 - Answer

34

M.L. Springer
Question #3

35

M.L. Springer
Question #3 - Answer

36

M.L. Springer
Question #4

37

M.L. Springer
Question #4 - Answer

38

M.L. Springer
Cost Management
Describes the processes involved in planning,
estimating, budgeting and controlling cost so the
project is completed within the approved budget.

39

M.L. Springer
Question #1

40

M.L. Springer
Question #1 - Answer

41

M.L. Springer
Question #2

42

M.L. Springer
Question #2 - Answer

43

M.L. Springer
Question #3

44

M.L. Springer
Question #3 - Answer

45

M.L. Springer
Question #4

46

M.L. Springer
Question #4 - Answer

47

M.L. Springer
Communications Management
Describes the processes attendant to the timely and
appropriate generation, collection, dissemination,
storage and disposition of project information.
Communications Management consists of
communications planning, distribution,
performance reporting and managing stakeholders.

48

M.L. Springer
Question #1

49

M.L. Springer
Question #1 - Answer

50

M.L. Springer
Question #2

51

M.L. Springer
Question #2 - Answer

52

M.L. Springer
Question #3

53

M.L. Springer
Question #3 - Answer

54

M.L. Springer
Question #4

55

M.L. Springer
Question #4 - Answer

56

M.L. Springer
Quality Management

Project Quality Management includes the processes and activities of


the performing organization that determine quality policies,
objectives, and responsibilities so that the project will satisfy the
needs for which it was undertaken. Project Quality Management uses
policies and procedures to implement, within the project's context,
the organization's quality management system and, as appropriate, it
supports continuous process improvement activities as undertaken on
behalf of the performing organization. Project Quality Management
works to ensure that the project requirements, including product
requirements, are met and validated.

Project Management Institute, 2013, A Guide to the Project Management Body of Knowledge (PMBOK), 5th Ed

57

M.L. Springer
Question #1

58

M.L. Springer
Question #1 - Answer

59

M.L. Springer
Question #2

60

M.L. Springer
Question #2 - Answer

61

M.L. Springer
Question #3

62

M.L. Springer
Question #3 - Answer

63

M.L. Springer
Question #4

64

M.L. Springer
Question #4 - Answer

65

M.L. Springer
Human Resource Management
Describes the processes that organize and manage
the project team. Human Resource Management
consists of human resource planning, acquiring the
project team, developing the project team and
managing the project team.

66

M.L. Springer
Question #1

67

M.L. Springer
Question #1 - Answer

68

M.L. Springer
Question #2

69

M.L. Springer
Question #2 - Answer

70

M.L. Springer
Question #3

71

M.L. Springer
Question #3 - Answer

72

M.L. Springer
Question #4

73

M.L. Springer
Question #4 - Answer

74

M.L. Springer
Project Management Professional
Certification Exam

75

M.L. Springer
Exam Questions
The PMP exam contains 200 questions, of which 25 questions will not
be included in the pass/fail determination. These "pretest" items, as
PMI calls them, will be randomly placed throughout the exam to
gather statistical information on their performance to determine their
use for future exams. Accordingly, to pass the PMP exam, candidates
must answer a minimum of 106 of the 175 scored questions, or roughly
61 percent. Of the 175 scored questions:

 20 questions (11.6%) relate to initiating


 40 questions (22.7%) relate to planning
 48 questions (27.5%) relate to executing
 37 questions (21 %) relate to monitoring and controlling
 15 questions (8.6%) relate to closing
 15 questions (8.6%) relate to professional and social responsibility.

76

M.L. Springer
PMI’s 5 Process Groups

77

M.L. Springer
PMI’s 5 Project Groups - Definition
 Initiating Process Group –
 Defines or authorizes the project or project phase
 Planning Process Group –
 Defines and refines objectives and plans the course of action required to attain the
objectives and scope that the project was undertaken to address.
 Executing Process Group –
 Integrates people and other resources to carry out the project management plan for
the project
 Monitoring and Controlling Process Group –
 Regularly measures and monitors progress to identify variances from the project
management plan so the corrective action can be taken when necessary to meet
project objectives
 Closing Process Group –
 Formalizes acceptance of product, service or result and brings the project or project
phase to an orderly end

78

M.L. Springer
Process Group Interaction

79

M.L. Springer
PMI’s 10 Knowledge Areas
 Integration Management
 Scope Management
 Time Management
 Cost Management
 Quality Management
 Human Resource Management
 Communications Management
 Risk Management
 Procurement Management
 Stakeholder Management
80

M.L. Springer
Integration Management
Describes the processes and activities that
integrate the various elements of project
management, which are identified, defined,
unified and coordinated. It consists of developing
a project charter, developing a preliminary project
scope statement, developing a project management
plan, directing and managing project execution,
monitoring and controlling project work, change
control and closing the project.
81

M.L. Springer
Scope Management
Ensures the project contains all the work required, and
only the work required, to complete the project
successfully. Scope Management consists of scope
planning and definition, creating a Work Breakdown
Structure (WBS), scope verification and control.

82

M.L. Springer
Time Management
Defines the processes involved in the timely
completion of the project. Time Management
consists of defining and sequencing the work,
activity duration and resource estimations,
schedule development and schedule control.

83

M.L. Springer
Cost Management
Describes the processes involved in planning,
estimating, budgeting and controlling cost so the
project is completed within the approved budget.

84

M.L. Springer
Quality Management
Describes the processes involved in assuring the
project will satisfy the objectives for which it was
undertaken. Quality Management consists of
quality planning, quality assurance and quality
control.

85

M.L. Springer
Human Resource Management
Describes the processes that organize and manage
the project team. Human Resource Management
consists of human resource planning, acquiring the
project team, developing the project team and
managing the project team.

86

M.L. Springer
Communications Management
Describes the processes attendant to the timely and
appropriate generation, collection, dissemination,
storage and disposition of project information.
Communications Management consists of
communications planning, distribution,
performance reporting and managing stakeholders.

87

M.L. Springer
Risk Management
Concerned with the processes involved in
conducting effective risk management on a
project. Risk Management consists of risk
planning, identification, qualitative and
quantitative analysis, response planning,
monitoring and controlling.

88

M.L. Springer
Procurement Management
Describes the processes that purchase or acquire
products, services or results, as well as contract
management processes. Procurement Management
consists of planned purchases or acquisitions,
contracting, requesting seller responses and
subsequent selection, contract administration and
contract closure.

89

M.L. Springer
Stakeholder Management
Processes required to identify the people, groups or
organizations that could impact or be impacted by
the project, to analyze stakeholder expectations and
their impact to the project, and to develop
appropriate management strategies for effectively
engaging stakeholders in project decisions and
execution.

90

M.L. Springer
References
 Project Management Institute, 2013, A Guide to
the Project Management Body of Knowledge
(PMBOK), 5th Ed.
 Ward, Leroy, J., 2013, PMP Exam – Practice Test
and Study Guide, 9th Edition

91

M.L. Springer

You might also like