Professional Documents
Culture Documents
M3 PMI PMP Exam Questions - Rev J
M3 PMI PMP Exam Questions - Rev J
and
Exam Practice Questions
Project Management Institute, 2013, A Guide to the Project Management Body of Knowledge
(PMBOK), 5th Ed.
Ward, Leroy, J., 2013, PMP Exam – Practice Test and Study Guide, 9th Edition
M.L. Springer
Sections
Scope Management
Procurement Management
Time Management
Risk Management
Cost Management
Communications Management
Quality Management
Human Resource Management
Project Management Professional Certification Exam
M.L. Springer
Scope Management
Ensures the project contains all the work required, and only
the work required, to complete the project successfully.
Scope Management consists of scope planning and definition,
creating a Work Breakdown Structure (WBS), scope
verification and control.
M.L. Springer
Question #1
M.L. Springer
Question #1 - Answer
M.L. Springer
Question #2
M.L. Springer
Question #2 - Answer
M.L. Springer
Question #3
M.L. Springer
Question #3 Answer
M.L. Springer
Question #4
10
M.L. Springer
Question #4 - Answer
11
M.L. Springer
Procurement Management
Describes the processes that purchase or acquire
products, services or results, as well as contract
management processes. Procurement Management
consists of planned purchases or acquisitions,
contracting, requesting seller responses and
subsequent selection, contract administration and
contract closure.
12
M.L. Springer
Question #1
13
M.L. Springer
Question #1 - Answer
14
M.L. Springer
Question #2
15
M.L. Springer
Question #2 - Answer
16
M.L. Springer
Question #3
17
M.L. Springer
Question #3 - Answer
18
M.L. Springer
Question #4
19
M.L. Springer
Question #4 - Answer
20
M.L. Springer
Time Management
Defines the processes involved in the timely
completion of the project. Time Management
consists of defining and sequencing the work,
activity duration and resource estimations,
schedule development and schedule control.
21
M.L. Springer
Question #1
22
M.L. Springer
Question #1 - Answer
23
M.L. Springer
Question #2
24
M.L. Springer
Question #2 - Answer
25
M.L. Springer
Question #3
26
M.L. Springer
Question #3 - Answer
27
M.L. Springer
Question #4
28
M.L. Springer
Question #4 - Answer
29
M.L. Springer
Risk Management
Concerned with the processes involved in
conducting effective risk management on a
project. Risk Management consists of risk
planning, identification, qualitative and
quantitative analysis, response planning,
monitoring and controlling.
30
M.L. Springer
Question #1
31
M.L. Springer
Question #1 - Answer
32
M.L. Springer
Question #2
33
M.L. Springer
Question #2 - Answer
34
M.L. Springer
Question #3
35
M.L. Springer
Question #3 - Answer
36
M.L. Springer
Question #4
37
M.L. Springer
Question #4 - Answer
38
M.L. Springer
Cost Management
Describes the processes involved in planning,
estimating, budgeting and controlling cost so the
project is completed within the approved budget.
39
M.L. Springer
Question #1
40
M.L. Springer
Question #1 - Answer
41
M.L. Springer
Question #2
42
M.L. Springer
Question #2 - Answer
43
M.L. Springer
Question #3
44
M.L. Springer
Question #3 - Answer
45
M.L. Springer
Question #4
46
M.L. Springer
Question #4 - Answer
47
M.L. Springer
Communications Management
Describes the processes attendant to the timely and
appropriate generation, collection, dissemination,
storage and disposition of project information.
Communications Management consists of
communications planning, distribution,
performance reporting and managing stakeholders.
48
M.L. Springer
Question #1
49
M.L. Springer
Question #1 - Answer
50
M.L. Springer
Question #2
51
M.L. Springer
Question #2 - Answer
52
M.L. Springer
Question #3
53
M.L. Springer
Question #3 - Answer
54
M.L. Springer
Question #4
55
M.L. Springer
Question #4 - Answer
56
M.L. Springer
Quality Management
Project Management Institute, 2013, A Guide to the Project Management Body of Knowledge (PMBOK), 5th Ed
57
M.L. Springer
Question #1
58
M.L. Springer
Question #1 - Answer
59
M.L. Springer
Question #2
60
M.L. Springer
Question #2 - Answer
61
M.L. Springer
Question #3
62
M.L. Springer
Question #3 - Answer
63
M.L. Springer
Question #4
64
M.L. Springer
Question #4 - Answer
65
M.L. Springer
Human Resource Management
Describes the processes that organize and manage
the project team. Human Resource Management
consists of human resource planning, acquiring the
project team, developing the project team and
managing the project team.
66
M.L. Springer
Question #1
67
M.L. Springer
Question #1 - Answer
68
M.L. Springer
Question #2
69
M.L. Springer
Question #2 - Answer
70
M.L. Springer
Question #3
71
M.L. Springer
Question #3 - Answer
72
M.L. Springer
Question #4
73
M.L. Springer
Question #4 - Answer
74
M.L. Springer
Project Management Professional
Certification Exam
75
M.L. Springer
Exam Questions
The PMP exam contains 200 questions, of which 25 questions will not
be included in the pass/fail determination. These "pretest" items, as
PMI calls them, will be randomly placed throughout the exam to
gather statistical information on their performance to determine their
use for future exams. Accordingly, to pass the PMP exam, candidates
must answer a minimum of 106 of the 175 scored questions, or roughly
61 percent. Of the 175 scored questions:
76
M.L. Springer
PMI’s 5 Process Groups
77
M.L. Springer
PMI’s 5 Project Groups - Definition
Initiating Process Group –
Defines or authorizes the project or project phase
Planning Process Group –
Defines and refines objectives and plans the course of action required to attain the
objectives and scope that the project was undertaken to address.
Executing Process Group –
Integrates people and other resources to carry out the project management plan for
the project
Monitoring and Controlling Process Group –
Regularly measures and monitors progress to identify variances from the project
management plan so the corrective action can be taken when necessary to meet
project objectives
Closing Process Group –
Formalizes acceptance of product, service or result and brings the project or project
phase to an orderly end
78
M.L. Springer
Process Group Interaction
79
M.L. Springer
PMI’s 10 Knowledge Areas
Integration Management
Scope Management
Time Management
Cost Management
Quality Management
Human Resource Management
Communications Management
Risk Management
Procurement Management
Stakeholder Management
80
M.L. Springer
Integration Management
Describes the processes and activities that
integrate the various elements of project
management, which are identified, defined,
unified and coordinated. It consists of developing
a project charter, developing a preliminary project
scope statement, developing a project management
plan, directing and managing project execution,
monitoring and controlling project work, change
control and closing the project.
81
M.L. Springer
Scope Management
Ensures the project contains all the work required, and
only the work required, to complete the project
successfully. Scope Management consists of scope
planning and definition, creating a Work Breakdown
Structure (WBS), scope verification and control.
82
M.L. Springer
Time Management
Defines the processes involved in the timely
completion of the project. Time Management
consists of defining and sequencing the work,
activity duration and resource estimations,
schedule development and schedule control.
83
M.L. Springer
Cost Management
Describes the processes involved in planning,
estimating, budgeting and controlling cost so the
project is completed within the approved budget.
84
M.L. Springer
Quality Management
Describes the processes involved in assuring the
project will satisfy the objectives for which it was
undertaken. Quality Management consists of
quality planning, quality assurance and quality
control.
85
M.L. Springer
Human Resource Management
Describes the processes that organize and manage
the project team. Human Resource Management
consists of human resource planning, acquiring the
project team, developing the project team and
managing the project team.
86
M.L. Springer
Communications Management
Describes the processes attendant to the timely and
appropriate generation, collection, dissemination,
storage and disposition of project information.
Communications Management consists of
communications planning, distribution,
performance reporting and managing stakeholders.
87
M.L. Springer
Risk Management
Concerned with the processes involved in
conducting effective risk management on a
project. Risk Management consists of risk
planning, identification, qualitative and
quantitative analysis, response planning,
monitoring and controlling.
88
M.L. Springer
Procurement Management
Describes the processes that purchase or acquire
products, services or results, as well as contract
management processes. Procurement Management
consists of planned purchases or acquisitions,
contracting, requesting seller responses and
subsequent selection, contract administration and
contract closure.
89
M.L. Springer
Stakeholder Management
Processes required to identify the people, groups or
organizations that could impact or be impacted by
the project, to analyze stakeholder expectations and
their impact to the project, and to develop
appropriate management strategies for effectively
engaging stakeholders in project decisions and
execution.
90
M.L. Springer
References
Project Management Institute, 2013, A Guide to
the Project Management Body of Knowledge
(PMBOK), 5th Ed.
Ward, Leroy, J., 2013, PMP Exam – Practice Test
and Study Guide, 9th Edition
91
M.L. Springer