Professional Documents
Culture Documents
CON 2013.module 2
CON 2013.module 2
CON 2013.module 2
managing,
Scheduling and
Jobsite
Planning II
Module 2: Submittals, Shop
Drawings, Samples
1
Project Managing, Scheduling and Jobsite Planning II
Module 1 Review
Construction Documents
RFQ/RFP/ITQ
Module 2 Agenda
Submittals
Product Data
Shop Drawings
Samples
Objectives
• This chapter introduces the following:
– Purpose of submittals in the construction process
– Type of submittals used in the construction process
– Information expected in submittals
– Submittal process
– Use of the procurement schedule to control submittals to meet the
construction schedule
– Use of submittals during the construction process
MODULE 2- Submittals, Shop Drawings, Samples Copyright © 2017 Cengage Learning Mincks, Johnson- 4th edition 4
Project Managing, Scheduling and Jobsite Planning II
Introduction
• The construction documents, specifically the technical specifications,
require the contractor to submit product data, samples, and shop
drawings to the architect and engineer for approval.
• This is one of the first steps that is taken by the contractor after
execution of the construction contract and issuance of the Notice to
Proceed.
• Shop drawings, material data, and samples generally are referred to
as submittals.
MODULE 2- Submittals, Shop Drawings, Samples Copyright © 2017 Cengage Learning Mincks, Johnson- 4th edition 5
Project Managing, Scheduling and Jobsite Planning II
Introduction
• Submittals include:
– Shop drawings
– Material data
– Samples
• Submittal process:
– Very important
• Directly relates to quality, schedule, and overall project success
MODULE 2- Submittals, Shop Drawings, Samples Copyright © 2017 Cengage Learning Mincks, Johnson- 4th edition 6
Project Managing, Scheduling and Jobsite Planning II
Types of Submittals
MODULE 2- Submittals, Shop Drawings, Samples Copyright © 2017 Cengage Learning Mincks, Johnson- 4th edition 7
Project Managing, Scheduling and Jobsite Planning II
MODULE 2- Submittals, Shop Drawings, Samples Copyright © 2017 Cengage Learning Mincks, Johnson- 4th edition 8
Project Managing, Scheduling and Jobsite Planning II
Shop Drawings
• Drawing or set of drawings
– Produced by contractor, supplier, manufacturer, subcontractor, or
fabricator
• Not produced by architects or engineers under contract with owner
– More detail than construction documents
• Explains item fabrication
• Emphasis on particular product or installation
– Example: concrete reinforcing
MODULE 2- Submittals, Shop Drawings, Samples Copyright © 2017 Cengage Learning Mincks, Johnson- 4th edition 9
Project Managing, Scheduling and Jobsite Planning II
Shop Drawings
MODULE 2- Submittals, Shop Drawings, Samples Copyright © 2017 Cengage Learning Mincks, Johnson- 4th edition 10
Project Managing, Scheduling and Jobsite Planning II
MODULE 2- Submittals, Shop Drawings, Samples Copyright © 2017 Cengage Learning Mincks, Johnson- 4th edition 11
Project Managing, Scheduling and Jobsite Planning II
Samples
• Physical portion of specified product
– May be full product
• Used to confirm material quality and aesthetic level
– Usually required for finish selection or approval
• Stored at the jobsite
– Compared to material delivered
MODULE 2- Submittals, Shop Drawings, Samples Copyright © 2017 Cengage Learning Mincks, Johnson- 4th edition 12
Project Managing, Scheduling and Jobsite Planning II
MODULE 2- Submittals, Shop Drawings, Samples Copyright © 2017 Cengage Learning Mincks, Johnson- 4th edition 13
Project Managing, Scheduling and Jobsite Planning II
MODULE 2- Submittals, Shop Drawings, Samples Copyright © 2017 Cengage Learning Mincks, Johnson- 4th edition 14
Project Managing, Scheduling and Jobsite Planning II
MODULE 2- Submittals, Shop Drawings, Samples Copyright © 2017 Cengage Learning Mincks, Johnson- 4th edition 15
Project Managing, Scheduling and Jobsite Planning II
• Submittal process
– Refer to Figure 4-3
MODULE 2- Submittals, Shop Drawings, Samples Copyright © 2017 Cengage Learning Mincks, Johnson- 4th edition 16
Project Managing, Scheduling and Jobsite Planning II
MODULE 2- Submittals, Shop Drawings, Samples Copyright © 2017 Cengage Learning Mincks, Johnson- 4th edition 17
FIGURE 4–4 Example Architect’s Review Stamp
Delmar/Cengage Learning
MODULE 2- Submittals, Shop Drawings, Samples Copyright © 2017 Cengage Learning Mincks, Johnson- 4th edition 19
Project Managing, Scheduling and Jobsite Planning II
MODULE 2- Submittals, Shop Drawings, Samples Copyright © 2017 Cengage Learning Mincks, Johnson- 4th edition 20
Project Managing, Scheduling and Jobsite Planning II
MODULE 2- Submittals, Shop Drawings, Samples Copyright © 2017 Cengage Learning Mincks, Johnson- 4th edition 21
Project Managing, Scheduling and Jobsite Planning II
MODULE 2- Submittals, Shop Drawings, Samples Copyright © 2017 Cengage Learning Mincks, Johnson- 4th edition 22
Project Managing, Scheduling and Jobsite Planning II
MODULE 2- Submittals, Shop Drawings, Samples Copyright © 2017 Cengage Learning Mincks, Johnson- 4th edition 23
FIGURE 4–7 Example Contractor’s Review Stamp
Delmar/Cengage Learning
MODULE 2- Submittals, Shop Drawings, Samples Copyright © 2017 Cengage Learning Mincks, Johnson- 4th edition 25
Project Managing, Scheduling and Jobsite Planning II
Summary
• Submittals:
– Used for approval for compliance to the contract and quality control
– Required in several contract documents
– Approval process involves several steps
– Cooperation aids in the process
– Contractor reviews submittals for several reasons
MODULE 2- Submittals, Shop Drawings, Samples Copyright © 2017 Cengage Learning Mincks, Johnson- 4th edition 26
Project Managing, Scheduling and Jobsite Planning II
Review Questions
What are Submittals?
Next Module
Develop Project Budget