Pole Sounding and Replacement Procedure
Pole Sounding and Replacement Procedure
…………………………………. …………………………………………….
EST.DATE 03-05-22 RECENT REVIEW BY NEXT DOC ID V
REVIEW REVIEW
INC DATE 05-05-22 03-MAY- O. MAY-2025 PSR-PRO-3.2-10 [01]
2022 SEGOJWA
NAME OF ORGANISATION MICRARK INVESTMENTS(PTY)LTD
µ
MICRARK INVESTMENTS (PTY) LTD
P. O. Box 30440 Francistown, Botswana Tel +2672405847 / Fax: +267 2419980
Cell: 71459000 Email: chilisaa2002@gmail.com
NOTE: Boring method of inspecting a pole has not been covered here, can be explored for Pole
Maintenance Inspections (not for sounding before climbing)
TOOLS TO BE USED: For hitting the pole- 2 Pounds hammer for 7, 9, & 13m Poles
-4 Pounds hammer for 15m and above Poles
STAGE 1.
VISUAL INSPECTION;
4 Check for Bees, wasps or other insects that might inhabit the pole
1 With the use of appropriate tool described Avoid use of headphone or Competent person
below hit the pole 3 times at different spot hearing destructive tool or
30cm above the ground surface to as far above talking. (Pay attention)
as one can go at the same time paying attention
Second person needed for
to the sound produced.(hitting should be done
verification checks
in circular movements around the pole at each
height)
2 Repeat above step at a height more than 1 m Observe pole condition and Competent person
from the ground to as far as one can go. If no reduce next height to test
sign of decay detected from step above, then (interval can be reduced from
STEP 3 Applies 30m to smaller)
3 With the use of any appropriate tool, For poles with Competent person
dig/expose 30cm below the ground below the supporting structure like
ground level, hit the pole 3 times and pay stay wire ensure are in
attention to sound produced. place before digging.
If no sign of decay- Proceed to Step 4 If there For poles with take off
is decay- proceed to step 5 cables take precaution
not to damage
4 Proceed with the works (observe Pole Observe Pole Climbing Competent person
Climbing Procedures using Extension ladders) Procedures using Extension
ladders.
5 The Competent Person assesses the degree of Only one Person to Climb a Competent person
decay, if its critical the pole shall be replaced Supported pole.
first. If in doubt the pole shall be adequately
supported (Using a Crane to support against
the leaning angle)