Download as pdf or txt
Download as pdf or txt
You are on page 1of 1

Project: 5x800MW Yadadri TPS As on 02‐12‐2023

Drawings pending for resubmission with ISG


App. First Sub. App. Current Drg/Doc Comment
Sl. No Division Systems/Area Drawing No Title Resubmission Plan Status as on 02.12.23
Cat. Scheduled Code Rev No Uploaded on date
18‐Nov‐23
4 ISG CHP‐Civil IS‐1‐GA‐699‐100‐C014 ROAD : GA, Details & Layout of Road A 20‐Nov‐18 C,E 2 17‐Aug‐23 29‐Aug‐23 Pending With Customer

17‐Nov‐23
5 ISG CHP‐Civil IS‐4‐DC‐699‐104‐C202 TRANSFER POINT‐33 : Design of Foundations System A 15‐May‐18 C,E 1 09‐Sep‐20 14‐Sep‐20 Approved

29‐Nov‐23
6 ISG CHP‐Civil IS‐4‐DC‐699‐104‐C218 TRANSFER POINT‐35 : Design of Foundations System A 05‐Jun‐18 C,E 1 09‐Sep‐20 14‐Sep‐20 Pending With Customer

29‐Nov‐23
7 ISG CHP‐Civil IS‐1‐RC‐699‐104‐C219 TRANSFER POINT‐35 : GA & RC Detail of Foundation System A 20‐Jun‐18 C,E 1 09‐Sep‐20 14‐Sep‐20 Pending With Customer

30‐Nov‐23
17 ISG CHP‐Ele IS‐1‐EE‐699‐100‐E021 GA, Wiring diagram for distribution boards A 15‐Mar‐21 C,E 0 20‐Oct‐23 28‐Oct‐23 Re Submission Pending

GA, OGA, BOM & Wiring diagram for Local control panel for DE 30‐Nov‐23
18 ISG CHP‐Ele IS‐1‐EE‐699‐100‐E023 A 15‐Jun‐21 D,E 0 18‐Oct‐23 17‐Nov‐23 Re Submission Pending
system
30‐Nov‐23
20 ISG CHP‐Ele IS‐1‐EE‐699‐100‐E050 GA,Datasheet of Welding recepticles A 15‐Mar‐21 D,E 1 02‐Oct‐23 07‐Nov‐23 Re Submission Pending

30‐Nov‐23
21 ISG CHP‐Ele IS‐1‐EE‐699‐100‐E059 Lighting layout : CHP ER‐4 near Stockpile area I 15‐Apr‐21 D,E 0 16‐Oct‐23 15‐Nov‐23 Re Submission Pending

30‐Nov‐23
22 ISG CHP‐Ele IS‐1‐EE‐699‐100‐E060 Lighting layout : CHP ER‐5 near Bunker I 15‐Apr‐21 D,E 0 07‐Nov‐23 17‐Nov‐23 Re Submission Pending

30‐Nov‐23
55 ISG AHP‐Ele IS‐1‐EE‐699‐300‐E043 Control writeup for AHP A 15‐Apr‐21 C,D,E 1 05‐Sep‐23 12‐Oct‐23 Re Submission Pending

30‐Nov‐23
56 ISG AHP‐Ele IS‐1‐EE‐699‐300‐E046 List of Field Devices I 15‐Apr‐21 G,C,D 0 24‐Aug‐23 05‐Sep‐23 Re Submission Pending

29‐Nov‐23
81 ISG CHP‐MECH IS‐1‐GA‐699‐110‐M230E Piping Layout for Water System at WT‐1&2 and WT‐3&4 I 25‐Aug‐23 C,E 0 25‐Aug‐23 19‐Oct‐23 Re Submission Pending

30‐Nov‐23
82 ISG CHP‐Ele IS‐1‐EE‐699‐100‐E581 AVIADS‐Data Sheet for Misc Items A 25‐Sep‐23 D,E 0 11‐Oct‐23 15‐Nov‐23 Pending With Customer

27‐Nov‐23
83 ISG CHP‐Ele IS‐1‐EE‐699‐100‐E571 AVIADS‐GA & SLD Circuit Diagram & BOM of MLDB A 25‐Sep‐23 D,E 0 12‐Oct‐23 08‐Nov‐23 Approved

30‐Nov‐23
87 ISG AHP‐Ele IS‐1‐EE‐699‐300‐E501 FACIA FOR AHP ECP A 30‐Sep‐23 C,E 0 30‐Sep‐23 14‐Nov‐23 Re Submission Pending

BTL‐GA,SLD, BOM, Schematics for VFD Panels for Vibrating 30‐Nov‐23


88 ISG CHP‐Ele IS‐1‐EE‐699‐100‐E031 A 06‐Oct‐23 C,E 0 20‐Oct‐23 13‐Nov‐23 Re Submission Pending
feeders
27‐Nov‐23
90 ISG AHP‐MECH IS‐3‐GA‐699‐300‐M088 GA of Silo Vent Fan A 31‐Oct‐23 C,E 0 30‐Oct‐23 16‐Nov‐23 Re Submission Pending

GA & Data Sheet of Motorised Valves for DFDS, DS, PW & SW 27‐Nov‐23
91 ISG CHP‐MECH IS‐3‐GA‐699‐110‐M227F I 02‐Nov‐23 C,E 0 31‐Oct‐23 08‐Nov‐23 Re Submission Pending
System
21‐Nov‐23
133 ISG AHP‐MECH IS‐0‐PL‐699‐300‐M002A In Plant Piping Details for Ash handling system (Stage‐I) I 30‐Jul‐20 B,C,E,H 2 08‐Jul‐21 23‐Jul‐21 Pending With Customer

Ash Slurry Disposal Piping Layout (From FA silo Area to Ash 24‐Nov‐23
138 ISG AHP‐MECH IS‐1‐GA‐699‐317‐M024 I 10‐Jan‐21 B,H 2 05‐May‐23 11‐May‐23 Pending With Customer
Pond)
30‐Nov‐23
139 ISG AHP‐MECH IS‐4‐SC‐699‐300‐M002 Valve Schedule for AHP A 30‐Nov‐20 B,C,H,F 1 11‐Oct‐23 06‐Nov‐23 Re Submission Pending

Page 1 of 1

You might also like