Project : 5x800MW Yadadri TPS As on 02‐12‐2023

Drawings pending for first submission by BHEL ISG


App. First Sub. Days
Sl. No Unit System/Area Drawing No Title Current Status Plan for Submission Status as on 02.12.23
Cat. Scheduled Lapsed
First Submission More than 1 30‐Nov‐23
84 ISG CHP‐Ele IS‐1‐EE‐699‐100‐E068 Lighting Layout of BCN#8A/8B I 15‐Apr‐21 First Submission Due
Due Year
First Submission More than 1 30‐Nov‐23
85 ISG CHP‐Ele IS‐1‐EE‐699‐100‐E079 Lighting Layout of BCN#24A/24B I 15‐Apr‐21 First Submission Due
Due Year
First Submission More than 1 30‐Nov‐23
86 ISG CHP‐Ele IS‐1‐EE‐699‐100‐E080 Lighting Layout of BCN#25 Yard Conveyor I 15‐Apr‐21 First Submission Due
Due Year
First Submission More than 1 30‐Nov‐23
88 ISG CHP‐Ele IS‐1‐EE‐699‐100‐E082 Lighting Layout of BCN#27A/27B I 15‐Apr‐21 First Submission Due
Due Year
First Submission More than 1 30‐Nov‐23
89 ISG CHP‐Ele IS‐1‐EE‐699‐100‐E083 Lighting Layout of BCN#28 with pent house‐22 (ERH Conveyor) I 15‐Apr‐21 First Submission Due
Due Year
First Submission More than 1 30‐Nov‐23
110 ISG CHP‐Ele IS‐1‐EE‐699‐100‐E104 Lighting Layout of TP ‐6 I 15‐Apr‐21 First Submission Due
Due Year
First Submission More than 1 30‐Nov‐23
111 ISG CHP‐Ele IS‐1‐EE‐699‐100‐E105 Lighting Layout of TP ‐7 I 15‐Apr‐21 First Submission Due
Due Year
First Submission More than 1 30‐Nov‐23
112 ISG CHP‐Ele IS‐1‐EE‐699‐100‐E106 Lighting Layout of TP ‐8 I 15‐Apr‐21 First Submission Due
Due Year
First Submission More than 1 30‐Nov‐23
113 ISG CHP‐Ele IS‐1‐EE‐699‐100‐E107 Lighting Layout of TP ‐9 I 15‐Apr‐21 First Submission Due
Due Year
First Submission More than 1 30‐Nov‐23
124 ISG CHP‐Ele IS‐1‐EE‐699‐100‐E133 Lighting Layout of RTP‐3 I 15‐Apr‐21 First Submission Due
Due Year
First Submission More than 1 30‐Nov‐23
127 ISG CHP‐Ele IS‐1‐EE‐699‐100‐E137 Lighting Layout of Crusher House‐2 I 15‐Apr‐21 First Submission Due
Due Year
First Submission More than 1 30‐Nov‐23
130 ISG CHP‐Ele IS‐1‐EE‐699‐100‐E141 Lighting Layout of Wagon Tippler Complex‐2 I 15‐Apr‐21 First Submission Due
Due Year
First Submission More than 1 30‐Nov‐23
131 ISG CHP‐Ele IS‐1‐EE‐699‐100‐E142 Lighting Layout of Emergency Reclaim Hopper Complex‐1 I 15‐Apr‐21 First Submission Due
Due Year
First Submission More than 1 30‐Nov‐23
133 ISG CHP‐Ele IS‐1‐EE‐699‐100‐E144 Lighting Layout of RCERH‐1 I 15‐Apr‐21 First Submission Due
Due Year
First Submission More than 1 30‐Nov‐23
134 ISG CHP‐Ele IS‐1‐EE‐699‐100‐E145 Lighting Layout of RCERH‐2 I 15‐Apr‐21 First Submission Due
Due Year
First Submission More than 1 30‐Nov‐23
135 ISG AHP‐Ele IS‐1‐EE‐699‐300‐E013 GA, Datasheet, Characteristic Curves of HT Motors‐Compressors A 15‐Apr‐21 First Submission Due
Due Year
First Submission More than 1 30‐Nov‐23
137 ISG AHP‐Ele IS‐1‐EE‐699‐300‐E017 Control Cable Schedule I 15‐Apr‐21 First Submission Due
Due Year
First Submission More than 1 30‐Nov‐23
161 ISG AHP‐Ele IS‐1‐EE‐699‐300‐E053 Data Sheet for special VFD Cable A 30‐Oct‐21 First Submission Due
Due Year
First Submission B/w 6 Moths to 30‐Nov‐23
169 ISG AHP‐Ele IS‐1‐EE‐699‐300‐E071 P&ID of HCSD System A 31‐Mar‐23 First Submission Due
Due 1 Year
First Submission B/w 6 Moths to 30‐Nov‐23
172 ISG AHP‐Ele IS‐1‐EE‐699‐300‐E079 DATA SHEET OF TSS ANALYSER A 31‐Mar‐23 Re Submission Pending
Due 1 Year
First Submission B/w 6 Moths to 30‐Nov‐23
173 ISG AHP‐Ele IS‐1‐EE‐699‐300‐E080 DATA SHEET OF TURBIDITY METER A 31‐Mar‐23 Re Submission Pending
Due 1 Year
COMPRESSOR ROOM NEAR CRUSHER HOUSE: ARCHITECTURAL First Submission
176 ISG CHP‐CIVIL IS‐1‐CE‐699‐107‐C025 A 29‐Aug‐23 >60 & ≤90 Days 28‐Nov‐23 Pending With Customer
DETAILS Due

Page 1 of 2
Project : 5x800MW Yadadri TPS As on 02‐12‐2023
Drawings pending for first submission by BHEL ISG
App. First Sub. Days
Sl. No Unit System/Area Drawing No Title Current Status Plan for Submission Status as on 02.12.23
Cat. Scheduled Lapsed
COMPRESSOR ROOM NEAR CRUSHER HOUSE: GROUND FLOOR AND First Submission
177 ISG CHP‐CIVIL IS‐1‐RC‐699‐107‐C026 A 29‐Aug‐23 >60 & ≤90 Days 28‐Nov‐23 First Submission Due
EQUIPMENT FOUNDATION DETAILS Due
First Submission 30‐Nov‐23
178 ISG CHP‐Ele IS‐1‐EE‐699‐100‐E574 AVIADS‐GA & SLD Circuit Diagram & BOM of Lighting Panels A 25‐Sep‐23 >30 & ≤60 Days Pending With Customer
Due

Page 2 of 2