YTPS 5X800 MW UNIT-2 SCHEDULE

ACTIVITY JAN-24 FEB-24 MAR-24 APR-24 MAY-24 JUNE-24 JUL-24 AUG-24 SEP-24 OCT-24 NOV-24 DEC-24
EC CLEARANCE 15.04.24
1 BOILER LIGHT UP 22.04.24

04.05.24
CHEMICAL CLEANING COMPLETIION
2 & PIPING NORMALISATION
3 MDBFP (1 NO/UNIT
4 AUX. BOILER
TEMPORARY PIPING FOR STEAM
5 BLOWING
STEAM BLOWING & 15.07.24
6 NORMALISATION OF PIPING
7 BARRING GEAR
8 CPU SYSTEM
9 DG SYSTEM
10 BALANCE FANS
11 TG AUXILIARIES
12 CW / ACW SYSTEM
13 NDCT 50%
14 POWER EVACUATION
15 SYNCHRONISATION 22.07.24

TDBFP (2 NOS/UNIT) TDBFP#A


BARRING GEAR, TBFFP# BARRING
16 GEAR
MILLS FOR COAL FIRING (3) MILLS
17 READY E,F,G)

18 ASH HANDLING PLANT WET FLY ASH


19 RAILWAY SIDING
20 COAL HANDLING PLANT
07.09.24
21 COAL FIRING & REACHING 800 MW
22 BALANCE ESP PASSES
23 COOLING TOWER (100%)
24 BALANCE MILLS READINESS
25 TRIAIL OPERATION COMPLETION 17.09.24