Professional Documents
Culture Documents
Case Studies For Final
Case Studies For Final
Illegal truck to truck transfer resulting in loss incident. Standard Operating Procedures (SOP) not
followed. Compromised safety to speed up the process. Explosion of gas that leaked caused facility to
explode as well
Truck to truck transfers were a frequent & routine operating practice at the facility
PEAP:
Without sound leadership, the control of risks breaks down & unacceptable events occur
Immediate Causes:
• 2 condensate pumps – one shut down for maintenance and blanked off, not known to the night
crew.
• No work permits, or lockout permits were known of.
• Unknown reason for why second pump shutdown automatically
• Crew attempted to start first pump, condensate spewed out and vapour cloud exploded
• No fire water available
• Major failure in gas line
Basic Causes
PEAP: People: 2500 immediate fatalities (25000+ total fatalities) & 100,000+ offsite injuries
Environment: Vapour cloud of methyl isocyanate (MIC) released
Assets: ***
Production: ***
Water reacted with MIC in presence of metallic impurities. Rapid release of vapours through relief valve
system. Scrubber system was meant to deal with MIC gas alone, not mixed with liquid. It failed to
operate. Flare was down for maintenance and refrigeration was out of commission. Water sprinklers
didn’t provide enough water to neutralize the gases. The gas bypassed all the safety measures.
Immediate Cause
Basic Causes
• Human factors: Plant losing money (running at 40% capacity), low morale, safety rules and
permits not being effectively enforced, best employees leaving, manning cut by half, no
maintenance supervisor on second and third shirt, not a computerized plant, and rumors of
sabotage upset brining systems under control.
• Organizational Factors: Bhopal was an unprofitable plant in an unimportant division of the
corporation, operating under 40% capacity, plant was up for sale, 8 plant managers in 15 years
(many from non-chemical industry backgrounds), 10 major areas of concern that were not
corrected (5 contributed to the incident), no contingency plans for dealing with major incidents
and management system was of a poor quality.
• Technological Factors: Large storage of MIC, non-computerized plant, tank was not under
positive nitrogen pressure for 2 months (allowed metallic impurities enter and act as a catalyst),
plant design and piping system allowed a pathway for wash water to back into tank during
flushing operation, scrubber system designed for vapour only and no radio communication
system for operating staff.
• Poor government in Bhopal: local government allowed for urban development near plant, lack
of community awareness and emergency preparedness.
Latent causes
Basic causes
Engineering and design factors
• Available manufacturers literature on the bellows noted that only straight
connections were safe
Job factors
• No mechanical engineer of sufficient calibre on site when bypass was designed
• Senior management previously advertised for mechanical engineer – should have
had temporary solution
Personal Factors
• Chemical engineer was in charge
• Completed the temporary design for the bypass
• He thought he knew enough and was driven to satisfy his manager
Case Studies for Final ENGG 404
Latent causes
• RME 2 (RAMR) – No one recognized the hazard of installing an inadequately designed popping
spool
• RME 4 (MOC) – There was no formal review process to examine, analyze, and assess the change
in the piping system before it was being implemented.
STS-51L Challenger
Significant tension between management & engineers about what the data was saying about risk of
launch
*** Key lessons from Challenger: (Main ones from prof)
1) Maintain Sense of Vulnerability
2) Combat Normalization of Deviance
Combat Normalization of deviance with empowerment & accountability
Combat Complacency with Vigilance
Other key lessons:
Challenger was delayed 6 times. Engineers at contractors who worked on O-rings told NASA officials that
launch spoke against launches under 54F. Night before contractors had a call with NASA and told them it
will be too cold and that they shouldn’t launch. Contractors engineers did not sign off on the launch.
Contractor management made the decision to sign off on the launch because of an attitude of asking
engineers to prove that the O-rings would fail, and it would be unsafe to launch. Engineers consulted
their data but could not prove 100% that their would-be failure. There were 9 cases of primary O-Ring
failing but not secondary O-ring. NASA management and contractor management saw that secondary O-
ring was enough. O-rings expand and seal the cylinders. When temperature is too low, and the O-rings
cannot expand and seal the cylinders.
Immediate Causes:
• O-rings fail to seal solid rocket booster hot gases at joint due to low temperatures
• Temperature was out of their normal launch range
• Pre-flight leak tests caused more damage by puncturing O-ring seal
• Rubber O-ring seal failed, burned away, and caused solid rocket combustion gases to escape and
impinge on the LOx and H2 rocket tanks
Case Studies for Final ENGG 404
Latent Causes
STS-107 Colombia
Immediate Causes
• Heat resistant tiles were damaged by insulation impact
Latent Causes:
• Decision to launch despite known hazard (outside temp range)
• Management pressure on cost and schedule
• Failure to investigate previous incidents (previous issues with primary O-ring failing)
• Failure to do risk assessment/abide by risk assessment
• Failure to check and correct gaps in the risk management program
• Substandard Conditions:
o Inadequate ventilation system design & capability
o Thick layers of coal dust with unacceptably high levels of combustible matter
o Inadequate system to warn of high methane levels
Basic Causes:
Engineering & design Factors:
• Poor regulating control of maintaining air flow (inadequate technical design)
Job factors:
• Workers not engaged in day-to-day decision making, just follow orders (organizational
factor)
• Unqualified personnel & poor employee training (inadequate training)
• Poor compliance to best industry practices & legislated safety requirements (inadequate
job procedures)
Personal factors:
• Fear of retaliation from workers (perceived mental or psychological stress)
Latent Causes:
• Associated with weaknesses in MLCA, PE&CI, DC&S, O&P, EC&T
The following Pressures from client cause engineer to make such decisions:
• Money (Reduce costs for client)
• Might lose client
• Might get fired
Immediate Causes:
• Substandard work practices:
o Engineer completed deficient inspections of the mall
o Engineer didn’t read past inspection reports by other engineers
o Engineer didn’t inspect ceiling beam welds
• Substandard Conditions:
o Water leaking through roof-top parking deck
o Welds in ceiling beams of mall were corroded
Basic Causes:
Engineering & design factors:
• Original mall design allowed for water to infiltrate through roof (inadequate technical
design)
Job Factors:
• Municipal officials chose not to enforce their own bylaws (organizational factors)
• Inadequate maintenance of rooftop parking deck
Personal Factors:
• Engineer was more concerned about pleasing the mall owner (improper motivation)
Case Studies for Final ENGG 404
Latent Causes:
• Municipal officials & mall owner prioritized profit over safety (MLCA)