Sample Testing & Commissioning MSRA (Complete)
Sample Testing & Commissioning MSRA (Complete)
Project: Package G - Proposed Detention Tanks, SW1a, SW2, SW3 and Boardwalk at Existing
Singapore Zoological Gardens and Addition & Alteration to Existing Perimeter Drains on
LOT 01891M PT MK1A at Mandai Lake Road (Central Water Catchment Planning Area)
Contract no: G-SI-CON-289
Description & Contract Specifications Document No./Shop Drawing No./ Brand & Model
Item
Reference No./Material Sample/ Catalogue/Others
1. Method of Statement MEN-289-EXP-ME-MST-0081
2. Risk Assessment MEN-289-EXP-ME-GED-0081
Copies to:
☒ Client: Mandai Park Development Pte Ltd ☐ Landscape: Ramboll Studio Dreiseitl
☒ Architect: RSP Architects Planners & Engineers (Pte) Ltd ☐ QS: Arcadis Singapore Pte Ltd
☒ C&S: AECOM Singapore Pte Ltd ☒ Resident Engineer (Arch/C&S/M&E)
☒ M&E: Surbana Jurong Consultants Pte Ltd ☒ Resident Technical Officer (Arch/C&S/M&E)
RFA-R1 (2019)
PROPOSED DETENTION TANKS, SW1A, SW2, SW3 AND BOARDWALK AT
EXISTING SINGAPORE ZOOLOGICAL GARDENS AND ADDITION AND
ALTERATIONS TO EXISTING PERIMETER DRAINS ON LOT 01891M PT MK14 AT
MANDAI LAKE ROAD (CENTRAL WATER CATCHMENT PLANNING AREA)
METHOD STATEMENT
FOR
PLUMBING SYSTEM TESTING AND
COMMISSIONING AT SW1A, SW2 & SW3
Page | 1
PROPOSED DETENTION TANKS, SW1A, SW2, SW3 AND BOARDWALK
AT EXISTING SINGAPORE ZOOLOGICAL GARDENS AND ADDITION AND
ALTERATIONS TO EXISTING PERIMETER DRAINS ON LOT 01891M PT MK14
AT MANDAI LAKE ROAD (CENTRAL WATER CATCHMENT PLANNING AREA
TABLE OF CONTENTS
CONTENTS
1. Introduction .................................................................................................................................... 3
2. Scope of work.................................................................................................................................. 3
3. Roles and Responsibilities ............................................................................................................... 3
4. Work methodogy ............................................................................................................................ 3
4.1 Water Pipe Pressure Test (Underground & aboveground) ..................................... 3
4.2 House keeping .................................................................................................................... 4
5. Contingency Plan ............................................................................................................................ 4
6. List of Equipment & Tools ............................................................................................................... 5
7. Personal Protective Equipment (PPE) ............................................................................................. 5
8. Safe Work Procedure ...................................................................................................................... 5
8.1 Safe Work Procedure for Water Pipe Pressure Test................................................. 5
8.2 Safe work procedure for Electrical tools ..................................................................... 6
8.3 Other general safety measure and precaution ........................................................... 6
9. Environmental Controls .................................................................................................................. 7
10. Safety and Health ........................................................................................................................ 8
11. Emergency Response Flow Chart/ Contact ................................................................................. 9
12. Appendix ................................................................................................................................... 11
Page | 2
PROPOSED DETENTION TANKS, SW1A, SW2, SW3 AND BOARDWALK
AT EXISTING SINGAPORE ZOOLOGICAL GARDENS AND ADDITION AND
ALTERATIONS TO EXISTING PERIMETER DRAINS ON LOT 01891M PT MK14
AT MANDAI LAKE ROAD (CENTRAL WATER CATCHMENT PLANNING AREA
1. INTRODUCTION
This statement is to document the method of Test & Commissioning works for Plumbing
System at SW3, SW2 and SW1a/DT5.
2. SCOPE OF WORK
Plumbing system testing and commissioning work at SW1a/DT5, SW2 & SW3.
4. WORK METHODOGY
4.1 Water Pipe Pressure Test (Underground & aboveground)
1. Fix the end cap with valves both sides. 1st point to release the Air/Water and 2nd point to fix
T-connection with stop cock/gate valve and pressure gauge.
Page | 3
PROPOSED DETENTION TANKS, SW1A, SW2, SW3 AND BOARDWALK
AT EXISTING SINGAPORE ZOOLOGICAL GARDENS AND ADDITION AND
ALTERATIONS TO EXISTING PERIMETER DRAINS ON LOT 01891M PT MK14
AT MANDAI LAKE ROAD (CENTRAL WATER CATCHMENT PLANNING AREA
6. Submit Inspection Form along with calibration certificate. Call RTO for Inspection.
7. Take 1st reading with RTO. 2nd reading after 24hrs.
8. On successful completion of the pressure testing process, the T-connection shall be
disconnected from the pipe and the pipe properly plugged.
5. CONTINGENCY PLAN
In an event of Heavy Rainfall;
1. All excavation works shall be suspended;
2. All tools and material shall be properly stored away from the edge
3. The trench shall be covered to prevent rainwater from entering
4. During the connection work overhead shelter/ tent provided at both connection
points.
Page | 4
PROPOSED DETENTION TANKS, SW1A, SW2, SW3 AND BOARDWALK
AT EXISTING SINGAPORE ZOOLOGICAL GARDENS AND ADDITION AND
ALTERATIONS TO EXISTING PERIMETER DRAINS ON LOT 01891M PT MK14
AT MANDAI LAKE ROAD (CENTRAL WATER CATCHMENT PLANNING AREA
1. To provide adequate sign board e.g. No Entry, Pressure Test in progress, etc.
2. To barricade the pressure test area.
3. Ensure calibrated record is available and submitted.
4. Ensure no one enters into the testing area without authorization
5. Ensure SWP & RA is briefed and made clear to all involved in operation
6. Due to overnight testing, ensure that proper and efficient barricade is provided with
warning sign
7. Testing Pressure is 177psi and duration is 24hrs.
Page | 5
PROPOSED DETENTION TANKS, SW1A, SW2, SW3 AND BOARDWALK
AT EXISTING SINGAPORE ZOOLOGICAL GARDENS AND ADDITION AND
ALTERATIONS TO EXISTING PERIMETER DRAINS ON LOT 01891M PT MK14
AT MANDAI LAKE ROAD (CENTRAL WATER CATCHMENT PLANNING AREA
1. Before using the electrical tools must check valid LEW sticker place on it.
2. No cables are allowed to lie on ground or floor. If unavoidable, the cables shall be of
weatherproof types, with adequate protection.
3. Use proper warning sign.
4. All electrical installations & equipment are of good construction, sound material and free
from defects.
5. If any repair in electrical tools only qualified person can do all repair works.
6. Use proper PPE i.e., rubber gloves, non-conducting shoes etc.
7. Carry out electrical connection by the authorized and competent person.
1. Foreman to ensure workers to put on safety helmet, safety shoe, safety belt and hand
glove at all time.
2. Tool-box talks to be conducted before the start of work on the safety measure and
precaution of the job by foreman.
3. If hand-tool were to be used, check physical condition of the hand-tool. Do not use damage
tool.
4. If power-tool were to be used workers need to be in-house trained and register with the
main-con, safety dept. If hand held grinder to be used, follow strictly on the SWP for hand
held grinder.
5. If hand held grinder to be used, follow strictly on the SWP for hand held grinder.
6. Inspect all power cords for wear and damage. Do not use equipment with damaged cords.
7. Do not let wire cords laid on the floor or any metal object. Hung up wire with non-metallic
object such as timber.
8. Wear eye protection, hearing protection and dust mask if hacking or chiseling is required
for the job. Material handling- use proper lifting techniques. Ask for help or assistance
when moving heavy or bulky object.
Page | 6
PROPOSED DETENTION TANKS, SW1A, SW2, SW3 AND BOARDWALK
AT EXISTING SINGAPORE ZOOLOGICAL GARDENS AND ADDITION AND
ALTERATIONS TO EXISTING PERIMETER DRAINS ON LOT 01891M PT MK14
AT MANDAI LAKE ROAD (CENTRAL WATER CATCHMENT PLANNING AREA
9. ENVIRONMENTAL CONTROLS
1. Prior to work commencement, the proposed work area shall be assessed for
suitability to carry out the works by the Environmental Manager.
2. All workers shall be properly inducted and undergone required training prior to work
commencement.
3. Where necessary, noise barrier will be installed around the pipe jointing area to
minimize the construction noise.
4. All works carried out shall be normal working hours (between 0800-1700hrs) on
weekdays, and may be further worked around park operations in order to avoid
disruptions. Where works are required to be carried out during the night (e.g
shutdown as required by WRS), the works shall be assessed in accordance with
EMMP requirements and measures implemented accordingly.
5. At all times, the T&C work team shall be accompanied by an authorized Expand
staff and/or delegated MPD/stakeholders’ representative. Entry into restricted
areas shall be strictly with the permission from MPD/stakeholders.
6. Any water collected in sump pit should be pumped into the ECM tank. After
treatment the water should discharge to drain.
7. Wildlife response plan shall be adhered during construction works.
8. Food shall not be consumed on site, but only at designated rest area (with
designated bins for proper disposal of food waste).
9. All food waste shall be contained in plastic bags before disposal into wildlife-proof
bins. They should be removed daily to prevent attraction of pests and smell
nuisance.
10. All workers and visitors shall be educated to ensure that all workplaces are kept
clean and waste materials are not left in open areas.
11. If possible, windows or openings facing the forested areas will be sealed with
acoustic sheets at designated work sites to prevent light spillage (and provide
screening effects to noise generated from the construction works.
12. Keep windows and doors closed during indoor overnight construction works,
whenever safe to do so, to reduce extent and intensity of light escaping buildings.
Page | 7
PROPOSED DETENTION TANKS, SW1A, SW2, SW3 AND BOARDWALK
AT EXISTING SINGAPORE ZOOLOGICAL GARDENS AND ADDITION AND
ALTERATIONS TO EXISTING PERIMETER DRAINS ON LOT 01891M PT MK14
AT MANDAI LAKE ROAD (CENTRAL WATER CATCHMENT PLANNING AREA
13. Ensure temporary lighting used indoors for construction activities located near
glass walls as well as open windows or doors are blocked with acoustic sheets and
pointed away from vegetated areas including CCNR, Eco-Link, Track 15 Stream
and TPZ.
14. Restrict outdoor movements by workers to use of designated sanitary facilities (or
in the case of an emergency, evacuation from buildings), workers will remain
indoors from 6 pm to 10pm. When workers step outside of buildings,
flashlights/headlamps for walking to and from sanitary facilities for safety purposes
will be kept pointed towards the ground and away from the CCNR and other
vegetated areas.
Page | 8
PROPOSED DETENTION TANKS, SW1A, SW2, SW3 AND BOARDWALK
AT EXISTING SINGAPORE ZOOLOGICAL GARDENS AND ADDITION AND
ALTERATIONS TO EXISTING PERIMETER DRAINS ON LOT 01891M PT MK14
AT MANDAI LAKE ROAD (CENTRAL WATER CATCHMENT PLANNING AREA
Page | 9
PROPOSED DETENTION TANKS, SW1A, SW2, SW3 AND BOARDWALK
AT EXISTING SINGAPORE ZOOLOGICAL GARDENS AND ADDITION AND
ALTERATIONS TO EXISTING PERIMETER DRAINS ON LOT 01891M PT MK14
AT MANDAI LAKE ROAD (CENTRAL WATER CATCHMENT PLANNING AREA
1) Mr. Tay Kor Yong (M&E Site Manager) & Mr. Nyi Soe Tun (M&E Engineer) will be the first
contact person in case of emergency and will be the overall in charge on site representing
Expand Construction Pte Ltd.
Page | 10
PROPOSED DETENTION TANKS, SW1A, SW2, SW3 AND BOARDWALK
AT EXISTING SINGAPORE ZOOLOGICAL GARDENS AND ADDITION AND
ALTERATIONS TO EXISTING PERIMETER DRAINS ON LOT 01891M PT MK14
AT MANDAI LAKE ROAD (CENTRAL WATER CATCHMENT PLANNING AREA
12. APPENDIX
1. Risk Assessment (document number: MEN-289-EXP-ME-GED-0081)
2. Testing & Commissioning check list
Page | 11
ACTIVITY-BASED RISK ASSESSMENT
PROPOSED DETENTION TANKS, SW1A, SW2, SW3 AND BOARDWALK AT EXISTING SINGPORE ZOOLOGICAL
GARDENS AND ADDITION AND ALTERATIONS TO EXISTING PERIMETER DRAINS ON LOT 01891M PT MK14 AT RA REFERENCE: MEN-289-EXP-ME-GED-0081
MANDAI LAKE ROAD (CENTRAL WATER CATCHMENT PLANNING AREA)
Reviewed by:
Company: WSG ENGINEERING PTE LTD RA Leader Mr. Saravanan
Mr. Lee Lam Huat
RA
Location: Mandai Zoo, SW1, SW2 & SW3 RA Member Date: 10/12/2021
Member Rev No.
Org. Assessment RA Approved by: 00
8TH May 2020 RA Member
Date: Member Mr. Jack Cheong
RA
Last Review Date: 8th May 2020 RA Member Designation: P. Director
Member
RA
Next Review Date: 8th May 2023 RA Member Date: 10/12/2021
Member
Risk Matrix
Negligible (1) Not likely to cause injury or ill-Health. Low Risk (1) Low Risk (2) Low Risk (3) Medium Risk (4) Medium Risk (5)
Hazard / Environmental Aspect Identification Risk / Environmental Impact Evaluation Control Measures
Action
Officer,
Ref Hazard / Env Possible Risk /
Work Activity Existing Control Measures S L RPN Additional Control Measures S L RPN Designation
No. Aspect Env, Impact
(Follow up
date)
1. Plumbing & Sanitary Testing / Commissioning Works
1.1. Water Pipe Pressure Pressurizing test Multiply injury 1) The affected area to be cordon off and warning 5 2 10 1) Only allow to perform testing 5 1 5 Site Supervisor
Test - exposure to even fatality. signs to be displayed. (Pressure control refer to at silent hours
compressed or Floods and method statement) 2) Install the pressure safety
pressured contact with fluids To communicate with other subcon working near by relief valves
gas/water. secondary protection for pressure hoses 3) The pressure is increasing
Struck or hit by safety distancing for pressure testing gradually by 50% each interval.
the pressurised temporary support to the installed pipes 4) The mustering point is
pipe/ hoses 2) A watchman to be standby for monitoring designated and free from
Flanges improper 3) Ensure all the pipes to be tested are secured. obstruction
tightened 4) Ensure the pipes are not over-pressurized 5) Ensure the pressure is closed
5) Ensure correct blind is used & tightened properly. monitored and no over pressure
6) Check for leakage prior testing due to thermal expansion
7) Proper access is available and ensure no
obstruction of access walkway
PPE
Wear appropriate PPE, e.g., safety glass & hand
gloves.
1.2. Falling into the Workers may fall Engineering Control 3 1 3 N. A 3 1 3 Site Supervisor
IC/ MH into IC/ MH 1) Keep workers away from operations area with
Sanitary Pipe (objects/ people) resulting in bodily exclusion zone.
Hydrostatic Test injuries. 2) Inform all other workers of work activities during
Toolbox Meeting.
3) IC/ MH to be barricaded.
PPE
Wear safety helmets, gloves and safety shoes.
Insufficient It can cause Engineering Control 4 2 8 Engineering Control 4 1 4 Site Supervisor
barricade / serious injuries to 1) Conduct toolbox meeting daily. 1) Site foreman to ensure the
improper signage workers. 2) Safety supervisor to visit site on daily basis. work site is properly barricaded
around testing PPE with blinker & signage to warn
area Wear safety helmets, gloves and safety shoes motorist and worker put on PPE
in the work area at all time.
Administrative Control
1) Conduct independent check
to ensure compliance.
2) Supervisor to provide
regularly safety briefing and
conduct daily check on the site.
Hazard / Environmental Aspect Identification Risk / Environmental Impact Evaluation Control Measures
Action
Officer,
Ref Hazard / Env Possible Risk /
Work Activity Existing Control Measures S L RPN Additional Control Measures S L RPN Designation
No. Aspect Env, Impact
(Follow up
date)
1.3. Use of electrically Damaged/Non- Electrocution Substitution 4 2 8 Administrative Control 4 1 4 Site Supervisor
powered tools insulated 1. Use battery/pneumatic-operated tools. Conduct regular toolbox meeting
electrical parts Engineering Control discussions on electrical safety.
1. Ensure all electrically powered tools are directly
connected the SOA/DB protected by Earth Leakage
Circuit Breaker (ELCB).
2. Ensure the electrical connection is not more than
3m long from the electrically powered tool.
Administrative Control
1. Ensure all electrically powered tools are inspected
by a Licensed Electrical Worker (LEW) once every
month.
2. Ensure tools with damaged housing are removed
from site.
PPE
1. Wear safety shoes with rubber soles.
Final Reading
Time
Date
Checked By Witnessed By
Name Name
Signature Signature
Date Date
Verified By
Name
Signature
Date