WATERPROOFING REPORT
RAFT FOUNDATION OF FL-05
CONTRACTOR:
CONTENTS
1. PROJECT PARTICIPANTS:..........................................................................................................................................2
2. PROJECT BRIEF:........................................................................................................................................................2
3. INTRODUCTION & BACKGROUND:..........................................................................................................................2
4. RAFT FOUNDATION POURING:................................................................................................................................2
5. RETAINING WALL.....................................................................................................................................................3
6. CONSTRCUTION JOINT:...........................................................................................................................................3
7. PICTURES:................................................................................................................................................................4
1.
WATERPROOFING REPORT 1
1. PROJECT PARTICIPANTS:
2. PROJECT BRIEF:
Raft Slab of FL-5 (Tower 1,2,3 &4) located at Naya Nazimabad was planned b/w Grid A1 to
S1 and 1 to 57 which included 2 Ramps.
the waterproofing of Basement 2 of T1, T2,T3 and T4 was required because the previous
cold bituminous coating of retaining wall upto Ground floor was failed to serve its purpose
and water penetrates from retaining wall , construction joints of T1 and T2, T2 and T3 it was
also observed at number of location in basement that water keeps penetrating from the
top of raft thus initially it was difficult to identify exact location of points that needs to be
treated because of this firstly Construction Joint 2 and 3 was treated and retaining wall was
treated simultaneously after that water points between tower 2 and 3 were treated when
most of area of basement dried then waterproofing team moved to treat Construction joint
of tower 1 and 2 as well as water points between tower 1 and 2 where as retaining wall was
treated simultaneously .
Sr.
Activity Start Date Finish Date
No.
1. Pouring of Tower 1 Raft 23/5/2022 25/5/2022
WATERPROOFING REPORT 2
5. RETAINING WALL
Retaining wall waterproofing Starts by Grinding the surface of wall , if water pressure of point is high then grout
(Cementitious) is injected then crystalline coating is done in 2 coats. After this joint between raft and retaining wall is
treated by chiseling, application of primer, then chamfer is made after this double coat of crystalline waterproofing is
done.
6. CONSTRCUTION JOINT:
Construction Joint is treated by chiseling the joint then drilling pressure points upto 1’ to 2’ based on pressure i.e.
higher the pressure greater will be depth then grout is injected with machine immediately after injection joint is
plugged with hardener and cement then double coat of crystalline waterproofing material is applied.
WATERPROOFING REPORT 3
Treatment of retaining wall and raft joint (Chamfer)
WATERPROOFING REPORT 4
Tower 1 and Tower 2 Construction Joint
WATERPROOFING REPORT 5
Construction Joint Tower 2 and Tower 3
WATERPROOFING REPORT 6
Treatment of retaining wall and raft joint (Chamfer)
WATERPROOFING REPORT 7
Water Seeping Points along retaining wall
Pit Treatment
WATERPROOFING REPORT 8
Waterseeping Points Between Tower 1 and Tower 2
WATERPROOFING REPORT 9
Sump pit Treatment
Waterseeping Point
WATERPROOFING REPORT 10
Waterseeping Point
WATERPROOFING REPORT 11
Retaining Wall Corner Treatment Tower 3
WATERPROOFING REPORT 12
Retaining Wall Corner Tower 3
WATERPROOFING REPORT 13