Download as pdf or txt
Download as pdf or txt
You are on page 1of 3

WHITE PAPER:

CONSERVATION VOLTAGE REDUCTION DURING PEAK LOADING TIMES

Contributed by Chris Mullins & Brandon Horne, which distributors lower the voltage on their
October 2011 system for a short duration. Lowering the voltage
on a system will temporarily lower the power de-
ABSTRACT manded by the loads connected to those circuits.
JCPB is charged a demand component for each
The Johnson City Power Board is an electric kw demanded by the system in its entirety. Thus,
power distributor located in Johnson City, Tennes- lowering the demand of the system as a whole
see, serving over 75,000 customers in 5 counties. during peak times will reduce the demand charge
JCPB operates and maintains over 2000 miles from TVA.
of 13KV distribution lines and over 120 miles
of 69KV transmission. The peak system load on Typical factors for percent load reduction are 0.5
JCPB’s system is 550 MW. JCPB has 30 distribu- to 1.2 for every percent of voltage reduced. ANSI
tion substations with over 100 distribution feeders. C84.1 allows for a minimum voltage at the end
JCPB purchases power from the Tennessee Valley customer’s metering point to be no less than 114
Authority. In March 2010, TVA converted their volts during normal operation. JCPB needed to
billing structure to include demand power charges find a way to measure the voltage at the end of the
for each distributor. Therefore JCPB decided to line in order to maintain minimum voltage at the
implement a conservation voltage reduction plan customer’s billing point and achieve the maximum
during peak loading times in order to save on peak reduction in voltage at the substation. Figure 1. Custom dashboard
demand charges. showing station loading,
PROBLEM DEFINITION end of line voltages, and
CONTEXT voltage reduction status. 17
JCPB operates an unlicensed 900 MHz radio sys- Boomerang devices are online
Conservation voltage reduction is a process by tem for communication with substations and some at the time of the screenshot.

Page 1 CS2 © 2016 Power Monitors, Inc. • Call Us: (800) 296-4120 • www.powermonitors.com
WHITE PAPER:
CONSERVATION VOLTAGE REDUCTION DURING PEAK LOADING TIMES

Figure 2. Monthly load


profile with voltage reduction
initiated only during peak
time of the month.

field devices. Because they are unlicensed, the ly bias the voltage regulation devices to achieve
power output of the radios is restricted to 1 watt. maximum benefit. Many products, such as AMI
Line of sight is required for these radios to com- systems, record and report the voltage back to
municate reliably with one another. JCPB’s system their servers. Often there is a latency between the
is in the hills of the Appalachian Mountains and measurement and the time that it is reported. This
has many hills and valleys where line of sight could cause either an underperforming system
communication is difficult. In many cases, multi- or the voltage to be below the minimum voltage
ple repeaters were required to achieve the line of range. In addition to the latency, many AMI ven-
sight between the radios. In order to communicate dors do not have an application to allow a SCADA
with any end of line voltage devices using these system to access this voltage information. The
radios, a large investment would have been needed equipment selected to report the voltage would
in radios and repeaters. Additionally, as JCPB’s have to do so with a high degree of accuracy, in
system grows and changes are made to the feeders near real-time, and be able to interface with our
and substations, the point on each feeder with the SCADA system.
lowest voltage may change. This would require
additional investment in radios and repeaters. SOLUTION
Installing 900 MHz radios and repeaters to com-
municate with an end of line voltage sensor would JCPB selected the Power Monitors Boomerang
be time consuming and expensive. Each month device to report the end of line voltages back to
that JCPB is not receiving the end of line voltages JCPB’s SCADA system. Each Boomerang oper-
from critical feeders lessens the amount of demand ates over a GSM cellular network and has a static
reduction that JCPB can achieve. IP address. There is a DNP protocol interface
for each device that allows SCADA communica-
GOALS OF EQUIPMENT APPLICATION tion. Since the communications infrastructure is
already in place with these devices, there was no
System automation is required to eliminate any need for JCPB to purchase and install additional
human error in a voltage reduction program and radios and repeaters. JCPB used a model of the
achieve maximum benefit. There is a need to power system to determine which feeders on each
acquire near real-time measurements to adequate- substation would have the lowest voltages during

Page 2 CS2 © 2016 Power Monitors, Inc. • Call Us: (800) 296-4120 • www.powermonitors.com
WHITE PAPER:
CONSERVATION VOLTAGE REDUCTION DURING PEAK LOADING TIMES

Figure 3. Zoom of
voltage reduction showing
approximate 7 MW
reduction in load

peak loading. Using this model, one or two feeders CONCLUSION


out of each station had the highest load or the
longest line that resulted in the lowest voltage out The Johnson City Power Board installed 27
of that station. The ends of these feeders were se- Boomerang devices on the system to maximize
lected to install a Boomerang device to report the the benefit of conservation voltage reduction
voltage. JCPB personnel visited each feeder with while maintaining above minimum voltage on
a powered Boomerang device to verify communi- the customers’ point of service. The conservation
cations. Once communications were verified, the voltage reduction program will lower JCPB’s cost
Boomerang devices were installed on the lines and of providing power, therefore driving rates down.
programmed into the SCADA. Voltage measure- The Boomerang solution allows for accurate and
ments for the ends of those lines were now avail- real-time measurements of end of line voltages
able in SCADA for achieving maximum benefit of and is easily relocated at minimum cost as the
the voltage reduction program. Custom scripts for system changes. The conservation voltage reduc-
the SCADA system were then written to automate tion program in conjunction with the Boomerang
the voltage reduction program. These scripts are devices allows JCPB to operate its power system in
programmed to bias the regulators from the end of a more efficient manner, serve the customers better
line voltages and maintain peak performance from by keeping rates low, and help the environment by
the voltage reduction program. Many other scripts reducing carbon emissions from fossil fuel burning
were written to automate the entire system, result- generation plants.
ing in the voltage reduction program to be called
upon only when a new monthly peak is going to Brandon Horne, PE, MBA
be achieved. As the JCPB’s system changes over System Design Engineer
time, the Boomerang devices are easily relocated Johnson City Power Board
without the expense of installing additional com- www.jcpb.com
munication infrastructure. Hence, the Boomerang
devices and custom automation scripts provide Chris Mullins
JCPB with an efficient and reliable solution for VP of Engineering and Operations
achieving conservation voltage reduction. cmullins@powermonitors.com
https://www.powermonitors.com
(800) 296-4120

Page 3 CS2 © 2016 Power Monitors, Inc. • Call Us: (800) 296-4120 • www.powermonitors.com

You might also like