Professional Documents
Culture Documents
White Paper:: Conservation Voltage Reduction During Peak Loading Times
White Paper:: Conservation Voltage Reduction During Peak Loading Times
Contributed by Chris Mullins & Brandon Horne, which distributors lower the voltage on their
October 2011 system for a short duration. Lowering the voltage
on a system will temporarily lower the power de-
ABSTRACT manded by the loads connected to those circuits.
JCPB is charged a demand component for each
The Johnson City Power Board is an electric kw demanded by the system in its entirety. Thus,
power distributor located in Johnson City, Tennes- lowering the demand of the system as a whole
see, serving over 75,000 customers in 5 counties. during peak times will reduce the demand charge
JCPB operates and maintains over 2000 miles from TVA.
of 13KV distribution lines and over 120 miles
of 69KV transmission. The peak system load on Typical factors for percent load reduction are 0.5
JCPB’s system is 550 MW. JCPB has 30 distribu- to 1.2 for every percent of voltage reduced. ANSI
tion substations with over 100 distribution feeders. C84.1 allows for a minimum voltage at the end
JCPB purchases power from the Tennessee Valley customer’s metering point to be no less than 114
Authority. In March 2010, TVA converted their volts during normal operation. JCPB needed to
billing structure to include demand power charges find a way to measure the voltage at the end of the
for each distributor. Therefore JCPB decided to line in order to maintain minimum voltage at the
implement a conservation voltage reduction plan customer’s billing point and achieve the maximum
during peak loading times in order to save on peak reduction in voltage at the substation. Figure 1. Custom dashboard
demand charges. showing station loading,
PROBLEM DEFINITION end of line voltages, and
CONTEXT voltage reduction status. 17
JCPB operates an unlicensed 900 MHz radio sys- Boomerang devices are online
Conservation voltage reduction is a process by tem for communication with substations and some at the time of the screenshot.
Page 1 CS2 © 2016 Power Monitors, Inc. • Call Us: (800) 296-4120 • www.powermonitors.com
WHITE PAPER:
CONSERVATION VOLTAGE REDUCTION DURING PEAK LOADING TIMES
field devices. Because they are unlicensed, the ly bias the voltage regulation devices to achieve
power output of the radios is restricted to 1 watt. maximum benefit. Many products, such as AMI
Line of sight is required for these radios to com- systems, record and report the voltage back to
municate reliably with one another. JCPB’s system their servers. Often there is a latency between the
is in the hills of the Appalachian Mountains and measurement and the time that it is reported. This
has many hills and valleys where line of sight could cause either an underperforming system
communication is difficult. In many cases, multi- or the voltage to be below the minimum voltage
ple repeaters were required to achieve the line of range. In addition to the latency, many AMI ven-
sight between the radios. In order to communicate dors do not have an application to allow a SCADA
with any end of line voltage devices using these system to access this voltage information. The
radios, a large investment would have been needed equipment selected to report the voltage would
in radios and repeaters. Additionally, as JCPB’s have to do so with a high degree of accuracy, in
system grows and changes are made to the feeders near real-time, and be able to interface with our
and substations, the point on each feeder with the SCADA system.
lowest voltage may change. This would require
additional investment in radios and repeaters. SOLUTION
Installing 900 MHz radios and repeaters to com-
municate with an end of line voltage sensor would JCPB selected the Power Monitors Boomerang
be time consuming and expensive. Each month device to report the end of line voltages back to
that JCPB is not receiving the end of line voltages JCPB’s SCADA system. Each Boomerang oper-
from critical feeders lessens the amount of demand ates over a GSM cellular network and has a static
reduction that JCPB can achieve. IP address. There is a DNP protocol interface
for each device that allows SCADA communica-
GOALS OF EQUIPMENT APPLICATION tion. Since the communications infrastructure is
already in place with these devices, there was no
System automation is required to eliminate any need for JCPB to purchase and install additional
human error in a voltage reduction program and radios and repeaters. JCPB used a model of the
achieve maximum benefit. There is a need to power system to determine which feeders on each
acquire near real-time measurements to adequate- substation would have the lowest voltages during
Page 2 CS2 © 2016 Power Monitors, Inc. • Call Us: (800) 296-4120 • www.powermonitors.com
WHITE PAPER:
CONSERVATION VOLTAGE REDUCTION DURING PEAK LOADING TIMES
Figure 3. Zoom of
voltage reduction showing
approximate 7 MW
reduction in load
Page 3 CS2 © 2016 Power Monitors, Inc. • Call Us: (800) 296-4120 • www.powermonitors.com