Professional Documents
Culture Documents
Chaper 56
Chaper 56
Chapter 5
1) If ABAC want to build a new campus due to increasing number of students, what would be the key factors for
selecting a new location. Please specify 3 factors and explain how each of them is important.
Solution
Solution will vary. Anyway, some key factors might be as follows:
No. Factors Importance
1 Transportation/Accessibility Convenient for students to access
2 Community around campus Image of university and safety concern
3 Land cost Capital savings
2) A firm is considering two location alternatives. At location A, fixed cost would be $40,000 per month, and
variable costs $3.0 per unit. At alternative B, fixed cost would be $36,000 per month, with variable costs of
$3.5 per unit. At alternative C, fixed cost would be $32,000 per month, with variable costs of $5.0 per unit.
Identify the area that has the minimum total cost per month. If monthly demand is expected to be 5,000 units,
which plant offers the lowest total cost?
Solution
4) A firm is studying a plan to set up new warehouse to serve five department stores (S1,S2,S3,S4,S5). All stores
location (in x, y coordinates) and demand required per month are as follows:
Store x, y coordinates Monthly Delivery (Units)
S1 5, 10 2,000
S2 6, 2 5,000
S3 1, 15 1,500
S4 9, 2 10,000
S5 12, 12 6,000
Determine the best location (x, y coordinate) for this new warehouse by using CG method.
Solution
Monthly Delivery
Store x coordinates y coordinates x*Q y*Q
(Units)
5) The management of a factory is going to erect a maintenance building with a connecting electrical generator
and water tank. The activities, activity descriptions, and estimated durations are given in the following table:
Solution
Develop the project network, and determine the critical path, the expected project duration, and variance.
What is the probability the project will be completed within eight years (or 96 months)?
Activity a m b t
1 6 10 24 11.67 9.00
2 20 35 60 36.67 44.44
3 5 17 33 17.67 21.78
4 2 8 21 9.17 10.03
5 6 9 15 9.50 2.25
6 7 12 17 12.00 2.78
7 6 16 27 16.17 12.25
8 18 25 42 26.67 16.00
9 5 8 11 8.00 1.00
10 4 11 16 10.67 4.00
11 5 10 13 9.67 1.78
12 5 9 26 11.17 12.25
13 10 15 18 14.67 1.78
14 11 14 21 14.67 2.78
15 12 16 26 17.00 5.44
16 3 5 6 4.83 0.25
Critical path = 2-5-9-11-15-16
Project completion time = 85.67 months
Project variance = 44.44 + 2.25 + 1.00 + 1.78 + 5.44 + 0.25 = 55.16
Therefore, = 7.43
Z = (96 – 85.67) / 7.43 = 1.39 → Area = 0.4177
P(x<=96) = 0.5 + 0.4177 = 0.9177 or 91.77%