Professional Documents
Culture Documents
Fence Installation
Fence Installation
Fence Installation
Issue Record
Location of the Work; Access, Egress, Traffic Management and Storage Areas
Locations as shown in the attached drawing:-
Approvals
Separate area for making fence post precast to be made and barricaded.
Proper scaffolding to be erected for holding the fence posts in proper alignment and level.
Shuttering to be made for the size 300 x 300 x 750 mm deep as per the drawing and fence posts to be
placed inside the formwork.
Site mix concrete of grade C 20 shall be made as per the approved design and concrete shall be done.
The pre-casted post shall be striked next day and shall be cured for 7 days.
Type A fence posts (corner/strainer/end posts) to be pre-casted based on the approved drawing.
All the operatives involved in the works shall be wearing appropriate PPE mandatorily
With class B permit, the excavation using JCB shall be carried out as per the permit and HSE
procedure.
JCB to be PDO spec and the competent operator to operate the plant.
Trained rigger to give instructions to the JCB operator for the work and 3.0 m rule to be followed.
In case of rock exposure while excavation, breaker shall be used to do the excavation.
During excavation, water shall be spread over the excavating area to avaid dust spreading in air.
Excavation up to required depth shall be made and plant shall be moved to the next footing
Excavation shall be done for plinth beam too along with footing for a depth of 300 mm all around the
fence line.
The excavated earth shall be used for backfilling and the excess shall be removed from the site.
The pre-casted fence posts shall be lifted using tele-handler and shall be placed into the excavated
area
Intermediate posts are placed at evry 3.0m interval and strainer posts are placed at every 30.0 m
interval
The posts shall be aligned for line and level before backfilling.
The side angle support to be fixed for the strainer posts and to be concreted for holding the entire
fence for rigidity.
Once the posts are set out, then backfilling shall be done and compacted
Following this, tension wires are pulled and tied using the eyebolt from one strainer to another strainer
posts for rigidity
The fence PVC coated G.I mesh shall be tied over this and pulled enough for getting the fence in line.
Then barbed wire at the top shall be pulled and fixed using mobile tower.
With G.I mesh going 50 mm inside the plinth beam formwork, concreting to be done below the mesh
area in between the posts.
The formwork shall be removed and nitocote to be applied before backfilling the plinth beams.
The fence area to be well compacted using 1.0 ton plate compactor.
Known Hazards
Trip and fall
Permits to work
Quality
The pre-inspections to be completed before commencement of work.
Ensure availability of latest released for Construction Drawing
Resources
Supervision Arrangements
RESPONSIBILITIES
Operatives
Shall be site inducted.
Shall be inducted with the Method statement and Risk assessment
Lighting
Lighting at workplace to be 100-150 lux (If not naturally )
Materials
Materials are brought to site as per requirement to site.
Protection Arrangements
Temporary Alterations to Existing Installations and Services
It is not expected that any temporary alterations to services or isolation of services will be required.
Segregation
There shall be a separate track for vehicles & pedestrians
Security Arrangements
Plan must be managed to ensure there is no unauthorised access. Visitor log should be maintained at site
Emergency Arrangements
Trained First Aider must be on site during all work activities.
Vehicle & Driver on site at all times
Fire warden at site always
Emergency Contact
GSM: +968 99054338
Mohammed Tairq Operations Manager
CUG:206
Waste Management
All waste to be segregated and recycled where possible. (Waste Management Plan not implemented at this time)
Distribution of Information
PDO – IFM safety advisor to review this Method Statement using the Method Statement Review Record and
approvals from PDO team.
Details of Method Statement to be communicated to operations team via toolbox talk, all stakeholders must
sign the Method Statement record and the end of this Method Statement.
Site Manager, Foreman to brief key points of this Method Statement to work force using the TRIC.
Welfare
Adequate shaded rest area, toilet facilities, assembly point, water and first aid facilities shall be provided at site for
workers.
Change Management
If during the work this method statement fails to cover all aspects and risks the job must be stopped and new method
statement put in place authorised by the Project Director.
Additional Information
Project Manager, Engineers, Foreman and charge hand (In the language they understand) will be explained about
Risk Assessment of the construction works related to the substructure works
The Site Engineer and Foreman will instruct the plant operator, banks man and general site labour of any adverse
hazards and the required precautions.
The foreman will ensure that operatives remove themselves from any area when overhead lifting is taking place.
Quite likely
Most likely
Fence posts installation
Unlikely
Title In case of emergency
likely
Assessed by Jacob Contract Construction of hazard waste All Risk Assesments must be written Major
Extent of possible
incident or injury
Gsm: 24385555, PDO landline - 5555 R R A G
Serious R R A G
Approved Mohammed Tariq Site Qarnalam by a Competent Risk Assessor.
Site incharge - Parwinder - 96379396 Minor R A G G
by
Low R A G G
Part 2 – Review History All Risk Assessments must, as a minimum, be reviewed annually. Once reviewed the updated
document must be communicated to all those who use it. Once a document has been
reviewed twice (or three years since it was originally created) it must be rewritten. The Risk Rating should
Date
Reviewer Signature R Red Do not proceed – Re-assess
be determined using the
Review 1 A Amber Review the Control Measures
(Date)
G
matrix setGreen Proceed with activity
out on the right.
Review 2
(Date)
1 (Control Measures)
Employee
Amber
Amber
Green
Green
Public
Client
Other
Red
.
Red
SC
Employee
2.
Plant Movement / Accident / Spillage Green The plant should follow the designated route.
Green
Amber
Amber
Public
Client
Other
Toppling
Red
Red
All the plants will be provided with trained Banks man, approved operator.
SC
Employee
3.
Trip hazards Injury Excavation Sign Board shall be placed.
Green
Green
Amber
Amber
Public
Client
Other
Red
Red
The area to be barricaded.
SC
Employee
4.
Nature of Ground Injury (Due to collapse) Battering the area by 45 degree angle.
Green
Green
Amber
Amber
Public
Client
Other
Red
Red
Benching also provided in desired areas.
SC
Employee
5.
Improper manual handling Injury Mandatory glove policy in place.
Green
Green
Amber
Amber
Public
Client
Other
Red
Red
Lifting forks shall be used.
SC
IMS-FM-614A: Rev. 0
Rev 003 06/07/2014 Page 9 of 10
Method Statement for Fence installation
CARILLION GROUP Form
HEALTH, SAFETY, SUSTAINABILITY & QUALITY
Method Statement FENCE INSTALLATION
Ref.
CALLC-MS-PDO-
NIMR-02-Rev-00
Sheet No.
02
02 Risk Assessment – (continuation sheet)
This Risk Assessment should be accompanied by a Point of Work Assessment
relating to the specific location and completed on the day/shift by the person leading
the work activity
Part 3 – Hazards & Risks Who could be To what extent? This is how
(continued)
What might go
wrong?
Outcome or
consequence
affected?
Select all relevant options.
Select only one option.
How we will stop this activity from going safe we have
made it!
Specify “other” in the Control measures should always seek to eliminate the hazards that are
Additional Safety This Risk Rating is wrong described.
Employee
Information box. 1
Improper manual handling Injury
Green
Mandatory glove policy in place.
Amber
Amber
Public
Client
Gree
Other
4
Red
Red
n
Lifting forks shall be used.
Employee
1
House Keeping Tripp hazard, environmental
Green
All are inducted & instructed in TBT to maintain a clean and hygienic work place.
Amber
Amber
Public
5
Client
Gree
Other
Red
Red
causes
n
Employee
1
Fatigue
Green
Weather Condition The employees are instructed to drink a lot of fluids in TBT. Resting areas are provided.
Amber
Amber
Public
6
Client
Gree
Other
Red
Red
Summer action plan been organized
n
Employee
1
Injury/fatal/damage to
Green
Services Use cable detector, use PPE, check for warning tape and signs, trial pit
Amber
Amber
Public
Client
Gree
Other
Red
Red
property
n
S
Employee
C 1
Green
dust Respiration problem Amber
Nose mask to be worn, water spreading to reduce the dust shall
Amber
Public
Client
Gree
Other
8.
Red
Red
be done using tanker
S n
C
Employee
19
Green
Amber
Amber
Public
Client
Gree
Other
Red
Red
n
Employee
20
Green
Amber
Amber
Public
Client
Gree
Other
Red
Red
n
Employee
Green
Amber
Amber
Public
Client
Gree
Other
1
Red
Red
n