Professional Documents
Culture Documents
Bcee 478 Lecture 1
Bcee 478 Lecture 1
- Owner functions:
o Defining the scope of the project
o Planning the project
o Financing the project
o Ensuring the project team understands the project’s goals
- Design phase
o Primary requirement for any facility is that it must be safe!!
o Building codes
o Owner and A/E schedule design reviews • schematic drawings
o preliminary drawings
o Working drawings
- Bid phase
o First step is to decide whether or not to bid the job. Contractors are
generally limited in their ability to bid by two factors:
§ Their bonding capacity
§ Policies of management: factors contractors consider in deciding
whether or not to bid a particular project include:
• Location of the work
• Identity of the owner
• Availability of the owner
• Availability of key company personnel
• Experience in the type of work solicited
• Whether or not there is financing for the project
• Size of the project
- Bid preparation
o Bid preparation is expensive. In preparing a bid, contractors must consider
the cost of:
§ Equipment
§ Labor
§ Materials
§ Subcontractors
- Notice to proceed
o Contractor cannot begin the work until the notice to proceed is received.
o Use the time between the bid opening and the award to prepare a detailed
pre-project planning
- Pre-project planning: Planning how the work will proceed and in what sequence
o Construction procedures
o Type of equipment to be used
o Job access
o Location of the field office and storage areas
o Final selection of subcontractors and suppliers
o Cash flow analysis should be completed to determine if the company
needs to borrow money
o Detailed project schedule is prepared
o Work breakdown structure (WBS) and pay schedule are planned
- Contracts are broken down into activities for purposes of scheduling, estimating,
progress control, and cost control. Large projects can have several hundred
activities. It’s important to know which activities are critical.
- Critical activities are those that could impact the cost of the work by at least one
half of one percent of the bid price. For example, on a $1,000,000 project, any
activity with a potential for cost over-run or under-run of $5,000 or more is by
definition a critical activity.
- Pareto’s 80-20 rule: 20% of the activities are critical and should be managed
carefully. The other 80% will average out.
- Schedule control:
o Critical path: by definition, activities on the critical path will delay the entire
project if they are delayed.
o Physical progress can be compared with the financial progress to
determine if the project is
§ On schedule or late
§ Over budget or under budget
- Ensure that materials are delivered in a timely manner to the site in the quantity
and quality required. When materials arrive, they are:
o Counted
o Inspected
o Tested
- Materials management à must determine the latest order date accounting for
the:
o Shop drawing
§ Preparation
§ Submission
§ Approval time
o Lead time required for fabrication
o Shipping
Risks management
- Risks are inherent in construction. Managing risk means
o Minimizing risks
o Insuring against risks
o Sharing risks
- Value engineering: main objective to reduce project cost, without reducing the
quality of the structure.
- VE exists because contractors know better ways to build projects, and owners
are willing to pay for that knowledge.