NORTH TOWER - MEPF WORKS

SCHEDULE TO COMPLETE THE BALANCES - CORE SERVICES (CORE AREA)

NOTE: POWER ON 23-Feb-24


WATER ON 4-Mar-24

MECHANICAL WORKS ELECTRICAL WORKS PLUMBING/SANITARY WORKS FIRE PROTECTION WORKS


FLOOR AREA
Start Finish Start Finish Start Finish Start Finish
MALE TOILET 27-Oct-23 15-Nov-23 27-Oct-23 17-Nov-23 27-Oct-23 19-Nov-23 27-Oct-23 17-Nov-23
FEMALE TOILET 27-Oct-23 15-Nov-23 27-Oct-23 17-Nov-23 27-Oct-23 19-Nov-23 27-Oct-23 17-Nov-23
PWD 27-Oct-23 15-Nov-23 27-Oct-23 17-Nov-23 27-Oct-23 19-Nov-23 27-Oct-23 17-Nov-23
AHU ROOM 27-Oct-23 15-Nov-23 27-Oct-23 17-Nov-23 27-Oct-23 19-Nov-23 27-Oct-23 17-Nov-23
EE ROOM 27-Oct-23 17-Nov-23 10-Nov-23 8-Dec-23 N/A N/A N/A N/A
6F
AUX ROOM 28-Oct-23 14-Nov-23 28-Oct-23 19-Nov-23 N/A N/A N/A N/A
PRV 27-Oct-23 13-Nov-23 27-Oct-23 19-Nov-23 28-Oct-23 19-Nov-23 28-Oct-23 17-Nov-23
P.E. LOBBY
S.E. LOBBY 27-Oct-23 17-Nov-23 27-Oct-23 19-Nov-23 N/A N/A 27-Oct-23 17-Nov-23
HALLWAY
MALE TOILET 25-Oct-23 13-Nov-23 25-Oct-23 15-Nov-23 25-Oct-23 17-Nov-23 25-Oct-23 15-Nov-23
FEMALE TOILET 25-Oct-23 13-Nov-23 25-Oct-23 15-Nov-23 25-Oct-23 17-Nov-23 25-Oct-23 15-Nov-23
PWD 25-Oct-23 13-Nov-23 25-Oct-23 15-Nov-23 25-Oct-23 17-Nov-23 25-Oct-23 15-Nov-23
AHU ROOM 25-Oct-23 13-Nov-23 25-Oct-23 15-Nov-23 25-Oct-23 17-Nov-23 25-Oct-23 15-Nov-23
EE ROOM 27-Oct-23 15-Nov-23 8-Nov-23 6-Dec-23 N/A N/A N/A N/A
5F
AUX ROOM 26-Oct-23 12-Nov-23 28-Oct-23 17-Nov-23 N/A N/A N/A N/A
PRV 27-Oct-23 10-Nov-23 27-Oct-23 17-Nov-23 26-Oct-23 17-Nov-23 26-Oct-23 15-Nov-23
P.E. LOBBY
S.E. LOBBY 27-Oct-23 15-Nov-23 26-Oct-23 17-Nov-23 N/A N/A 25-Oct-23 15-Nov-23
HALLWAY
MALE TOILET 23-Oct-23 11-Nov-23 23-Oct-23 13-Nov-23 23-Oct-23 15-Nov-23 23-Oct-23 13-Nov-23
FEMALE TOILET 23-Oct-23 11-Nov-23 23-Oct-23 13-Nov-23 23-Oct-23 15-Nov-23 23-Oct-23 13-Nov-23
PWD 23-Oct-23 11-Nov-23 23-Oct-23 13-Nov-23 23-Oct-23 15-Nov-23 23-Oct-23 13-Nov-23
AHU ROOM 23-Oct-23 11-Nov-23 23-Oct-23 13-Nov-23 23-Oct-23 15-Nov-23 23-Oct-23 13-Nov-23
EE ROOM 25-Oct-23 13-Nov-23 6-Nov-23 4-Dec-23 N/A N/A N/A N/A
4F
AUX ROOM 24-Oct-23 10-Nov-23 26-Oct-23 15-Nov-23 N/A N/A N/A N/A
PRV 25-Oct-23 8-Nov-23 25-Oct-23 15-Nov-23 24-Oct-23 15-Nov-23 24-Oct-23 13-Nov-23
P.E. LOBBY
S.E. LOBBY 25-Oct-23 13-Nov-23 24-Oct-23 15-Nov-23 N/A N/A 23-Oct-23 13-Nov-23
HALLWAY
MALE TOILET 16-Nov-23 19-Nov-23 15-Oct-23 3-Nov-23 18-Oct-23 26-Oct-23 8-Nov-23 11-Nov-23
FEMALE TOILET 16-Nov-23 19-Nov-23 16-Oct-23 3-Nov-23 18-Oct-23 27-Oct-23 8-Nov-23 11-Nov-23
PWD 17-Nov-23 19-Nov-23 17-Oct-23 4-Nov-23 15-Oct-23 25-Oct-23 8-Nov-23 11-Nov-23
AHU ROOM 7-Nov-23 12-Dec-23 18-Oct-23 7-Nov-23 17-Oct-23 24-Oct-23 6-Nov-23 9-Nov-23
EE ROOM 15-Nov-23 17-Nov-23 20-Nov-23 22-Dec-23 N/A N/A N/A N/A
GF
AUX ROOM 17-Nov-23 19-Nov-23 15-Nov-23 2-Dec-23 N/A N/A N/A N/A
PRV 17-Nov-23 19-Nov-23 15-Nov-23 2-Dec-23 15-Oct-23 31-Oct-23 8-Nov-23 11-Nov-23

S.E. LOBBY 16-Nov-23 19-Nov-23 12-Nov-23 12-Dec-23 N/A N/A 6-Nov-23 9-Nov-23
HALLWAY
MECHANICAL WORKS ELECTRICAL WORKS PLUMBING/SANITARY WORKS FIRE PROTECTION WORKS
FLOOR AREA
Start Finish Start Finish Start Finish Start Finish
MALE TOILET 6-Oct-23 19-Oct-23 11-Oct-23 19-Oct-23 16-Oct-23 19-Oct-23 16-Oct-23 19-Oct-23
FEMALE TOILET 6-Oct-23 19-Oct-23 10-Oct-23 19-Oct-23 16-Oct-23 21-Oct-23 16-Oct-23 19-Oct-23
PWD 6-Oct-23 19-Oct-23 12-Oct-23 19-Oct-23 16-Oct-23 21-Oct-23 16-Oct-23 19-Oct-23
AHU ROOM 6-Oct-23 21-Oct-23 18-Oct-23 21-Oct-23 16-Oct-23 27-Oct-23 16-Oct-23 21-Oct-23
EE ROOM 15-Nov-23 17-Nov-23 13-Nov-23 8-Dec-23 N/A N/A N/A N/A
BSMT. 1
AUX ROOM 15-Nov-23 17-Nov-23 23-Oct-23 15-Nov-23 N/A N/A N/A N/A
PRV 15-Nov-23 17-Nov-23 6-Nov-23 8-Nov-23 16-Oct-23 21-Oct-23 16-Oct-23 18-Oct-23

S.E. LOBBY 6-Oct-23 14-Oct-23 10-Oct-23 13-Oct-23 N/A N/A 26-Oct-23 28-Oct-23
HALLWAY 15-Nov-23 23-Oct-23 8-Nov-23 26-Oct-23 28-Oct-23
MALE TOILET 20-Nov-23 23-Dec-23 22-Nov-23 28-Nov-23 11-Dec-23 22-Dec-23 6-Nov-23 9-Nov-23
FEMALE TOILET 20-Nov-23 23-Dec-23 22-Nov-23 28-Nov-23 8-Dec-23 22-Dec-23 6-Nov-23 9-Nov-23
PWD 20-Nov-23 23-Dec-23 22-Nov-23 28-Nov-23 8-Dec-23 22-Dec-23 6-Nov-23 9-Nov-23
AHU ROOM 20-Nov-23 23-Dec-23 25-Nov-23 2-Dec-23 11-Dec-23 22-Dec-23 6-Nov-23 9-Nov-23
EE ROOM 20-Nov-23 23-Dec-23 11-Dec-23 12-Jan-24 N/A N/A N/A N/A
BSMT. 2
AUX ROOM 20-Nov-23 23-Dec-23 11-Dec-23 5-Jan-23 N/A N/A N/A N/A
PRV 20-Nov-23 23-Dec-23 27-Nov-23 5-Dec-23 8-Dec-23 22-Dec-23 6-Nov-23 9-Nov-23

S.E. LOBBY 20-Nov-23 23-Dec-23 27-Nov-23 5-Dec-23 N/A N/A 6-Nov-23 9-Nov-23
HALLWAY 20-Nov-23 23-Dec-23 N/A N/A 1-Dec-23 22-Dec-23 6-Nov-23 9-Nov-23
MALE TOILET 4-Dec-23 6-Jan-24 3-Dec-23 12-Dec-23 29-Dec-23 5-Jan-24 13-Nov-23 30-Nov-23
FEMALE TOILET 4-Dec-23 6-Jan-24 3-Dec-23 12-Dec-23 29-Dec-23 12-Jan-24 13-Nov-23 30-Nov-23
PWD 4-Dec-23 6-Jan-24 1-Dec-23 12-Dec-23 29-Dec-23 12-Jan-24 13-Nov-23 30-Nov-23
AHU ROOM 4-Dec-23 6-Jan-24 3-Dec-23 14-Dec-23 15-Jan-24 26-Jan-24 13-Nov-23 30-Nov-23
EE ROOM 4-Dec-23 6-Jan-24 4-Dec-23 12-Jan-24 N/A N/A N/A N/A
BSMT. 3
AUX ROOM 4-Dec-23 6-Jan-24 5-Dec-23 20-Dec-23 N/A N/A N/A N/A
PRV 4-Dec-23 6-Jan-24 6-Dec-23 29-Dec-23 14-Jan-24 22-Jan-24 13-Nov-23 30-Nov-23

S.E. LOBBY 4-Dec-23 6-Jan-24 6-Dec-23 19-Dec-23 N/A N/A 13-Nov-23 30-Nov-23
HALLWAY 4-Dec-23 6-Jan-24 N/A N/A 15-Jan-24 30-Jan-24 13-Nov-23 30-Nov-23