Download as doc, pdf, or txt
Download as doc, pdf, or txt
You are on page 1of 6

METHOD OF STATEMENT :

INSTALLATION OF G.I. / HDPE PIPE

DOYES ENGINEEERING SDN. BHD. Doc. No. : DESB/HKL/MS/E-C3 Rev. No: 00


Date Issued: 15 / 05 / 2013 Page 1 OF 6

Project Title :

NAIK TARAF HOSPITAL KUALA LUMPUR.

PREPARED BY REVIEWED BY APPROVED BY

Signature : Signature : Signature :

Name : Name : Name :


Designation: : Designation: Designation:

Date:14-06-2011 Date: Date:

APPROVAL BY CONSULTANT / CLIENT

STATUS APPROVAL
A B C

COMPANY

NAME

DESIGNATION

SIGNATURE
DATE

A - APPROVED

B- APPROVED WITH COMMENTS

C- REJECTED

1st. Issue For Review & Approval


METHOD OF STATEMENT :

INSTALLATION OF G.I. / HDPE PIPE

DOYES ENGINEEERING SDN. BHD. Doc. No. : DESB/HKL/MS/E-C3 Rev. No: 00


Date Issued: 15 / 05 / 2013 Page 2 OF 6

CONTENTS :

1.0 PURPOSE

2.0 REFERENCE

3.0 SCOPE OF WORKS

4.0 TOOLS AND TESTING EQUIPMENTS

5.0 IMPLEMENTATION / METHODOLOGY PROCEDURES

5.1 Method of Installation of G.I. Pipe

5.2 Installation of Corrugated HDPE Pipe

5.3 Back-filling and Compaction of Sand

5.4 Cables Marker Sheet

5.5 Back-filling of Top Soil

6.0 TESTING PROCEDURES

7.0 SAFETY FEATURES

1st. Issue For Review & Approval


METHOD OF STATEMENT :

INSTALLATION OF G.I. / HDPE PIPE

DOYES ENGINEEERING SDN. BHD. Doc. No. : DESB/HKL/MS/E-C3 Rev. No: 00


Date Issued: 15 / 05 / 2013 Page 3 OF 6

1.0 PURPOSE

This method statement provides information concerning the equipment, material and
method of construction to ensure compliance with contract requirements, drawings,
technical specification and quality control.

2.0 REFERENCE

a. Construction drawings and shop drawings


b. Contract Specification
c. Relevant Malaysian Standard, such as SIRIM, etc.
d. 16th Edition of the IEE Wiring Regulation
e. Tenaga Nasional Bhd Rules and Regulations
f. Suruhanjaya Tenaga (JBE) Standard Practices
g. Department of Environment Code of Practices

3.0 SCOPE OF WORKS

The scope of this Electrical Services i.e. Installation of G.I. / HDPE Pipe is only for
the above mentioned project. This scope mention herein is limited to the installation
of G.I. / HDPE Pipe and all the related works.

4.0 TOOLS & TESTING EQUIPMENTS

The tools and testing equipment in provision as required and if necessary are as
follows:-

a. Transportation i.e van, pickup truck, cranes, etc.


b. Basic hand tools.
c. Excavator machine such as JCB or backhoe.
d. Compactor machine.
e. Pulled wire.

1st. Issue For Review & Approval


METHOD OF STATEMENT :

INSTALLATION OF G.I. / HDPE PIPE

DOYES ENGINEEERING SDN. BHD. Doc. No. : DESB/HKL/MS/E-C3 Rev. No: 00


Date Issued: 15 / 05 / 2013 Page 4 OF 6

5.0 IMPLEMENTATION / METHODOLOGY PROCEDURES

5.1 Method of Installation of G.I Pipe

5.1.1 Outline of Works

The works shall apply to the excavation of soil, common base rock
excavation, gravel and crushed limestone base using heavy equipment such
as JCB excavator and basic hand tools and laying of G.I pipe.

5.1.2 Construction methodology

Establish the necessary line position for the excavation of ground trenches. In
establishing the lines and position, stakes and markers shall be installed.

After establishing the necessary lines and position based on the working
drawing layout, proceed with mobilization of required work force, tools and
equipments.

5.1.3 Installation – Preparation of Trench

After the pipeline route survey has been completed, the ground is dug up to
the recommended depth. Once the trench is ready, the pipes should be laid
as soon as possible after making sure that :-

a. The bed of the trench is reasonably flat to give adequate support to


pipe spacer and pipes over its overall length.

b. There are no protruding rocks or unwanted materials in the trench bed.

c. If necessary the trench bed can be filled by fine sub-soil in areas where
the soil is rock laden.

1st. Issue For Review & Approval


METHOD OF STATEMENT :

INSTALLATION OF G.I. / HDPE PIPE

DOYES ENGINEEERING SDN. BHD. Doc. No. : DESB/HKL/MS/E-C3 Rev. No: 00


Date Issued: 15 / 05 / 2013 Page 5 OF 6

5.2 Installation of Corrugated HDPE Pipe

a. The method of works is quite similar to the installation of G.I. pipe as


described in item 5.1.1, 5.1.2 and 5.1.3 i.e. until the preparation of trench.

b. Upon completion of the trenching works activity, the engineer and client
representative is required to be notified for the site inspection and approval.

c. Upon obtaining the approval from the relevant parties, the next layer is to fill
with layer of 50mm sand before the laying of pipes can take place.

d. Then the pipe shall be laid accordingly. The spacing between ducts, all pipe
jointing using sleeve, etc. shall follow strictly as per drawing and specification
requirement.

e. Upon completion, the site inspection for approval is required by all parties
concern before back-filling.

5.3 Back-filling and Compaction of Sand

a. When the pipes have been laid and approval has been obtained, the back-
filling with sand between ducts and the top layer of 50mm is being carried out
accordingly.

b. The back-filling material shall be progressively compacted as the trench is


filled with sub-soil.

c. The finish layer of the working area shall be making good to its original
condition such as re-planting with grass, etc.

5.4 Cables Marker Sheet

When the process of back-filling and compaction of sand is completed, cables


marker sheet is laid on it as per specification.

1st. Issue For Review & Approval


METHOD OF STATEMENT :

INSTALLATION OF G.I. / HDPE PIPE

DOYES ENGINEEERING SDN. BHD. Doc. No. : DESB/HKL/MS/E-C3 Rev. No: 00


Date Issued: 15 / 05 / 2013 Page 6 OF 6

5.5 Back-filling of Topsoil

a. Back-filling of topsoil shall be progress after all the works of cables marker
sheet are completed and inspected.

b. During the back-filling process, the compaction is progressively required to


ensure full compactness is achieved.

6.0 TESTING PROCEDURES

All site testing shall be carried out accordingly to the specification and consultant’s
requirement and approval.

7.0 SAFETY FEATURES

All operation during this work shall be done in an efficient and safe manner and in
accordance to the Safety Procedures. However there are issues concerning safety
for this work that are to be observed base on the results of the audit, relevant safety
measures shall be proposed and implemented as follows:-

a. Carry out a hazard Identification Audit (HIA) before start of work each day and
before the start of a new task.

b. The material shall be in good condition, clean and free from defect and crack
during the installation.

c. All materials shall be transported by lorry to the site. Upon arrival, the
materials shall be unloaded at identified storage yard, either manually or by
machinery.

d. All material shall be checked and inspected by the supervisor and consultant.
It must be stacked on timber and cover with non-staining plastic sheet.

1st. Issue For Review & Approval

You might also like