Programe For Urbisha

You might also like

Download as xlsx, pdf, or txt
Download as xlsx, pdf, or txt
You are on page 1of 5

Block work Programe for Block--D & E

Block-DP-1 Block-DP-2 Block-EP-1 Block-EP-2


Sl No Floor
Start Date Finish Date Start Date Finish Date Start Date Finish Date Start Date Finish Date
1 1st floor
2 2nd floor
3 3rd floor
4 4th floor 2/5/2024 2/10/2024
5 5th floor 2/10/2024 2/10/2024 2/25/2024 2/25/2024
6 6th floor 3/2/2024 3/2/2024 3/17/2024 3/17/2024
7 7th floor 3/22/2024 3/22/2024 4/6/2024 4/6/2024
8 8th floor 4/11/2024 4/11/2024 4/26/2024 4/26/2024
9 9th floor 5/2/2024 5/2/2024 5/17/2024 5/17/2024
10 10th floor 5/22/2024 5/22/2024 6/6/2024 6/6/2024
11 11th floor 6/11/2024 6/11/2024 6/26/2024 6/26/2024
WATERPROOFING WORK SCHEDULE FOR URBISHA SITE AS ON 22-01-24
Nozzle
Surface Cleaning Drill & Nozzle Groove Patching Nozzle Pressure VDF Flooring VDF Flooring
Sl no Area of Work Groove Cutting Breaking & T1 Coating T2 Coating
& Preparation fixing Work grouting Start Date End Date
Patching

1 Block-C/Sump Complete Complete Complete Complete Complete Complete Complete Complete

2 Block-F/Sump 3/1/2024 3/4/2024 3/6/2024 3/8/2024 3/10/2024 3/13/2024 3/15/2024 3/17/2024

3 Drain--Block-E 2/10/2024 2/13/2024 2/14/2024 2/16/2024 2/18/2024 2/21/2024 2/22/2024 2/24/2024

4 Drain--Block-D 2/11/2024 2/14/2024 2/15/2024 2/17/2024 2/19/2024 2/22/2024 2/23/2024 2/25/2024

5 Drain--Block-C 3/1/2024 3/3/2024 3/4/2024 3/6/2024 3/8/2024 3/11/2024 3/13/2024 3/15/2024

6 Drain--Block-Club

Retaining Wall- W/P 2/4/2024 2/6/2024 2/8/2024 2/10/2024 2/12/2024 2/15/2024 2/19/2024
7 Block--E

Retaining Wall- W/P 2/14/2024 2/16/2024 2/18/2024 2/20/2024 2/21/2024 2/24/2024 2/28/2024
8 Block--D

Retaining Wall- 2/9/2024 2/13/2024 2/15/2024 2/17/2024 2/19/2024 2/21/2024 2/24/2024 2/28/2024
9 Block--C

Retaining Wall- 3/7/2024 3/11/2024 3/15/2024 3/17/2024 3/19/2024 3/21/2024 3/24/2024 3/28/2024
10 Club

11 Floor--Block-D 2/11/2024 2/15/2024 2/19/2024 2/21/2024 2/22/2024 2/26/2024 2/28/2024 3/3/2024 3/5/2024

12 Floor--Block-E W/P 2/24/2024 2/8/2024 2/27/2024

13 Floor--Block-C 2/20/2024 2/28/2024 3/3/2024 3/5/2024 3/7/2024 3/9/2024 3/11/2024 3/15/2024 3/18/2024

14 Floor--Block-F 3/20/2024 3/28/2024 4/3/2024 4/5/2024 4/7/2024 4/9/2024 4/11/2024 4/15/2024 4/20/2024

15 Lift in Block E 4/20/2024

16 Lift in Block D 4/25/2024

17 Lift in Block C 4/30/2024

18 Lift in Block F 5/5/2024


Block work, Electrical Work and Plaster Programe for Block--D & E
Block-D/P-1 & 2 Block-E/P-1 &2
Sl No Floor Electrical chase cutting,
Block Work with plaster Block Work with plaster
conduit fixing, Chase Inside Plaster
tippa tippa
filling
Start Date Finish Date Start Date Finish Date Start Date Finish Date Start Date Finish Date
1 1st floor complete 1/31/2024 2/25/2024 1/30/2024
2 2nd floor Complete 1/31/2024 2/15/2024 2/2/2024
3 3rd floor 2/5/2024 2/15/2024 3/15/2024 2/10/2024
4 4th floor 2/11/2024 2/23/2024 3/20/2024 2/18/2024
5 5th floor 2/19/2024 3/3/2024 4/12/2024 3/3/2024
6 6th floor 3/10/2024 3/20/2024 4/30/2024 3/25/2024
7 7th floor 3/30/2024 4/10/2024 5/18/2024 4/14/2024
8 8th floor 4/19/2024 4/29/2024 5/30/2024 5/5/2024
9 9th floor 5/10/2024 5/20/2024 6/15/2024 5/25/2024
10 10th floor 5/30/2024 6/10/2024 6/30/2024 6/14/2024
11 11th floor 6/19/2024 6/29/2024 7/20/2024 7/3/2024
Block-E/P-1 &2
Electrical chase cutting,
conduit fixing, Chase Inside Plaster
filling
Start Date Finish Date Start Date Finish Date
2/5/2024 2/22/2024
2/15/2024 3/7/2024
2/25/2024 3/17/2024
3/5/2024 3/25/2024
3/13/2024 4/12/2024
3/30/2024 4/20/2024
4/21/2024 5/12/2024
5/12/2024 6/2/2024
5/31/2024 6/20/2024
6/20/2024 7/10/2024
7/10/2024 7/30/2024