(As on Date)

PHYSICAL PROGRESS REPORT - PERFORMA


FOR UNDER CONSTRUCTION UNITS

SECTOR: CENTRAL/STATE/PRIVATE

NAME OF THE THERMAL POWER PROJECT WITH NO OF UNITS & RESPECTIVE CAPACITY: LARA STPP, STAGE-II (2X800 MW)

DEVELOPER NAME/ IMPLEMETING AGENCY : NTPC LTD.


COMPLETE ADDRESS OF TPP :
CONTACT DETAILS OF NODAL OFFICER ,NAME, EMAIL, MOBILE NO: SH. JAY PRAKASH E-GEN PORTAL REGISTRATION STATUS- YES/NO, If Yes Registration
GUPTA, JAYPRAKASHGUPTA@NTPC.CO.IN, 9650812225 No (Unit wise)

NOTE: TENDERING BY EPC AGENCY IS IN PROGRESS


MAIN PLANT PACKAGE (EPC CONTRACTOR): BHEL (LOA DATE: 29.08.23)

Sl. Packages Vendor/Contracting UNIT Date of Award/ Present Status % Completion Original Date of Anticipated Date of
Agency Start date Completion Completion
CIVIL WORKS
STRUCTURAL WORKS
UNIT-01
PRESSURE PARTS
COMPLETION
1 BOILER
CIVIL WORKS
STRUCTURAL WORKS UNIT-02
PRESSURE PARTS
COMPLETION
BRIEF WRITEUP ABOUT CURRENT STATUS OF BOILER WORKS:

CIVIL WORKS
STRUCTURAL WORKS UNIT-01
PRESSURE PARTS
COMPLETION
2 TG
CIVIL WORKS
STRUCTURAL WORKS UNIT-02
PRESSURE PARTS
COMPLETION

BRIEF WRITEUP ABOUT CURRENT STATUS OF TG WORKS:


PASS STATUS UNIT-01
3 ESP
PASS STATUS UNIT-02

BRIEF WRITEUP ABOUT CURRENT STATUS OF ESP WORKS:.

CIVIL WORK
MATERIAL SUPPLY UNIT-01
FGD Plant ERECTION WORK
3A (AGENC
Y NAME) CIVIL WORK
MATERIAL SUPPLY UNIT-02
ERECTION WORK
BRIEF WRITEUP ABOUT CURRENT STATUS OF FGD WORK:
STATUS OF BOPs
Sl. Packages/ Linked Vendor/Contracting Date of Award/Start date Present Status % Completion Original Date of Actual/Anticipated Date of
Project Milestones Agency Completion Completion
Unit-1 Unit-2
Chimney
1
incl (Erect. & Comm)

Conveyor Package
Coal Handling
2
Plant Wagon Tippler
Stacker reclaimer Package
3 Ash Handling Plant
4 Fuel Oil System
5 Cooling Towers
CW Pump house &
6
Piping
7 PT Plant
8 DM Plant
9 Air Compressor
Fire Protection
10
System
11 Switch Yard
Station
12
Transformers
Generator
13
Transformer
14 Unit Transformers
15 Railway siding

16 Power Evacuation

BRIEF WRITEUP ABOUT CURRENT STATUS OF BOPs WORK:


UNDER-CONSTRUCTION UNITS WISE MILESTONE DATES (ACTUAL / ANTICIPATED )
UNIT-01 UNIT-02
MILESTONE Original Date of Actual/Anticipated Original Date of Actual/Anticipated REMARKS
Sl.
Completion Date of Completion Completion Date of Completion
1 COMPLETION OF BOILER FOUNDATION
2 START OF BOILER ERECTION
3 BOILER CEILING GIRDER LIFTING
COMPLETION
4 CONDENSER ERECTION START
5 TG ERECTION START
6 HP PIPING ERECTION START
7 BOILER HYDRO TEST (DRAINABLE)
COMPLETION
8 BOILER HYDRO TEST (NON-DRAINABLE)
COMPLETION
9 TG BOX UP
10 HP PIPING ERECTION COMPLETION
11 START OF OIL FLUSHING
12 BOILER LIGHT UP
13 CHEMICAL CLEANING COMPLETION
14 STEAM BLOWING START
15 STEAM BLOWING COMPLETION
16 ROLLING & SYNC.
17 FULL LOAD
18 TRIAL RUN
19 COD
20 PG TEST START AND COMPLETION
Other Details
TOTAL EXPENDITURE UPTO LAST FY:
EXPENDITURE OF CURRENT MONTH (FOR WHICH PROGRESS DATA IS BEING PROVIDED):
TOTAL EXPENDITURE TILL DATE (From Inception):.
Note: Projects to ensure that financial data needs to be same as provided at NIP portal.
LAND POSSESSION DETAILS:
REASONS OF DELAY (BTG & BOP, mention separately) :
CRITICAL AREA/ ASSSISTANC EREQUIRED:
Change (if Any) regarding Clearances, PPA, Fuel Supply or any other matter provided in static data (provided already) needs to be intimated as early as possible.