Professional Documents
Culture Documents
3 Monthly Progress Report Format
3 Monthly Progress Report Format
SECTOR: CENTRAL/STATE/PRIVATE
NAME OF THE THERMAL POWER PROJECT WITH NO OF UNITS & RESPECTIVE CAPACITY: LARA STPP, STAGE-II (2X800 MW)
Sl. Packages Vendor/Contracting UNIT Date of Award/ Present Status % Completion Original Date of Anticipated Date of
Agency Start date Completion Completion
CIVIL WORKS
STRUCTURAL WORKS
UNIT-01
PRESSURE PARTS
COMPLETION
1 BOILER
CIVIL WORKS
STRUCTURAL WORKS UNIT-02
PRESSURE PARTS
COMPLETION
BRIEF WRITEUP ABOUT CURRENT STATUS OF BOILER WORKS:
CIVIL WORKS
STRUCTURAL WORKS UNIT-01
PRESSURE PARTS
COMPLETION
2 TG
CIVIL WORKS
STRUCTURAL WORKS UNIT-02
PRESSURE PARTS
COMPLETION
CIVIL WORK
MATERIAL SUPPLY UNIT-01
FGD Plant ERECTION WORK
3A (AGENC
Y NAME) CIVIL WORK
MATERIAL SUPPLY UNIT-02
ERECTION WORK
BRIEF WRITEUP ABOUT CURRENT STATUS OF FGD WORK:
STATUS OF BOPs
Sl. Packages/ Linked Vendor/Contracting Date of Award/Start date Present Status % Completion Original Date of Actual/Anticipated Date of
Project Milestones Agency Completion Completion
Unit-1 Unit-2
Chimney
1
incl (Erect. & Comm)
Conveyor Package
Coal Handling
2
Plant Wagon Tippler
Stacker reclaimer Package
3 Ash Handling Plant
4 Fuel Oil System
5 Cooling Towers
CW Pump house &
6
Piping
7 PT Plant
8 DM Plant
9 Air Compressor
Fire Protection
10
System
11 Switch Yard
Station
12
Transformers
Generator
13
Transformer
14 Unit Transformers
15 Railway siding
16 Power Evacuation