BILL OF QUANTITY

Pekerjaan : PEMBANGUNAN KANTOR BARU


Lokasi : KAWASAN JATAKE - TANGERANG BANTEN

Harga sat (Rp) Sub-Total (Rp)


No. Uraian Pekerjaan Satuan Volume Total Harga (Rp)
Material Upah + alat Harga Satuan
1 PEKERJAAN PERSIAPAN
Mobilisasi & demobilisasi alat & tenaga kerja Ls 1.00 0.00 2,500,000.00 2,500,000.00 2,500,000.00
2 PEKERJAAN RANGKA BETON DAN FINISHING
A. PEKERJAAN KOLOM 250 X 250 X 4000 Unit 4.00
Formwork m² 12.80 145,000.00 70,000.00 215,000.00 2,752,000.00
Rebar Ǿ 13 mm kg 50.40 13,000.00 5,000.00 18,000.00 907,200.00
Rebar Ǿ 10 mm kg 44.40 13,000.00 5,000.00 18,000.00 799,200.00
Concrete K- 225 m³ 5.00 830,000.00 250,000.00 1,080,000.00 5,400,000.00
B. PEKERJAAN KOLOM PRAKTIS 150 X 300
Formwork m² 9.95 145,000.00 70,000.00 215,000.00 2,138,175.00
Rebar Ǿ 10 mm kg 148.00 13,000.00 5,000.00 18,000.00 2,664,000.00
Rebar Ǿ 6 mm kg 118.80 13,000.00 5,000.00 18,000.00 2,138,400.00
Concrete K- 225 m³ 7.30 830,000.00 250,000.00 1,080,000.00 7,884,000.00
C. PEKERJAAN BETON LANTAI T.0,10
Formwork m² 11.00 145,000.00 70,000.00 215,000.00 2,365,000.00
Bambu Btg 50.00 18,000.00 12,500.00 30,500.00 1,525,000.00
Kayu Kaso m³ 3.00 1,200,000.00 250,000.00 1,450,000.00 4,350,000.00
Wiremesh M8 (1 Layer) Sht 2.00 775,000.00 225,000.00 1,000,000.00 2,000,000.00
Multiplex 10mm Sht 30.00 125,000.00 70,000.00 195,000.00 5,850,000.00
Concrete K- 225 m³ 4.00 830,000.00 250,000.00 1,080,000.00 4,320,000.00
D. PEKERJAAN PASANGAN DINDING
Dinding Bata Ringan m2 44.00 115,750.00 55,000.00 170,750.00 7,513,000.00
Plesteran dan acian dinding (Adukan 1:5) m2 72.70 137,000.00 70,000.00 207,000.00 15,048,900.00
E. PEKERJAAN PENUTUP LANTAI
Lantai keramik 40/40 cm m2 30.00 67,800.00 85,000.00 152,800.00 4,584,000.00
Plesteran Keramik (Adukan 1:3) m2 30.00 155,000.00 70,000.00 225,000.00 6,750,000.00
F. PEKERJAAN PLAFOND
Plafon PVC & rangka hollow m2 30.00 220,000.00 40,000.00 260,000.00 7,800,000.00
List plafond 7 cm m 44.00 50,000.00 17,000.00 67,000.00 2,948,000.00
G. PEKERJAAN PINTU DAN JENDELA
Pintu Kaca Temperd 12 mm ( 210x90 ) unit 1.00 4,450,000.00 1,500,000.00 5,950,000.00 5,950,000.00
Jendela Alluminium Kaca 4 Inchi Powder Coating ( 120x60 ) unit 4.00 475,000.00 250,000.00 725,000.00 2,900,000.00
3 PEKERJAAN ELEKTRIKAL
Instalasi Saklar brocco dengan lampu Ttk 5.00 85,000.00 25,000.00 110,000.00 550,000.00
Instalasi Stopkontak brocco multifungsi Ttk 6.00 85,000.00 25,000.00 110,000.00 660,000.00
Instalasi Saklar AC Ttk 2.00 85,000.00 25,000.00 110,000.00 220,000.00
Kabel 3 x 2,5 NYM Roll 1.00 475,000.00 125,000.00 600,000.00 600,000.00
Kabel 2 x 1,5 NYM Roll 2.00 255,000.00 125,000.00 380,000.00 760,000.00
Armatur Lampu led 30x60 bj 2.00 375,000.00 50,000.00 425,000.00 850,000.00
Armatur Downlight 20 watt bh 8.00 150,000.00 50,000.00 200,000.00 1,600,000.00
4 PEKERJAAN PAINT FINISH
Cat Dasar Dinding Ruangan Dalam / Interior m2 44.00 27,700.00 15,000.00 42,700.00 1,878,800.00
Cat Dinding interior ex.Dulux m2 44.00 41,500.00 15,000.00 56,500.00 2,486,000.00
Cat Dasar Dinding Ruangan Luar / Exterior m2 44.00 27,700.00 15,000.00 42,700.00 1,878,800.00
Cat Dinding eksterior ex. Dulux m2 44.00 41,500.00 15,000.00 56,500.00 2,486,000.00
JUMLAH 115,056,475.00