Professional Documents
Culture Documents
Simulationto Evaluate Several Critical Factors Effecting Ma
Simulationto Evaluate Several Critical Factors Effecting Ma
net/publication/221112887
CITATION READS
1 503
3 authors:
Dietmar Moeller
University of Hamburg
41 PUBLICATIONS 144 CITATIONS
SEE PROFILE
All content following this page was uploaded by Gregory Harris on 22 September 2015.
Production
Daily Production WIP
2000
4. LINE BALANCING
2
Daily production as a function of the number of operators is
given in Figure 3. Note that adding a sixth operator did not 6 7 8
Number of Operators (two machines at STA3 and STA6)
increase production and instead increased WIP to 1,350
parts. Therefore, the maximum production and the lowest
work-in-process are achieved with five operators.
Figure 4. Production and WIP as function of number of
operators (with two machines at STA3 and STA6)
Daily Production
3000
Production 2,440 2,440 5. KANBAN CAPACITY
WIP
Let us assume after applying several lean manufacturing
2000 1920
principles that all the mean station cycle times are now 10
1,440 seconds. However, most manufacturing processes have
1,350 variability. Lean manufacturing stresses reducing
960 variability by continuously improving the process.
1000
Variability can be introduced into the simulation by
480
changing the station cycle times from constants to
distributions such as triangular distributions.
0 0 0 0 2
Finished assemblies
Production
Station utilization - 100% Station1, 90% Station2,
90% Station3
220
Production increased with an input queue of one (the input
queue was 0 for the baseline run). Likewise, station
utilization increased to 100% for Station1, 99% for Station2
and 98% for Station3. The production of 235 with a
Kanban of one closely approximated the theoretical 200
production of 240. Increasing the input queue to two parts 5 15 25 35
did not increase production. Consequently, there would be ROP at Fulfillment Center for
Parts from Supplier3
no need to allocate additional floor space beyond one part.
7.1 Reorder Quantity (ROQ) for Parts from Supplier3 Figure 9. Production versus ROP at Fulfillment Center for
The results of the baseline run indicated that the inventory at Parts from Supplier3
the end of the simulation at the Fulfillment Center for Part3
was zero. As a result of increasing the Kanban size, a new
baseline was established with a Kanban = 1. All subsequent 7.3 ROQs for Parts from Suppliers
simulation runs were with Kanban = 1. Figure 10 is a plot of production as a function of the reorder
quantities of parts at each supplier. For the new baseline the
Figure 8 is a plot of production as a function of the reorder reorder quantity from each supplier was 100. This quantity
quantity of parts from Supplier 3. Increasing the reorder was reduced to 90, 70 and 60. Production was 235 for
quantity from 100 to 130 did not increase production. It reorder quantities of 100 and decreased to 220 when the
appears that the limiting model constraint is the Kanban size ROQs for parts from the suppliers were 60.
at the assembly line.
Theoretical production 240
240
240
Production
220
220
200
100 90 70 60
200 ROQs for parts from each supplier
100 110 120 130
ROQ for parts from Supplier3
Figure 10. Production versus ROQ’s for parts from each
supplier
Figure 8. Production versus ROQ from Supplier3
7.4 Delivery Time from Supplier3
Figure 11 is a plot of production as a function of the time Acknowledgements
for an order to be delivered from Supplier3 to the This project was funded in part by U.S. Department of
Fulfillment Center. As the delivery time increased beyond Transportation, Office of the Secretary, Grant No. DTOS59-
180 minutes the production dropped. Reducing the delivery 05-G-0021 and the Fund for the Improvement of
time to 150 minutes did not increase production that was Postsecondary Education, U.S. Department of Education
close to the theoretical. #P116J040009 and the European Commission DG XII
Education and Culture under the EC reference number
04D032408EUJ12987.