Moslima Bibi Invoice No-1

You might also like

Download as pdf or txt
Download as pdf or txt
You are on page 1of 1

MOSLIMA BIBi

CIVIL CONTRACTOR

VILL-ELAMNAGAR PAN-BRKPB9296B
MOUJA-CHANDPUR EIP VENDOR CODE-P12101090798000
J.L,NO-38,UTTARPARA GSTIN-19BRKPB9296B1ZJ
BERHAMPUR Email-moslimabibi26@gmail.com
P.O-CHANDPUR,P.S-NOWDA MOB-9734875019/7029620515
DIST-MURSHIDABAD ,PIN-742121(W.B)

Ref No……………….

To, Bill FTM- Dec 23


M/S. Larsen & Toubro Construction Limited
VENDOR NAME-MOSLIA BIBI
SCB MEDICAL EXPANSION PROJECT.
TALADANDA CENAL,CUTTAK-753013 BILL PERIOD- 26-11-23 to 25-12-23
INVOICE NO -1
INVOICE DATE - 17/01/2024
S.No Item Code Item Description This bill
Uom Rate Qty Amount
1 6C15S02BK L/C for constructing 150mm thick brick work Sqm 205 792.267 1,62,414.735
with fly ash lime bricks (flag bricks)/block work
conforming to IS :12894-1989,class designation
10,in cement mortar 1:4 in superstructure at all
levels including embedding in cement mortar
2nos of 6 mm dia steel reinforcementat every
4th course including raking out joints,
housekeeping of the work area etc and labour
complete ., and wherever the length of the wall
is more than 3.60m without joint 230x230mm
brick pilaster to be provided all labour ,including
fixing hoop reinforcement ,shifting of required
no of bricks in working floorlevel,shifting of
sand from stockyard to working location,
housekeeping of the work are ,racking out joints
etc..all labour complete
2 6C15S0458 L/c for shifting &lifting of bricks of Sqm 20 792.267 15,845.340
150/115/125mm from Brickwork stockyard to
workplace/respective floor/ work location
3 6C15S04M1 L/C for unloading of cement bag directly at site Nos 3 900.00 2,700.00
4 6C13S06DO L/C for tying of reinforcement &shuttering Rmt 150 50.00 7,500.00
including shifting of all required materials
&other supporting works for lintel mullion of
size 1500mm x 200 mm
5 6C15S04BM L/C for plastering of internal walls conforming Sqm 115 478.700 55,050.500
to IS:1661 with the mix and thickness as
specified . Rate shall include all junctions of
masonary wall and all labour complete including
shifting of recron fibre if required,shifting of
waterproofing compound,including fixing of
chicken mesh,shifting of sand from stockyard to
working location ,including hacking on RCC
surface ,proper housekeeping of the work areas
and directed by EIC
TOTAL 2,43,510.575
IGST@18% 43,831.903

TOTAL AMOUNT PAYABLE 2,87,342.478