CA Lic.

#825156
418 Ramsell Street, San Francisco, CA 94132 CA DIR Registration #1000010599
Tel: 415-587-8729 Fax: 415-587-8732 Signatory to Local Union #377 & #378

Proposal No.: 2021047R1


Cost Proposal Date: 06/29/2021

To: J.H. Fitzmaurice, Inc.


Attn: Kyan Hakimi
Project: Jefferson UHSD Faculty/Staff Housing
705 Serramonte Blvd., Daly City

A. SCOPE OF COVERAGE (Base Bid ):


1 Furnish & Install the following items with associated plates/angles and bolts as shown on Architectural Drawings
a. Aluminum parapet rails at 16ea locations at 4th floor per ASI 15 dated 04/01/2021.
NOTE: Aluminum tube 1.5"Øx3/16" T6061-T6, typ.; mill finish. Assumed vertical arms are 48"OC max. and no field weld splice.

B BID REFERENCE
1 Addendum: NONE
2 Arch. / Structural Drawings: ASI 15 Dated 04/01/2021
3 Related Specification NONE

C NOTES AND CONDITIONS:


1 Our price is good for 10 days from the date of our proposal.
2 See attached for our current GL & WC coverage and limits. Client agrees to pay the premium for any addition insurance coverage & limit.
3 Temporary electric power and hookup, including 220V/50Amp power for welding, shall be provided at no cost to IBS at Job Site.
4 Controlling lines and benchmarks must be provided at each floor by G.C. for our field measurements and installations.
5 Man hoist(s) should be provided per OSHA at no cost to IBS.
6 Our price is based upon work performed in a continuous manner -- regular 40 hours, five (5) day work week and Monday through Friday. Premium time
and shift work shall be considered extra cost to IBS, U. O. N.;
7 Your attention is directed to Sections 8034, 8200 et seq., California Civil Code which requires us to notify you by way of California Preliminary Notice "that
if bills are not paid in full for labor, services, equipment or material furnished, or to be furnished, the improved property (which is described herein) may be
subject to liens." This statement is applicable to private work only. This is not a reflection on the integrity of you or any contractor or subcontractor.
8 This Proposal, as written, must be incorporated as a part of the sub-contract document in any resulting contract.
9 This proposal automatically supersedes our previous proposal(s), if any, of the same job prevailing by their date.

D PROJECT SPECIFIC EXCLUSIONS (Design/Engineering, Submittals, Material, Fabrication & Installation, applied to all Add
Alternates/Provision Items, U.O.N.)
1 Engineering for rails, attachment and backing, etc.
2 Flashing boot on rails.
3 Removal and disposal of existing safety rails, if any.
4 Any finish on rails, if any.
5 Local hiring, any LBE/SLBE/WBEMBE goal.

E STANDARD EXCLUSIONS (Design/Engineering, Submittals, Material, Fabrication & Installation, applied to all Add
Alternates/Provision Items, U.O.N.)
1 Demolition, Removal, Modification, Rectification, Protection, and / or Reinstallation of Existing Items;
2 Shoring, Waling, Structural Supporting Platform / Trestle, Patch up, Concrete & Reinforcement, and Grouting;
3 Digging and Concrete Work for Fence / Gate posts; General Scaffolding / Protection / Lighting / Access at Site;
4 Non-PC Stair Tread Safety Nosing (U.O.N.); Warning tapes; Wood Top Rail for Guardrail; Glazed Guardrail;
5 All Wood / Metal Studs / Gage Metal-to-Steel fasteners, Nuts & Washers for Threaded Studs, Simpson and similar hardware, Headed/Threaded Studs on
Beam Top, and Anchor bolts for others; Protection for Others’ Works;
6 Temporary Perimeter Safety Cables at all locations; Flag Pole & Sign Post; Abrasive Coating;
7 All gage metals/sheet metals (under 3/16” thick), Light gage stud framing, Metal Deck and Accessories (Hoisting, Beam-Top studs, Deck supports,
Closures, Flashing, Trimming, etc.), Siding, Standing seam metal roofing, Unistrut systems, Suspended T-bar ceiling and supports, Stainless Steel,
Aluminum, Alloys, Copper, Brass, Bronze, Cast Iron, Cast Steel, Wrought Iron, FRP, Re-bar, wood, Glazing, and other non-ferrous items (U.O.N.);
8 All Frames, Fabric, and attachments at Chain-link Fences & C.L. Gates, and Chain-link Guardrails; Bike Rack;
9 Inspection Fee, Testing & Laboratory fee, Licensed Surveyor, 3rd party charges / expenses, Design & Engineering (U.O.N.);

Page 1 of 2 Jefferson UHSD Faculty/Staff Housing Proposal # 2021047R1


CA Lic. #825156
418 Ramsell Street, San Francisco, CA 94132 CA DIR Registration #1000010599
Tel: 415-587-8729 Fax: 415-587-8732 Signatory to Local Union #377 & #378

10 Installation of embed/cast-in items (Anchor bolts, columns/posts, wall embed plate, etc.), Rebar welding, Rebar Scanning (X-ray and/or any other
methods), Core Drilling (U.O.N.); Warning Tape & Concrete Infill for Bollard;
11 Finish paint; Primer on galvanized items; Powder coating; Epoxy primer; Blast-cleaning; Fireproofing;
12 Paint/primer removals at steel members for metal deck and shear stud welding; Proprietary Counter Support;
13 Site Layout, Loading / Offloading, Storage, Custody, Traffic Control and Installation for all FOB items;
14 Loading / Offloading, Fasteners and Safety provisions for all other trades;
15 Hazardous material abatement, including all testing, monitoring, removals and disposal of hazardous materials;
16 Doors, Windows, Louvers, Lintel and Frames for the same; Ventilation or Evacuation of welding fumes;
17 Sumps, Drains, Grates, Downspouts / RWL / Scupper, and Supports for the same (U.O.N.);
18 All electrical components and hardware (i.e. Locks, Intercoms, Panic bar, operators, etc., except hinges and rollers) for metal gate , cutting/drilling holes at
metal gate for installation of electrical components and hardware if they are not shown on design plan;
19 Doors, Windows, Louvers, Lintel and Frames for the same; Ventilation or Evacuation of welding fumes;
20 Sumps, Drains, Grates, Downspouts / RWL / Scupper, and Supports for the same (U.O.N.);
21 Sleeves, Pipes, Holes and Reinforcements at steel members for Electrical and Mechanical penetrations;
22 Reference to Demolition, Civil, Mechanical, Plumbing, Electrical, Fire Protection, Telecom/IT and Security, etc. Drawings;
23 Bonds and Permits; All site insurances & sub-contractor’s general liabilities for condominium / OCIP project;
24 All others items or work are not stated in Scope of Coverage above. Special Allowances as per GC bidding document, if any.

F PRICING
1 Base Bid:Eight Hundred Eighty Thousand Dollars ($89,300.00)

2 BID ALTERNATE
Furnish and install Galvanized steel rails in stead of aluminum rails ----- $45,000.00
G PAYMENT SCHEDULE
10% Upon shop drawing submittal, 90% Progress Payment; 5% max. retention.

H ACCEPTANCE

ACCEPTANCE OF PROPOSAL IBS USA, INC.


The above prices, specification and conditions are satisfactory and are hereby This proposal may be withdrawn by us if not accepted within 30 day, or days as
accepted. You are authorized to do the work as per specified. Payments specified in the bid document.
terms to be mutually agreed by both parties.

Authorized Signature: __________________________________ Authorized Signature:


KJ Tong

Date: ________________________________ Date: Tuesday, June 29, 2021

For questions regarding this proposal, please call KJ Tong at 415-272-1388 or email kjtprojects@yahoo.com

Page 2 of 2 Jefferson UHSD Faculty/Staff Housing Proposal # 2021047R1