Professional Documents
Culture Documents
Specification For Protective Paint and Coatings: Minimum Works Obligations
Specification For Protective Paint and Coatings: Minimum Works Obligations
00102W-C-G0-G000-ML-SPC-0007 Rev 1
14 December 2011
NOTICE: "These materials are the Work Product of WorleyParsons, and no reliance on this work
product is authorized by WorleyParsons, and WorleyParsons accepts no liability for any reliance
by any person on the Work product contained herein. BP Iraq NV has expressly authorized
WorleyParsons to issue this disclaimer."
Laughlin-
McCann
Hold
Para. Description of Hold
No.
00102W-C-G0-G000-ML-SPC-0007 Page 3 of 46
Rev 1 (14 December 2011)
RUMAILA PROJECT
SPECIFICATION FOR PROTECTIVE PAINT AND COATINGS
MINIMUM WORKS OBLIGATIONS
CONTENTS
CONTENTS ....................................................................................................................................... 4
1. INTRODUCTION................................................................................................................ 7
3. MATERIALS ..................................................................................................................... 12
00102W-C-G0-G000-ML-SPC-0007 Page 4 of 46
Rev 1 (14 December 2011)
RUMAILA PROJECT
SPECIFICATION FOR PROTECTIVE PAINT AND COATINGS
MINIMUM WORKS OBLIGATIONS
7. REPAIRS ......................................................................................................................... 23
8. EXECUTION .................................................................................................................... 25
9.1 General............................................................................................................................. 27
00102W-C-G0-G000-ML-SPC-0007 Page 5 of 46
Rev 1 (14 December 2011)
RUMAILA PROJECT
SPECIFICATION FOR PROTECTIVE PAINT AND COATINGS
MINIMUM WORKS OBLIGATIONS
A2.2 PROCESS AND UTILITY PIPING IDENTIFICATION MARKING COLOUR BANDING SYSTEM 41
00102W-C-G0-G000-ML-SPC-0007 Page 6 of 46
Rev 1 (14 December 2011)
RUMAILA PROJECT
SPECIFICATION FOR PROTECTIVE PAINT AND COATINGS
MINIMUM WORKS OBLIGATIONS
1. INTRODUCTION
1.1 Scope
This specification defines the minimum requirements for the surface preparation of and protective coating
application to metallic surfaces both in shop and in the field.
This specification covers the painting of exterior surfaces of all above ground equipment, piping, structural steel
and internal linings for vessels and tanks. It defines the generic coating/lining systems to be used, the minimum
properties of the coating/lining materials and the minimum application requirements.
This specification does not cover below ground coating systems and galvanizing.
The document is provided to the SUPPLIERS for the specification and definition of the CONTRACTOR’S
minimum requirements. These requirements shall be imposed by the SUPPLIER on all SUB-SUPPLIERS.
1.2 Definitions
COMPANY shall mean B.P. Iraq NV
CONTRACTOR shall mean WorleyParsons which carries out all or part of the design and engineering of the
project.
SUPPLIER shall mean the party that manufactures or supplies equipment and services to perform the duties
specified by the COMPANY or CONTRACTOR.
SUB-SUPPLIER shall mean the party supplying goods, equipment or material specified by the SUPPLIER.
INSPECTION AUTHORITY shall mean the inspection bodies which work under the supervision of the
COMPANY or CONTRACTOR. In some cases the COMPANY may also act as the INSPECTION
AUTHORITY.
PLANT - Shall mean permanent facilities designed, constructed and completed as a result of execution of
the WORK under the Contract, located at the Rumaila Project Iraq.
SITE - Shall mean the premises and places on, under, in, over or through which the WORK is to be executed
or carried out including CONTRACTOR’S engineering office and the Plant.
WORK - Shall mean all and any of the works and / or services and / or materials required to be provided by
the CONTRACTOR under the Contract with COMPANY.
00102W-C-G0-G000-ML-SPC-0007 Page 7 of 46
Rev 1 (14 December 2011)
RUMAILA PROJECT
SPECIFICATION FOR PROTECTIVE PAINT AND COATINGS
MINIMUM WORKS OBLIGATIONS
1.3 Abbreviations -
CS Carbon Steel
EN Euro Norm
HP High Pressure
ISO International
LP Low Pressure
SS Stainless Steel
00102W-C-G0-G000-ML-SPC-0007 Page 8 of 46
Rev 1 (14 December 2011)
RUMAILA PROJECT
SPECIFICATION FOR PROTECTIVE PAINT AND COATINGS
MINIMUM WORKS OBLIGATIONS
2. REFERENCED DOCUMENTS
ASTM B117 Standard Practice for Operating Salt Spray (Fog) Apparatus
ISO 4628 - General Title Paints and Varnishes - Evaluation of degradation of paint
coatings - Designation of intensity, quantity and size of common
types of defect.
00102W-C-G0-G000-ML-SPC-0007 Page 9 of 46
Rev 1 (14 December 2011)
RUMAILA PROJECT
SPECIFICATION FOR PROTECTIVE PAINT AND COATINGS
MINIMUM WORKS OBLIGATIONS
ISO 8502 - General Title Preparation of steel substrates before application of paints and
related products-Tests for the assessment of surface
cleanliness
ISO 8502 - 1 Part 1: Field test for soluble iron corrosion products
ISO 8504 – General Title Preparation of steel substrates before application of paints and
related products — Surface preparation methods
The edition of the Reference Documents shall be the edition current at the effective date of the agreement.
SUPPLIER shall advise CONTRACTOR of any conflict between the referenced documents and any technical
specification. CONTRACTOR shall determine which shall govern. Resolution of any conflict shall be obtained
from the CONTRACTOR in writing before proceeding.
00102W-C-G0-G000-ML-SPC-0007 Page 10 of 46
Rev 1 (14 December 2011)
RUMAILA PROJECT
SPECIFICATION FOR PROTECTIVE PAINT AND COATINGS
MINIMUM WORKS OBLIGATIONS
The precedence applying for use of the Codes, Standards, Specifications and Regulatory requirements for
this project is as follows:
• International Laws, Standards and Regulations (where they do not conflict with Item 1)
• BP corporate and project standards (ETP’s) (where they do not conflict with items 1 and 2)
• Recognised Contractor, Manufacturers and Technology codes and standards (where they do not
conflict with 1,2, and 3)
In the event of an inconsistency, conflict or discrepancy between any of the Standards, Specifications and
Regulatory, the most stringent and safest requirement applicable to the project will prevail to the extent of the
inconsistency, conflict or discrepancy. Any inconsistencies critical to the design shall be brought to the
attention of the Engineering Manager for resolution.
00102W-C-G0-G000-ML-SPC-0007 Page 11 of 46
Rev 1 (14 December 2011)
RUMAILA PROJECT
SPECIFICATION FOR PROTECTIVE PAINT AND COATINGS
MINIMUM WORKS OBLIGATIONS
3. MATERI ALS
The CONTRACTOR reserves the right to instruct the SUPPLIER to use approved materials from paint
manufacturers other than those listed in Appendix 1. Prequalification of other manufacturers' products is
subject to compliance with CONTRACTOR procedures and requirements.
Unless otherwise approved by the CONTRACTOR, products specified in this section and Appendix 1 shall
be used.
3.2 Abrasives
• SILICA SAND AND OTHER MEDIA PRODUCING SILICA DUST SHALL NOT BE USED.
• Abrasives for blast cleaning shall be clean, dry and free of any constituent part that could be
detrimental to long term coating performance, and shall be selected to provide the required surface
profile for the coating to be applied.
• Abrasive for use on carbon steel and low alloy steels shall be in accordance with ISO 8504-2.
Abrasives shall be grit manufactured from chilled iron, steel, and malleable iron or non-metallic
abrasives such as aluminium oxide, copper slag and garnet.
• Abrasives for use on stainless steel shall be glass beads, aluminium oxide or garnet and shall be free
from chlorides, zinc, and iron/steel contamination. Copper slag shall not be used on stainless steel.
• All blast media to be used shall be submitted to CONTRACTOR for approval prior to initiation of any
surface preparation work.
The Inspector shall check the cleanliness of the compressed air using a white absorbent cloth (the “blotter
test“) in accordance with ASTM D4285.
00102W-C-G0-G000-ML-SPC-0007 Page 12 of 46
Rev 1 (14 December 2011)
RUMAILA PROJECT
SPECIFICATION FOR PROTECTIVE PAINT AND COATINGS
MINIMUM WORKS OBLIGATIONS
Paints for use over stainless steels shall not contain zinc, chlorides or other halides and shall be approved by
the paint manufacturer for use on stainless steel.
Paints shall be factory sealed in metal containers and factory labelled. Thinners and solvents shall be as
identified in the manufacturer’s data sheets. All containers shall remain closed in factory sealed containers
until required for use. Each container shall have the manufacturer’s name, the product name/identification,
the batch number, the date of manufacture, the shelf life or expiry date, identify the appropriate health &
safety data sheets, material data sheets and a contact telephone number for technical service.
Storing, thinning, mixing and handling, of paint materials shall be in accordance with the manufacturer’s
recommendations. Only thinning materials approved by the paint manufacturer shall be used.
Primer colours shall be manufacturer’s standard colours. Finish colours, except for silicone aluminium, shall
be as noted in the colour schedule in Appendix 2. Heat stable colours shall be used for services above
93°C.
The VOC level of the coating materials shall not exceed 420 grams/litre or the limit set by local agencies
whichever is lower.
SUPPLIER shall be completely responsible for determining the compatibility of coating materials being
applied to the same item that are the products of different manufacturers.
00102W-C-G0-G000-ML-SPC-0007 Page 13 of 46
Rev 1 (14 December 2011)
RUMAILA PROJECT
SPECIFICATION FOR PROTECTIVE PAINT AND COATINGS
MINIMUM WORKS OBLIGATIONS
4. GENERAL REQUIREMENTS
Requirements for painting of pipework to suit temperature conditions involved shall include the entire
pipework system comprising pipe, fittings, flanges, strainers, traps etc., together with valves where the valve
manufacturers' standard coating system does not offer sufficient protection for the environmental conditions
involved.
Ladders, stair treads, cages and platform gratings shall be galvanized and shall not be over painted.
Hand-railing (posts, mid-bars and top rail) shall be painted. The tubular top rail shall be over painted in
accordance with this specification. (This may apply to other steel items requiring application of high visibility
coating.)
All uninsulated portions of insulated equipment comprising vessel nozzles, manway covers, valves, relief
valves, etc. shall be painted to suit temperature conditions involved.
All equipment supports, including vessel skirts, legs, saddles, etc. shall be coated with the paint system
specified in Table 1 for the temperature range up to 120°C.
The paint system shall be based on the maximum operating temperature of the equipment and pipework.
Where the paint system is applied for low temperature service, the effect of lowest temperature shall also be
considered.
Process equipment shall be prepared and painted only after completion of all heat treatment, pressure
testing and non-destructive examinations.
• Brickwork, concrete structures and foundations, fireproofing, building floors, the underside of site
erected tank bottoms and pavement not subject to attack from corrosive substances.
• Brass, copper, slate, glass, tile, uninsulated stainless steels and similar weather resisting
materials.
00102W-C-G0-G000-ML-SPC-0007 Page 14 of 46
Rev 1 (14 December 2011)
RUMAILA PROJECT
SPECIFICATION FOR PROTECTIVE PAINT AND COATINGS
MINIMUM WORKS OBLIGATIONS
• Any equipment furnished completely primed and finish painted by the manufacturer (e.g.
Instruments, Instrument boards, Motors) unless specifically required to repair paint damage or to
match a colour scheme.
• Metallic, aluminium pigmented or light coloured insulation coating (fabric reinforcement and
mastic).
• Stainless steels when protected by guards or not covered with insulation. Aluminium fins of air
coolers
• Insulation jacketing
• Operating parts of machinery and equipment, e.g. valve stems and shafts
• Stainless steel piping (all types) with a nominal diameter less than 26 mm
• Stainless steel surfaces directly exposed to the atmosphere (i.e. stainless steel surfaces without
thermal or acoustic insulation.
4.3 Fasteners
Shop applied coatings for fasteners (bolts, studs and nuts) shall be spun galvanized – i.e. hot dip galvanized
and centrifuged. Hot dip galvanizing shall be in accordance with the requirements of the specification for
galvanizing and centrifuged to remove all excess zinc from threads, the minimum coating thickness shall be
43 microns.
Fasteners that are not supplied shop coated shall be coated as per Appendix 1 as part of the site painting
activities.
• All external, shop and field assembled, flanged connections, including insulated flange bolting at or
below a service temperature of 200 ºC.
• Galvanized bolts shall not be used on austenitic SS piping/flanges (e.g. type 304L and 316L grades).
• Equipment bolting that requires removal for scheduled maintenance and inspection.
Shop coated fasteners shall not generally be utilized for the following:
• Structural bolting
00102W-C-G0-G000-ML-SPC-0007 Page 15 of 46
Rev 1 (14 December 2011)
RUMAILA PROJECT
SPECIFICATION FOR PROTECTIVE PAINT AND COATINGS
MINIMUM WORKS OBLIGATIONS
Stainless steel shall be protected from contact with galvanized or zinc coated surfaces, including zinc
coatings on flanges, support legs, pipe hangers, or clamps. Zinc primers are prohibited for stainless steel
surfaces and precautions shall be taken to prevent contact especially from accidental overspray during
nearby painting activities. This shall apply to all types of stainless steels; nickel alloys and also 9% nickel
steel components.
Rags and other waste material soiled with paints, thinners or solvents shall be kept in tightly closed metal
containers while on the job or not in use.
Extreme precautions shall be used when working with paint materials, cleaning fluids, etc. especially in close
proximity to oxygen piping or oxygen equipment. Heavy concentrations of volatile or toxic fumes shall be
avoided. When working in confined areas, blowers or exhaust fans shall be used.
Abrasive blast-cleaning equipment shall be of an intrinsically safe construction and equipped with a remote
shutoff valve triggered by the release of a dead man’s handle at the blasting nozzle.
Where air-operated equipment is used, the operator’s hood or headgear shall be ventilated by clean, cool air
served through a regulator filter, to prevent blast cleaning residues from being inhaled.
00102W-C-G0-G000-ML-SPC-0007 Page 16 of 46
Rev 1 (14 December 2011)
RUMAILA PROJECT
SPECIFICATION FOR PROTECTIVE PAINT AND COATINGS
MINIMUM WORKS OBLIGATIONS
• Control valves;
• Couplings;
• Machined surfaces;
• Screws;
• Conduit;
• Nameplates/Code stampings;
• Tags;
Dust, dirt and debris shall be removed from the substrate surfaces by high pressure fresh water washing.
Stubborn deposits shall be removed by scrubbing with stiff plastic brushes. The water wash shall continue
until all water soluble salts are removed from the surfaces.
Surface contaminants such as oil, grease, hydrocarbons etc. shall be removed using water based
biodegradable cleaner in accordance with the manufacturer’s instructions and recommendations for the
cleaner.
00102W-C-G0-G000-ML-SPC-0007 Page 17 of 46
Rev 1 (14 December 2011)
RUMAILA PROJECT
SPECIFICATION FOR PROTECTIVE PAINT AND COATINGS
MINIMUM WORKS OBLIGATIONS
The degreased surfaces shall be further washed with fresh water to remove all traces of the cleaner
chemicals and thoroughly dried before proceeding with any further coating work.
Preparation of welds shall use hand tools, powered tools and abrasive blasting as necessary to remove
burrs, weld spatter, weld flux, slivers, indentations, protrusions and other foreign matter. When grinding the
weld and base metals shall not be ground below the surface.
If stainless steel items need to be smoothed as required by an abrasive grinding wheel, then they shall be
done using a grinding wheel approved for the grinding of stainless steel. Under no circumstances shall
grinding wheels or tools used on carbon steel surfaces be used on stainless steel surfaces. Tools shall
always be kept segregated.
If grinding is to be carried out after blast cleaning, the ground surface shall be re-blasted to restore the
specified surface profile.
Supports for items to be blast cleaned shall have a configuration such that the contact points are as small as
possible to limit surface area covered.
Surface profile or surface roughness (also called “anchor pattern”) shall comply with the requirements of the
paint system to be applied and the approved application procedure. All blasted surfaces shall be visually
inspected to confirm the surface profile has been achieved using the methods and equipment as noted in
Section 10. The results shall be recorded.
After blast cleaning, the surface shall be inspected for metal protrusions, slivers or other metal imperfections;
these shall be ground out and if bigger than 50 mm x 50 mm shall be re-blasted to restore the profile.
Surfaces shall be clean, free of dust and abrasive particles by brushing, blowing with clean compressed air
or vacuum cleaning. Care shall be taken to keep cleaned surfaces free of contamination from dirt, dust,
grease, weld slag, and any other foreign material. Surface preparation shall be subject to inspection before
the prime coat is applied to ensure all traces of dust and foreign matter have been removed.
Blast cleaned surfaces shall be primed within 4 hours of completion of surface preparation and before
occurrence of visible rusting.
00102W-C-G0-G000-ML-SPC-0007 Page 18 of 46
Rev 1 (14 December 2011)
RUMAILA PROJECT
SPECIFICATION FOR PROTECTIVE PAINT AND COATINGS
MINIMUM WORKS OBLIGATIONS
Galvanized or zinc primed surfaces shall be free of all zinc salts, oil and grease before application of any
surface treatment or coating. Zinc salts, oil and grease shall be removed by fresh water washing and/or
suitable solvent. Then, surfaces shall be lightly blast cleaned with garnet or aluminium oxide abrasive to
ensure proper adhesion of subsequently applied coating. Copper slag shall not be used. Any other surface
treatment shall require CONTRACTOR approval.
Stainless steel surfaces shall be abrasive-blasted to an equivalent of ISO 8501-1 grade Sa2½ using a good
quality stainless steel or silica-safe non-metallic abrasive low in chlorides and heavy metal elements, such as
aluminium oxide or a proprietary abrasive based on inert aluminium silicate. Blast cleaning shall achieve a
25-40 micron profile. Surface profile shall be checked by the SUPPLIER. Where abrasive-blasting cannot
be used, the surfaces may be prepared using power-driven flexible disc sanders fitted with coarse grade
abrasive paper, e.g. P60 at CONTRACTOR discretion. Wire brushing shall only be used at weld areas and
shall use brushes with stainless steel bristles
For shop applied coatings light abrasive blasting is mandatory, the use of steam or solvent cleaning only is
not acceptable.
For site applied coatings where restrictive conditions make the abrasive blasting of stainless steel
impractical, light abrasive blasting is not mandatory. The proposed cleaning procedure shall meet the paint
manufacturer’s recommendations.
00102W-C-G0-G000-ML-SPC-0007 Page 19 of 46
Rev 1 (14 December 2011)
RUMAILA PROJECT
SPECIFICATION FOR PROTECTIVE PAINT AND COATINGS
MINIMUM WORKS OBLIGATIONS
6. APPLICATION PROCEDURES
• The paint manufacturer’s data sheets for all paint materials to be used including safety data
sheets;
• Surface preparation method along with chloride and dust acceptance criteria
Ends of pipe and related components, tank plate, structural steel, and like areas of other items that will
require subsequent welding at site, shall be masked off after blast cleaning and left uncoated for a distance
of 50 mm from all areas requiring welding. The masking material shall be removed as soon as possible after
priming or painting. The SUPPLIER shall ensure that all masking material is thoroughly removed from the
equipment and any damage to the primed/painted surface is repaired prior to shipment.
Mixing of the paint shall be in accordance with the manufacturer’s requirements. All mixing shall be done
using power mixers. Mixing units of paint systems shall be as per the manufacturers’ instructions using only
complete units of measure. Mixing of approximate proportions is not permitted.
• The surface temperature is more than 3°C above the dew point;
• The metal surface temperature does not exceed that recommended by the paint manufacturer
for application;
• Adverse weather conditions are not expected within two hours of completing the coating
application e.g. sand storms & blowing sand, fog or rain etc.
• The surface to be coated is free of all moisture e.g. rain, condensation or dampness;
00102W-C-G0-G000-ML-SPC-0007 Page 20 of 46
Rev 1 (14 December 2011)
RUMAILA PROJECT
SPECIFICATION FOR PROTECTIVE PAINT AND COATINGS
MINIMUM WORKS OBLIGATIONS
• Exception to these conditions will be considered on a case by case basis only and subject to
agreement by the paint manufacturer.
6.3.1 General
Paint systems shall be selected from the Painting Schedule for External Surfaces (Table 1) and Paint
Systems (Table 2) all found in Appendix 1. Flanges, nozzles, clips, access ways, saddles and other
attachments which protrude through insulation shall be considered un-insulated and shall be painted
accordingly.
Primer application of the prepared surface shall begin as soon as possible after blast cleaning is complete
and before visible rusting; in all cases the period between blasting and coating application shall not exceed 4
hours.
Paints shall be applied by airless spray or a spray method as recommended by the paint manufacturer.
Brush and or roller application shall be restricted to those conditions given in Sections 7.3.3 & 7.3.4
respectively. The grade of paint shall match the application method.
All dry thicknesses as specified shall be strictly adhered to within a tolerance of -0/+20% unless otherwise
agreed by the CONTRACTOR. The dry film thickness of each coat shall be checked with calibrated film
thickness gauges, using the magnetic resistance or eddy currents principle, such as Elcometer, Micro-test,
Tinsley, etc. The equipment shall be calibrated at least twice daily in accordance with the equipment
manufacturers' recommendations. In order to achieve the specified dry film thickness, frequent checks of
wet film thickness shall be carried out during the paint application with film thickness gauges such as the
Elcometer wheel or comb type.
Paint shall be applied to dry, clean, prepared surfaces under acceptable environmental conditions (Section
7.2) and in accordance with the manufacturer’s data and application sheets.
All coatings shall be uniformly applied without runs, sags, dry spray or other blemishes. All blemishes and
other irregularities shall be repaired or completely removed and recoated. Special attention shall be paid to
crevices, corners, edges, weld lines, bolt heads, nuts, and small brackets, to apply the specified minimum
dry film thickness by brush application. This is known as stripe coating and shall be applied for primer,
intermediate and finish coats.
Continuous agitation type spray pots shall be used when applying metal pigmented coatings such as zinc or
aluminium loaded coatings.
A mist coat or tie coat of organic primer shall be applied over inorganic zinc primer to seal the coating prior to
application of the intermediate coat. This shall be done when the inorganic zinc primer has reached a
satisfactory level of cure. The CONTRACTOR shall exercise necessary care to ensure a smooth and
uniform coating is applied over inorganic zinc primer.
00102W-C-G0-G000-ML-SPC-0007 Page 21 of 46
Rev 1 (14 December 2011)
RUMAILA PROJECT
SPECIFICATION FOR PROTECTIVE PAINT AND COATINGS
MINIMUM WORKS OBLIGATIONS
Surfaces that will be inaccessible after assembly, including the surfaces of lap joint flanges, nozzle necks,
lap joint stub ends, lap rings, bolt holes and some welded joints, shall receive the complete painting system
before being assembled. Contact surfaces of bolted connections are to be primed only.
Contamination between coats shall be minimized by maintaining proper cleanliness and by applying
intermediate and finish coats within the time period recommended by the manufacturer.
Adhesion qualification test plates shall be prepared at the same time and under the same conditions as the
production coating work.
The spray gun shall be held at right angles to the substrate and no closer than 200 mm or more than 600
mm from the surface to be coated. Each pass shall overlap the previous one by 50 %. For large surface
areas the direction of spray application between coats shall be at right angles to each other.
Pressures and spray fan shall be adjusted so that the optimum spray pattern is utilized for the surface being
coated.
• When applying the stripe coat of paint to corners, edges, crevices, holes, welds or other irregular
surfaces prior to spray application.
Paint brushes used shall be of a type and quality that will permit appropriate application of the material being
applied.
Material applied by brush shall be smooth, uniform in thickness, without any surface defects such as brush
marks, runs or sags.
7. REP AIRS
Before application of any further coat of material, all damage to previous coats shall be repaired.
Surface preparation shall wherever possible be carried out by dry blast cleaning. If dry blast cleaning is not
required or not feasible (e.g. due to limited access, risks of damage to equipment, the proximity of electrical
components or instrumentation) then manual cleaning shall be performed.
Manual cleaning shall be performed using hand wire brushes, or power operated tools (e.g. grinders,
chippers or wire brush) in accordance with ISO 8504-3 to provide a roughly abraded surface. A burnished
surface is not acceptable.
If the surface being prepared lies adjacent to a sound coated surface which is not to be repaired, the surface
preparation shall overlap the coated surface by at least 25 mm. The remainder of existing coated surface
shall be properly protected with shields or screens to prevent any possible damage to the coating.
Inorganic zinc primer shall not overlap adjacent intermediate and finish coats.
Areas with inadequate coating thickness shall be thoroughly cleaned and, if necessary, abraded, and
additional compatible coats applied until they meet this Specification. These additional coats shall blend in
with the final coating on adjoining areas. Colour match shall be achieved.
The coating around the damaged area shall be chamfered, using an approved method, to ensure continuity
of the patch coating. The required number of paint coats shall be applied in accordance with this
specification to re-establish the full coating system.
00102W-C-G0-G000-ML-SPC-0007 Page 23 of 46
Rev 1 (14 December 2011)
RUMAILA PROJECT
SPECIFICATION FOR PROTECTIVE PAINT AND COATINGS
MINIMUM WORKS OBLIGATIONS
a) Abrasive blasting of the surface to the specified standard of cleanliness and profile.
b) Light abrasive blasting of the surrounding zinc silicate primer extending a minimum distance of 25 mm,
to ensure removal of all zinc corrosion products.
c) Apply the repair primer to the steel surface and surrounding zinc silicate primer.
The repair primer shall be a zinc-rich, polyamide epoxy primer subject to it being suitable for the intended
service temperature. In the event that the service temperature prevents the use of a zinc-rich polyamide
epoxy primer the SUPPLIER shall submit a detailed repair procedure, along with paint data sheets, for
CONTRACTOR review. The paint manufacturer should confirm the compatibility of the proposed silicate
primer and surface preparation requirements.
Surface preparation by any other method than abrasive blast cleaning shall be permitted only with the written
approval of the CONTRACTOR.
Under no circumstance shall zinc silicate primer be allowed to overlap adjacent intermediate and finish
coats, or be applied over visible zinc corrosion products.
00102W-C-G0-G000-ML-SPC-0007 Page 24 of 46
Rev 1 (14 December 2011)
RUMAILA PROJECT
SPECIFICATION FOR PROTECTIVE PAINT AND COATINGS
MINIMUM WORKS OBLIGATIONS
8. EXECUTION
The SUPPLIER shall submit a Work Plan/Method Statement delineating painting work execution between
shop and field painting and obtain CONTRACTOR approval.
Standard paint systems offered by the SUPPLIER for standard items such as control and electrical
equipment, pumps, motors, compressors, etc must be capable of a minimum corrosion resistance of 2000
hours when tested in accordance with ASTM B117.
The SUPPLIER shall submit the paint specification/application procedures for review by the
CONTRACTOR/COMPANY REPRESENTATIVE. All SUPPLIER specification/procedures shall comply with
the requirements of this Specification and shall not be considered in lieu of or substitution for the procedures
and requirements stated in this Specification.
The manufacturer shall copy all technical correspondence with the SUPPLIER to the CONTRACTOR.
• Supply and application of all paint materials, labour, supervision, coating equipment, inspection tools
and each and every item of expense necessary for complete application of the paint system.
• Supply, erection and removal of scaffolding to perform the painting work. Scaffolding shall be
inspected by a qualified safety inspector and certified safe before being released for use.
00102W-C-G0-G000-ML-SPC-0007 Page 25 of 46
Rev 1 (14 December 2011)
RUMAILA PROJECT
SPECIFICATION FOR PROTECTIVE PAINT AND COATINGS
MINIMUM WORKS OBLIGATIONS
• Application of the paint systems to the extent stated in the procurement documents and in accordance
with this specification and all other relevant documents such as site regulations, safety rules,
referenced standards and codes, etc.
• Removal of identification marks on bare or unfinished equipment, piping and structural steel and re-
application of the identification marks on the finished surfaces.
• Protection from abrasives and paint overspray of all items and surfaces not being painted.
• Collection and disposal of all toxic waste materials from the work site.
• Appropriate arrangements for technical services of the paint manufacturer before and during planning
and application of the paint systems. The SUPPLIER’S purchase order for paint materials shall include
a provision stating that the manufacturer’s technical representative shall directly report to the
CONTRACTOR regarding the acceptability and workmanship of the paint application.
• Obtaining latest paint data sheets and application procedures and maintaining the same for use by all
the parties.
• Providing qualified painting inspectors and testing instruments and tools for carrying out specified
inspection and quality control measures.
• Maintenance of the paint work until completion of the contract. This shall include the repair of damage
caused by third parties. Refer to Section 13.
00102W-C-G0-G000-ML-SPC-0007 Page 26 of 46
Rev 1 (14 December 2011)
RUMAILA PROJECT
SPECIFICATION FOR PROTECTIVE PAINT AND COATINGS
MINIMUM WORKS OBLIGATIONS
9.1 General
Before painting activities commence the SUPPLIER shall submit an Inspection & Test Plan (ITP) for review
by the CONTRACTOR. The ITP shall incorporate all inspection requirements, hold points and the required
inspection frequency and number of readings. For production work the checks shall include paint material
inspection, blast material inspection, environmental conditions, surface condition and cleanliness, the
surface profile, the coating thickness, a visual assessment and repairs and corrective actions taken.
Adhesion and cure tests may be carried out on test plates prepared and coated at the same time - and to the
same standard - as the work.
The SUPPLIER shall employ a qualified painting inspector whose resume shall be approved by the
CONTRACTOR.
The CONTRACTOR shall have the right to inspect coating activities at all stages and to reject any tools,
materials, equipment or work which do not conform to this Specification.
All items coated by the SUB-SUPPLIER shall be inspected on arrival and damaged areas shall be repaired
by the SUPPLIER. If repairs amount to more than 5 % of the surface areas, or the finish coat appearance is
not acceptable, then the CONTRACTOR may instruct the SUPPLIER to apply an additional finish coat to
improve appearance at no cost to CONTRACTOR/COMPANY.
Activity Instrument
Test instruments shall be calibrated on a routine basis determined on the frequency of use and maintained in
good working condition at all times.
00102W-C-G0-G000-ML-SPC-0007 Page 27 of 46
Rev 1 (14 December 2011)
RUMAILA PROJECT
SPECIFICATION FOR PROTECTIVE PAINT AND COATINGS
MINIMUM WORKS OBLIGATIONS
a) Verify the required blast surface cleanliness and surface profile has been achieved. Surface profile
assessment shall be carried out in accordance with ISO 8503 2.
b) Verify the surfaces are free of contamination. Tests to indicate the presence of chlorides and dust
shall be carried out in accordance with ISO 8502-1, ISO-8502 and ISO 8502-3. The acceptance
criteria for chlorides and dust shall be detailed in the application procedure.
c) Verify that surfaces not to be coated are masked off, or otherwise protected.
d) Check the air temperature, relative humidity, and substrate surface temperature.
e) Record the actual paint materials to be applied and they match the specified coating system. Verify
that storage, mixing, thinning, and application of primer, intermediate, and finish coats are in
accordance with the Application Procedure.
f) Immediately before paint application, re-inspect the surface to confirm freedom from moisture and
other contaminants are present.
g) Take wet film thickness (WFT) measurements during paint application to ensure that the film thickness
is being achieved.
h) Take dry film thickness (DFT) measurements at each stage of the system application to ensure that
the film thickness is being achieved.
Visual inspection shall be carried out at each stage of the coating system. If loss of adhesion is found or
suspected then an adhesion test shall be made. The adhesion of the primer to the steel substrate and the
inter-coat adhesion of the subsequent coat(s) after curing shall be determined by the application of either a
cross-cut test in accordance with ISO 2409 or a pull-off test described in ISO 4624. Coatings applied to blast
2
cleaned carbon steel exhibiting an adhesion of less than 15 kg/cm shall be rejected.
Each painting system and repair method shall be tested on a test plate for an adhesion qualification test.
The test plate shall be coated at the same time and to the same standard as the production work.
Repairs made in the field shall be documented and inspected in accordance with this Specification.
00102W-C-G0-G000-ML-SPC-0007 Page 28 of 46
Rev 1 (14 December 2011)
RUMAILA PROJECT
SPECIFICATION FOR PROTECTIVE PAINT AND COATINGS
MINIMUM WORKS OBLIGATIONS
g) Painting periods
Remedial actions, if any, shall be determined based on the results of the inspection.
00102W-C-G0-G000-ML-SPC-0007 Page 29 of 46
Rev 1 (14 December 2011)
RUMAILA PROJECT
SPECIFICATION FOR PROTECTIVE PAINT AND COATINGS
MINIMUM WORKS OBLIGATIONS
Facilities and methods of yard storage and protection of the pipe during transportation shall be subject to
approval by the CONTRACTOR.
Preparation of coated items for shipment shall be in accordance with CONTRACTOR standards and this
Specification. Procedures shall be established to prevent mechanical damage to the applied coating system
and corrosion during transit and at the jobsite. The procedures shall cover the following activities:
• Pipe end caps - Pipe ends shall be capped at all times after final coating.
The procedure shall include checking for damaged or loose fitting
caps and replacement as required.
• Packing & padding - To ensure sufficient support and padding to prevent movement
• Lifting - To ensure correct usage of lifting apparatus and slings that will not
damage the coating e.g. rubber straps, canvas belts.
Ropes, hooks, chains and cables shall be prohibited.
Coated items shall be treated with a solvent-based, rust preventative fluid to provide medium- to long-term
protection during storage and handling at the job site prior to use. The SUPPLIER shall submit data sheets
of the rust preventative fluid for CONTRACTOR approval.
Coated items shall be stored off the ground on padded skids that are suitably levelled and spaced to support
the coated item. Coated items shall be separated or protected from adjacent items.
Gasket contact surfaces and machined surfaces shall be protected with CONTRACTOR approved rust
preventative fluid to provide medium to long-term protection during transportation and storage.
00102W-C-G0-G000-ML-SPC-0007 Page 30 of 46
Rev 1 (14 December 2011)
RUMAILA PROJECT
SPECIFICATION FOR PROTECTIVE PAINT AND COATINGS
MINIMUM WORKS OBLIGATIONS
12. GUARANTEE
The SUPPLIER shall guarantee the performance of the paint system – both shop and field applied - for a
period of 5 years from the date of final acceptance by the CONTRACTOR/COMPANY.
This guarantee applies to painting of carbon steel, galvanized steel, stainless steel and all items painted in
accordance with the SUPPLIER/SUB-SUPPLIER and CONTRACTOR procedures.
The SUPPLIER shall be liable for remedial actions such as spot repair and the over coating and
refurbishment of extended areas with paint failures/defects at site when:
• The estimated amounts of rust breakthrough on a coating and of total apparent rust (rust breakthrough
plus under film) rust exceeds ISO 4628-3 rust scale Ri 1(0.05% area rusted).
• Defects in the paint film such as blistering, peeling, flaking, inter-coat delamination, mud cracking, etc.
affecting the overall integrity of the coating.
The repair procedure shall be subject to approval by the CONTRACTOR. All defective spots shall be
repaired. If the area requiring repair is greater than 20% of the total surface of an individual item then the
entire item shall be refurbished.
The degree of blistering shall be evaluated in accordance with ISO 4628-2. The degree of cracking and
flaking in a coating shall be evaluated in accordance with ISO 4628-4, ISO 4628-5 and ISO 4628-6,
respectively.
The SUPPLIER shall undertake to carry out remedial painting at any time within the guarantee period as
directed and agreed by the CONTRACTOR/COMPANY, at the expense of the SUPPLIER. “Remedial
painting” shall include all site activities necessary for the removal of defective coating where necessary,
surface preparation, paint material supply and the application of paint in conformity with this Specification.
00102W-C-G0-G000-ML-SPC-0007 Page 31 of 46
Rev 1 (14 December 2011)
RUMAILA PROJECT
SPECIFICATION FOR PROTECTIVE PAINT AND COATINGS
MINIMUM WORKS OBLIGATIONS
Galvanized surfaces
Stainless Steels
00102W-C-G0-G000-ML-SPC-0007 Page 32 of 46
Rev 1 (14 December 2011)
RUMAILA PROJECT
SPECIFICATION FOR PROTECTIVE PAINT AND COATINGS
MINIMUM WORKS OBLIGATIONS
Notes – Table 1:
1. For painting requirements, low alloy steels shall include all Cr-Mo steels containing up to 9% Cr.
2. With regard to coating of the soil side: the tank floor plates shall be masked off 100 mm from the edge
to prevent coating application. The coating shall be holiday tested and coating repairs completed prior
to plate welding.
3. Galvanized gratings, stair treads, cages, ladders, etc shall not be painted unless otherwise specified.
4. Paint systems with IOZ or other zinc rich primers shall not be used for austenitic stainless steel piping
and pressurized equipment
5. GRP/FRP equipment exposed above ground shall be coated in accordance with the
manufacturer/supplier recommendations. For GRP/FRP piping only identification banding - as per
Appendix 2 - shall be necessary.
6. For all electrical equipment items manufacturers standard coating system and finish colour is
acceptable.
00102W-C-G0-G000-ML-SPC-0007 Page 33 of 46
Rev 1 (14 December 2011)
RUMAILA PROJECT
SPECIFICATION FOR PROTECTIVE PAINT AND COATINGS
MINIMUM WORKS OBLIGATIONS
2 CS Sa2½ Zinc Rich Epoxy (75 µ) Hi-build MIO epoxy Acrylic modified polyurethane 320 120
(2 x100 µ) (60 µ)
(100 µ) (2 x100 µ)
5 CS Sa2½ Zinc rich epoxy Red oxide epoxy tie coat 100 NA
(75 µ) (25 µ)
(30µ)
00102W-C-G0-G000-ML-SPC-0007 Page 34 of 46
Rev 1 (14 December 2011)
RUMAILA PROJECT
SPECIFICATION FOR PROTECTIVE PAINT AND COATINGS
MINIMUM WORKS OBLIGATIONS
8 Galvanised See Section 6.5 Epoxy primer Polyamide MIO epoxy Aliphatic polyurethane 155 120
Copper (40 µ) (40 µ) (75 µ)
10 SS Sa2½ 2 pack polyurethane primer - Hi-build MIO epoxy Acrylic modified polyurethane 310 120
Notes
a) Thickness of inorganic zinc silicate primer shall not exceed 60 microns. DFT values greater than 60 microns shall be subject to removal by blasting and re-
application of primer. The requirements of the surface preparation shall be subject to approval by CONTRACTOR.
b) Precautions shall be taken against over-thickness application of aluminium silicone resin based coats. Adhesion tests are mandatory. High temperature finish
coating must be capable of "cold curing" to handle ambient temperature.
c) Inorganic zinc silicate paints may be water based or solvent based and shall have metallic zinc of at least 85% (by weight) in the dried film.
00102W-C-G0-G000-ML-SPC-0007 Page 35 of 46
Rev 1 (14 December 2011)
RUMAILA PROJECT
SPECIFICATION FOR PROTECTIVE PAINT AND COATINGS
MINIMUM WORKS OBLIGATIONS
00102W-C-G0-G000-ML-SPC-0007 Page 36 of 46
Rev 1 (14 December 2011)
RUMAILA PROJECT
SPECIFICATION FOR PROTECTIVE PAINT AND COATINGS
MINIMUM WORKS OBLIGATIONS
00102W-C-G0-G000-ML-SPC-0007 Page 37 of 46
Rev 1 (14 December 2011)
RUMAILA PROJECT
SPECIFICATION FOR PROTECTIVE PAINT AND COATINGS
MINIMUM WORKS OBLIGATIONS
A2.1 General
Safety colour coding and identification of equipment and piping for this project shall be in accordance with
this Specification. SUPPLIERS shall use the BS 4800 standard colours or equivalent. Equivalent German
colour standard numbers, RAL 840, may be substituted depending on the in-country availability of particular
colours, but this shall be agreed with the CONTRACTOR.
Table 4 lists basic piping systems, equipment, and the required finish colour for that particular piping system
and major equipment type. Any item that is not listed below, but is part of this project, shall be brought to the
attention of the CONTRACTOR for selection of the finish colour and exact colour coding and marking
requirements.
Components such as junction boxes / auxiliary piping etc. attached directly to the prime equipment or
equipment driver shall be painted to the same colour (as per Table 4) as the major item to which it is
attached.
Pipes shall be identified by pipe body colour and with colour coded self adhesive bands or by painting (for
cases where bands are not practical or commercially available). In such cases, pipe marking shall follow all
the coding and marking in accordance with this specification.
00102W-C-G0-G000-ML-SPC-0007 Page 38 of 46
Rev 1 (19 December 2011)
RUMAILA PROJECT
SPECIFICATION FOR PROTECTIVE PAINT AND COATINGS
MINIMUM WORKS OBLIGATIONS
Utilities - all other than cooling water or firewater lines Grey up to 120°C. Aluminium 00A05/Aluminium
above 120°C
Acid alkali and other corrosive storage except toxic Grey up to 120°C or 00A05/Aluminium
contents. aluminium above 120°C 10E53
Number and description
stencilled on yellow block
Outdoor Instrumentation Items Black 00E53
e.g., control valves, transmitters, gauges. Where such
items require painting for weather protection, they shall be
black.
FIRE FIGHTING EQUIPMENT - Valves, hydrants, hose Red 04E53
boxes, firewater and foam-lines, dry risers
00102W-C-G0-G000-ML-SPC-0007 Page 39 of 46
Rev 1 (19 December 2011)
RUMAILA PROJECT
SPECIFICATION FOR PROTECTIVE PAINT AND COATINGS
MINIMUM WORKS OBLIGATIONS
00102W-C-G0-G000-ML-SPC-0007 Page 40 of 46
Rev 1 (19 December 2011)
RUMAILA PROJECT
SPECIFICATION FOR PROTECTIVE PAINT AND COATINGS
MINIMUM WORKS OBLIGATIONS
• Adhesive PVC marker tape - the primary colour. This also indicates the direction of the pipe
contents flow with an arrow.
Prior to the band application, the pipe surface shall be thoroughly cleaned of all surface contamination such
as oil, grease, scale dust etc. by the application of an approved cleaning solvent compatible with the coating
system using only clean rags or brushes. The cleaned surface shall be allowed to completely dry out before
applying the PVC colour bands.
The PVC colour bands shall be applied to the pipework immediately after the solvent cleaned surface is dry.
The banding system shall be applied as follows:
• The length of the tapes needed shall be removed by applying a length of tape around the pipework
with the backing paper still attached. An overlap of 50 mm shall be allowed for, and the tapes cut to
the required length.
• The corner edges (approx. 25 mm) shall be cut off at an angle of 45º at the overlap end of the tapes to
prevent peel-off.
• The backing paper shall be removed from the primary band tape to the extent that the arrow under
which the text strip is to be placed is clear.
• The arrow shall point in the direction of pipe contents flow and the text strip shall be applied to the
back face of the primary tape so that the text is centrally located and clearly visible within the
transparent flow arrow window.
• The tape shall be held with both hands against the pipe and the flow arrow adjusted into the best
reading position for the operations personnel. The tape shall be applied by smoothing it onto the
pipework by hand, avoiding trapping air bubbles and without stretching. It should be a snug fit on the
pipework with a 50 mm overlap.
• The two secondary plain band tapes shall be applied in the same manner as the band tape.
The PVC banding system shall be applied on all piping, oriented so that the flow directional arrow and label
text is clearly visible by operations personnel. The banding system shall be applied immediately adjacent to
the following items and additionally at approximately 5 m intervals:
• All valves;
00102W-C-G0-G000-ML-SPC-0007 Page 41 of 46
Rev 1 (19 December 2011)
RUMAILA PROJECT
SPECIFICATION FOR PROTECTIVE PAINT AND COATINGS
MINIMUM WORKS OBLIGATIONS
CHEMICALS
Biocide Violet 22C37 Pink 04E49
Hypochlorite Violet 22C37 Red 04E53
Demulsifier Violet 22C37 Brown 06D45
Antifoam Violet 22C37 DK Yellow 08E51
Deoiler Violet 22C37 Yellow Ochre 08C53
Methanol Violet 22C37 Blue 20D45
Oxygen scavenger (future) Violet 22C37 Dark Green 14C39
Corrosion inhibitor Violet 22C37 White 00E55
Scale inhibitor Violet 22C37 Green 12D45
Asphaltene Disperant Violet 22C37 Light Blue 20E51
Fire fighting Foam Red 04E53
Black 00E53
PROCESS FLUIDS
Hydrocarbon Gas Yellow Ocre 08C35 Brown 06C39
Fuel Gas Yellow Ocre 08E35 Blue 18E50
Hydrocarbon Liquid Brown 06C39 Light Blue 20E51
Two Phase Hydrocarbon Brown 06C39 Violet 22C37
Produced Water Green 12D45 Yellow Ocre 08C53
UTILITIES GAS FLUID
Instrument Air Light Blue 20E51 White 00E55
Plant Air Light Blue 20E51 Brown 06C39
Nitrogen Light Blue 20E51 Red 04E53
Cooling Medium Blue 18E50 Yellow Ochre 08C53
(30% TEG / 70% Water)
Lean TEG Blue 18E50 White 00E55
Rich TEG Blue 18E50 Black 00E53
WATER
Injection Water Dark Green 14C39 Red 04E53
Seawater Green 12D45 Red 04E53
Potable Water (sterilised) Green 12D45 Blue 18E53
Fresh Water Green 12D45 Blue 18E53
00102W-C-G0-G000-ML-SPC-0007 Page 42 of 46
Rev 1 (19 December 2011)
RUMAILA PROJECT
SPECIFICATION FOR PROTECTIVE PAINT AND COATINGS
MINIMUM WORKS OBLIGATIONS
00102W-C-G0-G000-ML-SPC-0007 Page 43 of 46
Rev 1 (19 December 2011)
RUMAILA PROJECT
SPECIFICATION FOR PROTECTIVE PAINT AND COATINGS
MINIMUM WORKS OBLIGATIONS
Tanks and Spheres All sizes- See A2.5 500 to 1000 mm high
For insulated lines text size shall be based on pipe diameter plus (2x) insulation thickness.
BAND A B B BAND A B
Figure 1
NOTE:
00102W-C-G0-G000-ML-SPC-0007 Page 44 of 46
Rev 1 (19 December 2011)
RUMAILA PROJECT
SPECIFICATION FOR PROTECTIVE PAINT AND COATINGS
MINIMUM WORKS OBLIGATIONS
Band width
Band A = 100mm
Band B = 50mm
Band A = 150mm
Band B = 75mm
Band A = 200mm
Band B = 75mm
Band A = 300mm
Band B = 100mm
00102W-C-G0-G000-ML-SPC-0007 Page 45 of 46
Rev 1 (19 December 2011)
RUMAILA PROJECT
SPECIFICATION FOR PROTECTIVE PAINT AND COATINGS
MINIMUM WORKS OBLIGATIONS
The method for applying equipment labelling should be considered as painting particularly for larger text
sizes (see section A2.4). However, SUPPLIER shall propose more practical and economical alternatives
should they be considered more suitable and commercially available, for CONTRACTOR review.
Unit item/identification number shall be painted onto the web of structural steel base plate members on both
sides of the unit.
Equipment included in enclosures shall have the unit/identification number painted onto both sides of the
enclosure.
For horizontal equipment the unit item/identification number shall be painted at the equipment centre-line on
both sides of the equipment. For vertical equipment the unit item/identification number shall be painted on
both sides of the equipment at approximately one quarter of the height of the equipment, up to a maximum
elevation of 5 m.
Where applicable, storage tank and/or pressure vessel contents shall be included with the unit/identification
number, located beneath this number. This information is provided primarily, for safety purposes for both
operations and emergency services. Location and design of this label shall reflect this.
SUPPLIER shall review his equipment layout upon installation and specify, on a case by case basis, how
and where each item of equipment will be labeled. In all cases, equipment label locations shall be convenient
for recognition by Operations and Emergency services and this may take precedence over a prescribed
location.
Requirements for COMPANY logos and signage shall also be considered. This will be developed and
detailed by the COMPANY.
00102W-C-G0-G000-ML-SPC-0007 Page 46 of 46
Rev 1 (19 December 2011)