PARTICULAR SPECIFICATIONS
Sr.
Description Visual Test Readings Documentation
No.
19.1 GENERAL
i. Boom barriers shall be installed in all the entry and exit of the campus
ii. The location of boom barrier will be as per Master plan. The lengths may slightly vary
as per the road layout.
iii. Boom barrier shall be shall support integration with Fire Alarm System to free Open or
Lock the defined doors / boom barrier in case of Fire.
iv. Boom barrier shall be completely automatic with optical beam sensor. Manual override
shall also be provided.
v. For 2 wheelers, side entry option will be there as per Master Plan.
vi. Barriers shall be designed for intensive duty cycles.
vii. Housing for drives and controller shall be IP-55 rated.
viii. The operation will be controlled/ monitored from guard room/ control room.
CA No. CEDZ / TOKEN- 5 OF 2022 SERIAL PAGE NO. 704
PARTICULAR SPECIFICATIONS
20. LIFTS
20.1 SCOPE
The scope of this section comprises the supply, delivery, erection, testing and commissioning of
machine room less lifts as per the tender requirements. The scope also includes getting all
statutory approvals for lift.