CA No. CEDZ / TOKEN- 5 OF 2022 SERIAL PAGE NO.

703

PARTICULAR SPECIFICATIONS

Sr.
Description Visual Test Readings Documentation
No.

All cables are tested for continuity,


1 √
insulation, resistance etc.

2 System installation proper as per drawing √

Carry out visual checks on all speakers &


Processors are free from any mechanical
3 √
damage, cables, inter phase modules
etc.to ensure they are properly installed.

Check for proper termination of bootlace


4 √
lugs & feruling

5 Check Input A/C Supply Voltage √

Check location / spacing of loudspeakers


6 √ √
as in drawing.

Check Distribution of Zones as per


7 √ √
Drawing.

Check full load speaker sound quality &


8 measure Sound pressure level (SPL) in √ √
dB.

Check if local loudspeakers overrides by


9 voice messages in case of emergency √ √
evacuation.

If power fails, whether Voice evacuation


10 system is working on battery supply if yes √
for what time

Check if recorder messages are CLEAR,


free from any noise distortion & easy to
11 √ √
understand with Room acoustic speech
transmission Index (RaSTI) value >0.5.

Processor LED’s and all keys are working


12 √
properly

Check for Microphone locations & the


13 √ √
sensitivity by paging

14 Play a soft music & check sound quality √

19. TYRE KILLER WITH BOOM BARRIER

19.1 GENERAL
i. Boom barriers shall be installed in all the entry and exit of the campus
ii. The location of boom barrier will be as per Master plan. The lengths may slightly vary
as per the road layout.
iii. Boom barrier shall be shall support integration with Fire Alarm System to free Open or
Lock the defined doors / boom barrier in case of Fire.
iv. Boom barrier shall be completely automatic with optical beam sensor. Manual override
shall also be provided.
v. For 2 wheelers, side entry option will be there as per Master Plan.
vi. Barriers shall be designed for intensive duty cycles.
vii. Housing for drives and controller shall be IP-55 rated.
viii. The operation will be controlled/ monitored from guard room/ control room.
CA No. CEDZ / TOKEN- 5 OF 2022 SERIAL PAGE NO. 704

PARTICULAR SPECIFICATIONS

ix. There should be provision of RFID technology also in future.

19.2 TECHNICAL DATA TO BE FILLED BY OEM:

S.N. Description Comply/Not


Comply
1. Tyre Killer with boom barrier in single drive unit Blocking
element with welded on steel spikes.
2. Spike of steel material.
3. BLOCKING Width: Up to 5 Meter.
4. Underground housing: LxWxH: (blocking width + 600mm) x
400mm x 110 mm
5. Blocking Height: 150 mm spikes or more.
6. WHEEL LOAD : 100 kN according to SLW 60 – DIN 1072
7. Operating Time: Raising: approx. 4 sec. - lowering: approx. 4
sec.
8. Drive Cabinet: Single drive cabinet only for electric boom
barrier & tyre killer for fast & reliable operation. It requires no
further integration for synchronized operation of boom barrier
along with tyre killer.
9. There shouldn’t be any external wiring for integration of tyre
killer with boom barrier, so that very less maintenance issues
during life time of equipments.
10. Working Technology
o Type of Motor Electro Mechanical Torque
Drive Motor
o Working Voltage 230V, 50 Hz Single Phase
o Working Temperature 0°C to +50°C
o Type of Working • Auto or Manual (Make it
sure that in case of supply failure manual can
be operated
o Boom Barrier with Tyre Killer should be
operated rapidly at the time of any attack for
the purpose of defence.
o Single drive motor for electric boom barrier &
tyre killer for fast & reliable operation.
o Control Unit • Raise – Stop – Lower (Should
be established in Control room).
o Control unit in same drive cabinet of boom
barrier & tyre killer.
11. Power : 230 V, 50 Hz
12. CONTROL
Control unit. Raise – Lower
Control unit in same drive cabinet of boom barrier & tyre
killer. Control Unit should come with all factories setting for
integrated use of boom barrier with tyre killer.
13. Operation: Access Control Reader or push Button.
14. Spikes: Color RAL 3000, R
Underground housing: RAL 7030 stone grey
Cover plate : RAL 1007 daffodil yellow
15. PROTECTION AGAINST CORROSION
• Should be Long term protection against corrosion by zinc
based multi layer plastic coating.
• Firm will submit a certificate according to ISOE N7253/
ISO9227 from Original Equipment Manufacturer (OEM) for
salt testing period of minimum 2000hrs with no significant
corrosion on product through any authorized third party.

20. LIFTS

20.1 SCOPE
The scope of this section comprises the supply, delivery, erection, testing and commissioning of
machine room less lifts as per the tender requirements. The scope also includes getting all
statutory approvals for lift.