OFFICE OF THE DIRECTOR OF INDUSTRIES, ODISHA, CUTTACK,
ORDER SHEET
MSEFC Case No.50/2022.
Mis Kalinga Insulation, Petitioner
At-Udayabhat, Dochhaki,
Po-Paradeep Garh, P.S-Paradeep,
District-Jagatsinghpur
Versus
Opp.Parties
1.Mis AES(India) Pvt. Ltd.,
AtUnit1117, 11" Floor, Block-B, Batika tower,
Sector-54, Golf Road, Gurgaon,
Haryana
2.0disha Power Generation Corporation Ltd.,.
Executive Director, Zone-A, 7” Floor,
Fortune Towers, Chandrasekharpur,
Bhubaneswar
3.Odisha Power Generation Corporation Ltd.,
1B Thesmal Power Station,
At/Po-Banarpali,
District-Jharsuguda
The MSEFC met on 30.01.2023 at 10.00 A.M. to adjudicate the claims of Micro & Small
Enterprises i.e. M/s Kalinga Insulation, AtUdayabhat, Dochhaki, Po-Paradeep Gath,
P.S-Paradeep, District-Jagatsinghpur Vrs. 1.M/s AES(India) Pvi. Ltd,, AL-Unitt 117, 11"
Floor, Block-B, Batika tower,Sector-54, Golf Road, Gurgaon, Haryana 2.Odisha Power
Generation Corporation Ltd., Executive Director, Zone-A, 7" Floor, Fortune Towers,
Chandrasekharpur, Bhubaneswar. 3.Odisha Power Generation Corporation Ltd.,|B
Thermal Power Station AUPo-Banarpali, District-Jharsuguda
Md. Sadique Alam , LAS., Chairman
Director of Industries-cum-M.D,OSFC.
Sri Goutam Patra, Member
Convener, SLBC
3. Sri Deepak Kajaria, Member
Presideni, OSSIAHistory of the case.
MSEFC on 13.10.2022 claiming total amount of Rs. 3,26,60,881.31 ( Rs
1,96,01,693.00 towards principal + Interest. Rs.1,30,59,188.31 ( From 09.01.2020 to
21.06.2022) from the O.P.
‘The petitioner provided services to the O.P. The O.P has made part payment leaving a
balance outstanding amount(Principal) of Rs 3,26,60,881.31
The claim petition was forwarded to the O.Ps on 13,08,2022 to file the Counter.
The O.P No.01 has filed the counter on 13.10, 2022.
The O.P No.02 & 03 have prayed four weeks time to file the written statement,
The Petitioner has filed the Rejoinder on dt.1.14 2022.
The O.Ps purchased & held 49% of the equity shareholding in O.P No.02 ie Odisha
Power Generation Corporation Ltd Pursuant to Government of Odisha policy for
Subcontractors including EDAC & one Bhavani Erectors Pvt. Ltd ( Bhavani). Both
Bhavani & EDAC engaged the petitioner as a specialized Scaffolding contractor to work
on the project
Notice has been issued to all the parties to attend 97" Sitting of the MSEFC to be held
on 17.11.2022,
The petitioner, O.P No. 01 & O.P No. 02 are present in 97" Sitting of the MSEFC heid
on 17.11.2022,The summary of the submission by O.P No.01 are as under.
Sometime on or around 1999, with its associated company purchased & held
49% of the equity shareholding in OP No.02 ie Odisha Power Generation
Corporation Ltd. pursuant to Govemment of Odisha policy for opening up the
energy Sector to private enterprises,
“ OP No.02 & Bharat Heavy Electricals Utd. BHEL) entered into a contract for
Supply of equipment & a contract for services Pertaining to construction of OPGC
Unil3 & § Expansion Project, The O.P No. 01 is Not a party to it. BHEL appointed
Warious principal sub-contractors including EDAC Engineering Ltd. & Bhavani
Erectors Pvt. Ltd, (Bhavani). In turn, Bhavani & Edac engaged the petitioner as a
Specialize scaffolding contractor to work on the Project.
This O.P has only stepped in to a limited extent to facilitate completion & hence
to that intent entered into incentives contracts with the petitioner.
tinder such contracts & no balance payable amount is pending with the OP
No.01 & further claims by the petitioner are wrongly raised,
“ This O.P is not in any manner concemed with the contracts between the
ettioner and/ or O.P No.02 and/or BHEL andior EDAC and/or Bhavani, Hence
the petitioner's alleged claim, if any, can only against O.P No, 02 and/or BHEL
and for EDAC and / or Bhavani and not against this O.P.
“The petitioner seeks to abuse the beneficial legislation that is the MSMED Act,
2006 and seeks to unjustly enrich itself at the cost of this O iBUpon perusal of the records, the Council noticed that the petitioner has submitted
‘eloinder affidavit against the counter of O.P No. 01 on 14.11.2022 which has been
acknowledged by the O.P No. 01 on the same day ie 14.11.2022.
The petitioner submits that the O.P No. 01 has admitted that they stepped into the
arena of construction work of unit-3 & unit-4 as it was not satisfied with timely
Progress, LOls issued at different dates only corroborate the extent of involvement of
the O.P no. 01 in the project. The petitioner further submits that the change of
alternation, moderation in share pattern of the Company can not absolve its liability
and as such the bonafide claim of the petitioner can not be obliterated by the change
of shareholding pattern of the Company. The petitioner further submits that the O.P
a No 91 has admitted that it has the contractual liability to pay the petitioner all the
B
dues springing forth from the LOI No.13. The petitioner further submits that the OP
n
fay
9
A
No.01 admits to have issued LO!s at different times and received the usufructs
thereof, can not exhibit Corporate hand's off to disown its liability.
The O.P No.02 & 03 pleaded before the Council that they can not be impleaded as
Contesting parties since they have not entered into any kind ofd agreement with the
petitioner on the project
The Council observed that the O.P No. 02 & O.P No. 03 have not filed counters
against the claim petition of the petitioner.
Under the above circumstances, the Council initiates conciliation process under section
18(2) of the MSMED Act 2006 for amicable settlement of the dispute among the erring
parties,‘The Council directed the petitioner to file detail spread sheet incorporating O.P wise/Eill
wise/Date wise claim made & payment received against such claims before the next
Sitting of the Council
The O.P No. 01 is directed to file the counter against the rejoinder affidavit
of the petitioner before the next Siting of the Councit & send the copy of the same
sitectly to the petitioner under intimation to the Council. Further the O.P No 02 &8 OP
No.03 are directed to file the counter against the claim petition of the petitioner in the
Council & send the copy of the same to the petitioner directly under intimation to the
unc,
The case is adjourned.
‘Notice has been issued to both the parties to attend 98" Sitting of the MSEFC to be
held on 27.12.2022.
Both the parties are present in 98" Sitting held on 27.12.2022
The O.P No.02 & O.P No. 03 filed the written statement against the claim petition of the
petitioner on 27.12.2022 & the copy of the same has been acknowledged by the
petitioner on the same day i.e 27.12.2022.
The O.P No. 02 & 03 have literally stated in their written statement that the petitioner &
the OP No. 01 Le M/s AES India had a contractual relationship and accordingly
governed by the same. However the there is no leeway to claim verbal commitments as
stated by the petitioner with respect to OPGC. The OPGC is ne way connected to the
claimant & had never given any verbal commitment to anybody.
The Council noticed that the petitioner has submitted detail spread sheet incorporating
OP wiselbill wise/date wise claim as per the direction of the Council in 97" Sitting held
‘on 17.11.2022 the copy of the same has been acknowledged by the O.P on 22.12.2022Under the above circumstances the Council declares the conciliation process under
section 18(2) as failed & invokes the arbitration Proceeding under section 18(3) of the
MSMED Act 2006 for settlement of the dispute among the parties.
The Council further directed the petitioner to file rejoinder against the written
Statement of O.Ps before next Sitting of the Council & send a copy of the same to the
O.Ps directly under intimation to this Council.
The case is adjourned
Notice has been issued to both the Parties to attend 99" Sitting of the MSEFC to be
held on 30.01.2023.
‘The petitioner & the OPs are present in 99" Sitting of the MSEFC held on 30.01 2023.
The petitioner filed rejoinder against the written statement of the Ops on 30.01.2023 &
the copy of the same have been received by the OPs on 30.01.2023,
‘The major submissions of the petitioner in their rejoinder are as under.
') The whole job which is involved in the case has been undertaken was
performed at Unit 3 & Unit 4 at the OPGC Site and Power Houses where
work was done is located at OPGC Banharpali Site. It was also specifically
indicated therein that “Payment shall be made as per certified quantities of
OPGC Engineer In charge with agreed Unit Price”. In fact Bills of the claimant
which were paid had in fact been certified by the OPGC Engineer. Therfore it
's entirely false to say that OPGC is stranger to the present proceeding and
as such there is no mis-joinder and/or non-joinder of parties.
ii) The entire work was initiated, processed & concluded under the aegis of
OPGC which is major share holder. After the CCI order and looking into the
share holding structure, OPGC can not be absolved of the liability,Mi) AES is a different registered legal entity but it was the share holder of the
company at whose location contracts were duly performed at it's Baanharpali
Power House Site
The OP No. 2.& 3 prayed before the Council to exonerate them as contesting parties
as they do not have any role in the dispute which the Council rejected at this stage
of the adjudication.
ORDER
~~ Under the above circumstances the Council continues the arbitration proceeding under
section 18(3) of the MSMED Act 2006 for settlement of the dispute among the parties.
The case is adjourned.
1, Md, Sadique Alam , LAS., otc Se ou
Director of Industries-cum-M.D,OSEC Chairman. MS Es
ino sisha, Cuttack.
2. Sti Goutam Patra, Member
OPalR
Convener, SLBC
2/0] (25
3. Sri Deepak Kajaria, .. Member
President, OSSIA dip
ae\ily